    "stable_id": "evt-next-doicesti-fid",
    "name": "Doicești conditional shareholder investment decision",
    "project_id": "prj-nuscale-romania",
    "date": {
      "value": "2026-02-12",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "fid",
    "summary": "Shareholder approval was subject to conditions; not a construction start.",
    "sources": [
      "src-next-snn-fid"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-next-doicesti-conditions",
    "name": "Doicești FID conditions remain unresolved",
    "project_id": "prj-nuscale-romania",
    "date": {
      "value": "2026-07-15",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "SNN reported unmet conditions and continuing commercial negotiations.",
    "sources": [
      "src-next-snn-july"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-next-wylfa-contract",
    "name": "Wylfa programme design contract signed",
    "project_id": "prj-rr-wylfa",
    "date": {
      "value": "2026-04-13",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "contract",
    "summary": "Contract initiates site-specific design and planning before a future investment decision.",
    "sources": [
      "src-next-wylfa-contract"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-next-letart",
    "name": "Elementl announces Letart BWRX-300 proposal",
    "project_id": "prj-elementl-letart",
    "date": {
      "value": "2026-06-18",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Named host and early works agreement; no construction permit inferred.",
    "sources": [
      "src-next-elementl-letart"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-darlington-ltc",
    "name": "CNSC grants Darlington construction licence",
    "event_type": "other",
    "project_id": "prj-darlington-bwrx",
    "date": {
      "value": "2025-04",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "Licence to construct one BWRX-300 issued.",
    "sources": [
      "src-cnsc-darlington"
    ],
    "confidence": "high",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-darlington-lto-app",
    "name": "OPG applies for operating licence",
    "event_type": "other",
    "project_id": "prj-darlington-bwrx",
    "date": {
      "value": "2026-03-25",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Operating licence application filed.",
    "sources": [
      "src-cnsc-darlington"
    ],
    "confidence": "high",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htrpm-cod",
    "name": "HTR-PM commercial operation",
    "event_type": "commercial_operation",
    "project_id": "prj-htr-pm-shidaowan",
    "date": {
      "value": "2023-12-06",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Commercial operation reported for HTR-PM.",
    "sources": [
      "src-cae-htrpm",
      "src-pris",
      "src-iaea-pris-stats-cn-20261009"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-cfpp-cancel",
    "name": "UAMPS CFPP cancelled",
    "event_type": "cancellation",
    "project_id": "prj-uamps-cfpp",
    "date": {
      "value": "2023-11-08",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "UAMPS and NuScale announced mutual termination on 8 November 2023. NRC recorded a 10 November 2023 withdrawal letter and suspended its review on 13 November 2023.",
    "sources": [
      "src-uamps-cfpp-press-20231108",
      "src-nrc-cfpp-past-licensing"
    ],
    "confidence": "high",
    "last_checked": "2026-10-19",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aurora-pdsa",
    "name": "Oklo announces DOE approval of the Aurora-INL preliminary safety analysis",
    "event_type": "announcement",
    "project_id": "prj-aurora-inl",
    "date": {
      "value": "2026-06-11",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Company statement of 11 June 2026. Oklo says DOE's Idaho Operations Office approved the preliminary documented safety analysis for the Aurora powerhouse at Idaho National Laboratory under the Reactor Pilot Program. The DOE approval document was not opened; an NRC audit plan confirms only that Oklo submitted the analysis to DOE. A preliminary safety analysis approval is not authority to load fuel or operate.",
    "sources": [
      "src-oklo-pdsa-2026",
      "src-nrc-oklo-doe-authorization-audit-plan-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-longmott-fonsi",
    "name": "X-energy reports Long Mott environmental finding",
    "event_type": "announcement",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-05-18",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "X-energy reported NRC completion of the environmental assessment and finding of no significant impact. NRC's 20 May notice says the environmental assessment, finding and related exemptions were available or issued on 18 May. These are environmental-review actions, not a construction permit.",
    "sources": [
      "src-nrc-xenergy-dow",
      "src-next-xenergy-ea",
      "src-fr-longmott-ea-fonsi-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-08",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natrium-cp",
    "name": "Natrium construction permit",
    "event_type": "regulatory_step",
    "project_id": "prj-natrium-kemmerer",
    "date": {
      "value": "2026-03-09",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The NRC construction-permit record dates CPAR-1 to 9 March 2026. This event is the same decision, not a separate announcement.",
    "sources": [
      "src-fr-natrium-cpar1-2026",
      "src-nrc-terrapower",
      "src-det-331ef88455"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-hermes2-groundbreak",
    "name": "Hermes 2 groundbreaking",
    "event_type": "groundbreaking",
    "project_id": "prj-hermes-2",
    "date": {
      "value": "2026-04-17",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Groundbreaking reported for Hermes 2.",
    "sources": [
      "src-energynote-2026",
      "src-kairos-hermes2-groundbreaking-20260417"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-rellis-2025-02-04",
    "name": "Texas A&M offers RELLIS land to four reactor companies",
    "event_type": "announcement",
    "project_id": "prj-aalo-rellis",
    "date": {
      "value": "2025-02-04",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Chancellor announced agreements to pursue Kairos, Natura, Terrestrial, and Aalo projects at RELLIS.",
    "sources": [
      "src-tamus-rellis-2025"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-imsr-rellis-lease",
    "name": "Terrestrial Energy RELLIS ground lease",
    "event_type": "contract",
    "project_id": "prj-imsr-rellis",
    "date": {
      "value": "2026-06-18",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Ground lease and research agreements for about 77 acres. Not a reactor licence.",
    "sources": [
      "src-tamus-rellis-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-mark0-criticality",
    "name": "Antares Mark-0 zero-power criticality",
    "event_type": "first_criticality",
    "project_id": "prj-antares-mark0-inl",
    "date": {
      "value": "2026-06-04",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Zero-power fueled criticality at INL. Not grid connection.",
    "sources": [
      "src-doe-mark0-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward250-criticality",
    "name": "Ward 250 zero-power criticality",
    "event_type": "first_criticality",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2026-06-18",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Zero-power fueled criticality at Utah San Rafael Energy Lab.",
    "sources": [
      "src-doe-ward250-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-unity-criticality",
    "name": "Unity criticality demonstration",
    "event_type": "first_criticality",
    "project_id": "prj-unity-inl",
    "date": {
      "value": "2026-06-30",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE fact sheet dates the INL demonstration 30 Jun 2026. Electrical output not stated.",
    "sources": [
      "src-doe-golden-era-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aalo-x-criticality",
    "name": "Aalo-X zero-power criticality",
    "event_type": "first_criticality",
    "project_id": "prj-aalo-x-inl",
    "date": {
      "value": "2026-07-04",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Zero-power fueled criticality at INL. Not the RELLIS commercial proposal.",
    "sources": [
      "src-doe-aalo-x-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-oklo-sodi-option",
    "name": "Oklo SODI land option for two Ohio powerhouses",
    "event_type": "contract",
    "project_id": "prj-oklo-ohio",
    "date": {
      "value": "2024-02-01",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Option and right of first refusal for two powerhouses at the former Portsmouth site. Later company materials describe a larger phased campus on this same effort.",
    "sources": [
      "src-oklo-sodi-2024"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-bapeten-kelasa",
    "name": "BAPETEN approves Kelasa site evaluation",
    "event_type": "other",
    "project_id": "prj-thorcon-kelasa",
    "date": {
      "value": "2025-07-30",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Site-evaluation approval. Not a construction licence.",
    "sources": [
      "src-bapeten-kelasa-2025"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-parent-osge-ostroleka",
    "name": "OSGE Ostrołęka BWRX-300 proposal documented",
    "summary": "One of six locations named in OSGE decisions in principle. Further regulatory applications are required; this is not a construction licence. The 24-unit fleet total does not establish a site module count.",
    "sources": [
      "src-parent-osge-six"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-osge-ostroleka",
    "event_type": "announcement",
    "date": {
      "value": "2023-12-07",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-osge-dabrowa-gornicza",
    "name": "OSGE Dąbrowa Górnicza BWRX-300 proposal documented",
    "summary": "One of six locations named in OSGE decisions in principle. Further regulatory applications are required; this is not a construction licence. The 24-unit fleet total does not establish a site module count.",
    "sources": [
      "src-parent-osge-six"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-osge-dabrowa-gornicza",
    "event_type": "announcement",
    "date": {
      "value": "2023-12-07",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-osge-nowa-huta",
    "name": "OSGE Kraków / Nowa Huta BWRX-300 proposal documented",
    "summary": "One of six locations named in OSGE decisions in principle. Further regulatory applications are required; this is not a construction licence. The 24-unit fleet total does not establish a site module count.",
    "sources": [
      "src-parent-osge-six"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-osge-nowa-huta",
    "event_type": "announcement",
    "date": {
      "value": "2023-12-07",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-rr-tusimice",
    "name": "Rolls-Royce SMR Tušimice candidate location proposal documented",
    "summary": "Named location under study in the ČEZ / Rolls-Royce SMR partnership. Site selection studies and a proposal do not establish construction or a committed unit count.",
    "sources": [
      "src-parent-cez-additional"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-rr-tusimice",
    "event_type": "announcement",
    "date": {
      "value": "2026-07-21",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-rr-detmarovice",
    "name": "Rolls-Royce SMR Dětmarovice candidate location proposal documented",
    "summary": "Named location under study in the ČEZ / Rolls-Royce SMR partnership. Site selection studies and a proposal do not establish construction or a committed unit count.",
    "sources": [
      "src-parent-cez-additional"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-rr-detmarovice",
    "event_type": "announcement",
    "date": {
      "value": "2026-07-21",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-sealer-untra",
    "name": "Blykalla SEALER Untra / Tierp proposal documented",
    "summary": "Company reports an application for up to eight units and up to 440 MWe total. First-half-2030s operation is conditional on approvals; no construction is established.",
    "sources": [
      "src-parent-blykalla-tierp"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-sealer-untra",
    "event_type": "announcement",
    "date": {
      "value": "2026-08-25",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Blykalla reports application for up to eight SEALER units at Untra, Tierp",
      "what": "Blykalla reports an application for up to eight units and up to 440 MWe in total. Operation in the first half of the 2030s is conditional on approvals.",
      "limit": "No construction is established."
    }
  },
  {
    "stable_id": "evt-parent-sealer-norrsundet",
    "name": "Blykalla SEALER Norrsundet / Gävle proposal documented",
    "summary": "March 2026 planning release describes six units and about 300 MW; the same page describes a 55 MWe design. A later application may revise the configuration. Capacity stays unknown pending reconciliation; this is distinct from Untra.",
    "sources": [
      "src-parent-blykalla-gavle"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-sealer-norrsundet",
    "event_type": "announcement",
    "date": {
      "value": "2026-03-19",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-belews-creek",
    "name": "Duke Belews Creek technology-neutral SMR proposal documented",
    "summary": "Early site permit application considers several SMR / advanced reactor alternatives. No design, vendor or construction decision is selected. A planning capacity is not a selected reactor capacity.",
    "sources": [
      "src-parent-duke-belews"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-belews-creek",
    "event_type": "announcement",
    "date": {
      "value": "2025-12-30",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-holtec-oyster-creek",
    "name": "Holtec Oyster Creek SMR proposal documented",
    "summary": "Company proposes four SMR-300 units with expected combined output of 1,360 MWe, gross/net unspecified. Approval of the former station decommissioning plan is not an SMR construction permit.",
    "sources": [
      "src-parent-holtec-oyster"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-holtec-oyster-creek",
    "event_type": "announcement",
    "date": {
      "value": "2026-07-30",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-holtec-blue-castle",
    "name": "Holtec Green River / Blue Castle, Utah proposal documented",
    "summary": "SMR-300 project partnership at Green River, Utah. Separate from Tata / BWXT Green River in Wyoming. No module count or construction start is established.",
    "sources": [
      "src-parent-holtec-bluecastle"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-holtec-blue-castle",
    "event_type": "announcement",
    "date": {
      "value": "2026-05-28",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-last-energy-haskell",
    "name": "Last Energy Haskell County PWR-20 campus proposal documented",
    "summary": "Last Energy announced thirty proposed PWR-20 units at one controlled Haskell County campus. The announcement did not specify the electrical gross/net basis; the later NRC pre-application page calls 20 MWe per unit gross. This is one proposed site, not thirty deployment sites, and no early site permit is recorded.",
    "sources": [
      "src-parent-haskell",
      "src-nrc-last-energy-haskell-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-last-energy-haskell",
    "event_type": "announcement",
    "date": {
      "value": "2025-02-28",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-last-energy-llynfi",
    "name": "Last Energy Llynfi PWR-20 proposal documented",
    "summary": "Four PWR-20 units proposed at the former Llynfi coal station. ONR's 2 February 2026 licensing page, read 5 October 2026, still describes pre-application engagement, not a filed site-licence application and not an issued licence. The 2027 first-power date is a target.",
    "sources": [
      "src-parent-llynfi"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-last-energy-llynfi",
    "event_type": "announcement",
    "date": {
      "value": "2025-02-17",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-last-energy-london-gateway",
    "name": "Last Energy London Gateway PWR-20 proposal documented",
    "summary": "Port power proposal under an MOU, targeting 2030. This announcement does not establish financing, permission to construct or physical construction.",
    "sources": [
      "src-parent-london-gateway"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-last-energy-london-gateway",
    "event_type": "announcement",
    "date": {
      "value": "2025-09-15",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-aep-rockport",
    "name": "AEP Rockport BWRX-300 proposal documented",
    "summary": "Indiana site named for a potential BWRX-300 deployment in an application for federal support. Funding and development remain conditional; no construction start is established.",
    "sources": [
      "src-parent-aep-sites"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-aep-rockport",
    "event_type": "announcement",
    "date": {
      "value": "2025-01-17",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-aep-joshua-falls",
    "name": "AEP Joshua Falls SMR proposal documented",
    "summary": "Virginia locality identified for potential advanced nuclear development. Reactor technology remains under assessment; grant and site planning activity are not permission to construct.",
    "sources": [
      "src-parent-aep-sites"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-aep-joshua-falls",
    "event_type": "announcement",
    "date": {
      "value": "2025-01-17",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-ap300-teesside",
    "name": "Community Nuclear Power North Teesside AP300 proposal documented",
    "summary": "Private proposal for four AP300 units in North Teesside. A 2027 site-licence date and operation in the 2030s are targets, not completed authorizations.",
    "sources": [
      "src-parent-teesside"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-ap300-teesside",
    "event_type": "announcement",
    "date": {
      "value": "2024-02-08",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-taftoy-smr",
    "name": "Taftøy Aure / Heim SMR proposal documented",
    "summary": "Government approved the impact assessment programme in February 2026. This is not a construction permit or final policy decision. Technology and unit configuration remain unselected.",
    "sources": [
      "src-parent-taftoy"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-taftoy-smr",
    "event_type": "announcement",
    "date": {
      "value": "2026-02-11",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-tarapur-bsmr-200",
    "name": "Tarapur BSMR-200 lead proposal documented",
    "summary": "DAE names Tarapur for a 220 MWe BSMR-200 lead unit. Product name does not imply 200 MWe. This is separate from existing Tarapur BWR and PHWR plants.",
    "sources": [
      "src-parent-india-lead-sites"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-tarapur-bsmr-200",
    "event_type": "announcement",
    "date": {
      "value": "2026-02-04",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-tarapur-smr-55",
    "name": "Tarapur SMR-55 lead proposal documented",
    "summary": "DAE's SMR-55 lead proposal at Tarapur is separate in capacity and stage from the BSMR-200 proposal and the operating conventional units.",
    "sources": [
      "src-parent-india-lead-sites"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-tarapur-smr-55",
    "event_type": "announcement",
    "date": {
      "value": "2026-02-04",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-barc-vizag-htgcr",
    "name": "BARC Visakhapatnam HTGCR hydrogen demonstration proposal documented",
    "summary": "DAE names BARC Vizag for an up-to-5 MWth hydrogen reactor. Thermal demonstration capacity is not electrical output or commercial operation.",
    "sources": [
      "src-parent-india-lead-sites"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-barc-vizag-htgcr",
    "event_type": "announcement",
    "date": {
      "value": "2026-02-04",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-radiant-buckley",
    "name": "Radiant Kaleidos Buckley Space Force Base proposal documented",
    "summary": "Company reports Air Force / DIU selection for Buckley. Delivery by 2028 is a target. Separate from the INL demonstration and the unnamed fifteen-base Army fleet.",
    "sources": [
      "src-parent-radiant-buckley"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-radiant-buckley",
    "event_type": "announcement",
    "date": {
      "value": "2026-04-22",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "evt-parent-prodigy-belledune",
    "name": "Belledune Prodigy transportable nuclear proposal documented",
    "summary": "Pabineau and Eel River Bar First Nations / Prodigy proposal for up to 50 MWe. The packaging platform is not a selected reactor design. No construction start or precise parcel is established.",
    "sources": [
      "src-parent-prod-bel"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "project_id": "prj-prodigy-belledune",
    "event_type": "announcement",
    "date": {
      "value": "2026-09-01",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Belledune: First Nations and Prodigy transportable nuclear proposal of up to 50 MWe",
      "what": "The Pabineau and Eel River Bar First Nations and Prodigy propose a transportable nuclear plant of up to 50 MWe at Belledune. The packaging platform is not a selected reactor design.",
      "limit": "No construction start or precise parcel is established."
    }
  },
  {
    "stable_id": "evt-clinch-cp-20260929",
    "name": "TVA announces Clinch River Unit 1 construction permit",
    "summary": "TVA announced on 29 September 2026 that the NRC had issued a construction permit for Clinch River Unit 1. The NRC notice dates the permit 28 September 2026. The announcement is not a construction start.",
    "sources": [
      "src-parent-clinch-permit"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified",
    "event_type": "announcement",
    "project_id": "prj-clinch-river-bwrx",
    "date": {
      "value": "2026-09-29",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "TVA announces NRC construction permit for Clinch River Unit 1",
      "what": "TVA announced that the NRC had issued a construction permit for Clinch River Unit 1.",
      "limit": "The announcement is not a construction start.",
      "date_label": "Announced",
      "dates_note": "The NRC notice dates the permit 28 September 2026."
    }
  },
  {
    "stable_id": "evt-last-energy-pdsa-statement-2026",
    "name": "Last Energy states DOE approved a PWR-5 preliminary safety analysis",
    "event_type": "announcement",
    "project_id": "prj-last-energy-rellis",
    "date": {
      "value": "2026-05-28",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Company statement of 28 May 2026. It says DOE approved a preliminary documented safety analysis for the RELLIS pilot, described as scaled for 5 MW electrical. The DOE letter was not opened, so this records the announcement, not a confirmed DOE decision or a completed construction milestone.",
    "sources": [
      "src-last-energy-pwr5-pdsa-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-acceptance-2026",
    "name": "NRC completes acceptance review of the KRONOS construction permit application",
    "event_type": "other",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2026-05-18",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "NRC milestone marked actual: docketing decision letter issued and acceptance review complete. This accepts the application for review. It is not a construction permit.",
    "sources": [
      "src-nrc-uiuc-kronos-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-schedule-2026",
    "name": "NRC issues the KRONOS review schedule",
    "event_type": "other",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2026-06-16",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "NRC milestone marked actual: review schedule established and schedule letter issued. The later 2027 dates on that schedule are targets.",
    "sources": [
      "src-nrc-uiuc-kronos-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-draft-se-target",
    "name": "NRC target for a draft KRONOS safety evaluation",
    "event_type": "other",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2027-02",
      "precision": "month",
      "basis": "target"
    },
    "summary": "NRC schedule target for a draft safety evaluation. Not a completed decision.",
    "sources": [
      "src-nrc-uiuc-kronos-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-final-se-target",
    "name": "NRC target for a final KRONOS safety evaluation",
    "event_type": "other",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2027-09",
      "precision": "month",
      "basis": "target"
    },
    "summary": "NRC schedule target for a final safety evaluation. Not a completed decision.",
    "sources": [
      "src-nrc-uiuc-kronos-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-draft-ea-target",
    "name": "NRC target for a draft KRONOS environmental assessment",
    "event_type": "other",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2027-02",
      "precision": "month",
      "basis": "target"
    },
    "summary": "NRC schedule target for a draft environmental assessment. Not a completed decision.",
    "sources": [
      "src-nrc-uiuc-kronos-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-final-ea-target",
    "name": "NRC target for a final KRONOS environmental assessment",
    "event_type": "other",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2027-05",
      "precision": "month",
      "basis": "target"
    },
    "summary": "NRC schedule target for a final environmental assessment. Not a completed decision.",
    "sources": [
      "src-nrc-uiuc-kronos-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-jimmy-dac-update-20260723",
    "name": "Jimmy submits an updated Bazancourt creation-authorization file",
    "event_type": "other",
    "project_id": "prj-jimmy-bazancourt",
    "date": {
      "value": "2026-07-23",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "ASNR states that Jimmy filed an updated design and the remaining answers on 23 July 2026, and that MSNR referred that file to ASNR for review on 24 July 2026. The update is not a creation authorization.",
    "sources": [
      "src-asnr-prm-20261005"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-stellaria-alpha-seized-20251222",
    "name": "MSNR asks ASNR to review the Stellaria INB Alpha application",
    "event_type": "other",
    "project_id": "prj-stellaria-alvin-cadarache",
    "date": {
      "value": "2025-12-22",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "ASNR states that MSNR referred the INB Alpha creation-authorization application, filed on 19 December 2025, to it for review on 22 December 2025. As of the page fetched 5 October 2026, technical review is suspended pending further information. The page does not date that suspension. No creation authorization has been granted.",
    "sources": [
      "src-asnr-prm-20261005"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ssm-malma-opinion-20260603",
    "name": "SSM opinion on the ReFirm Målma government-approval application",
    "event_type": "other",
    "project_id": "prj-knxt-valdemarsvik",
    "date": {
      "value": "2026-06-03",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "SSM's 3 June 2026 opinion says the ReFirm Målma AB government-approval application is high-level and that some statements are deficient or incorrect. SSM says no Nuclear Activities Act licence application has been filed, and that the government has to decide whether this application level is reasonable. The opinion is not a permit and not a refusal.",
    "sources": [
      "src-ssm-ny-karnkraft-20261005"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-belews-esp-docketed-2026",
    "name": "Federal Register notice: NRC has accepted and docketed the Belews Creek early site permit application",
    "event_type": "other",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-02-09",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Published 9 February 2026 at 91 FR 5787: NRC staff accepted and docketed Duke Energy Carolinas' early site permit application under Docket No. 52-055. Hearing requests were due by 10 April 2026. A later NRC notice dates the acceptance letter 8 February 2026. Acceptance for docketing starts the detailed review. It is not a permit.",
    "sources": [
      "src-fr-belews-esp-docketed-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-belews-esp-eis-scoping-2026",
    "name": "NRC gives notice it will prepare an environmental impact statement for the Belews Creek early site permit",
    "event_type": "other",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-04-27",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Published 27 April 2026 at 91 FR 22549: the NRC will prepare an environmental impact statement for the early site permit application and opened a 30-day scoping period, with the U.S. Army Corps of Engineers as a cooperating agency.",
    "sources": [
      "src-fr-belews-esp-eis-scoping-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-belews-esp-hearing-2026",
    "name": "Uncontested hearing on the Belews Creek early site permit application",
    "event_type": "other",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-09-17",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The NRC's notice of 6 August 2026 (91 FR 50896) scheduled the uncontested hearing for 17 September 2026 in Danbury, North Carolina, and the NRC's project page marks that hearing as held. A hearing is a review step, not a decision. The permit decision date is listed as to be determined.",
    "sources": [
      "src-nrc-belews-creek-esp-page",
      "src-fr-belews-esp-hearing-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified",
    "reader": {
      "headline": "NRC holds uncontested hearing on the Belews Creek early site permit application",
      "what": "The NRC scheduled the uncontested hearing for 17 September 2026 in Danbury, North Carolina, and its project page marks the hearing as held. The permit decision date is listed as to be determined.",
      "limit": "A hearing is a review step, not a decision.",
      "dates_note": "Hearing notice: 6 August 2026."
    }
  },
  {
    "stable_id": "evt-pele-fuel-delivery-2025",
    "name": "Advanced nuclear fuel delivered to INL for Project Pele",
    "event_type": "other",
    "project_id": "prj-pele-inl",
    "date": {
      "value": "2025-11",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "DOE stated on 23 May 2026 that advanced nuclear fuel for Project Pele was delivered to Idaho National Laboratory in November 2025. The Army's article of 3 December 2025 says the first TRISO fuel delivery arrived at INL that week. The month is not settled between those official statements, and neither statement gives a calendar day. Delivery of fuel is not fuel loading, startup or operation.",
    "sources": [
      "src-doe-one-year-eo-20260523",
      "src-army-pele-fuel-20251203"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-radiant-dome-selection-2025",
    "name": "DOE conditionally selects Radiant for the first DOME tests",
    "event_type": "other",
    "project_id": "prj-radiant-kaleidos-inl",
    "date": {
      "value": "2025-07-01",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "On 1 July 2025 DOE made conditional selections of Radiant and Westinghouse to perform the first tests in the DOME test bed at Idaho National Laboratory, and said both were working through DOE's multi-phase authorization process. A conditional selection is not an authorization to start up a reactor.",
    "sources": [
      "src-doe-dome-first-experiments-20250701"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-radiant-dome-campaign-2026",
    "name": "DOME test bed complete; Radiant begins its test campaign",
    "event_type": "other",
    "project_id": "prj-radiant-kaleidos-inl",
    "date": {
      "value": "2026-04-08",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE reported on 8 April 2026 that construction of the DOME test bed was complete and that Radiant had started its scheduled year-long test campaign of the Kaleidos unit. Initial startup of the reactor was anticipated in the summer, which is a plan and not a recorded startup.",
    "sources": [
      "src-doe-dome-open-20260408"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-blue-energy-cpa-statement-2026",
    "name": "Blue Energy states it submitted the first part of an NRC construction permit application",
    "event_type": "announcement",
    "project_id": "prj-blue-energy-victoria",
    "date": {
      "value": "2026-09-16",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Company statements of 16 September 2026 say the first part of a construction permit application for the Port of Victoria project was submitted to the NRC. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only, and no Federal Register notice was found on 5 October 2026. A submitted application part is not a permit.",
    "sources": [
      "src-blue-energy-victoria-cpa-20260916",
      "src-gevh-blue-energy-victoria-20260916",
      "src-nrc-blue-energy-preapp"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified",
    "reader": {
      "headline": "Blue Energy says it submitted Part 1 of an NRC construction permit application",
      "what": "Blue Energy statements say the first part of a construction permit application for the Port of Victoria project was submitted to the NRC.",
      "limit": "A submitted application part is not a permit.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-aalo-x-dsa-2026",
    "name": "DOE approves the Aalo-X documented safety analysis",
    "event_type": "other",
    "project_id": "prj-aalo-x-inl",
    "date": {
      "value": "2026-04-30",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE's Reactor Pilot Program update of July 2026 lists the Aalo preliminary documented safety analysis as approved on 3 March 2026 and the documented safety analysis as approved on 30 April 2026, before zero-power criticality on 4 July 2026. The slides do not reproduce the approval documents. A safety-analysis approval for a zero-power test does not authorize a later power reactor.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-mark0-dsa-2026",
    "name": "DOE approves the Antares Mark-0 documented safety analysis",
    "event_type": "other",
    "project_id": "prj-antares-mark0-inl",
    "date": {
      "value": "2026-04",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "DOE's Reactor Pilot Program update of July 2026 lists the Antares preliminary documented safety analysis as approved in January 2026 and the documented safety analysis as approved in April 2026, before zero-power criticality on 4 June 2026. The update gives months, not days. The slides do not reproduce the approval documents. A safety-analysis approval for a zero-power test does not authorize a later power reactor.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-unity-dsa-2026",
    "name": "DOE approves the Unity critical experiment documented safety analysis",
    "event_type": "other",
    "project_id": "prj-unity-inl",
    "date": {
      "value": "2026-06-11",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE's Reactor Pilot Program update of July 2026 lists the Deployable Energy preliminary documented safety analysis as approved on 22 May 2026 and the documented safety analysis as approved on 11 June 2026, before criticality on 30 June 2026. The slides do not reproduce the approval documents. A safety-analysis approval for a zero-power test does not authorize a later power reactor.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward250-dsa-2026",
    "name": "DOE approves the Ward 250 documented safety analysis",
    "event_type": "other",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2026-04-23",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE's Reactor Pilot Program update of July 2026 lists the Valar Atomics preliminary documented safety analysis as approved in February 2026 and the documented safety analysis as approved on 23 April 2026, before zero-power criticality on 18 June 2026. The slides do not reproduce the approval documents.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward250-full-power-2026",
    "name": "Ward 250 reaches 100 kW thermal with electricity generation (DOE update)",
    "event_type": "electricity_generation",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2026-07-02",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE's Reactor Pilot Program update of July 2026 lists 2 July 2026 as the day Ward 250 achieved full power of 100 kW thermal, with electricity generation. Valar's own statement dates electricity generation to 1 July 2026. The 250 kW thermal rating stored for this reactor comes from DOE's categorical exclusion; the update's full-power figure is 100 kW thermal.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-marvel-criticality-target-2027",
    "name": "MARVEL dry initial criticality anticipated",
    "event_type": "first_criticality",
    "project_id": "prj-inl-marvel",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "summary": "DOE's project page, read on 5 October 2026, says dry initial criticality is anticipated in 2027; it gives a year, not a day. INL's release dated 6 October 2026 says criticality is anticipated to occur in December, with initial startup tests this winter; it prints no year beside December, and SMRMap reads it as the coming December only from that context. The two official targets therefore appear to differ. Neither is an achieved criticality or operating authority.",
    "sources": [
      "src-doe-ne-marvel-project-20261005",
      "src-inl-marvel-fdsa-20261006"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-marvel-full-power-target-2028",
    "name": "MARVEL full-power operation and electricity generation anticipated",
    "event_type": "electricity_generation",
    "project_id": "prj-inl-marvel",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "summary": "DOE's project page says the transition to full-power operation is anticipated in 2028, with electricity generation first. The page gives a year, not a day. This is a target. It is not commercial operation and not authority to operate.",
    "sources": [
      "src-doe-ne-marvel-project-20261005"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aurora-nrc-feedback-20260605",
    "name": "NRC preliminary feedback on its observation of Aurora-INL DOE submittals",
    "event_type": "other",
    "project_id": "prj-aurora-inl",
    "date": {
      "value": "2026-06-05",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "On 5 June 2026 the NRC sent Oklo preliminary feedback from observing DOE authorization submittals, including a preliminary documented safety analysis. The letter says DOE's own determination is independent and that a final audit report will follow. It does not approve the analysis and does not issue a licence.",
    "sources": [
      "src-nrc-aurora-prelim-feedback-20260605"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-blue-energy-cpa-letter-20260915",
    "name": "Blue Energy files Construction Permit Application Part 1 for Port of Victoria Unit 1",
    "event_type": "other",
    "project_id": "prj-blue-energy-victoria",
    "date": {
      "value": "2026-09-15",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Blue Energy's letter of 15 September 2026, ADAMS ML26258A339, project number 99902137, submits Part 1 of a construction permit application for Nuclear Unit 1 at the Port of Victoria, Texas. Part 1 asks the NRC to approve a limited work authorization for deep foundation work and a crane pad. The letter says the preliminary safety analysis report is not for construction-permit review now. The applicant asks for acceptance review of specified items by 20 November 2026; that is a request, not an NRC date. The letter is the applicant's submittal. It is not an NRC acceptance and not a permit.",
    "sources": [
      "src-blue-energy-cpa-part1-20260915"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-army-pele-fuel-report-20251203",
    "name": "Army reports the first TRISO fuel delivery to INL that week",
    "event_type": "other",
    "project_id": "prj-pele-inl",
    "date": {
      "value": "2025-12-03",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The Army's article dated 3 December 2025 says Idaho National Laboratory received the first TRISO fuel delivery for Project Pele that week. The article does not give the delivery day. It is not a safety-analysis approval, not authorization to load fuel, and not authorization to operate.",
    "sources": [
      "src-army-pele-fuel-20251203"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-marvel-assembly-target-2026",
    "name": "MARVEL assembly expected to finish",
    "event_type": "other",
    "project_id": "prj-inl-marvel",
    "date": {
      "value": "2026",
      "precision": "year",
      "basis": "target"
    },
    "summary": "DOE's project page, read on 5 October 2026, says assembly is expected to finish in 2026. It does not give a day or a quarter. This is a target, not an achieved milestone, and not a safety approval.",
    "sources": [
      "src-doe-ne-marvel-project-20261005"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-marvel-process-heat-estimate-2029",
    "name": "MARVEL process-heat stage likely",
    "event_type": "other",
    "project_id": "prj-inl-marvel",
    "date": {
      "value": "2029",
      "precision": "year",
      "basis": "estimated"
    },
    "summary": "DOE's project page says a second stage, likely in 2029, would supply process heat after electricity. The page says likely. This is not an achieved milestone and not authority to operate.",
    "sources": [
      "src-doe-ne-marvel-project-20261005"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ghana-voygr12-agreement",
    "name": "DOE reports the Ghana VOYGR-12 agreement",
    "project_id": "prj-ghana-voygr12",
    "date": {
      "value": "2024-08-29",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Department of Energy article: one agreement to deploy a single VOYGR-12 plant. Not a construction start and not a signed engineering contract.",
    "sources": [
      "src-doe-ghana-voygr12-2024"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ghana-voygr12-npg-2025",
    "name": "NPG describes 12 modules and says no contract is signed",
    "project_id": "prj-ghana-voygr12",
    "date": {
      "value": "2025-03-27",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Ghana News Agency: no formal contract had been signed. NPG described 12 modules of 77 MW, totaling 924 MW, and said the location was still being determined.",
    "sources": [
      "src-gna-ghana-vendors-2025"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-standard-power-ohio-2023",
    "name": "NuScale announces the Standard Power Ohio facility",
    "project_id": "prj-standard-power-ohio",
    "date": {
      "value": "2023-10-06",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Announcement of one Ohio facility. The 24-module and 1,848 MWe figures are combined with Pennsylvania and are not stored on this record.",
    "sources": [
      "src-nuscale-standard-power-2023"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-standard-power-pennsylvania-2023",
    "name": "NuScale announces the Standard Power Pennsylvania facility",
    "project_id": "prj-standard-power-pennsylvania",
    "date": {
      "value": "2023-10-06",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Announcement of one Pennsylvania facility. The 24-module and 1,848 MWe figures are combined with Ohio and are not stored on this record.",
    "sources": [
      "src-nuscale-standard-power-2023"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-05",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-fanco-indiana-park-2025",
    "name": "First American Nuclear and Indiana announce an EAGL-1 energy park plan",
    "project_id": "prj-fanco-eagl1-indiana",
    "date": {
      "value": "2025-11-04",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "FANCO and the State of Indiana announced plans for FANCO's headquarters, manufacturing facilities and one energy park in Indiana. No county or site is named. Not a construction permit and not a module count. ANS reported the announcement on 10 November 2025.",
    "sources": [
      "src-fanco-indiana-announcement-2025",
      "src-ans-fanco-indiana-2025"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-11",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-haiyang-siting-opinion-2024",
    "name": "Haiyang integrated small reactor: regulator siting review opinion issued",
    "project_id": "prj-haiyang-integrated-small-reactor",
    "date": {
      "value": "2024-09-10",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NNSA issued site-selection review opinion No. 2414; a siting opinion, not a construction licence.",
    "sources": [
      "src-nnsa-haiyang-siting-opinion-2024"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-huakun-eia-accepted-2025",
    "name": "Huakun One: siting-stage environmental assessment accepted",
    "project_id": "prj-huakun-one-taipingling",
    "date": {
      "value": "2025-12-02",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "The ecology ministry accepted the siting-stage environmental impact report for the floating platform at the Taipingling site.",
    "sources": [
      "src-mee-huakun-eia-notice-2025"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-sinap-smtmsr-eia-2026",
    "name": "SINAP small modular thorium molten-salt research reactor: siting-stage assessment resubmitted",
    "project_id": "prj-sinap-minqin-smtmsr",
    "date": {
      "value": "2026-01",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "January 2026 resubmission of the siting-stage environmental impact report (30 MWt, 10 MWe), posted by the ecology ministry on 12 March 2026.",
    "sources": [
      "src-mee-sinap-smtmsr-eia-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-shenyang-nhr200-approval-2001",
    "name": "Shenyang nuclear heating project: state approval of the project proposal",
    "project_id": "prj-shenyang-nhr200-2001",
    "date": {
      "value": "2001-04",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "INET states the 2 x 200 MW project proposal received state approval in April 2001.",
    "sources": [
      "src-inet-nhr200-page"
    ],
    "confidence": "low",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-belledune-banr-selected-2026",
    "name": "Belledune transportable plant: BWXT BANR microreactor selected",
    "project_id": "prj-prodigy-belledune",
    "date": {
      "value": "2026-10-05",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "BWXT announces BANR selection and two planned reactors for the up to 50 MWe transportable plant; New Brunswick signed a letter of intent to buy power. Planned count is not constructed units, and this announcement is not a licence or construction start.",
    "sources": [
      "src-bwxt-banr-belledune-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "reader": {
      "headline": "BWXT announces BANR selection for Belledune transportable plant",
      "what": "BWXT announced the selection of BANR, with two reactors planned for the up to 50 MWe transportable plant. New Brunswick signed a letter of intent to buy power.",
      "limit": "This announcement is not a licence or a construction start.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-wc-atucha-tender-authorised-2026",
    "name": "Reported: Atucha shareholders authorise a public tender for a privately financed reactor",
    "project_id": "prj-atucha-new-smr",
    "date": {
      "value": "2026-09-23",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Reported shareholders' meeting decision: the reactor initiative declared of business interest and the board authorised to call a public tender for a privately financed reactor over 12 hectares of the land reserved for the cancelled Atucha III. Not an award.",
    "sources": [
      "src-dinamicarg-atucha-tender-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified",
    "reader": {
      "headline": "Atucha shareholders reportedly authorise a tender for a privately financed reactor",
      "what": "Shareholders reportedly declared the reactor initiative of business interest and authorised the board to call a public tender for a privately financed reactor over 12 hectares of land reserved for the cancelled Atucha III.",
      "limit": "Authorising a tender is not an award."
    }
  },
  {
    "stable_id": "evt-wc-studsvik-partners-2026",
    "name": "Studsvik selects GE Vernova Hitachi and Samsung C&T for a four-unit BWRX-300 project",
    "project_id": "prj-studsvik-nykoping",
    "date": {
      "value": "2026-09-03",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "contract",
    "summary": "Strategic partners selected for an initial four-unit BWRX-300 project of up to 1.2 GW at Nyköping or Målma; the first site is still to be decided. Not an investment decision.",
    "sources": [
      "src-studsvik-partners-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified",
    "reader": {
      "headline": "Studsvik selects GE Vernova Hitachi and Samsung C&T for a four-unit BWRX-300 project",
      "what": "Studsvik selected GE Vernova Hitachi and Samsung C&T as strategic partners for an initial four-unit BWRX-300 project of up to 1.2 GW at Nyköping or Målma. The first site is still to be decided.",
      "limit": "This is not an investment decision."
    }
  },
  {
    "stable_id": "evt-wc-doicesti-gms-2026",
    "name": "Doicești: shareholders reject a strategy reassessment and note unmet investment-decision conditions",
    "project_id": "prj-nuscale-romania",
    "date": {
      "value": "2026-07-15",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Nuclearelectrica's shareholders acknowledged information on the work to fulfil the conditions attached to the February 2026 final investment decision and rejected initiating a reassessment of the 2022 SMR implementation strategy.",
    "sources": [
      "src-snn-gms-resolutions-20260715"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-pioneer-psar-2026",
    "name": "Pioneer 1 and 2: preliminary safety analysis report submitted (construction permit application part 2)",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2026-09-30",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Holtec reported that the preliminary safety analysis report completed the second part of its phased construction-permit application. Press anticipated a later limited-work-authorization safety evaluation in December 2026, while the NRC milestone table already lists a draft safety evaluation report with information gaps on 31 August 2026; these are dated reports, not a new permission. No LWA or construction permit is recorded. The NRC's notice of receipt published 10 November 2026 confirms it received Part 2 on 30 September 2026 and says its staff was then undertaking its acceptance review; acceptance for docketing would be a later, separate step.",
    "sources": [
      "src-holtec-pioneer-regulatory-2026",
      "src-wnn-pioneer-psar-2026",
      "src-nrc-holtec-pioneer-page",
      "src-fr-pioneer-part2-receipt-20261110"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified",
    "reader": {
      "headline": "Holtec says Pioneer safety analysis report completes permit application part 2",
      "what": "Holtec reported that the preliminary safety analysis report completed the second part of its phased construction-permit application for Pioneer Units 1 and 2.",
      "limit": "No limited work authorization or construction permit is recorded.",
      "dates_note": "NRC draft safety evaluation report: 31 August 2026. Press anticipated an LWA safety evaluation in December 2026."
    }
  },
  {
    "stable_id": "evt-pioneer-excavation-walls-exemption-2026",
    "name": "NRC issued narrow Pioneer excavation-wall exemption",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2026-08-28",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "The NRC allowed specified permanent support-of-excavation walls before a limited work authorization. It did not issue an LWA or construction permit, and the notice does not establish that physical work began.",
    "sources": [
      "src-fr-pioneer-excavation-exemption-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-09",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-veron-debate-report-2026",
    "name": "Véron: CNDP notice updated; debate reports available",
    "project_id": "prj-newcleo-veron-lfr-as-30",
    "date": {
      "value": "2026-09-30",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "The CNDP notice, posted on 29 September and updated on 30 September 2026, says the debate reports are available. This event dates the notice update, not the publication of each report. The linked chairman's assessment separately bears 1 October 2026. The notice gives newcleo and RTE until 30 December to explain how they take the debate into account and communicate their decision; this is not a regulator's licensing-decision deadline.",
    "sources": [
      "src-cndp-veron-report-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified",
    "reader": {
      "headline": "Véron newcleo proposal: CNDP says the debate reports are available",
      "what": "A CNDP notice says the debate reports are available. It gives newcleo and RTE until 30 December to explain how they take the debate into account and communicate their decision.",
      "limit": "The 30 December date is not a regulator's licensing-decision deadline.",
      "date_label": "Notice updated",
      "dates_note": "Notice posted 29 September, updated 30 September 2026. Chairman's assessment dated 1 October 2026."
    }
  },
  {
    "stable_id": "evt-wc-myanmar-implementation-2026",
    "name": "Myanmar: Russia says implementation of the agreements is starting",
    "project_id": "prj-myanmar-ritm-smr",
    "date": {
      "value": "2026-08-19",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Statement by the Russian prime minister during the Myanmar president's visit; the site is still not named.",
    "sources": [
      "src-atomic-energy-myanmar-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified",
    "reader": {
      "headline": "Myanmar: Russian prime minister says implementation of the agreements is starting",
      "what": "The Russian prime minister said during the Myanmar president's visit that implementation of the agreements is starting.",
      "limit": "The site is still not named."
    }
  },
  {
    "stable_id": "evt-wc-tarapur-aec-site-2026",
    "name": "Tarapur: DAE tells Parliament the Atomic Energy Commission approved the site for the BSMR-200 and SMR-55 lead units",
    "project_id": "prj-tarapur-bsmr-200",
    "date": {
      "value": "2026-08",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Written answers posted in August and September 2026 state Atomic Energy Commission approval of Tarapur as the site and in-principle approval for engineering and construction; sanction and regulator consent are not reported.",
    "sources": [
      "src-dae-parliament-answers-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified",
    "reader": {
      "headline": "Tarapur approved as site for BSMR-200 and SMR-55 lead units, DAE tells Parliament",
      "what": "Written answers to Parliament posted in August and September 2026 state that the Atomic Energy Commission approved Tarapur as the site and gave in-principle approval for engineering and construction.",
      "limit": "Sanction and regulator consent are not reported."
    }
  },
  {
    "stable_id": "evt-wc-vizag-siting-consent-2026",
    "name": "BARC Visakhapatnam hydrogen reactor: siting consent and environmental terms of reference reported",
    "project_id": "prj-barc-vizag-htgcr",
    "date": {
      "value": "2026-03",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "DAE's written answers state siting consent received and environmental-clearance terms of reference issued; the consent's date and issuing body are not stated.",
    "sources": [
      "src-dae-parliament-answers-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-daegu-bid-lapsed-2026",
    "name": "Daegu Gunwi: first-unit bid lapses after KHNP's coastal-site requirement",
    "project_id": "prj-daegu-gunwi-ismr",
    "date": {
      "value": "2026-02-03",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Daegu said its plan to host the first SMR unit fell through because KHNP's site call required coastal sites; it will pursue a later unit.",
    "sources": [
      "src-yonhap-daegu-lapsed-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-wc-yantai-nhr200-approval-2003",
    "name": "Yantai nuclear seawater desalination project: state approval of the project proposal",
    "project_id": "prj-yantai-nhr200-desalination-2003",
    "date": {
      "value": "2003-03",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "INET's NHR200 page states that the Shandong nuclear seawater desalination project received state approval of its project proposal in March 2003. The 2019 INPRO slides name that project at Yantai.",
    "sources": [
      "src-inet-nhr200-page",
      "src-inet-inpro-nhr-2019"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-06",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aurora-nepa-20260720",
    "name": "DOE approves Aurora-INL environmental categorical exclusion",
    "event_type": "other",
    "project_id": "prj-aurora-inl",
    "date": {
      "value": "2026-07-20",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE Idaho approved environmental determination DOE-ID-INL-26-018 for the proposed Aurora-INL reactor scope. It is not a safety-analysis approval or proof that reactor construction or operation began.",
    "sources": [
      "src-doe-id-inl-26-018-aurora-20260720"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pwr5-nepa-20260930",
    "name": "DOE approves PWR-5 Phase 1 environmental categorical exclusion",
    "event_type": "other",
    "project_id": "prj-last-energy-rellis",
    "date": {
      "value": "2026-09-30",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "DOE signed environmental determination DOE-ID-26-008 for proposed initial criticality and low-power testing. This is not startup authorization or proof that criticality occurred.",
    "sources": [
      "src-doe-id-26-008-pwr5-20260930"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pwr5-dsa-announcement-20261007",
    "name": "Last Energy announces DOE approval of PWR-5 final safety analysis",
    "event_type": "announcement",
    "project_id": "prj-last-energy-rellis",
    "date": {
      "value": "2026-10-07",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "On 7 October Last Energy said DOE approved its final Documented Safety Analysis. The DOE letter and exact decision date were not opened. The company says DOE readiness review and startup authorization are still ahead; this announcement does not establish operating authority or criticality.",
    "sources": [
      "src-last-energy-pwr5-dsa-20261007"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-08",
    "review_state": "verified",
    "reader": {
      "headline": "Last Energy says DOE approved its PWR-5 final safety analysis",
      "what": "Last Energy said DOE approved its final Documented Safety Analysis for the PWR-5 pilot at Texas A&M-RELLIS. The company says DOE readiness review and startup authorization are still ahead.",
      "limit": "The announcement does not establish operating authority or criticality.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-marvel-pdsa-approval-20260311",
    "name": "INL reports DOE approval of MARVEL's preliminary documented safety analysis",
    "event_type": "other",
    "project_id": "prj-inl-marvel",
    "date": {
      "value": "2026-03-11",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "INL's release of 11 March 2026 says DOE's Idaho Operations Office has approved MARVEL's preliminary documented safety analysis for a dry initial-criticality configuration. The date shown is the release date, a report date; the release gives no approval date, and the DOE approval document was not opened. The release does not report startup or criticality.",
    "sources": [
      "src-inl-marvel-pdsa-20260311"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-marvel-fdsa-approval-20261006",
    "name": "INL reports DOE approval of MARVEL's final documented safety analysis",
    "event_type": "other",
    "project_id": "prj-inl-marvel",
    "date": {
      "value": "2026-10-06",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "INL's release of 6 October 2026 says DOE's Idaho Operations Office approved MARVEL's final documented safety analysis just before the primary coolant system arrived at INL in mid-September 2026, and describes it as a key safety document authorizing a dry criticality configuration at near-zero power with no coolant. The date shown is the release date, a report date; no approval day is given and the DOE approval document was not opened. The release anticipates criticality in December, a target. It does not identify a separate startup authorization or report achieved criticality.",
    "sources": [
      "src-inl-marvel-fdsa-20261006"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified",
    "reader": {
      "headline": "INL reports DOE approval of MARVEL's final documented safety analysis",
      "what": "INL says DOE's Idaho Operations Office approved MARVEL's final documented safety analysis just before the primary coolant system arrived at INL in mid-September 2026.",
      "why": "INL describes it as a key safety document authorizing a dry criticality configuration at near-zero power with no coolant.",
      "limit": "Criticality in December is a target; the release does not report achieved criticality.",
      "date_label": "Release dated",
      "dates_note": "The release gives no approval day."
    }
  },
  {
    "stable_id": "evt-radiant-kaleidos-dark-statement-20260209",
    "name": "Radiant announces DOE approval of the Kaleidos authorization request (DARK)",
    "event_type": "announcement",
    "project_id": "prj-radiant-kaleidos-inl",
    "date": {
      "value": "2026-02-09",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Company statement of 9 February 2026. Radiant says DOE granted approval of its DOE Authorization Request for Kaleidos (DARK), designed to meet the intent of a preliminary documented safety analysis, and calls it the second of three safety document submittals in DOE's authorization pathway. Radiant says it is now preparing the final documented safety analysis submittal and readiness review, leading to authorization and startup at INL that summer. This is Radiant's account; the DOE approval document was not opened. No startup or criticality is recorded.",
    "sources": [
      "src-radiant-dark-approval-20260209"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-08",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-egino-wind-down-statement-20251203",
    "name": "Welsh Government announces intention to dissolve Cwmni Egino",
    "event_type": "other",
    "project_id": "prj-trawsfynydd-egino",
    "date": {
      "value": "2025-12-03",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The Welsh Government's written statement of 3 December 2025 says the Welsh Ministers, as sole shareholder, intend at the end of the current agreement on 31 March 2026 to pass a special resolution directing the directors to dissolve Cwmni Egino, the company set up in 2021 to deliver a site development plan for Trawsfynydd. It notes that in May 2024 the UK Government did not include Trawsfynydd among the initial sites considered in its SMR competition, and that Cwmni Egino's work will be archived for possible future use. The statement records an intention. The Companies House register read on 9 October 2026 still lists the company as active with no dissolution filing, so the dissolution is not recorded as completed.",
    "sources": [
      "src-gov-wales-egino-ws-20251203",
      "src-companies-house-cwmni-egino-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-09",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-darlington-physical-start-20260422",
    "name": "IAEA PRIS records construction start for Darlington SMR1",
    "event_type": "construction_start",
    "project_id": "prj-darlington-bwrx",
    "date": {
      "value": "2026-04-22",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "PRIS records physical construction start of Darlington SMR1 on 22 April 2026. This is distinct from the CNSC licence to construct in April 2025 and from the pending operating-licence application.",
    "sources": [
      "src-det-b26f60ab8a",
      "src-iaea-pris-darlington-status-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-11-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pioneer-draft-eis-target-20261031",
    "name": "NRC target for Pioneer draft environmental impact statement",
    "event_type": "other",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2026-10-31",
      "precision": "day",
      "basis": "target"
    },
    "summary": "The NRC milestone table targeted a draft environmental impact statement for 31 October 2026. The NRC's project page, updated 30 October 2026, lists that milestone's date as TBD and shows no draft as issued. This is a target, not an achieved review or permission.",
    "sources": [
      "src-nrc-holtec-pioneer-page"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-03",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pioneer-advanced-ser-target-20270131",
    "name": "NRC target for Pioneer advanced safety evaluation report",
    "event_type": "other",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2027-01-31",
      "precision": "day",
      "basis": "target"
    },
    "summary": "The NRC milestone table targets an advanced safety evaluation report without open items for 31 January 2027. This is a target, not an issued report, authorization or permit.",
    "sources": [
      "src-nrc-holtec-pioneer-page"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-09",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pioneer-final-ser-target-20270331",
    "name": "NRC target for Pioneer final safety evaluation report",
    "event_type": "other",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2027-03-31",
      "precision": "day",
      "basis": "target"
    },
    "summary": "The NRC milestone table targets the final safety evaluation report for 31 March 2027. This is a target, not an issued report, authorization or permit.",
    "sources": [
      "src-nrc-holtec-pioneer-page"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-09",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pioneer-final-eis-target-20270331",
    "name": "NRC target for Pioneer final environmental impact statement",
    "event_type": "other",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2027-03-31",
      "precision": "day",
      "basis": "target"
    },
    "summary": "The NRC milestone table targets the final environmental impact statement for 31 March 2027. This is a target, not an issued statement, authorization or permit.",
    "sources": [
      "src-nrc-holtec-pioneer-page"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-09",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-se-videberg-state-aid-application-2025",
    "name": "Swedish Government announces receipt of Videberg Kraft's state-support application",
    "project_id": "prj-videberg-varo-rr-smr",
    "date": {
      "value": "2025-12-23",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "On 23 December 2025 the Government announced that it had received the first application for state support for new nuclear, from Videberg Kraft, for reactors of about 1,500 MW in total on the Värö peninsula at Ringhals. An application is not an award.",
    "sources": [
      "src-se-gov-videberg-aid-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-10",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-se-videberg-state-stake-2026",
    "name": "Swedish Government decides to take a 60% stake in Videberg Kraft",
    "project_id": "prj-videberg-varo-rr-smr",
    "date": {
      "value": "2026-06-25",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "The Government decided that the state will own 60% of Videberg Kraft, with Vattenfall and Industrikraft at 20% each; formal transfer is expected in the second half of 2027 and the negotiated support terms go to the European Commission for state-aid review. Not an investment decision, permit or construction start.",
    "sources": [
      "src-se-gov-videberg-stake-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-10",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-longmott-final-se-target",
    "milestone": {
      "key": "final_safety_evaluation",
      "scope": "longmott_construction_permit"
    },
    "met_by": "evt-longmott-final-se-completed-202610",
    "name": "NRC target for the Long Mott final safety evaluation",
    "event_type": "other",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-11",
      "precision": "month",
      "basis": "target"
    },
    "summary": "NRC schedule target for issuing its final safety evaluation of the construction-permit application. NRC news release 26-083 of 9 November 2026 says staff completed the safety evaluation in October, one month ahead of schedule, and the permit has been issued. The NRC's project page, re-read on 10 November, still showed the November target. The evaluation was completed; the target date itself is kept as the schedule that was stated.",
    "sources": [
      "src-nrc-longmott-page-2026",
      "src-xenergy-longmott-fser-20261030",
      "src-nrc-news-26-083-longmott-cp-20261109"
    ],
    "confidence": "high",
    "last_checked": "2026-11-01",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-longmott-acrs-report-20261016",
    "name": "NRC's reactor safeguards committee reports on Long Mott; its review supports issuing the construction permit",
    "event_type": "regulatory_step",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-10-16",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The NRC's Advisory Committee on Reactor Safeguards wrote to the NRC Chairman on 16 October 2026 that it had completed its review of the Long Mott construction-permit application and the staff's safety evaluation at its 6–9 October meeting (the Long Mott session was scheduled for 7 October), and that its review supports issuance of the construction permit. It listed important work remaining for an operating licence application, including fuel and material performance at peak accident temperatures. This is an advisory report, not a permit decision.",
    "sources": [
      "src-nrc-acrs-longmott-20261016",
      "src-fr-acrs-739-meeting-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-11-01",
    "review_state": "verified",
    "reader": {
      "headline": "Long Mott: NRC's safety advisory committee supports issuing the construction permit",
      "what": "The NRC's Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review of the Long Mott construction-permit application supports issuance of the permit.",
      "limit": "An advisory report, not a permit decision; the committee lists important work still needed for an operating licence."
    }
  },
  {
    "stable_id": "evt-longmott-final-se-announced-20261030",
    "name": "X-energy announces that the NRC has completed its final safety evaluation for Long Mott",
    "event_type": "announcement",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-10-30",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "X-energy announced on 30 October 2026 that the NRC had completed its final safety evaluation report for the Long Mott construction-permit application, documenting the staff's conclusion that the proposed plant and site provide the safety basis to begin construction. The release gives no NRC document number or issue date. When checked on 1 November, the NRC had posted no news release about it, and its Long Mott page (last updated 14 September) still listed the final evaluation as a November 2026 target. A safety evaluation is not a construction permit; as of that 1 November reading, the hearing outcome and permit decision had not been recorded here. The later NRC release of 9 November separately confirms October completion and issuance of the construction permit; those developments have their own records.",
    "sources": [
      "src-xenergy-longmott-fser-20261030",
      "src-nrc-longmott-page-2026",
      "src-nrc-news-26-083-longmott-cp-20261109"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-01",
    "review_state": "verified",
    "reader": {
      "headline": "Long Mott: X-energy says the NRC has completed its final safety evaluation",
      "what": "X-energy announced on 30 October 2026 that the NRC's final safety evaluation report for the Long Mott construction-permit application is complete.",
      "limit": "Reported by the company; the NRC's project page still showed a November target on 1 November. A safety evaluation is not a construction permit."
    }
  },
  {
    "stable_id": "evt-letart-unit1-construction-target",
    "name": "Elementl target for starting construction of the first Letart unit",
    "event_type": "other",
    "project_id": "prj-elementl-letart",
    "date": {
      "value": "2030",
      "precision": "year",
      "basis": "target"
    },
    "summary": "Elementl expects construction of the first unit to begin in 2030, subject to a final investment decision and NRC and Ohio Power Siting Board approvals, with the first unit's completion anticipated in 2034. A company target, not a commitment, a permission or a construction start.",
    "sources": [
      "src-next-elementl-letart",
      "src-elementl-meigs-factsheet-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-11",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-longmott-cli-26-10",
    "name": "NRC Commission dismisses the applicant's intervention appeal as moot (CLI-26-10)",
    "event_type": "other",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-08-07",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The Commission dismissed Long Mott Energy's appeal of the Licensing Board's January 2026 ruling admitting an intervenor, because the Board had since dismissed both admitted contentions as moot. It took no position on the intervenor's separate petition for review. This is an adjudicatory order, not a permit decision; the construction-permit application was still under review at that date. The Commission later denied the intervenor's petition for review (CLI-26-15, 6 November 2026) and the NRC issued the construction permit on 9 November 2026.",
    "sources": [
      "src-nrc-cli-26-10"
    ],
    "confidence": "high",
    "last_checked": "2026-10-11",
    "review_state": "verified",
    "reader": {
      "headline": "Long Mott: Commission dismisses applicant's appeal after contentions ruled moot",
      "what": "The Commission dismissed Long Mott Energy's appeal of the Licensing Board's January 2026 ruling admitting an intervenor, because the Board had since dismissed both admitted contentions as moot.",
      "limit": "An adjudicatory order, not a permit decision. The petition for review was later denied (CLI-26-15, 6 Nov 2026) and the permit issued 9 Nov 2026."
    }
  },
  {
    "stable_id": "evt-unity-dome-selection-20260930",
    "name": "INL announces Unity selection for a conditional DOME test",
    "summary": "INL names DOME as the host for Unity’s planned 2027 full-power test. The self-funded slot is conditional on readiness, fuel and regulatory milestones; selection is not authorization.",
    "sources": [
      "src-inl-unity-dome-20260930"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "project_id": "prj-unity-dome-2027",
    "event_type": "announcement",
    "date": {
      "value": "2026-09-30",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "INL names DOME as host for Unity's planned 2027 full-power test",
      "what": "INL named DOME as the host for Unity's planned 2027 full-power test. The self-funded slot is conditional on readiness, fuel and regulatory milestones.",
      "limit": "Selection is not authorization.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-unity-dome-target-2027",
    "name": "Unity full-power DOME test targeted",
    "summary": "INL’s 30 September 2026 release targets 2027 for Unity testing at DOME. Conditional schedule, not an achieved test.",
    "sources": [
      "src-inl-unity-dome-20260930"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "project_id": "prj-unity-dome-2027",
    "event_type": "other",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    }
  },
  {
    "stable_id": "evt-radiant-dome-completion-report-20260930",
    "name": "INL reports Radiant completed the first DOME test",
    "summary": "This is the publication date of INL’s statement, not the physical completion date. INL supplies no completion day, achieved power or scope of completion; no operating-stage promotion or final authorization is inferred.",
    "sources": [
      "src-inl-unity-dome-20260930",
      "src-kifi-dome-deployable-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "project_id": "prj-radiant-kaleidos-inl",
    "event_type": "announcement",
    "date": {
      "value": "2026-09-30",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "INL reports Radiant completed the first DOME test",
      "what": "INL published a statement reporting that Radiant completed the first DOME test.",
      "limit": "INL gives no completion day, achieved power or scope of completion.",
      "date_label": "Published"
    }
  },
  {
    "stable_id": "evt-isu-art-site-20260916",
    "name": "ISU identifies its Business and Research Park as the ART site",
    "summary": "University announcement identifies the future Advanced Research and Test Reactor site at the Business and Research Park. No numerical reactor coordinates or nuclear permission are established.",
    "sources": [
      "src-isu-art-site-20260916"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "project_id": "prj-isu-nucube-art",
    "event_type": "announcement",
    "date": {
      "value": "2026-09-16",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Idaho State University names site for its Advanced Research and Test Reactor",
      "what": "An Idaho State University announcement identifies the Business and Research Park as the site of the future Advanced Research and Test Reactor.",
      "limit": "The announcement establishes no nuclear permission.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-deep-fission-parsons-target-2027",
    "name": "Deep Fission Parsons DOE pilot targeted",
    "summary": "Undated company project page read 13 October 2026 targets the DOE pilot phase in 2027 and still lists DOE authorization as a next step. A data well and non-nuclear canister are not a fuelled reactor.",
    "sources": [
      "src-deep-fission-parsons"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "project_id": "prj-deep-fission-parsons",
    "event_type": "other",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    }
  },
  {
    "stable_id": "evt-starcore-first-power-target-2030",
    "name": "StarCore targets first commercial power",
    "summary": "Current undated investor page identifies Whiteshell first facility and targets first commercial power 2030. Company schedule only; no plant rating, module count or permission is inferred. The undated Pinawa page separately targets operations by end 2028; the company schedules are unreconciled.",
    "sources": [
      "src-starcore-investors-current",
      "src-starcore-pinawa"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "project_id": "prj-starcore-pinawa",
    "event_type": "commercial_operation",
    "date": {
      "value": "2030",
      "precision": "year",
      "basis": "target"
    }
  },
  {
    "stable_id": "evt-yakutia-environment-announcement-2024",
    "name": "Yakutia: environmental-expert conclusion on Unit 1 licence materials reported",
    "project_id": "prj-yakutia-ritm",
    "date": {
      "value": "2024-05-23",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Atom Media reported Rosprirodnadzor approval of a positive environmental-expert conclusion on Unit 1 construction-licence supporting materials, including environmental impact assessment. The date is the announcement, not an established decision date. No nuclear construction permit or physical reactor-construction start is inferred.",
    "sources": [
      "src-atommedia-yakutia-environment-2024"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-alfred-roadmap-2031",
    "name": "ALFRED: RATEN roadmap target for siting permit",
    "project_id": "prj-alfred-mioveni",
    "date": {
      "value": "2031",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "RATEN's 2026 workshop roadmap targets siting permit in 2031. This is a planning target, not an achieved milestone or granted permission.",
    "sources": [
      "src-raten-alfred-iaea-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-alfred-roadmap-2032",
    "name": "ALFRED: RATEN roadmap target for construction permit",
    "project_id": "prj-alfred-mioveni",
    "date": {
      "value": "2032",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "RATEN's 2026 workshop roadmap targets construction permit in 2032. This is a planning target, not an achieved milestone or granted permission.",
    "sources": [
      "src-raten-alfred-iaea-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-alfred-roadmap-2036",
    "name": "ALFRED: RATEN roadmap target for commissioning permit",
    "project_id": "prj-alfred-mioveni",
    "date": {
      "value": "2036",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "RATEN's 2026 workshop roadmap targets commissioning permit in 2036. This is a planning target, not an achieved milestone or granted permission.",
    "sources": [
      "src-raten-alfred-iaea-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-alfred-roadmap-2037",
    "name": "ALFRED: RATEN roadmap target for operation",
    "project_id": "prj-alfred-mioveni",
    "date": {
      "value": "2037",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "RATEN's 2026 workshop roadmap targets operation in 2037. This is a planning target, not an achieved milestone or granted permission.",
    "sources": [
      "src-raten-alfred-iaea-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-yakutia-hearings-reported-2026",
    "name": "Yakutia: Units 1 and 2 siting-material hearings reported",
    "project_id": "prj-yakutia-ritm",
    "date": {
      "value": "2026-02-27",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Atomnaya energiya reports that public hearings on siting-licence supporting materials for Units 1 and 2 took place on 26 February 2026. The event date here is the report publication. A hearing is not a siting or construction licence. The linked operator original was inaccessible on this review.",
    "sources": [
      "src-atomic-energy-yakutia-hearings-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-yakutia-operation-target-2031",
    "name": "Yakutia: reported operation target",
    "project_id": "prj-yakutia-ritm",
    "date": {
      "value": "2031",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "The 27 February 2026 report gives 2031 as the planned operation year. This reported target is not an operating licence or achieved operation. Rosatom in May 2024 described first-unit launch in 2027 and commissioning in 2028. The February 2026 report concerns a two-unit facility. These are separate dated statements; a directly comparable revision of the same unit and milestone is not established.",
    "sources": [
      "src-atomic-energy-yakutia-hearings-2026",
      "src-atommedia-uzbekistan-contract-20240527"
    ],
    "stated": {
      "value": "2026-02-27",
      "precision": "day"
    },
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-xuwei-preconstruction-inspection-20261009",
    "name": "Xuwei Unit 3: NNSA inspection finds preparations meet construction-licence conditions",
    "summary": "NNSA's report on its 15–18 September 2026 inspection before first concrete for Unit 3, signed 9 October and published 12 October, says the inspection team found that site management and technical preparations met the conditions for issuing a construction licence. It also sets seven corrective requirements. The report does not itself issue a construction licence or establish that first concrete occurred.",
    "sources": [
      "src-nnsa-xuwei-inspection-20261009"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-xuwei-htgr-unit3",
    "date": {
      "value": "2026-10-09",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "reader": {
      "headline": "Xuwei preparations meet construction-licence conditions",
      "what": "NNSA's inspection team found that site management and technical preparations met the conditions for issuing a construction licence, while setting seven corrective requirements.",
      "limit": "The report itself does not issue that licence or establish that first concrete occurred.",
      "date_label": "Report dated",
      "dates_note": "Inspection: 15–18 September. Report published: 12 October."
    }
  },
  {
    "stable_id": "evt-balder-earliest-tests-2028",
    "name": "BALDER: first tests no earlier than 2028",
    "project_id": "prj-psi-copenhagen-atomics",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "PSI’s Q3 2026 planning statement (re-read 10 November 2026) gives an earliest boundary for first tests, not a commitment to tests during 2028. The application and permissions remain pending.",
    "sources": [
      "src-psi-balder-faq"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-alvin-criticality-target-2029-stated-20250312",
    "name": "Alvin: company target for first criticality (March 2025 statement)",
    "project_id": "prj-stellaria-alvin-cadarache",
    "date": {
      "value": "2029",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "first_criticality",
    "summary": "Stellaria's 12 March 2025 description of its development stages planned Alvin, its critical experiment, for 2029. Its 23 April 2026 description gives 2030. A company target, not a regulatory date or achieved milestone.",
    "sources": [
      "src-stellaria-aps-alvin-20250312"
    ],
    "stated": {
      "value": "2025-03-12",
      "precision": "day"
    },
    "confidence": "medium",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "first_criticality",
      "scope": "alvin"
    }
  },
  {
    "stable_id": "evt-alvin-criticality-target-2030",
    "name": "Alvin: company target for first criticality",
    "project_id": "prj-stellaria-alvin-cadarache",
    "date": {
      "value": "2030",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "first_criticality",
    "summary": "Stellaria’s 23 April 2026 programme description targets Alvin criticality in 2030. This is a company target, not a regulatory decision or achieved operation.",
    "sources": [
      "src-stellaria-alpha-20260423"
    ],
    "stated": {
      "value": "2026-04-23",
      "precision": "day"
    },
    "revises": "evt-alvin-criticality-target-2029-stated-20250312",
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "milestone": {
      "key": "first_criticality",
      "scope": "alvin"
    }
  },
  {
    "stable_id": "evt-htr-pm-shidaowan-construction-start-2012-12-09",
    "name": "HTR-PM construction start (IAEA PRIS)",
    "project_id": "prj-htr-pm-shidaowan",
    "date": {
      "value": "2012-12-09",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "HTR-PM construction start (IAEA PRIS).",
    "sources": [
      "src-iaea-pris-stats-cn-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htr-pm-shidaowan-first-criticality-2021-09-12",
    "name": "HTR-PM first criticality (IAEA PRIS unit date)",
    "project_id": "prj-htr-pm-shidaowan",
    "date": {
      "value": "2021-09-12",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_criticality",
    "summary": "HTR-PM first criticality (IAEA PRIS unit date). PRIS lists the twin-module plant as one unit; this is the unit-level first-criticality date.",
    "sources": [
      "src-iaea-pris-stats-cn-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htr-pm-shidaowan-grid-connection-2021-12-14",
    "name": "HTR-PM grid connection",
    "project_id": "prj-htr-pm-shidaowan",
    "date": {
      "value": "2021-12-14",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "grid_connection",
    "summary": "HTR-PM grid connection.",
    "sources": [
      "src-iaea-pris-stats-cn-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-lomonosov-construction-start-2007-04-15",
    "name": "Akademik Lomonosov construction start (both units, IAEA PRIS)",
    "project_id": "prj-lomonosov",
    "date": {
      "value": "2007-04-15",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "Akademik Lomonosov construction start (both units, IAEA PRIS).",
    "sources": [
      "src-iaea-pris-stats-ru-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-lomonosov-first-criticality-2018-11-02",
    "name": "Akademik Lomonosov Unit 1 first criticality",
    "project_id": "prj-lomonosov",
    "date": {
      "value": "2018-11-02",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_criticality",
    "summary": "Akademik Lomonosov Unit 1 first criticality. Unit-level event (unit-lomonosov-1).",
    "sources": [
      "src-iaea-pris-stats-ru-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-lomonosov-first-criticality-2018-11-08",
    "name": "Akademik Lomonosov Unit 2 first criticality",
    "project_id": "prj-lomonosov",
    "date": {
      "value": "2018-11-08",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_criticality",
    "summary": "Akademik Lomonosov Unit 2 first criticality. Unit-level event (unit-lomonosov-2).",
    "sources": [
      "src-iaea-pris-stats-ru-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-lomonosov-grid-connection-2019-12-19",
    "name": "Akademik Lomonosov grid connection (both units)",
    "project_id": "prj-lomonosov",
    "date": {
      "value": "2019-12-19",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "grid_connection",
    "summary": "Akademik Lomonosov grid connection (both units).",
    "sources": [
      "src-iaea-pris-stats-ru-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-lomonosov-commercial-operation-2020-05-22",
    "name": "Akademik Lomonosov commercial operation (both units)",
    "project_id": "prj-lomonosov",
    "date": {
      "value": "2020-05-22",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "commercial_operation",
    "summary": "Akademik Lomonosov commercial operation (both units). The project field commercial_operation already holds this date; the record has no event row for it.",
    "sources": [
      "src-iaea-pris-stats-ru-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-linglong-one-construction-start-2021-07-13",
    "name": "Linglong-1 construction start (IAEA PRIS)",
    "project_id": "prj-linglong-one",
    "date": {
      "value": "2021-07-13",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "Linglong-1 construction start (IAEA PRIS).",
    "sources": [
      "src-iaea-pris-stats-cn-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natrium-kemmerer-regulatory-step-2024-05-21",
    "name": "NRC dockets Kemmerer Unit 1 construction permit application",
    "project_id": "prj-natrium-kemmerer",
    "date": {
      "value": "2024-05-21",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "NRC dockets Kemmerer Unit 1 construction permit application.",
    "sources": [
      "src-det-331ef88455"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natrium-kemmerer-other-2026-03-04",
    "name": "NRC mandatory hearing on Kemmerer Unit 1 construction permit",
    "project_id": "prj-natrium-kemmerer",
    "date": {
      "value": "2026-03-04",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NRC mandatory hearing on Kemmerer Unit 1 construction permit.",
    "sources": [
      "src-det-331ef88455"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-hermes-1-regulatory-step-2021-11-29",
    "name": "NRC dockets Hermes construction permit application",
    "project_id": "prj-hermes-1",
    "date": {
      "value": "2021-11-29",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "NRC dockets Hermes construction permit application.",
    "sources": [
      "src-det-1c00152982"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-hermes-1-groundbreaking-2024-07",
    "name": "Kairos breaks ground at the Hermes site",
    "project_id": "prj-hermes-1",
    "date": {
      "value": "2024-07",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "groundbreaking",
    "summary": "Kairos breaks ground at the Hermes site.",
    "sources": [
      "src-det-f24a3b10b0"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-hermes-1-construction-start-2025-05-01",
    "name": "Hermes nuclear safety-related construction begins",
    "project_id": "prj-hermes-1",
    "date": {
      "value": "2025-05-01",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "Kairos's 8 May 2025 release says safety-related construction started on 1 May 2025, focused on the building foundation. Its letter to the NRC dated 1 May 2025, required by permit condition 3.D, says excavation for the first drilled pier of the safety-related foundation began that day. Company statements; the first safety-related concrete is a separate event.",
    "sources": [
      "src-det-f24a3b10b0",
      "src-kairos-hermes-excavation-notice-20250501"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-hermes-1-first-concrete-2025-05",
    "name": "First nuclear safety-related concrete at Hermes",
    "project_id": "prj-hermes-1",
    "date": {
      "value": "2025-05",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "first_concrete",
    "summary": "First nuclear safety-related concrete at Hermes. Release dated 8 May 2025 reports the pour as completed; exact pour day not stated.",
    "sources": [
      "src-det-f24a3b10b0"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-hermes-2-regulatory-step-2023-09-11",
    "name": "NRC dockets Hermes 2 construction permit application",
    "project_id": "prj-hermes-2",
    "date": {
      "value": "2023-09-11",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "NRC dockets Hermes 2 construction permit application.",
    "sources": [
      "src-det-b1d2a212a5"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-long-mott-regulatory-step-2025-05-12",
    "name": "NRC dockets Long Mott construction permit application",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2025-05-12",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "NRC dockets Long Mott construction permit application.",
    "sources": [
      "src-nrc-longmott-page-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-clinch-river-bwrx-regulatory-step-2025-05-20",
    "name": "TVA submits construction permit application Part Two (PSAR)",
    "project_id": "prj-clinch-river-bwrx",
    "date": {
      "value": "2025-05-20",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "TVA submits construction permit application Part Two (PSAR).",
    "sources": [
      "src-nrc-clinch-river-cpa"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-clinch-river-bwrx-regulatory-step-2025-07-09",
    "name": "NRC completes PSAR acceptance review (application docketed)",
    "project_id": "prj-clinch-river-bwrx",
    "date": {
      "value": "2025-07-09",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "NRC completes PSAR acceptance review (application docketed).",
    "sources": [
      "src-nrc-clinch-river-cpa"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-clinch-river-bwrx-other-2026-08-13",
    "name": "NRC mandatory hearing on Clinch River construction permit",
    "project_id": "prj-clinch-river-bwrx",
    "date": {
      "value": "2026-08-13",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NRC mandatory hearing on Clinch River construction permit.",
    "sources": [
      "src-nrc-clinch-river-cpa"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "NRC holds mandatory hearing on Clinch River construction permit",
      "what": "The NRC held a mandatory hearing on the Clinch River construction permit for TVA's BWRX-300."
    }
  },
  {
    "stable_id": "evt-aurora-inl-construction-start-2025",
    "name": "Oklo-reported Aurora-INL construction start",
    "project_id": "prj-aurora-inl",
    "date": {
      "value": "2025",
      "precision": "year",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "Oklo-reported Aurora-INL construction start. Company statement. DOE CX-035336 (Dec 2025) covered non-nuclear site/support construction with no reactor components; do not read as nuclear construction.",
    "sources": [
      "src-oklo-idaho-aurora-20261007"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aurora-inl-commercial-operation-2028",
    "name": "Aurora-INL commercial deployment target",
    "project_id": "prj-aurora-inl",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "commercial_operation",
    "summary": "Aurora-INL commercial deployment target of 2028 on Oklo's undated Idaho page, read on 7 October and 11 November 2026. Oklo's report on Form 10-Q signed 6 November 2026 gives a target of 2028-2029 for deploying its first powerhouse at INL, where its report signed 7 August 2026 gave 2028. Company targets, not an achieved milestone.",
    "sources": [
      "src-oklo-idaho-aurora-20261007",
      "src-oklo-10q-20261106",
      "src-oklo-10q-20260807"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-brest-od-300-regulatory-step-2021-02-10",
    "name": "Rostekhnadzor construction licence for BREST-OD-300 issued to Siberian Chemical Combine",
    "project_id": "prj-brest-od-300",
    "date": {
      "value": "2021-02-10",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "Rostekhnadzor construction licence for BREST-OD-300 issued to Siberian Chemical Combine. Date from IAEA PRIS constructionLicenseDate; WNN (11 Feb 2021) says the licence was signed 'yesterday'. Official Rostekhnadzor instrument not opened, so recorded as an event, not a regulatory action.",
    "sources": [
      "src-det-a2d326130d"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-brest-od-300-construction-start-2021-06-08",
    "name": "BREST-OD-300 construction start (IAEA PRIS)",
    "project_id": "prj-brest-od-300",
    "date": {
      "value": "2021-06-08",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "BREST-OD-300 construction start (IAEA PRIS).",
    "sources": [
      "src-iaea-pris-stats-ru-20261009"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-brest-od-300-other-2026-09-14",
    "name": "First stage of concreting the BREST-OD-300 reactor-vessel inner cavity completed (TVEL release)",
    "project_id": "prj-brest-od-300",
    "date": {
      "value": "2026-09-14",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "First stage of concreting the BREST-OD-300 reactor-vessel inner cavity completed (TVEL release). Date is the release date; the release does not give the completion day. Company statement relayed by atomic-energy.ru.",
    "sources": [
      "src-tvel-brest-concreting-20260914"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "TVEL: first stage of concreting BREST-OD-300 reactor-vessel inner cavity completed",
      "what": "TVEL said the first stage of concreting the BREST-OD-300 reactor-vessel inner cavity at Seversk was completed.",
      "date_label": "Release dated",
      "dates_note": "The release does not give the completion day."
    }
  },
  {
    "stable_id": "evt-brest-od-300-other-2027",
    "name": "Concreting of the BREST-OD-300 reactor vessel to finish (company target)",
    "project_id": "prj-brest-od-300",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Concreting of the BREST-OD-300 reactor vessel to finish (company target). Source says 'winter 2027' (season precision not supported by schema). A target, not an achieved milestone.",
    "sources": [
      "src-tvel-brest-concreting-20260914"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ritm-jizzakh-other-2026-03-24",
    "name": "Concrete works begin on foundation preparation for the small (RITM-200N) unit, same day as supplementary agreement",
    "project_id": "prj-ritm-jizzakh",
    "date": {
      "value": "2026-03-24",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Concrete works begin on foundation preparation for the small (RITM-200N) unit, same day as supplementary agreement. Levelling/waterproofing/earthing works (~900 m3 of concrete); not first nuclear (safety-related) concrete.",
    "sources": [
      "src-strana-rosatom-uzbekistan-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ritm-jizzakh-other-2026-06",
    "name": "First concrete poured for the foundation of the first RITM-200N unit (Uzatom)",
    "project_id": "prj-ritm-jizzakh",
    "date": {
      "value": "2026-06-04",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_concrete",
    "summary": "Uzatom reports that at a ceremony on 4 June 2026 in Farish district, first concrete was poured for the foundation of the first unit with a RITM-200N reactor: 133 cubic metres at the initial stage of more than 10,000. It says the pour gives the plant official under-construction status. The regulator decided the same day to issue the unit's construction licence. World Nuclear News dates its report 5 June.",
    "sources": [
      "src-d3-uzatom-first-concrete-20260604",
      "src-d3-wnn-jizzakh-first-concrete-20260605"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "reader": {
      "headline": "First concrete poured for Uzbekistan's first RITM-200N unit",
      "what": "Uzbekistan's atomic energy agency says first concrete was poured into the first SMR unit's foundation on 4 June 2026, after the regulator decided to licence its construction.",
      "limit": "This covers the first SMR unit only; the second unit has no reported construction licence."
    }
  },
  {
    "stable_id": "evt-ritm-jizzakh-first-criticality-2029",
    "name": "First criticality of first RITM-200N unit (expected late 2029)",
    "project_id": "prj-ritm-jizzakh",
    "date": {
      "value": "2029",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "first_criticality",
    "summary": "First criticality of first RITM-200N unit (expected late 2029). Source says 'late 2029'. A target, not an achieved milestone.",
    "sources": [
      "src-wna-uzbekistan"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-holtec-palisades-regulatory-step-2026-02-13",
    "name": "NRC finds Part 1 of the Pioneer phased CP application (with LWA request) acceptable for docketing",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2026-02-13",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "NRC finds Part 1 of the Pioneer phased CP application (with LWA request) acceptable for docketing.",
    "sources": [
      "src-det-430600b26e"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-holtec-palisades-other-2026-08-31",
    "name": "NRC draft safety evaluation report (with information gaps) completed",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2026-08-31",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NRC draft safety evaluation report (with information gaps) completed.",
    "sources": [
      "src-nrc-holtec-pioneer-page"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "NRC completes draft safety evaluation report for Pioneer, with information gaps",
      "what": "The NRC completed a draft safety evaluation report, with information gaps, for Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)."
    }
  },
  {
    "stable_id": "evt-holtec-palisades-other-2026-12-31",
    "name": "Applicant-requested date for LWA and 10 CFR 50.10(d) exemption issuance",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2026-12-31",
      "precision": "day",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Applicant-requested date for LWA and 10 CFR 50.10(d) exemption issuance. Applicant's requested review schedule, not an NRC commitment. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-pioneer-general-financial-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-holtec-palisades-construction-start-2028-4",
    "name": "Start of full-scope nuclear construction (applicant expectation)",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2028-Q4",
      "precision": "quarter",
      "basis": "target"
    },
    "event_type": "construction_start",
    "summary": "Start of full-scope nuclear construction (applicant expectation). Conditional on Part 2 submittal and NRC construction-permit issuance. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-pioneer-general-financial-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-holtec-palisades-other-2031",
    "name": "Construction of both Pioneer units completed (applicant expectation)",
    "project_id": "prj-holtec-palisades",
    "date": {
      "value": "2031",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Construction of both Pioneer units completed (applicant expectation). A target, not an achieved milestone.",
    "sources": [
      "src-nrc-pioneer-general-financial-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pele-inl-other-2025-11-05",
    "name": "Pele TRISO core (40,000 fuel compacts) delivered to INL TREAT facility (day per INL)",
    "project_id": "prj-pele-inl",
    "date": {
      "value": "2025-11-05",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Pele TRISO core (40,000 fuel compacts) delivered to INL TREAT facility (day per INL). Refines the existing month-precision fuel-delivery event (2025-11). ANS relays INL; the Army article of 3 Dec 2025 ('this week') is an announcement date, not the delivery day.",
    "sources": [
      "src-det-f5a96717a0"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pele-inl-other-2025-07",
    "name": "BWXT core assembly production began",
    "project_id": "prj-pele-inl",
    "date": {
      "value": "2025-07",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "BWXT core assembly production began.",
    "sources": [
      "src-bwxt-pele-page-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pele-inl-other-2026-06",
    "name": "Pele core stacking complete (BWXT)",
    "project_id": "prj-pele-inl",
    "date": {
      "value": "2026-06",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Pele core stacking complete (BWXT).",
    "sources": [
      "src-bwxt-pele-page-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pele-inl-other-2027",
    "name": "Formal Pele system testing (BWXT plan, as early as)",
    "project_id": "prj-pele-inl",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Formal Pele system testing (BWXT plan, as early as). A target, not an achieved milestone.",
    "sources": [
      "src-det-f5a96717a0"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-pele-inl-other-2028",
    "name": "Pele first electricity at INL (BWXT plan, as soon as)",
    "project_id": "prj-pele-inl",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "electricity_generation",
    "summary": "Pele first electricity at INL (BWXT plan, as soon as). A target, not an achieved milestone.",
    "sources": [
      "src-det-f5a96717a0"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-yakutia-ritm-regulatory-step-2023-04-21",
    "name": "Rostekhnadzor issues Rosenergoatom a siting licence for the Yakutia land-based SMR (Ust-Yansky ulus) (reported)",
    "project_id": "prj-yakutia-ritm",
    "date": {
      "value": "2023-04-21",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "Rostekhnadzor issues Rosenergoatom a siting licence for the Yakutia land-based SMR (Ust-Yansky ulus) (reported). Rosatom corporate newspaper report; licence instrument not opened. URL slug says 'construction' but text says siting (razmeshchenie). Station-level siting licence; Feb 2026 hearings covered unit-level siting-licence materials for Units 1 and 2.",
    "sources": [
      "src-strana-yakutia-siting-2023"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-baimsky-floating-other-2026-05",
    "name": "First RITM-200S reactor for the first PEB-106 floating unit manufactured",
    "project_id": "prj-baimsky-floating",
    "date": {
      "value": "2026-05",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "First RITM-200S reactor for the first PEB-106 floating unit manufactured.",
    "sources": [
      "src-strana-rosatom-ritm200s-set-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-baimsky-floating-other-2026-09-24",
    "name": "Second RITM-200S completed at ZiO-Podolsk, completing the reactor set for the first PEB-106",
    "project_id": "prj-baimsky-floating",
    "date": {
      "value": "2026-09-24",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Second RITM-200S completed at ZiO-Podolsk, completing the reactor set for the first PEB-106. Date is the publication date; completion day not stated.",
    "sources": [
      "src-strana-rosatom-ritm200s-set-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "Second RITM-200S completed at ZiO-Podolsk for the first PEB-106",
      "what": "The second RITM-200S was completed at ZiO-Podolsk, completing the reactor set for the first PEB-106 floating unit for Baim / Cape Nagloynyn.",
      "date_label": "Published",
      "dates_note": "Completion day not stated."
    }
  },
  {
    "stable_id": "evt-baimsky-first-unit-target-2027-stated-20220831",
    "name": "First Baimsky floating unit: reported power-service target (August 2022)",
    "project_id": "prj-baimsky-floating",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "At the August 2022 keel-laying, WNN reported that the first unit would supply power at Cape Nagloynyn by 2027. An Interfax report of 13 August 2026 states, in its own background note, that the first unit is expected to be put into service in 2028. A target, not an achieved milestone.",
    "sources": [
      "src-d3-wnn-baim-keel-20220831"
    ],
    "stated": {
      "value": "2022-08-31",
      "precision": "day"
    },
    "confidence": "medium",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "power_service",
      "scope": "first_floating_power_unit"
    }
  },
  {
    "stable_id": "evt-baimsky-floating-commercial-operation-2028",
    "name": "First Baimsky floating unit: reported power-service target",
    "project_id": "prj-baimsky-floating",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "First of four Baimsky floating power units commissioned (target). 'введут первый блок' = put into service; exact milestone type (commissioning vs commercial operation) not specified. A target, not an achieved milestone.",
    "sources": [
      "src-interfax-baimsky-units"
    ],
    "stated": {
      "value": "2026-08-13",
      "precision": "day"
    },
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-baimsky-floating-commercial-operation-2031",
    "name": "Fourth Baimsky floating power unit commissioned (target)",
    "project_id": "prj-baimsky-floating",
    "date": {
      "value": "2031",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "commercial_operation",
    "summary": "Fourth Baimsky floating power unit commissioned (target). A target, not an achieved milestone.",
    "sources": [
      "src-interfax-baimsky-units"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aalo-x-inl-other-2026-03-03",
    "name": "DOE approves the Aalo-X preliminary documented safety analysis",
    "project_id": "prj-aalo-x-inl",
    "date": {
      "value": "2026-03-03",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "DOE approves the Aalo-X preliminary documented safety analysis.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aalo-x-inl-other-2027",
    "name": "Aalo-X full-power test (30 MWth, ~10 MWe) planned",
    "project_id": "prj-aalo-x-inl",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Aalo-X full-power test (30 MWth, ~10 MWe) planned. Full-power test is beyond the zero-power critical assembly covered by CX-271002. A target, not an achieved milestone.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-antares-mark0-inl-other-2026-01",
    "name": "DOE approves the Antares Mark-0 preliminary documented safety analysis",
    "project_id": "prj-antares-mark0-inl",
    "date": {
      "value": "2026-01",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "DOE approves the Antares Mark-0 preliminary documented safety analysis.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-unity-inl-other-2026-05-22",
    "name": "DOE approves the Unity critical experiment preliminary documented safety analysis",
    "project_id": "prj-unity-inl",
    "date": {
      "value": "2026-05-22",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "DOE approves the Unity critical experiment preliminary documented safety analysis.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-unity-inl-other-2026",
    "name": "Unity reactor-physics testing incl. passive shutdown and decay-heat tests (planned)",
    "project_id": "prj-unity-inl",
    "date": {
      "value": "2026",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Unity reactor-physics testing incl. passive shutdown and decay-heat tests (planned). A target, not an achieved milestone.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward-250-other-2025-11-17",
    "name": "Project Nova: Valar zero-power test core operated by Los Alamos at NCERC (Nevada)",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2025-11-17",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Project Nova: Valar zero-power test core operated by Los Alamos at NCERC (Nevada). A separate zero-power test core proving Ward 250 physics, not the Ward 250 reactor itself.",
    "sources": [
      "src-valar-castle-country-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward-250-other-2026-02-15",
    "name": "Operation Windlord: Ward 250 modules airlifted by C-17 to Hill AFB, then trucked to Emery County",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2026-02-15",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Operation Windlord: Ward 250 modules airlifted by C-17 to Hill AFB, then trucked to Emery County.",
    "sources": [
      "src-valar-castle-country-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward-250-other-2026-02",
    "name": "DOE approves the Ward 250 preliminary documented safety analysis",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2026-02",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "DOE approves the Ward 250 preliminary documented safety analysis.",
    "sources": [
      "src-doe-rpp-update-202607"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward-250-other-2026-06-26",
    "name": "Ward 250 passive-safety demonstration: shutdown with all active cooling off and simulated total loss of power",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2026-06-26",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Ward 250 passive-safety demonstration: shutdown with all active cooling off and simulated total loss of power. Supplies the date the IAEA outlook omits for the loss-of-forced-cooling demonstration (company statement).",
    "sources": [
      "src-valar-castle-country-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ward-250-other-2026-07-01",
    "name": "Ward 250 first electricity",
    "project_id": "prj-ward-250",
    "date": {
      "value": "2026-07-01",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "electricity_generation",
    "summary": "Valar says Ward 250 generated its first electricity on 1 July 2026 and that the electricity directly powered an NVIDIA chip. DOE's Reactor Pilot Program update says full power of 100 kWt, with the electricity used to power an NVIDIA Spark, on 2 July 2026. Both dates are kept. Neither source states a kilowatt-electric rating or a grid connection.",
    "sources": [
      "src-valar-castle-country-2026",
      "src-doe-rpp-update-202607"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-15",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-last-energy-rellis-construction-start-2026",
    "name": "Last Energy states it began PWR-5 construction at RELLIS",
    "project_id": "prj-last-energy-rellis",
    "date": {
      "value": "2026",
      "precision": "year",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "Last Energy states it began PWR-5 construction at RELLIS.",
    "sources": [
      "src-last-energy-pwr5-pdsa-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-last-energy-rellis-other-2025-08",
    "name": "Last Energy selected for DOE's Reactor Pilot Program",
    "project_id": "prj-last-energy-rellis",
    "date": {
      "value": "2025-08",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Last Energy selected for DOE's Reactor Pilot Program.",
    "sources": [
      "src-last-energy-pwr5-pdsa-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-sealer-untra-other-2026-08-28",
    "name": "Government assigns Uppsala county administrative board to draft a facility plan for Untra",
    "project_id": "prj-sealer-untra",
    "date": {
      "value": "2026-08-28",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Government assigns Uppsala county administrative board to draft a facility plan for Untra.",
    "sources": [
      "src-se-gov-untra-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "Government assigns Uppsala county administrative board to draft Untra facility plan",
      "what": "The Government assigned the Uppsala county administrative board to draft a facility plan for Untra."
    }
  },
  {
    "stable_id": "evt-sealer-untra-other-2027-04-30",
    "name": "Untra facility plan proposal due to the Government",
    "project_id": "prj-sealer-untra",
    "date": {
      "value": "2027-04-30",
      "precision": "day",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Untra facility plan proposal due to the Government. A target, not an achieved milestone.",
    "sources": [
      "src-se-gov-untra-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-sealer-untra-other-2026-08-31",
    "name": "Untra Nuclear Power AB applies for Swedish state support",
    "project_id": "prj-sealer-untra",
    "date": {
      "value": "2026-08-31",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Untra Nuclear Power AB applies for Swedish state support.",
    "sources": [
      "src-det-411fde0e36"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "Untra Nuclear Power AB applies for Swedish state support",
      "what": "Untra Nuclear Power AB applied for Swedish state support."
    }
  },
  {
    "stable_id": "evt-sealer-norrsundet-other-2026-05-28",
    "name": "Government assigns Gävleborg county administrative board to draft a facility plan for Norrsundet",
    "project_id": "prj-sealer-norrsundet",
    "date": {
      "value": "2026-05-28",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Government assigns Gävleborg county administrative board to draft a facility plan for Norrsundet.",
    "sources": [
      "src-se-gov-norrsundet-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-sealer-norrsundet-other-2026-12-31",
    "name": "Norrsundet facility plan proposal due to the Government",
    "project_id": "prj-sealer-norrsundet",
    "date": {
      "value": "2026-12-31",
      "precision": "day",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Norrsundet facility plan proposal due to the Government. A target, not an achieved milestone.",
    "sources": [
      "src-se-gov-norrsundet-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-sealer-norrsundet-other-2026-06-05",
    "name": "Government receives Blykalla's state-support application for Norrsundet",
    "project_id": "prj-sealer-norrsundet",
    "date": {
      "value": "2026-06-05",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Government receives Blykalla's state-support application for Norrsundet.",
    "sources": [
      "src-next-blykalla-finance"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-belews-creek-other-2026-07",
    "name": "NRC draft safety evaluation sections completed for the Belews Creek ESP",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-07",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NRC draft safety evaluation sections completed for the Belews Creek ESP.",
    "sources": [
      "src-det-3a47471b58"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-belews-creek-other-2026-09-29",
    "name": "NRC fixed-fee-cap letter and updated review schedule for the Belews Creek ESP",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-09-29",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "schedule_change",
    "summary": "NRC letter ML26259A008, dated 29 September 2026 and signed by Michelle W. Hayes, sets a $2,178,000 fixed cap on NRC review fees for the Belews Creek early site permit. The cap is a service-fee limit, not a project cost, a permit or a design selection. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The same letter accelerates the 8 February 2026 acceptance-letter schedule (ML26016A624): advanced final safety evaluation report without open items from March 2027 to December 2026; final safety evaluation report from May 2027 to February 2027; draft environmental impact statement from February 2027 to December 2026; final environmental impact statement from May 2027 to March 2027. The revised dates remain targets.",
    "sources": [
      "src-det-3a47471b58",
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "reader": {
      "headline": "NRC caps Belews Creek review fees and brings forward its review schedule",
      "what": "An NRC letter sets a $2,178,000 fixed cap on NRC review fees for the Belews Creek early site permit, a service-fee limit rather than a project cost, and accelerates the review schedule.",
      "limit": "The revised review dates remain targets.",
      "date_label": "Letter dated",
      "dates_note": "Moved earlier: advanced final safety evaluation report and draft environmental impact statement to December 2026; final safety evaluation report to February 2027; final environmental impact statement to March 2027."
    }
  },
  {
    "stable_id": "evt-belews-creek-other-2026-10-01",
    "name": "Duke submits Revision 2 of the Belews Creek ESP application",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-10-01",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "Duke Energy Carolinas letter RA-26-0157 (ML26274A437), dated 1 October 2026, submits Revision 2 of the Belews Creek early site permit application in response to regulatory-audit questions. The letter states that Duke is not requesting a limited work authorization, so no Site Redress Plan under 10 CFR 52.17(c) is provided. Parts 2, 3, 5 and 10 were revised for audit items; Parts 7 and 8 were unchanged. Revision 2 is an applicant filing, not an NRC permit, a design selection or a construction start.",
    "sources": [
      "src-det-3a47471b58",
      "src-duke-belews-esp-rev2-20261001"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "reader": {
      "headline": "Duke files Revision 2 of its Belews Creek early site permit application",
      "what": "Duke Energy Carolinas submitted Revision 2 of the Belews Creek early site permit application in response to regulatory-audit questions. Duke states it is not requesting a limited work authorization.",
      "limit": "Revision 2 is an applicant filing, not an NRC permit, a design selection or a construction start.",
      "date_label": "Letter dated"
    }
  },
  {
    "stable_id": "evt-belews-creek-afser-target-20260208",
    "name": "NRC target: advanced final safety evaluation report without open items for the Belews Creek ESP (February 2026 schedule)",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2027-03",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "The NRC's acceptance-review letter dated 8 February 2026 (ML26016A624) estimated the advanced final safety evaluation report without open items for March 2027, as tabulated in the NRC's 29 September 2026 schedule letter. That letter revised the estimate to December 2026. The February letter itself was not opened here. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-02-08",
      "precision": "day"
    },
    "confidence": "high",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "advanced_final_safety_evaluation",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-other-2026-12",
    "name": "NRC target: advanced final safety evaluation report without open items for the Belews Creek ESP",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-12",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "NRC target: advanced final safety evaluation report without open items for the Belews Creek ESP in December 2026, accelerated from March 2027 by the 29 September 2026 schedule letter. A target, not an achieved milestone.",
    "sources": [
      "src-det-3a47471b58",
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-09-29",
      "precision": "day"
    },
    "revises": "evt-belews-creek-afser-target-20260208",
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "milestone": {
      "key": "advanced_final_safety_evaluation",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-draft-eis-target-20260208",
    "name": "NRC target: draft environmental impact statement for the Belews Creek ESP (February 2026 schedule)",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2027-02",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "The NRC's acceptance-review letter dated 8 February 2026 (ML26016A624) estimated the draft environmental impact statement for February 2027, as tabulated in the NRC's 29 September 2026 schedule letter. That letter revised the estimate to December 2026. The February letter itself was not opened here. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-02-08",
      "precision": "day"
    },
    "confidence": "high",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "draft_environmental_impact_statement",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-draft-eis-2026-12",
    "name": "NRC target: draft environmental impact statement for the Belews Creek ESP",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2026-12",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "NRC target: draft environmental impact statement for the Belews Creek ESP in December 2026, accelerated from February 2027 by the 29 September 2026 schedule letter. A target, not an achieved milestone.",
    "sources": [
      "src-det-3a47471b58",
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-09-29",
      "precision": "day"
    },
    "revises": "evt-belews-creek-draft-eis-target-20260208",
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "milestone": {
      "key": "draft_environmental_impact_statement",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-final-se-target-20260208",
    "name": "NRC target: final safety evaluation for the Belews Creek ESP (February 2026 schedule)",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2027-05",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "The NRC's acceptance-review letter dated 8 February 2026 (ML26016A624) estimated the final safety evaluation for May 2027, as tabulated in the NRC's 29 September 2026 schedule letter. That letter revised the estimate to February 2027. The February letter itself was not opened here. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-02-08",
      "precision": "day"
    },
    "confidence": "high",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "final_safety_evaluation",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-other-2027-02",
    "name": "NRC target: final safety evaluation for the Belews Creek ESP",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2027-02",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "NRC target: final safety evaluation for the Belews Creek ESP in February 2027, accelerated from May 2027 by the 29 September 2026 schedule letter. A target, not an achieved milestone.",
    "sources": [
      "src-det-3a47471b58",
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-09-29",
      "precision": "day"
    },
    "revises": "evt-belews-creek-final-se-target-20260208",
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "milestone": {
      "key": "final_safety_evaluation",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-final-eis-target-20260208",
    "name": "NRC target: final environmental impact statement for the Belews Creek ESP (February 2026 schedule)",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2027-05",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "The NRC's acceptance-review letter dated 8 February 2026 (ML26016A624) estimated the final environmental impact statement for May 2027, as tabulated in the NRC's 29 September 2026 schedule letter. That letter revised the estimate to March 2027. The February letter itself was not opened here. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-02-08",
      "precision": "day"
    },
    "confidence": "high",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "final_environmental_impact_statement",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-other-2027-03",
    "name": "NRC target: final environmental impact statement for the Belews Creek ESP",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2027-03",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "NRC target: final environmental impact statement for the Belews Creek ESP in March 2027, accelerated from May 2027 by the 29 September 2026 schedule letter. A target, not an achieved milestone.",
    "sources": [
      "src-det-3a47471b58",
      "src-nrc-belews-esp-fee-schedule-20260929"
    ],
    "stated": {
      "value": "2026-09-29",
      "precision": "day"
    },
    "revises": "evt-belews-creek-final-eis-target-20260208",
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "milestone": {
      "key": "final_environmental_impact_statement",
      "scope": "early_site_permit"
    }
  },
  {
    "stable_id": "evt-belews-creek-commercial-operation-2036",
    "name": "Duke conditional plan: first SMR on line at Belews Creek in 2036",
    "project_id": "prj-belews-creek",
    "date": {
      "value": "2036",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "commercial_operation",
    "summary": "Duke conditional plan: first SMR on line at Belews Creek in 2036. A target, not an achieved milestone.",
    "sources": [
      "src-parent-duke-belews"
    ],
    "confidence": "low",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-radiant-kaleidos-inl-other-2026-07-01",
    "name": "Radiant receives first TRISO fuel tranche at INL's DOME facility",
    "project_id": "prj-radiant-kaleidos-inl",
    "date": {
      "value": "2026-07-01",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Radiant receives first TRISO fuel tranche at INL's DOME facility.",
    "sources": [
      "src-det-e55d1bc90b"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-radiant-kaleidos-inl-other-2026-08",
    "name": "Kaleidos reactor ships from El Segundo to INL",
    "project_id": "prj-radiant-kaleidos-inl",
    "date": {
      "value": "2026-08",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Kaleidos reactor ships from El Segundo to INL.",
    "sources": [
      "src-det-bebb12db6e"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "Radiant's Kaleidos reactor ships from El Segundo to INL",
      "what": "Radiant's Kaleidos reactor shipped from El Segundo to INL."
    }
  },
  {
    "stable_id": "evt-radiant-kaleidos-inl-other-2026-3",
    "name": "Radiant target: 150-hour continuous full-power run at DOME",
    "project_id": "prj-radiant-kaleidos-inl",
    "date": {
      "value": "2026-Q3",
      "precision": "quarter",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Radiant target: 150-hour continuous full-power run at DOME. A target, not an achieved milestone.",
    "sources": [
      "src-det-bebb12db6e"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natura-msr-1-acu-regulatory-step-2022-08-12",
    "name": "ACU submits construction permit application for the Molten Salt Research Reactor",
    "project_id": "prj-natura-msr-1-acu",
    "date": {
      "value": "2022-08-12",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "ACU submits construction permit application for the Molten Salt Research Reactor.",
    "sources": [
      "src-nrc-msrr-acu-application"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natura-msr-1-acu-regulatory-step-2022-11-28",
    "name": "Federal Register notice: NRC accepts and dockets the ACU construction permit application",
    "project_id": "prj-natura-msr-1-acu",
    "date": {
      "value": "2022-11-28",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "Federal Register notice: NRC accepts and dockets the ACU construction permit application.",
    "sources": [
      "src-det-c80f6bace0"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natura-msr-1-acu-other-2024-03-14",
    "name": "NRC issues environmental assessment and FONSI for the ACU construction permit",
    "project_id": "prj-natura-msr-1-acu",
    "date": {
      "value": "2024-03-14",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NRC issues environmental assessment and FONSI for the ACU construction permit.",
    "sources": [
      "src-nrc-msrr-acu-application"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natura-msr-1-acu-other-2025",
    "name": "Natura (MSR-1) selected for DOE's Reactor Pilot Program",
    "project_id": "prj-natura-msr-1-acu",
    "date": {
      "value": "2025",
      "precision": "year",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Natura (MSR-1) selected for DOE's Reactor Pilot Program.",
    "sources": [
      "src-det-32258ccb67"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natura-msr-1-acu-announcement-2026-07-21",
    "name": "Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1",
    "project_id": "prj-natura-msr-1-acu",
    "date": {
      "value": "2026-07-21",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1.",
    "sources": [
      "src-det-a8049e0a9b"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-natura-msr-1-acu-other-2026-09-18",
    "name": "Natura receives FLiBe coolant salt for MSR-1",
    "project_id": "prj-natura-msr-1-acu",
    "date": {
      "value": "2026-09-18",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "DOE says more than 4,700 pounds of FLiBe salt, once the coolant of Oak Ridge's Molten Salt Reactor Experiment, arrived at Natura's facility at Abilene Christian University on 18 September 2026 for MSR-1, shipped with Oak Ridge and Idaho national laboratories; Natura's release gives the same delivery date. A salt delivery is not fuel loading, criticality or operation.",
    "sources": [
      "src-det-706340d765",
      "src-doe-natura-flibe-20260922"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "FLiBe coolant salt arrives at Natura's MSR-1 facility at Abilene Christian University",
      "what": "DOE says more than 4,700 pounds of FLiBe salt, once the coolant of Oak Ridge's Molten Salt Reactor Experiment, arrived at Natura's facility for MSR-1, shipped with Oak Ridge and Idaho national laboratories.",
      "limit": "A salt delivery is not fuel loading, criticality or operation."
    }
  },
  {
    "stable_id": "evt-uiuc-kronos-other-2026-06-23",
    "name": "NRC formal review activities begin for the KRONOS construction permit application",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2026-06-23",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NRC formal review activities begin for the KRONOS construction permit application.",
    "sources": [
      "src-det-22fc57f7df"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-construction-start-2027",
    "name": "NANO expectation: initial construction activities at U. of I. in the second half of 2027",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "construction_start",
    "summary": "NANO expectation: initial construction activities at U. of I. in the second half of 2027. A target, not an achieved milestone.",
    "sources": [
      "src-det-22fc57f7df"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-other-2029",
    "name": "U. of I. expectation: system on-line in 2029–2030",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2029",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "U. of I. expectation: system on-line in 2029–2030. A target, not an achieved milestone.",
    "sources": [
      "src-det-d2e4678b10"
    ],
    "confidence": "low",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-blue-energy-victoria-commercial-operation-2032",
    "name": "Blue Energy target: five BWRX-300 units on line in 2032",
    "project_id": "prj-blue-energy-victoria",
    "date": {
      "value": "2032",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "commercial_operation",
    "summary": "Blue Energy target: five BWRX-300 units on line in 2032. A target, not an achieved milestone.",
    "sources": [
      "src-ans-blue-energy-five-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-blue-energy-victoria-regulatory-step-2027",
    "name": "Blue Energy target: submit the remaining construction permit application (Part 2) in 2027",
    "project_id": "prj-blue-energy-victoria",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "regulatory_step",
    "summary": "Blue Energy target: submit the remaining construction permit application (Part 2) in 2027. A target, not an achieved milestone.",
    "sources": [
      "src-gevh-blue-energy-victoria-20260916"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-knxt-valdemarsvik-other-2025-02-18",
    "name": "Kärnfull Next secures permanent land rights for an SMR park at Målma",
    "project_id": "prj-knxt-valdemarsvik",
    "date": {
      "value": "2025-02-18",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Kärnfull Next secures permanent land rights for an SMR park at Målma.",
    "sources": [
      "src-knxt-news"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-knxt-valdemarsvik-other-2026-05-08",
    "name": "Government assigns Östergötland county administrative board to draft a facility plan for Målma",
    "project_id": "prj-knxt-valdemarsvik",
    "date": {
      "value": "2026-05-07",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Government assigns Östergötland county administrative board to draft a facility plan for Målma.",
    "sources": [
      "src-se-gov-malma-plan-2026",
      "src-se-gov-studsvik-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-knxt-valdemarsvik-other-2026-12-31",
    "name": "Målma facility plan proposal due to the Government",
    "project_id": "prj-knxt-valdemarsvik",
    "date": {
      "value": "2026-12-31",
      "precision": "day",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Målma facility plan proposal due to the Government. A target, not an achieved milestone.",
    "sources": [
      "src-se-gov-malma-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-knxt-valdemarsvik-other-2026-05-11",
    "name": "Studsvik completes its acquisition of Kärnfull Next",
    "project_id": "prj-knxt-valdemarsvik",
    "date": {
      "value": "2026-05-11",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Studsvik completes its acquisition of Kärnfull Next.",
    "sources": [
      "src-knxt-news"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-knxt-valdemarsvik-other-2026-06-12",
    "name": "Government receives Studsvik's state-support application covering Valdemarsvik and Nyköping",
    "project_id": "prj-knxt-valdemarsvik",
    "date": {
      "value": "2026-06-12",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Government receives Studsvik's state-support application covering Valdemarsvik and Nyköping.",
    "sources": [
      "src-se-gov-studsvik-aid-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-knxt-valdemarsvik-other-2026-09-03",
    "name": "Studsvik selects GE Vernova Hitachi and Samsung C&T for an initial four-unit BWRX-300 project",
    "project_id": "prj-knxt-valdemarsvik",
    "date": {
      "value": "2026-09-03",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Studsvik selects GE Vernova Hitachi and Samsung C&T for an initial four-unit BWRX-300 project.",
    "sources": [
      "src-studsvik-partners-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "Studsvik selects GE Vernova Hitachi and Samsung C&T for four-unit BWRX-300 project",
      "what": "Studsvik selected GE Vernova Hitachi and Samsung C&T for an initial four-unit BWRX-300 project."
    }
  },
  {
    "stable_id": "evt-stellaria-alvin-cadarache-other-2026-04-23",
    "name": "Stellaria and CEA sign letter of intent on INB Alpha feasibility at Cadarache",
    "project_id": "prj-stellaria-alvin-cadarache",
    "date": {
      "value": "2026-04-23",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Stellaria and CEA sign letter of intent on INB Alpha feasibility at Cadarache.",
    "sources": [
      "src-stellaria-alpha-20260423"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-stellaria-alvin-cadarache-other-2032",
    "name": "INB Alpha: company target to convert the facility to MegAlvin",
    "project_id": "prj-stellaria-alvin-cadarache",
    "date": {
      "value": "2032",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "INB Alpha: company target to convert the facility to MegAlvin. A target, not an achieved milestone.",
    "sources": [
      "src-stellaria-alpha-20260423"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-dual-fluid-rwanda-other-2023-09",
    "name": "RAEB and Dual Fluid sign the CDE cooperation agreement",
    "project_id": "prj-dual-fluid-rwanda",
    "date": {
      "value": "2023-09",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "RAEB and Dual Fluid sign the CDE cooperation agreement.",
    "sources": [
      "src-raeb-dual-fluid-cde"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-dual-fluid-rwanda-other-2024-03-25",
    "name": "IAEA expert mission on CDE safety analysis and design safety features",
    "project_id": "prj-dual-fluid-rwanda",
    "date": {
      "value": "2024-03-25",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "IAEA expert mission on CDE safety analysis and design safety features.",
    "sources": [
      "src-raeb-dual-fluid-cde"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-dual-fluid-rwanda-other-2024-04",
    "name": "Preliminary site survey report finds the site suitable",
    "project_id": "prj-dual-fluid-rwanda",
    "date": {
      "value": "2024-04",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Preliminary site survey report finds the site suitable.",
    "sources": [
      "src-raeb-dual-fluid-cde"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-dual-fluid-rwanda-other-2025-02",
    "name": "Initial Safety Assessment Report (ISAR) review begins",
    "project_id": "prj-dual-fluid-rwanda",
    "date": {
      "value": "2025-02",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Initial Safety Assessment Report (ISAR) review begins.",
    "sources": [
      "src-raeb-dual-fluid-cde"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-dual-fluid-rwanda-construction-start-2026",
    "name": "CDE construction start (company target stated in February 2026, not reconfirmed by the May edition)",
    "project_id": "prj-dual-fluid-rwanda",
    "date": {
      "value": "2026",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "construction_start",
    "summary": "Earlier 2026 company construction-start target from the February 2026 paper, not an achieved milestone. The May edition instead describes core completion two years after financing and then two years of testing; that relative sequence does not reconfirm this calendar-year target. No comparable structured revision is inferred.",
    "sources": [
      "src-dual-fluid-whitepaper-202602",
      "src-dual-fluid-whitepaper-202605"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-27",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-dual-fluid-rwanda-other-2028",
    "name": "CDE testing phase (company target stated in February 2026, not reconfirmed by the May edition)",
    "project_id": "prj-dual-fluid-rwanda",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Earlier 2028 company testing target from the February 2026 paper, not an achieved milestone. The May edition instead describes core completion two years after financing and then two years of testing; that relative sequence does not reconfirm this calendar-year target. No comparable structured revision is inferred.",
    "sources": [
      "src-dual-fluid-whitepaper-202602",
      "src-dual-fluid-whitepaper-202605"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-27",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-xuwei-htgr-unit3-first-concrete-2026",
    "milestone": {
      "key": "first_nuclear_island_concrete",
      "scope": "xuwei_unit3"
    },
    "met_by": "evt-xuwei-u3-first-concrete-20261106",
    "name": "Xuwei Unit 3 (HTGR) first concrete expected",
    "project_id": "prj-xuwei-htgr-unit3",
    "date": {
      "value": "2026",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "first_concrete",
    "summary": "Xuwei Unit 3 (HTGR) first concrete expected. A target, not an achieved milestone.",
    "sources": [
      "src-wnn-xuwei-htgr-contract-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-xuwei-htgr-unit3-commercial-operation-2031",
    "name": "Xuwei Phase I (all three units) full completion expected",
    "project_id": "prj-xuwei-htgr-unit3",
    "date": {
      "value": "2031",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "China Energy News reported on 3 August 2026 that the whole of Xuwei Phase I, two Hualong One units and the Unit 3 high-temperature gas-cooled reactor, is expected to be fully completed and in use in 2031. This target covers the whole phase; it is not a Unit 3 commercial-operation date.",
    "sources": [
      "src-det-f859198460"
    ],
    "confidence": "low",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "reader": {
      "headline": "Xuwei Phase I, all three units, expected to be fully completed in 2031",
      "what": "A press report says the whole of Phase I, including the Unit 3 high-temperature reactor, is expected to be fully completed and in use in 2031.",
      "limit": "This target covers the whole phase; it is not a Unit 3 commercial-operation date."
    }
  },
  {
    "stable_id": "evt-tmsr-lf1-wuwei-construction-start-2018-09",
    "name": "TMSR-LF1 construction begins",
    "project_id": "prj-tmsr-lf1-wuwei",
    "date": {
      "value": "2018-09",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "TMSR-LF1 construction begins.",
    "sources": [
      "src-gif-tmsr-lf1"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-tmsr-lf1-wuwei-other-2022-08",
    "name": "Ministry of Ecology and Environment approves TMSR-LF1 commissioning plan",
    "project_id": "prj-tmsr-lf1-wuwei",
    "date": {
      "value": "2022-08-02",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "The Ministry of Ecology and Environment told SINAP on 2 August 2022 that its commissioning plan, version V1.3, was approved, as World Nuclear News reported. That approved the plan; it was not an operating licence.",
    "sources": [
      "src-wnn-tmsr-conversion-2025",
      "src-wnn-tmsr-startup-2022"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-tmsr-lf1-wuwei-first-criticality-2023-10-11",
    "name": "TMSR-LF1 first criticality",
    "project_id": "prj-tmsr-lf1-wuwei",
    "date": {
      "value": "2023-10-11",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_criticality",
    "summary": "TMSR-LF1 first criticality, dated 11 October 2023 by World Nuclear News and the IAEA Research Reactor Database. Operating licence 2307 sets the first approach to criticality as a hold point to be released by the Ministry of Ecology and Environment's Northwest Nuclear and Radiation Safety Supervision Station; no release document was opened.",
    "sources": [
      "src-wnn-tmsr-conversion-2025",
      "src-iaea-rrdb-tmsr-lf1",
      "src-nnsa-tmsr-lf1-operating-2023"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-tmsr-lf1-wuwei-other-2024-10",
    "name": "First thorium addition to TMSR-LF1",
    "project_id": "prj-tmsr-lf1-wuwei",
    "date": {
      "value": "2024-10",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "First thorium addition to TMSR-LF1.",
    "sources": [
      "src-wnn-tmsr-conversion-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-tmsr-lf1-wuwei-other-2025-11-01",
    "name": "SINAP announces first thorium-to-uranium fuel conversion",
    "project_id": "prj-tmsr-lf1-wuwei",
    "date": {
      "value": "2025-11-01",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "SINAP announces first thorium-to-uranium fuel conversion.",
    "sources": [
      "src-wnn-tmsr-conversion-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-httr-oarai-first-criticality-1998-11",
    "name": "HTTR first criticality",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "1998-11-10",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_criticality",
    "summary": "HTTR first criticality.",
    "sources": [
      "src-jaea-ard-symposium-2026",
      "src-d3-atomica-httr-history"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-httr-oarai-other-2001",
    "name": "HTTR reaches full-power operation",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2001",
      "precision": "year",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "HTTR reaches full-power operation.",
    "sources": [
      "src-wnn-httr-mhi-2023"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-httr-oarai-other-2010-03",
    "name": "HTTR 50-day continuous operation at 950°C",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2010-03",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "HTTR 50-day continuous operation at 950°C.",
    "sources": [
      "src-jaea-ard-symposium-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-httr-oarai-other-2021-07",
    "name": "HTTR resumes operation after new-regulatory-standard review",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2021-07-30",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "HTTR resumed operation on 30 July 2021 after the new-regulatory-standard installation-change permit and compliance work; JAEA's Oarai notice of that day records the restart.",
    "sources": [
      "src-jaea-ard-symposium-2026",
      "src-jaea-oarai-httr-restart-20210730",
      "src-jaea-oarai-httr-inspection-complete-20210922"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-httr-oarai-regulatory-step-2025-03-27",
    "name": "JAEA applies to the NRA to connect a hydrogen production plant to HTTR",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2025-03-27",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "JAEA applies to the NRA to connect a hydrogen production plant to HTTR.",
    "sources": [
      "src-jaea-httr-hydrogen-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-httr-oarai-other-2025-09-26",
    "name": "JAEA files an amendment to the HTTR hydrogen-coupling application",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2025-09-26",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "JAEA files an amendment to the HTTR hydrogen-coupling application.",
    "sources": [
      "src-jaea-httr-hydrogen-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-httr-oarai-other-2030",
    "name": "HTTR hydrogen production (JAEA target)",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2030",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "HTTR hydrogen production (JAEA target). A target, not an achieved milestone.",
    "sources": [
      "src-jaea-httr-hydrogen-2025"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htr10-inet-construction-start-1995-06",
    "name": "HTR-10 construction begins",
    "project_id": "prj-htr10-inet",
    "date": {
      "value": "1995-06",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "construction_start",
    "summary": "HTR-10 construction begins.",
    "sources": [
      "src-nnsa-htr10-2014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htr10-inet-other-2000-04",
    "name": "HTR-10 system commissioning begins",
    "project_id": "prj-htr10-inet",
    "date": {
      "value": "2000-04",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "HTR-10 system commissioning begins.",
    "sources": [
      "src-nnsa-htr10-2014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htr10-inet-fuel-load-2000-11-20",
    "name": "HTR-10 first fuel loading begins",
    "project_id": "prj-htr10-inet",
    "date": {
      "value": "2000-11-20",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "fuel_load",
    "summary": "HTR-10 first fuel loading begins.",
    "sources": [
      "src-nnsa-htr10-2014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htr10-inet-first-criticality-2000-12-01",
    "name": "HTR-10 initial criticality",
    "project_id": "prj-htr10-inet",
    "date": {
      "value": "2000-12-01",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_criticality",
    "summary": "HTR-10 initial criticality.",
    "sources": [
      "src-nnsa-htr10-2014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-htr10-inet-other-2003-01-26",
    "name": "HTR-10 reaches full power (10 MW thermal)",
    "project_id": "prj-htr10-inet",
    "date": {
      "value": "2003-01-26",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "HTR-10 reached full power of 10 MW on 26 January 2003. The same NNSA attachment states overall parameters of 10 MW thermal and 2 MW electric, so the 10 MW full-power figure is the thermal power. It does not state a measured electrical output or a grid connection.",
    "sources": [
      "src-nnsa-htr10-2014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-15",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-daqing-nhr200-other-1991",
    "name": "Decision to build an NHR-200 demonstration heating plant at Daqing",
    "project_id": "prj-daqing-nhr200",
    "date": {
      "value": "1991",
      "precision": "year",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Decision to build an NHR-200 demonstration heating plant at Daqing.",
    "sources": [
      "src-iaea-tecdoc-965"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-daqing-nhr200-other-1993",
    "name": "Daqing siting report, EIA and feasibility study approved",
    "project_id": "prj-daqing-nhr200",
    "date": {
      "value": "1993",
      "precision": "year",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Daqing siting report, EIA and feasibility study approved.",
    "sources": [
      "src-iaea-tecdoc-965"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-daqing-nhr200-construction-start-1997",
    "name": "Daqing NHR-200 construction start (historical target, not met)",
    "project_id": "prj-daqing-nhr200",
    "date": {
      "value": "1997",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "construction_start",
    "summary": "Daqing NHR-200 construction start (historical target, not met). A target, not an achieved milestone.",
    "sources": [
      "src-iaea-tecdoc-965"
    ],
    "confidence": "low",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ucri-ien-other-2025-03",
    "name": "Finep approves funding for the Brazilian microreactor project",
    "project_id": "prj-ucri-ien",
    "date": {
      "value": "2025-03",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Finep approves funding for the Brazilian microreactor project.",
    "sources": [
      "src-ien-mnb-20251111"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ucri-ien-other-2025-10-06",
    "name": "ANSN pre-licensing harmonisation meeting at AMAZUL",
    "project_id": "prj-ucri-ien",
    "date": {
      "value": "2025-10-06",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "ANSN pre-licensing harmonisation meeting at AMAZUL.",
    "sources": [
      "src-ansn-ucri-prelicensing-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ucri-ien-other-2025-12-09",
    "name": "CNEN ceremony marks formal start of UCRI site licensing",
    "project_id": "prj-ucri-ien",
    "date": {
      "value": "2025-12-09",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "CNEN ceremony marks formal start of UCRI site licensing.",
    "sources": [
      "src-cnen-ucri-licensing-20251215"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-deep-fission-parsons-regulatory-step-2026-08-06",
    "name": "Deep Fission announces DOE approval of the Gravity pilot NSDA",
    "project_id": "prj-deep-fission-parsons",
    "date": {
      "value": "2026-08-06",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "Deep Fission announced NSDA approval on 6 August 2026. Its later public NSDA cover attributes approval to DOE letter CLN260841 dated 14 July, which was not opened. The agreement defines an early safety framework and separate later readiness, startup and operating steps. This announcement is not an NRC licence or evidence of operating authority.",
    "sources": [
      "src-det-100da7cd6d",
      "src-deep-fission-public-nsda-rev0-20260717"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "Deep Fission announces DOE approval of its Gravity pilot NSDA",
      "what": "Deep Fission announced approval of the NSDA for its Gravity pilot at Parsons.",
      "why": "The agreement defines an early safety framework and separate later readiness, startup and operating steps.",
      "limit": "The announcement is not an NRC licence or evidence of operating authority.",
      "date_label": "Announced",
      "dates_note": "A later public NSDA cover attributes the approval to a DOE letter dated 14 July."
    }
  },
  {
    "stable_id": "evt-deep-fission-parsons-groundbreaking-2025-12",
    "name": "Groundbreaking for the Gravity pilot at Great Plains Industrial Park, Parsons",
    "project_id": "prj-deep-fission-parsons",
    "date": {
      "value": "2025-12",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "groundbreaking",
    "summary": "Groundbreaking for the Gravity pilot at Great Plains Industrial Park, Parsons. Groundbreaking is not first nuclear concrete; check whether the record already holds it.",
    "sources": [
      "src-det-2d89643d1e"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-rr-temelin-regulatory-step-2026-10",
    "name": "ČEZ submits EIA documentation for the Temelín Rolls-Royce SMR to the Ministry of the Environment",
    "project_id": "prj-rr-temelin",
    "date": {
      "value": "2026-10",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "ČEZ submits EIA documentation for the Temelín Rolls-Royce SMR to the Ministry of the Environment.",
    "sources": [
      "src-det-00c203d8ff"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "reader": {
      "headline": "ČEZ submits EIA documentation for the Temelín Rolls-Royce SMR",
      "what": "ČEZ submitted EIA documentation for the Temelín Rolls-Royce SMR to the Ministry of the Environment."
    }
  },
  {
    "stable_id": "evt-rr-temelin-other-2027",
    "name": "Temelín SMR EIA process expected to be completed",
    "project_id": "prj-rr-temelin",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Temelín SMR EIA process expected to be completed. A target, not an achieved milestone.",
    "sources": [
      "src-det-00c203d8ff"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aalo-ascension-announcement-20260704",
    "name": "Aalo announces Project Ascension",
    "project_id": "prj-aalo-ascension-inl",
    "date": {
      "value": "2026-07-04",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "announcement",
    "summary": "Aalo names its proposed second reactor and future 10 MWe data-center demonstration. This is an announcement date, not a construction start or achieved generation.",
    "sources": [
      "src-aalo-ascension-20260704"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-15",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-aalo-ascension-datacenter-target-2027",
    "name": "Ascension on-site data-center supply target",
    "project_id": "prj-aalo-ascension-inl",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "The company targets 2027 pilot electricity supply. This is not achieved generation or a stated commercial-operation date.",
    "sources": [
      "src-aalo-ascension-20260704"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-15",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-doicesti-snn-egms-20261029",
    "name": "Nuclearelectrica shareholders adopt measures for RoPower Nuclear and note the Doicești conditions",
    "project_id": "prj-nuscale-romania",
    "date": {
      "value": "2026-10-29",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Extraordinary meeting held on 29 October 2026. Shareholders took note, without a vote, of the status of the February 2026 investment-decision conditions and the strategy update. They adopted the measures in Section 4 of the meeting's note, with 90.13 percent of the votes of shareholders present or represented, and authorized Nuclearelectrica's representative to vote for them at RoPower Nuclear's own meeting. The note says RoPower's plan should aim, at the least, to cut the staff working on the project by at least 60 percent, keeping only critical staff, over about six months, and asks RoPower for that plan within a month of the meeting; the resolution refers to the note and does not repeat it. Whether RoPower has carried the measures out is not recorded.",
    "sources": [
      "src-snn-egms-20261029-convening",
      "src-snn-doicesti-fid-conditions-note-202610",
      "src-snn-gms-resolutions-20261029"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "reader": {
      "headline": "Nuclearelectrica shareholders adopt RoPower measures",
      "what": "Shareholders took note of the Doicești conditions and strategy update without a vote, and adopted the measures in the meeting's note with about 90 percent of the votes present or represented.",
      "limit": "The resolution does not repeat the measures, and whether RoPower has carried them out is not recorded."
    }
  },
  {
    "stable_id": "evt-lomonosov-operating-licence-2019-06",
    "project_id": "prj-lomonosov",
    "event_type": "regulatory_step",
    "date": {
      "value": "2019-06-27",
      "precision": "day",
      "basis": "actual"
    },
    "name": "NucNet reports receipt of Akademik Lomonosov operating licence",
    "summary": "NucNet reported on 27 June 2019 that Rosenergoatom had received a ten-year Rostekhnadzor licence to operate the Akademik Lomonosov floating plant, valid until 2029, as announced by Rosatom. The event date is the report date; the issue date, instrument and licence number are unknown and the licence document has not been reviewed.",
    "sources": [
      "src-nucnet-lomonosov-ol-20190627"
    ],
    "confidence": "medium",
    "review_state": "verified",
    "last_checked": "2026-10-16"
  },
  {
    "stable_id": "evt-myanmar-survey-plans-reported-2026-08-24",
    "project_id": "prj-myanmar-ritm-smr",
    "event_type": "other",
    "date": {
      "value": "2026-08-24",
      "precision": "day",
      "basis": "actual"
    },
    "name": "Report describes Rosatom survey-contract and 2027 site-work plans for Myanmar",
    "summary": "Atomic Energy 2.0 reported on 24 August 2026, relaying Strana Rosatom, that Rosatom expects to sign a contract for primary engineering surveys by the end of 2026 and begin site work in 2027. The report describes the 18 August government meeting but does not separately date the Rosatom statement. The first stage is two RITM-200N reactors of 55 MW each, with possible later expansion to 330 MW. These remain plans; the site is not named. The event date is the report date.",
    "sources": [
      "src-atomic-energy-myanmar-surveys-20260824"
    ],
    "confidence": "medium",
    "review_state": "verified",
    "last_checked": "2026-10-16",
    "reader": {
      "headline": "Report: Rosatom expects Myanmar survey contract by end of 2026, site work in 2027",
      "what": "Atomic Energy 2.0, relaying Strana Rosatom, reported that Rosatom expects to sign a contract for primary engineering surveys by the end of 2026 and begin site work in 2027.",
      "limit": "These remain plans; the site is not named.",
      "date_label": "Reported",
      "dates_note": "The report describes an 18 August government meeting but does not separately date the Rosatom statement."
    }
  },
  {
    "stable_id": "evt-radiant-buckley-haleu-commitment-2026-07-23",
    "project_id": "prj-radiant-buckley",
    "event_type": "other",
    "date": {
      "value": "2026-07-23",
      "precision": "day",
      "basis": "actual"
    },
    "name": "DOE conditional HALEU commitment for the Buckley microreactor",
    "summary": "DOE made a conditional commitment on 23 July 2026 to provide high-assay low-enriched uranium to Radiant for its deployment of a microreactor to the Air Force's preferred location, Buckley Space Force Base; DOE will next begin the contracting process. This is a fuel allocation commitment, not delivery, a site decision or permission.",
    "sources": [
      "src-doe-haleu-round3-20260723"
    ],
    "confidence": "high",
    "review_state": "verified",
    "last_checked": "2026-10-16"
  },
  {
    "stable_id": "evt-httr-oarai-full-power-2021-09-19",
    "name": "HTTR reaches 100% power and 850°C after restart",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2021-09-19",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "JAEA reports that HTTR reached 100% reactor power and an 850°C coolant temperature on 19 September 2021, and that the periodic licensee inspection confirming performance at full power was completed on 22 September 2021, completing the reactor's new-regulatory-standard compliance. Thermal test operation; no electricity. The safety-demonstration test operation planned from about January 2022 is a plan in this notice, not an achieved event.",
    "sources": [
      "src-jaea-oarai-httr-inspection-complete-20210922"
    ],
    "confidence": "high",
    "review_state": "verified",
    "last_checked": "2026-10-16"
  },
  {
    "stable_id": "evt-httr-oarai-full-power-safety-test-2024-03",
    "name": "HTTR full-power thermal safety demonstration",
    "project_id": "prj-httr-oarai",
    "date": {
      "value": "2024-03",
      "precision": "month",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "JAEA's August 2026 symposium slides show an achieved March 2024 safety demonstration at 100% reactor power (30 MW thermal). This is thermal testing, not electricity generation, commercial service or a hydrogen-coupling permission. The source gives the month, so no exact day is assigned.",
    "sources": [
      "src-jaea-ard-symposium-2026"
    ],
    "confidence": "high",
    "review_state": "verified",
    "last_checked": "2026-10-16"
  },
  {
    "stable_id": "evt-vardo-assessment-programme-held-2024-11-22",
    "name": "Regional councils report the Energy Ministry's interim reply holding the Vardø assessment programme",
    "project_id": "prj-vardo-smr",
    "date": {
      "value": "2024-11-22",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "On 22 November 2024 the Øst-Finnmark and Vest-Finnmark regional councils reported that the Energy Ministry's interim reply of 1 October had put the Vardø assessment programme on hold pending the Aure and Heim hearing, and backed the municipality's objection. The event date is the councils' letter date; the ministry's reply was not opened. Subsequent status is not established by these documents; this report grants no project permission.",
    "sources": [
      "src-ofr-vfrr-vardo-statement-20241122"
    ],
    "confidence": "medium",
    "review_state": "verified",
    "last_checked": "2026-10-16"
  },
  {
    "project_id": "prj-natrium-kemmerer",
    "event_type": "construction_start",
    "date": {
      "value": "2026-04-23",
      "precision": "day",
      "basis": "actual"
    },
    "name": "TerraPower announces the official start of construction at Kemmerer Unit 1",
    "summary": "TerraPower announced on 23 April 2026 the official start of construction on Natrium Kemmerer Unit 1. The same release says TerraPower broke ground in June 2024 and began construction on non-nuclear support facilities. It does not say that safety-related or nuclear-island work began on 23 April 2026, and a senator quoted in it refers to construction on the energy island. This is a company announcement, not an NRC record of first safety-related concrete. An NRC inspection report dated 22 April 2026, the day before, on an inspection held on 23 to 26 March, says in passing that construction of the unit has not started. Stored electrical and thermal ratings are not changed.",
    "sources": [
      "src-terrapower-construction-2026",
      "src-nrc-terrapower-inspection-99902100-2026-201"
    ],
    "stable_id": "evt-natrium-official-construction-start-2026-04-23",
    "confidence": "medium",
    "review_state": "verified",
    "last_checked": "2026-10-17"
  },
  {
    "stable_id": "evt-natrium-kemmerer-bechtel-exit-2026-09",
    "name": "Bechtel and TerraPower part ways on Kemmerer Unit 1; EPC contract to be rebid",
    "summary": "Reported on 22 September 2026: Bechtel and TerraPower said they would move forward separately after considering the next phase of the project. Bechtel said its work had been under an earlier contract phase, before full EPC scope, and that it would remain on site to complete the Sodium Test & Fill Facility. TerraPower said it would rebid the EPC contract and manage the transition to protect the schedule.",
    "sources": [
      "src-d1-wnn-bechtel-20260922",
      "src-d1-nucnet-bechtel-20260923"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-natrium-kemmerer",
    "event_type": "contract",
    "date": {
      "value": "2026-09",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Bechtel steps away from Natrium Kemmerer Unit 1; TerraPower to rebid EPC contract",
      "what": "Bechtel and TerraPower said in September 2026 that they would move forward separately; Bechtel will finish the on-site Sodium Test & Fill Facility. TerraPower said it would rebid the engineering, procurement and construction contract.",
      "limit": "No replacement contractor is named; the company's statement that the schedule is unaffected is not a verified milestone.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-natrium-kemmerer-wyoming-permit-2025-01-14",
    "name": "TerraPower reports Wyoming Industrial Siting Council permit for Kemmerer Unit 1",
    "summary": "TerraPower announced on 14 January 2025 that the Wyoming Industrial Siting Council had approved its state permit for Kemmerer Unit 1, covering construction and operational activities outside NRC jurisdiction. The Council's order itself is not recorded here.",
    "sources": [
      "src-d1-terrapower-wy-isc-permit-20250114",
      "src-d1-wnn-wy-isc-permit-20250115"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-natrium-kemmerer",
    "event_type": "regulatory_step",
    "date": {
      "value": "2025-01-14",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Wyoming siting permit approved for the non-NRC parts of Kemmerer Unit 1",
      "what": "TerraPower said Wyoming's Industrial Siting Council approved its permit for construction and operational activities outside NRC jurisdiction.",
      "limit": "A state siting permit does not cover the nuclear island, which needed the NRC construction permit.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-natrium-kemmerer-construction-completion-target-2030",
    "name": "TerraPower target: Kemmerer Unit 1 construction completion in 2030",
    "summary": "A TerraPower spokesperson, quoted in September 2026, said the project timeline calls for construction completion in 2030 and commercial operation by 2031. These are company targets, not achieved milestones. POWER's 23 April 2026 timeline says US SFR Owner told the NRC it expects to complete construction by February 2031. The two statements are not reconciled here.",
    "sources": [
      "src-d1-nucnet-bechtel-20260923",
      "src-powermag-kemmerer-timeline-20260423"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-natrium-kemmerer",
    "event_type": "other",
    "date": {
      "value": "2030",
      "precision": "year",
      "basis": "target"
    },
    "reader": {
      "headline": "TerraPower targets 2030 construction completion for Kemmerer Unit 1",
      "what": "TerraPower said in September 2026 that its schedule calls for construction completion in 2030 and commercial operation by 2031.",
      "limit": "A target only; no operating licence application or operating licence is recorded. POWER reported in April 2026 that US SFR Owner told the NRC it expects to complete construction by February 2031."
    }
  },
  {
    "stable_id": "evt-clinch-river-doe-gen3-selection-2025-12-02",
    "name": "DOE selects TVA for $400 million to advance a BWRX-300 at Clinch River",
    "summary": "DOE announced on 2 December 2025 that it selected TVA for $400,000,000 of up to $800 million in federal cost-shared funding for early Gen III+ SMR deployments, to advance a GE Vernova Hitachi BWRX-300 at the Clinch River Nuclear site. A funding selection is not a construction decision or a permit.",
    "sources": [
      "src-doe-gen3-smr-selections-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-clinch-river-bwrx",
    "event_type": "other",
    "date": {
      "value": "2025-12-02",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "DOE selects TVA for $400 million in cost-shared funding for Clinch River BWRX-300",
      "what": "DOE named TVA one of two first-mover teams for Gen III+ small modular reactors, with $400 million in federal cost-shared funding for its Clinch River BWRX-300.",
      "limit": "A funding selection is not a final investment decision, construction start or NRC permission.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-holtec-palisades-doe-gen3-selection-2025-12-02",
    "name": "DOE selects Holtec for $400 million to deploy two SMR-300 reactors at Palisades",
    "summary": "DOE announced on 2 December 2025 that it selected Holtec Government Services, LLC for $400,000,000 of up to $800 million in federal cost-shared funding for early Gen III+ SMR deployments, to deploy two SMR-300 reactors at the Palisades site in Covert, Michigan. A funding selection is not a construction decision or a permit.",
    "sources": [
      "src-doe-gen3-smr-selections-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-holtec-palisades",
    "event_type": "other",
    "date": {
      "value": "2025-12-02",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "DOE selects Holtec for $400 million in cost-shared funding for two SMR-300s at Palisades",
      "what": "DOE named Holtec Government Services one of two first-mover teams for Gen III+ small modular reactors, with $400 million in federal cost-shared funding for two SMR-300 units at Palisades.",
      "limit": "A funding selection is not a final investment decision, construction start or NRC permission.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-hermes-1-construction-completion-target-2028",
    "name": "Kairos expects to complete Hermes construction in 2028",
    "summary": "In its March 2026 request to extend construction permit CPTR-6, Kairos said it now expects to complete construction of the Hermes test reactor facility in 2028; the NRC extended the latest completion date to 30 April 2029. The 2028 date is a company target.",
    "sources": [
      "src-d1-wnn-hermes1-extension-20260422",
      "src-fr-hermes1-extension-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-hermes-1",
    "event_type": "other",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "reader": {
      "headline": "Kairos expects Hermes test reactor construction to be complete in 2028",
      "what": "Kairos told the NRC in March 2026 that it expects to finish building the Hermes test reactor in 2028; the NRC later extended the permit’s latest completion date to April 2029.",
      "limit": "A construction target; no fuel-loading or operation date is stated and no operating licence is recorded."
    }
  },
  {
    "stable_id": "evt-aalo-x-inl-groundbreaking-2025-08",
    "name": "Aalo breaks ground at its Aalo-X site next to INL's Materials and Fuels Complex",
    "summary": "World Nuclear News reported on 29 August 2025 that Aalo had broken ground at a site next to Idaho National Laboratory's Materials and Fuels Complex to start building Aalo-X. No groundbreaking day is given. Aalo later said its Critical Test Reactor went from groundbreaking to criticality in less than eight months, which does not fit an August 2025 start for that building.",
    "sources": [
      "src-d2-wnn-aalo-groundbreaking",
      "src-aalo-ascension-20260704"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-aalo-x-inl",
    "event_type": "groundbreaking",
    "date": {
      "value": "2025-08",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Aalo breaks ground for Aalo-X next to INL's Materials and Fuels Complex",
      "what": "World Nuclear News reported in late August 2025 that Aalo had broken ground at a site next to Idaho National Laboratory's Materials and Fuels Complex to start building Aalo-X.",
      "limit": "Aalo's own timing for the Critical Test Reactor building does not match this date, and no groundbreaking day is published.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-antares-mark0-haleu-commitment-2025-08-26",
    "name": "DOE makes a conditional HALEU commitment to Antares for its first reactor",
    "summary": "On 26 August 2025 DOE made a conditional commitment of HALEU to Antares Nuclear for the microreactor design that was to reach criticality by 4 July 2026 under the Reactor Pilot Program. DOE's environmental determination for Mark-0 says Antares plans to use HALEU TRISO fuel in Mark-0 under a HALEU agreement with DOE. A conditional commitment is not a fuel delivery.",
    "sources": [
      "src-d2-doe-haleu-round2",
      "src-doe-cx-035340-pdf"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-antares-mark0-inl",
    "event_type": "other",
    "date": {
      "value": "2025-08-26",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "DOE commits HALEU to Antares for the reactor due to reach criticality by July 2026",
      "what": "DOE made a conditional commitment of HALEU to Antares Nuclear for the microreactor that was to reach criticality by 4 July 2026; DOE's environmental determination ties that fuel to Mark-0.",
      "limit": "A conditional commitment is not a delivery date or fuel loading.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-antares-mark0-doe-agreement-2025-09",
    "name": "Antares executes its agreement with DOE to take a reactor critical by 4 July 2026",
    "summary": "Antares said on 22 September 2025 that it had executed its agreement with DOE that week to take an advanced reactor critical by 4 July 2026. DOE's Mark-0 determination refers to an Other Transaction Agreement between Antares and DOE. The terms are not published. The agreement is not an authorization to operate.",
    "sources": [
      "src-d2-antares-doe-agreement",
      "src-doe-cx-035340-pdf"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-antares-mark0-inl",
    "event_type": "contract",
    "date": {
      "value": "2025-09",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Antares executes its DOE agreement to take a reactor critical by July 2026",
      "what": "Antares said it executed an agreement with DOE to take an advanced reactor critical by 4 July 2026; DOE's Mark-0 determination refers to an Other Transaction Agreement between the two.",
      "limit": "The agreement's terms are not published, and it is not an authorization to operate.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-pele-inl-groundbreaking-2024-09",
    "name": "Department of Defense breaks ground for Project Pele at INL",
    "summary": "DOE's article dated 24 September 2024 says the Department of Defense broke ground on the Project Pele microreactor project at Idaho National Laboratory. The article does not state the groundbreaking day. Groundbreaking is site work, not reactor installation or fuel loading.",
    "sources": [
      "src-doe-pele-groundbreaking"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-pele-inl",
    "event_type": "groundbreaking",
    "date": {
      "value": "2024-09",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Department of Defense breaks ground for Project Pele at Idaho National Laboratory",
      "what": "DOE reported in September 2024 that the Department of Defense had broken ground on the Project Pele microreactor project at Idaho National Laboratory.",
      "limit": "Groundbreaking is site work; the reactor is still being built in Lynchburg and has not been fuelled.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-pele-inl-core-barrel-2026-09",
    "name": "BWXT completes Pele core barrel cartridge installation",
    "summary": "BWXT's programme page lists core barrel cartridge installation as complete in September 2026, at its Lynchburg facility. This is a company statement about factory assembly, not shipment, fuel loading or operation.",
    "sources": [
      "src-bwxt-pele"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-pele-inl",
    "event_type": "other",
    "date": {
      "value": "2026-09",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "BWXT says Pele core barrel cartridge installation is complete",
      "what": "BWXT's programme page lists core barrel cartridge installation for the Pele reactor as complete in September 2026.",
      "limit": "The reactor has not yet shipped to INL or been loaded with fuel.",
      "date_label": "Company timeline"
    }
  },
  {
    "stable_id": "evt-pele-inl-bwxt-contract-2022-06",
    "name": "Strategic Capabilities Office awards BWXT the contract to build and deliver the Pele prototype",
    "summary": "BWXT's programme timeline says the Strategic Capabilities Office awarded it the contract to build and deliver the Pele prototype in June 2022. Company account; the contract value and day are not given.",
    "sources": [
      "src-bwxt-pele"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-pele-inl",
    "event_type": "contract",
    "date": {
      "value": "2022-06",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "BWXT awarded the contract to build and deliver the Pele prototype",
      "what": "BWXT says the Department of Defense's Strategic Capabilities Office awarded it the contract to build and deliver the Pele prototype in June 2022.",
      "limit": "The contract value and exact date are not stated.",
      "date_label": "Company timeline"
    }
  },
  {
    "stable_id": "evt-last-energy-rellis-announced-2025-10-15",
    "name": "Last Energy and the Texas A&M System announce the PWR-5 pilot at RELLIS",
    "summary": "On 15 October 2025 Last Energy and the Texas A&M University System announced the PWR-5 pilot at Texas A&M-RELLIS. Last Energy said it had secured a lease at the campus, procured a full core load of fuel, signed an Other Transaction Agreement with DOE and begun formal licensing submissions. Announcement only; not an authorization.",
    "sources": [
      "src-d2-le-rellis-partnership"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-last-energy-rellis",
    "event_type": "announcement",
    "date": {
      "value": "2025-10-15",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Last Energy and the Texas A&M System announce the PWR-5 pilot at RELLIS",
      "what": "Last Energy and the Texas A&M University System announced the PWR-5 pilot at Texas A&M-RELLIS; Last Energy said it had a site lease, a full core load of fuel and an agreement with DOE.",
      "limit": "The announcement is not DOE authorization.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-last-energy-rellis-criticality-target-2026",
    "name": "Last Energy targets a PWR-5 criticality demonstration in 2026",
    "summary": "Last Energy said in December 2025 that it was preparing for an anticipated 2026 criticality demonstration at RELLIS. In October 2026 it said it was moving into DOE's readiness review, the final step before DOE can issue startup authorization. A company target, not an achieved milestone.",
    "sources": [
      "src-d2-le-series-c",
      "src-last-energy-pwr5-dsa-20261007"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-last-energy-rellis",
    "event_type": "first_criticality",
    "date": {
      "value": "2026",
      "precision": "year",
      "basis": "target"
    },
    "reader": {
      "headline": "Last Energy targets a 2026 criticality demonstration for its RELLIS pilot",
      "what": "Last Energy said it expected to demonstrate criticality of the PWR-5 pilot in 2026, after DOE's readiness review and startup authorization.",
      "limit": "A target only; DOE has not published a startup authorization.",
      "date_label": "Target"
    }
  },
  {
    "stable_id": "evt-last-energy-llynfi-exim-letter-2024-12-13",
    "name": "EXIM issues a non-binding letter of interest for the first Llynfi microreactor",
    "summary": "Last Energy announced on 13 December 2024 that the Export-Import Bank of the United States had issued a non-binding letter of interest. The letter confirms EXIM's willingness to carry out due diligence on $103.7 million of financing for a Last Energy microreactor planned in South Wales. It is not a loan commitment.",
    "sources": [
      "src-d2-le-exim-loi",
      "src-d2-wnn-llynfi"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-last-energy-llynfi",
    "event_type": "other",
    "date": {
      "value": "2024-12-13",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "EXIM letter of interest for $103.7 million toward a Last Energy microreactor in South Wales",
      "what": "Last Energy said EXIM issued a non-binding letter of interest to carry out due diligence on $103.7 million of financing for its first planned microreactor in South Wales.",
      "limit": "A letter of interest is not a financing commitment.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-last-energy-llynfi-grid-offer-2025-01-16",
    "name": "Last Energy accepts an NGED grid connection offer for the first Llynfi unit",
    "summary": "Last Energy announced on 16 January 2025 that it had accepted a connection offer from National Grid Electricity Distribution for 22 MW of export capacity and 3 MW of import capacity for its first unit in South Wales. An accepted offer is not a physical grid connection.",
    "sources": [
      "src-d2-le-grid-offer"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-last-energy-llynfi",
    "event_type": "other",
    "date": {
      "value": "2025-01-16",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Last Energy accepts a 22 MW grid connection offer for its first Llynfi unit",
      "what": "Last Energy said it accepted an offer from National Grid Electricity Distribution for 22 MW of export and 3 MW of import capacity for its first unit in South Wales.",
      "limit": "An accepted connection offer is not a grid connection or a planning or site-licence decision.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-natura-msr-1-haleu-commitment-2025-08-26",
    "name": "DOE makes a conditional HALEU commitment to ACU and Natura for the research reactor",
    "summary": "On 26 August 2025 DOE made a conditional HALEU commitment to Abilene Christian University and Natura Resources for a new molten salt research reactor in Texas, which DOE described as under construction. A conditional commitment is not fuel delivery or fuel loading.",
    "sources": [
      "src-d2-doe-haleu-round2"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-natura-msr-1-acu",
    "event_type": "other",
    "date": {
      "value": "2025-08-26",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "DOE commits HALEU to Abilene Christian University and Natura for MSR-1",
      "what": "DOE made a conditional commitment of HALEU to Abilene Christian University and Natura Resources for their molten salt research reactor in Texas.",
      "limit": "A conditional commitment is not a delivery or fuel loading.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-natura-msr-1-doe-ota-2025-12",
    "name": "Natura executes an Other Transaction Agreement with DOE for MSR-1",
    "summary": "ANS reported on 19 December 2025 that Natura had executed an Other Transaction Agreement with DOE for the Molten Salt Research Reactor at Abilene Christian University, under which the project would proceed through DOE authorization. The execution day and terms are not published. The agreement is not an authorization to construct or operate.",
    "sources": [
      "src-d2-ans-natura-ota"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-natura-msr-1-acu",
    "event_type": "contract",
    "date": {
      "value": "2025-12",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Natura signs an Other Transaction Agreement with DOE for MSR-1",
      "what": "ANS reported that Natura executed an Other Transaction Agreement with DOE for its molten salt research reactor at Abilene Christian University, moving the project onto DOE's authorization pathway.",
      "limit": "The agreement is not DOE authorization to construct or operate.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-ward-250-groundbreaking-2025-09-17",
    "name": "Valar breaks ground on Ward 250 at the Utah San Rafael Energy Lab",
    "summary": "Valar dates the Ward 250 groundbreaking at the Utah San Rafael Energy Lab to 17 September 2025, the dateline of ETV News's report. DOE's environmental determination says construction stayed within the existing site with minimal excavation. A groundbreaking is site work, not fuel loading or operation.",
    "sources": [
      "src-d2-valar-ward250-page",
      "src-depth-20261017-ward-250",
      "src-doe-cx-271015-pdf"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-ward-250",
    "event_type": "groundbreaking",
    "date": {
      "value": "2025-09-17",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Valar breaks ground on Ward 250 at the Utah San Rafael Energy Lab",
      "what": "Valar dates the start of Ward 250 site work in Emery County, Utah, to 17 September 2025.",
      "limit": "The date is the developer's; no state or DOE construction record was opened.",
      "date_label": "Groundbreaking"
    }
  },
  {
    "stable_id": "evt-tmsr-lf1-wuwei-full-power-2024-06",
    "name": "TMSR-LF1 first reaches full power",
    "summary": "Economic Daily reported that the 2 MW thorium molten-salt experimental reactor first reached full-power operation in June 2024. The report gives the month, not the day.",
    "sources": [
      "src-d3-cppcc-economic-daily-tmsr-20260113"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-tmsr-lf1-wuwei",
    "event_type": "other",
    "date": {
      "value": "2024-06",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "TMSR-LF1 first reaches full power",
      "what": "A national newspaper reported that the 2 MW thermal experimental molten-salt reactor first ran at full power in June 2024.",
      "limit": "Thermal operation of a test reactor, not electricity generation.",
      "date_label": "Reported month"
    }
  },
  {
    "stable_id": "evt-httr-oarai-permit-application-1989-02",
    "name": "HTTR installation-permit application filed",
    "summary": "JAEA's history states that the HTTR installation-permit application was submitted to the state in February 1989.",
    "sources": [
      "src-d3-atomica-httr-history"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-httr-oarai",
    "event_type": "regulatory_step",
    "date": {
      "value": "1989-02",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "HTTR installation-permit application filed",
      "what": "JAEA's history says the application for the HTTR installation permit was submitted to the government in February 1989.",
      "limit": "An application is not a permit."
    }
  },
  {
    "stable_id": "evt-httr-oarai-installation-permit-1990-11",
    "name": "HTTR installation permit granted (JAEA account)",
    "summary": "JAEA's history states that the HTTR installation permit was obtained in November 1990. The permit document itself was not opened, so no number or day is recorded.",
    "sources": [
      "src-d3-atomica-httr-history"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-httr-oarai",
    "event_type": "regulatory_step",
    "date": {
      "value": "1990-11",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "HTTR installation permit granted",
      "what": "JAEA's history says the HTTR installation permit was granted in November 1990.",
      "limit": "Reported by the operator; the permit document and its number were not reviewed."
    }
  },
  {
    "stable_id": "evt-httr-oarai-construction-start-1991",
    "name": "HTTR construction begins",
    "summary": "JAEA's history states that construction of HTTR began in 1991, after the November 1990 installation permit; installation work was largely finished in 1996.",
    "sources": [
      "src-d3-atomica-httr-history"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-httr-oarai",
    "event_type": "construction_start",
    "date": {
      "value": "1991",
      "precision": "year",
      "basis": "actual"
    },
    "reader": {
      "headline": "HTTR construction begins",
      "what": "JAEA's history says construction of the 30 MW thermal test reactor began in 1991.",
      "limit": "The source gives the year only."
    }
  },
  {
    "stable_id": "evt-brest-od-300-turbine-hall-separators-2026-10-07",
    "name": "Separator-superheaters installed in BREST-OD-300 turbine hall (Rosatom, reported)",
    "summary": "World Nuclear News reported on 7 October 2026, relaying Rosatom, that two separator-superheaters had been installed in the turbine hall, that concreting of the turbine-generator foundation began in May 2026, and that the turbine-unit foundation is to be completed by the end of 2026. The date is the report date; the installation day is not given.",
    "sources": [
      "src-wnn-brest-turbine-20261007"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-brest-od-300",
    "event_type": "other",
    "date": {
      "value": "2026-10-07",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "BREST-OD-300 turbine hall receives separator-superheaters",
      "what": "Rosatom said two separator-superheaters were installed in the turbine hall; concreting of the turbine foundation began in May 2026.",
      "limit": "This is non-nuclear turbine-hall work; it does not change the operation schedule.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-brest-od-300-fuel-module-pilot-2024-12-25",
    "name": "BREST-OD-300 fuel fabrication module enters pilot-industrial operation",
    "summary": "Rosatom announced on 25 December 2024 that the on-site module for fabricating and refabricating BREST-OD-300 nitride fuel had entered pilot-industrial operation and had made mock-up fuel cassettes with depleted-uranium nitride pellets under a Rostekhnadzor licence of 29 March 2024. Production of uranium-plutonium nitride fuel awaited regulatory approval to handle plutonium. The date is the release date.",
    "sources": [
      "src-d3-atommedia-brest-mfr-20241225"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-brest-od-300",
    "event_type": "other",
    "date": {
      "value": "2024-12-25",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Fuel plant for BREST-OD-300 enters pilot operation",
      "what": "Rosatom said the on-site nitride-fuel module began pilot operation, making mock-up assemblies with depleted uranium.",
      "limit": "Uranium-plutonium fuel production awaited regulator approval; no first-core fuel is recorded as made.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-baimsky-floating-keel-laying-2022-08",
    "name": "Keel laid for the first Cape Nagloynyn floating unit's barge",
    "summary": "World Nuclear News reported on 31 August 2022, relaying Rosatom and Atomenergomash, that a keel-laying ceremony had been held at a Chinese shipyard for the barge of the first of four floating power units, which will later be fitted with two RITM-200S reactors. The ceremony day is not given.",
    "sources": [
      "src-d3-wnn-baim-keel-20220831"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-baimsky-floating",
    "event_type": "construction_start",
    "date": {
      "value": "2022-08",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Keel laid for first Baimsky floating unit barge",
      "what": "A keel-laying ceremony at a Chinese shipyard started construction of the barge for the first of four floating power units.",
      "limit": "This starts hull construction only; reactor installation, licensing for operation and towing to Chukotka remain ahead.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-yakutia-ritm-rusatom-overseas-licence-report-2021-08-06",
    "name": "Rusatom Overseas reports a Rostekhnadzor licence for construction of nuclear installations (Yakutia)",
    "summary": "Snob reported on 6 August 2021, citing Rusatom Overseas's press service, that Rostekhnadzor had issued the company a licence for construction of nuclear installations at the planned Yakutia plant after an inspection. The date is the report date. The report gives no licence number or scope. Later reporting shows the unit siting and construction licences still ahead, so this is not recorded as construction permission.",
    "sources": [
      "src-d3-snob-yakutia-licence-20210806"
    ],
    "confidence": "low",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-yakutia-ritm",
    "event_type": "regulatory_step",
    "date": {
      "value": "2021-08-06",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Rusatom Overseas reports a Rostekhnadzor construction-activity licence",
      "what": "A 2021 media report cited the developer as saying the regulator licensed it to construct nuclear installations for the Yakutia plant.",
      "limit": "No number or scope is given; it is not the unit construction licence, which later reports still place ahead.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-darlington-ontario-fid-2025-05-08",
    "name": "Ontario announces final investment decision for the first Darlington BWRX-300",
    "summary": "The Province of Ontario announced its final investment decision on 8 May 2025, giving OPG the go-ahead to build the first BWRX-300 at Darlington.",
    "sources": [
      "src-d4-wnn-dnnp-equity"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-darlington-bwrx",
    "event_type": "fid",
    "date": {
      "value": "2025-05-08",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Ontario announces final investment decision for the first Darlington BWRX-300",
      "what": "The Province of Ontario announced its final investment decision on 8 May 2025, giving OPG the go-ahead to build the first BWRX-300 small modular reactor at Darlington.",
      "limit": "An investment decision is not a construction start.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-darlington-cgf-bof-equity-2025-10",
    "name": "Canada Growth Fund and Building Ontario Fund commit equity to the Darlington New Nuclear Project",
    "summary": "Canada Growth Fund committed up to C$2 billion and Building Ontario Fund C$1 billion for minority stakes of 15% and 7.5% in the four-unit Darlington New Nuclear Project; the first tranche funds this first unit, and OPG remains majority owner and operator.",
    "sources": [
      "src-d4-wnn-dnnp-equity",
      "src-d4-fin-canada-wtfn",
      "src-d4-mpo-darlington"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-darlington-bwrx",
    "event_type": "other",
    "date": {
      "value": "2025-10",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Canada Growth Fund and Building Ontario Fund commit C$3 billion in equity to Darlington new nuclear",
      "what": "The two funds committed up to C$2 billion and C$1 billion for minority stakes of 15% and 7.5% in the four-unit project. The first tranche funds this first unit; OPG remains majority owner and operator.",
      "limit": "The capital is committed subject to conditions; it is not a record of funds drawn.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-darlington-first-nations-investment-2026-06-23",
    "name": "Williams Treaties First Nations announce C$700 million investment in the Darlington New Nuclear Project",
    "summary": "Seven Williams Treaties First Nations announced a C$700 million investment, structured as a loan to Darlington New Nuclear Project LP for construction of the first of four BWRX-300 units, converting to equity once all four are built. Federal and Ontario Indigenous loan-guarantee programmes support about C$715 million in financing.",
    "sources": [
      "src-d4-wnn-wtfn-stake",
      "src-d4-fin-canada-wtfn",
      "src-d4-wtfn-release"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-darlington-bwrx",
    "event_type": "other",
    "date": {
      "value": "2026-06-23",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Williams Treaties First Nations announce C$700 million investment in Darlington new nuclear",
      "what": "Seven First Nations will lend C$700 million to Darlington New Nuclear Project LP for construction of the first BWRX-300 unit; the loan converts to equity once all four units are built. Federal and Ontario programmes guarantee the financing.",
      "limit": "The stake is in the four-unit new-build project, not the existing Darlington station, and no ownership percentage is published.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-darlington-basemat-lift-2026-04",
    "name": "Reactor building basemat module lifted into the Darlington BWRX-300 shaft",
    "summary": "World Nuclear News reports that in April 2026 the basemat module, the foundation of the reactor building weighing nearly 953 tonnes, was lifted into the newly excavated reactor building shaft 35 metres below ground. The CNSC had removed the hold point for the reactor building foundation on 30 March 2026.",
    "sources": [
      "src-d4-wnn-wtfn-stake",
      "src-cnsc-darlington"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-darlington-bwrx",
    "event_type": "other",
    "date": {
      "value": "2026-04",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "Basemat module lifted into the Darlington BWRX-300 reactor building shaft",
      "what": "In April 2026 the basemat module, the roughly 953-tonne foundation of the reactor building, was lifted into the excavated reactor building shaft 35 metres below ground.",
      "limit": "A construction milestone reported by trade press, not a regulatory approval."
    }
  },
  {
    "stable_id": "evt-darlington-bwxt-rpv-contract-2025-01-27",
    "name": "GE Hitachi awards BWXT the reactor pressure vessel contract for the first Darlington BWRX-300",
    "summary": "GE Hitachi Nuclear Energy awarded BWX Technologies a contract to manufacture the reactor pressure vessel for the first BWRX-300 at the Darlington New Nuclear Project site.",
    "sources": [
      "src-d4-gev-bwxt-rpv"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-darlington-bwrx",
    "event_type": "contract",
    "date": {
      "value": "2025-01-27",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "GE Hitachi awards BWXT the reactor pressure vessel contract for the first Darlington BWRX-300",
      "what": "GE Hitachi Nuclear Energy awarded BWX Technologies a contract to manufacture the reactor pressure vessel for the first BWRX-300 at the Darlington New Nuclear Project site.",
      "limit": "A component supply contract under the reactor vendor; it does not make BWXT a construction contractor.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-darlington-cnsc-12-2-request-2025-07-25",
    "name": "CNSC issues a subsection 12(2) request to OPG after worker injuries at the Darlington new-build site",
    "summary": "The CNSC issued a request under subsection 12(2) of the General Nuclear Safety and Control Regulations after three serious contract-worker injuries on the Darlington New Nuclear Project construction site since April 2025. The CNSC later recorded OPG's response as sufficient and closed the request.",
    "sources": [
      "src-d4-cnsc-12-2-letter"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-darlington-bwrx",
    "event_type": "regulatory_step",
    "date": {
      "value": "2025-07-25",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "CNSC requests action from OPG after worker injuries at the Darlington new-build site",
      "what": "The CNSC asked OPG for information and corrective action after three serious contract-worker injuries on the construction site since April 2025. It later found OPG's response sufficient and closed the request.",
      "limit": "An enforcement request on conventional safety, not a licence decision."
    }
  },
  {
    "stable_id": "evt-arc100-lepreau-iaa-no-designation-2022-12-22",
    "name": "Federal minister decides the Point Lepreau SMR project does not warrant a federal impact assessment",
    "summary": "After a public designation request, the federal Minister of Environment and Climate Change determined that NB Power's SMR demonstration project at Point Lepreau does not warrant designation under the Impact Assessment Act.",
    "sources": [
      "src-d4-iaac-83998",
      "src-d4-iaac-minister-response"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-arc100-lepreau",
    "event_type": "regulatory_step",
    "date": {
      "value": "2022-12-22",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Federal minister declines to designate the Point Lepreau SMR for a federal impact assessment",
      "what": "After a public request, the federal environment minister determined that NB Power's SMR demonstration project at Point Lepreau does not warrant designation under the Impact Assessment Act.",
      "limit": "This is not a project approval; CNSC licensing and the provincial assessment still apply."
    }
  },
  {
    "stable_id": "evt-sealer-norrsundet-plan-consultation-2026-10-09",
    "name": "Gävleborg county board opens consultation on the proposed Norrsundet facility plan",
    "summary": "The Gävleborg county administrative board opened consultation on its proposed facility plan and environmental impact statement for the Norrsundet nuclear facility, running from 9 October to 13 November 2026. The plan covers about 40 hectares within the property Norrsundet 15:28; the board must submit its proposal to the Government by 31 December 2026.",
    "sources": [
      "src-d4-lst-gavleborg-norrsundet",
      "src-d4-lst-gavleborg-planbeskrivning",
      "src-blykalla-norrsundet-plan-20261015"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-sealer-norrsundet",
    "event_type": "regulatory_step",
    "date": {
      "value": "2026-10-09",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Consultation opens on the proposed Norrsundet facility plan",
      "what": "The Gävleborg county board opened consultation on its proposed facility plan and environmental impact statement for the six-reactor Norrsundet park, running from 9 October to 13 November 2026.",
      "limit": "A draft plan under consultation; it is not Government approval or a licence to build.",
      "date_label": "Consultation opened"
    }
  },
  {
    "stable_id": "evt-jimmy-bazancourt-complements-2025-02-13",
    "name": "Ministry requests further information on the Jimmy Bazancourt application",
    "summary": "After ASNR's analysis of the file, the ministry's nuclear-safety mission (MSNR) sent Jimmy Energy requests for further information on the Bazancourt Fermi creation-authorization application on 13 February 2025.",
    "sources": [
      "src-asnr-prm-20261014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-jimmy-bazancourt",
    "event_type": "regulatory_step",
    "date": {
      "value": "2025-02-13",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Ministry requests more information on Jimmy's Bazancourt reactor application",
      "what": "Following ASNR's analysis, the ministry asked Jimmy Energy on 13 February 2025 to complete its creation-authorization file for the Fermi reactor at Bazancourt.",
      "limit": "A request for information, not a refusal or an authorization."
    }
  },
  {
    "stable_id": "evt-stellaria-alvin-cadarache-complements-2026-06-16",
    "name": "Ministry requests further information on the INB Alpha application",
    "summary": "After ASNR's analysis, the ministry's nuclear-safety mission (MSNR) requested further information from Stellaria on the INB Alpha creation-authorization application on 16 June 2026; ASNR's technical review is suspended until it is provided.",
    "sources": [
      "src-asnr-prm-20261014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-stellaria-alvin-cadarache",
    "event_type": "regulatory_step",
    "date": {
      "value": "2026-06-16",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Ministry requests more information on Stellaria's INB Alpha application",
      "what": "Following ASNR's analysis, the ministry asked Stellaria on 16 June 2026 to complete its INB Alpha file. ASNR's technical review is suspended until that information arrives.",
      "limit": "A request for information, not a refusal or an authorization."
    }
  },
  {
    "stable_id": "evt-doicesti-fluor-feed2-contract-2024-07",
    "name": "RoPower and Nuclearelectrica sign the FEED Phase 2 contract with Fluor",
    "summary": "Nuclearelectrica and RoPower Nuclear signed the front-end engineering and design Phase 2 contract with Fluor for the Doicești SMR project, covering design and engineering services, an updated cost estimate and schedule, and safety analyses needed for an investment decision.",
    "sources": [
      "src-d4-wnn-exim-doicesti"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-nuscale-romania",
    "event_type": "contract",
    "date": {
      "value": "2024-07",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "RoPower signs FEED Phase 2 engineering contract with Fluor for Doicești",
      "what": "Nuclearelectrica and RoPower Nuclear signed the front-end engineering and design Phase 2 contract with Fluor, leading to an updated cost estimate, schedule and safety analyses.",
      "limit": "An engineering contract, not a construction contract.",
      "date_label": "Signed"
    }
  },
  {
    "stable_id": "evt-doicesti-exim-pre-project-loan-2024",
    "name": "US EXIM approves a USD 98 million loan for Doicești pre-project services",
    "summary": "The US Export-Import Bank's board approved a final commitment for a USD 98 million loan under its Engineering Multiplier Program for pre-project services for the first NuScale SMR in Romania; World Nuclear News reported it on 2 October 2024.",
    "sources": [
      "src-d4-wnn-exim-doicesti"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-nuscale-romania",
    "event_type": "other",
    "date": {
      "value": "2024",
      "precision": "year",
      "basis": "actual"
    },
    "reader": {
      "headline": "US EXIM approves a USD 98 million loan for Doicești pre-project services",
      "what": "The US Export-Import Bank's board approved a final commitment for a USD 98 million loan for pre-project services for the Doicești NuScale SMR.",
      "limit": "Pre-project financing, not construction financing.",
      "date_label": "Reported October 2024"
    }
  },
  {
    "stable_id": "evt-doicesti-us-finance-letters-2026-05",
    "name": "RoPower reports non-binding US EXIM and DFC financing interest",
    "summary": "RoPower Nuclear reported that US EXIM had expressed support in principle and was analysing financing instruments of about USD 5.6 billion, and that DFC had issued a letter of intent for loan and equity financing of up to USD 2 billion, capped at 25% of investment cost. Both letters are indicative and non-binding.",
    "sources": [
      "src-d4-energynomics-doicesti-us-finance"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-nuscale-romania",
    "event_type": "other",
    "date": {
      "value": "2026-05",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "RoPower reports non-binding US EXIM and DFC financing interest for Doicești",
      "what": "RoPower said EXIM was analysing instruments of about USD 5.6 billion and DFC had issued a letter of intent for up to USD 2 billion. Both are indicative and conditional on due diligence and approvals.",
      "limit": "Letters of interest are not financing commitments.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-doicesti-control-body-response-2026-07-28",
    "name": "Nuclearelectrica responds to the Prime Minister's Control Body report on the Doicești project",
    "summary": "Nuclearelectrica published clarifications on issues raised in the summary of a report by the Romanian Prime Minister's Control Body about the SMR project, saying the original schedule was an estimate and citing IAEA site-review missions of 2022, 2024 and 2025.",
    "sources": [
      "src-d4-snn-statement-20260728"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-nuscale-romania",
    "event_type": "other",
    "date": {
      "value": "2026-07-28",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Nuclearelectrica answers a government Control Body report on the Doicești SMR",
      "what": "Nuclearelectrica responded to a summary of the Prime Minister's Control Body report on the SMR project, saying the schedule was always an estimate and citing IAEA site-review missions.",
      "limit": "The company's response to a summary of the report. The full report was published on 11 September 2026."
    }
  },
  {
    "stable_id": "evt-ameresco-imsr-aberdeen-selection-2026-09-21",
    "name": "Army selects Ameresco to negotiate Aberdeen Proving Ground lease; IMSR planned for Phase 2",
    "summary": "Ameresco said the Army competitively selected it to negotiate a long-term lease for a power campus at Aberdeen Proving Ground and that it is working with Terrestrial Energy on an IMSR for the Phase 2 site. The lease is not yet signed and no construction will begin before environmental and regulatory reviews.",
    "sources": [
      "src-l1-ameresco-apg-20260921",
      "src-l1-wnn-terrestrial-tef-20261009"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-ameresco-imsr-aberdeen",
    "event_type": "announcement",
    "date": {
      "value": "2026-09-21",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Ameresco picked to negotiate Aberdeen Proving Ground power lease, with an IMSR planned",
      "what": "The Army selected Ameresco to negotiate a long-term lease for a power campus at Aberdeen Proving Ground in Maryland. Ameresco says it is working with Terrestrial Energy on an IMSR for the campus's Phase 2 site.",
      "limit": "The lease is still under negotiation; this is not a licence application, permit or construction start.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-cascade-enw-nrc-preapplication-2024-08",
    "name": "Energy Northwest begins NRC pre-application engagement for Cascade",
    "summary": "The NRC lists pre-application activities with Energy Northwest New Nuclear for a future construction permit application from August 2024. No application has been filed.",
    "sources": [
      "src-nrc-enw-preapp"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-cascade-enw",
    "event_type": "regulatory_step",
    "date": {
      "value": "2024-08",
      "precision": "month",
      "basis": "actual"
    },
    "reader": {
      "headline": "NRC pre-application engagement begins for Cascade",
      "what": "The NRC began pre-application activities with Energy Northwest New Nuclear in August 2024 for a future construction permit application.",
      "limit": "Pre-application engagement is not an application, review or permit.",
      "date_label": "Began"
    }
  },
  {
    "stable_id": "evt-cascade-enw-amazon-agreement-2024-10-16",
    "name": "Amazon and Energy Northwest agreement to fund Cascade feasibility phase",
    "summary": "Energy Northwest and Amazon announced an agreement under which Amazon funds the initial feasibility phase of the Xe-100 project near Columbia Generating Station and has the right to purchase electricity from the first four modules (320 MW).",
    "sources": [
      "src-n1-enw-amazon-2024"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-cascade-enw",
    "event_type": "announcement",
    "date": {
      "value": "2024-10-16",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Amazon to fund Cascade feasibility work, with rights to first-phase power",
      "what": "Amazon agreed to fund the initial feasibility phase of Energy Northwest's Xe-100 project. Amazon has the right to buy electricity from the first four modules, about 320 MW.",
      "limit": "It is not a power purchase agreement, investment decision or construction start.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-cascade-enw-design-build-negotiations-2025-10-23",
    "name": "Energy Northwest enters progressive design-build negotiations with Cascade Nuclear Partners",
    "summary": "Energy Northwest said it is in negotiations with Cascade Nuclear Partners, an equal joint venture of Kiewit, Black & Veatch and Aecon, to plan, design and build the first four Xe-100 modules under a progressive design-build model.",
    "sources": [
      "src-n1-enw-design-builder-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-cascade-enw",
    "event_type": "announcement",
    "date": {
      "value": "2025-10-23",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Kiewit, Black & Veatch and Aecon venture chosen to negotiate Cascade design-build",
      "what": "Energy Northwest is negotiating with Cascade Nuclear Partners to plan, design and build the first four Xe-100 modules. The development phase is meant to set scope, schedule and cost.",
      "limit": "Negotiations are not a signed construction contract.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-cascade-enw-engagement-plan-rev3-2026-03-26",
    "name": "ENNN files Regulatory Engagement Plan Revision 3 planning a two-part construction permit application",
    "summary": "Energy Northwest New Nuclear sent the NRC Revision 3 of its regulatory engagement plan, which plans a construction permit application in two parts, the first supporting early environmental review. The planned dates are withheld.",
    "sources": [
      "src-n1-nrc-ennn-rep-rev3"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "project_id": "prj-cascade-enw",
    "event_type": "regulatory_step",
    "date": {
      "value": "2026-03-26",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "headline": "Cascade licensing plan updated with a two-part permit application",
      "what": "Energy Northwest New Nuclear updated its NRC engagement plan in March 2026. It plans to file its construction permit application in two parts.",
      "limit": "The filing dates are withheld and no application has been submitted.",
      "date_label": "Filed"
    }
  },
  {
    "stable_id": "evt-htr10-inet-electricity-generation-2004-10",
    "name": "HTR-10 combined heat-and-power trial operation",
    "event_type": "electricity_generation",
    "project_id": "prj-htr10-inet",
    "date": {
      "value": "2004-10",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "NNSA's 2014 attachment records combined heat-and-power operation from October 2004 to April 2005 and from November 2005 to April 2006, during trial operation that began in December 2003. This is test operation; no grid connection, measured electrical output or commercial service is stated, and it is not evidence of current operation.",
    "sources": [
      "src-nnsa-htr10-2014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-19",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-clinch-final-se-target-202611-stated-20250725",
    "name": "NRC target: final safety evaluation for the Clinch River construction permit (July 2025 schedule)",
    "project_id": "prj-clinch-river-bwrx",
    "date": {
      "value": "2026-11",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "The NRC staff's letter of 25 July 2025 (ML25205A005) planned the final safety evaluation of the Clinch River construction permit application by November 2026, as its 18 June 2026 letter records. The July 2025 letter itself was not opened here. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-clinch-schedule-ml26160a308"
    ],
    "stated": {
      "value": "2025-07-25",
      "precision": "day"
    },
    "confidence": "high",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "final_safety_evaluation",
      "scope": "unit1_construction_permit"
    }
  },
  {
    "stable_id": "evt-clinch-final-se-target-202606-stated-20260618",
    "name": "NRC target: final safety evaluation for the Clinch River construction permit",
    "project_id": "prj-clinch-river-bwrx",
    "date": {
      "value": "2026-06",
      "precision": "month",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "On 18 June 2026 (ML26160A308) the NRC staff moved its planned issue of the Clinch River final safety evaluation to 30 June 2026, ahead of the November 2026 schedule, citing review efficiencies. A target, not an achieved milestone.",
    "sources": [
      "src-nrc-clinch-schedule-ml26160a308"
    ],
    "stated": {
      "value": "2026-06-18",
      "precision": "day"
    },
    "revises": "evt-clinch-final-se-target-202611-stated-20250725",
    "confidence": "high",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "final_safety_evaluation",
      "scope": "unit1_construction_permit"
    },
    "met_by": "evt-clinch-final-ser-issued-20260625"
  },
  {
    "stable_id": "evt-clinch-final-ser-issued-20260625",
    "name": "NRC issues the final safety evaluation report for the Clinch River construction permit application",
    "project_id": "prj-clinch-river-bwrx",
    "date": {
      "value": "2026-06-25",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "The NRC's project page lists the final safety evaluation report (ML26168A505) as issued on 25 June 2026, within the accelerated schedule. A safety evaluation supports the permit decision; it is not itself the construction permit.",
    "sources": [
      "src-nrc-clinch-river-cpa"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "milestone": {
      "key": "final_safety_evaluation",
      "scope": "unit1_construction_permit"
    }
  },
  {
    "stable_id": "evt-natrium-cod-target-2028-stated-20211116",
    "name": "TerraPower target: Natrium commercial operation (November 2021 statement)",
    "project_id": "prj-natrium-kemmerer",
    "date": {
      "value": "2028",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "When Kemmerer was selected in November 2021, TerraPower targeted a 2028 commercial operation date in line with the ARDP mandate, as POWER's 2026 project timeline records. POWER records that by April 2023 the target completion date had shifted from 2028 to 2030, attributed primarily to HALEU fuel availability. A target, not an achieved milestone.",
    "sources": [
      "src-powermag-kemmerer-timeline-20260423"
    ],
    "stated": {
      "value": "2021-11-16",
      "precision": "day"
    },
    "confidence": "medium",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "commercial_operation",
      "scope": "kemmerer_unit1"
    }
  },
  {
    "stable_id": "evt-natrium-online-target-2031-stated-20260123",
    "name": "Kemmerer Unit 1: reported online target at the end of 2031",
    "project_id": "prj-natrium-kemmerer",
    "date": {
      "value": "2031",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "other",
    "summary": "Utah Division of Public Utilities testimony dated 23 January 2026 projects the plant online at the end of 2031; this is the witness's projection, not an achieved milestone or a TerraPower commitment. POWER's 23 April 2026 retrospective timeline attributes a 2028 commercial-operation target to November 2021 and reports an interim 2030 completion target in 2023. These are selected historical statements, not consecutive revisions. The testimony does not define online as commercial operation, so no same-milestone change is calculated.",
    "sources": [
      "src-utah-dpu-natrium-testimony-20260123",
      "src-powermag-kemmerer-timeline-20260423"
    ],
    "stated": {
      "value": "2026-01-23",
      "precision": "day"
    },
    "supersedes": "evt-natrium-cod-target-2028-stated-20211116",
    "confidence": "medium",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "revision_note": "Selected historical endpoints, not consecutive revisions: POWER retrospectively reports a 2028 commercial-operation target in 2021 and an interim 2030 target in 2023. The later endpoint is Utah DPU’s January 2026 testimony projecting the plant online at the end of 2031; the source terms are not an identical commercial-operation definition.",
    "milestone": {
      "key": "online_projection",
      "scope": "kemmerer_unit1"
    }
  },
  {
    "stable_id": "evt-darlington-grid-target-2029-stated-20231130",
    "name": "OPG target: Darlington BWRX-300 Unit 1 online (November 2023 statement)",
    "project_id": "prj-darlington-bwrx",
    "date": {
      "value": "2029",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "grid_connection",
    "summary": "In November 2023 OPG planned to finish building the first Darlington BWRX-300 by the end of 2028 and to have it online by the end of 2029, as reported by WNN. A target, not an achieved milestone.",
    "sources": [
      "src-wnn-darlington-fuel-20231130"
    ],
    "stated": {
      "value": "2023-11-30",
      "precision": "day"
    },
    "confidence": "medium",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "grid_connection",
      "scope": "unit1"
    }
  },
  {
    "stable_id": "evt-darlington-grid-target-2030-stated-20251024",
    "name": "OPG target: connect Darlington BWRX-300 Unit 1 to the grid by the end of 2030",
    "project_id": "prj-darlington-bwrx",
    "date": {
      "value": "2030",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "grid_connection",
    "summary": "In October 2025 OPG said it expects to complete construction of SMR 1 by the end of the decade and connect it to the grid by the end of 2030, as reported by WNN. A target, not an achieved milestone.",
    "sources": [
      "src-d4-wnn-dnnp-equity"
    ],
    "stated": {
      "value": "2025-10-24",
      "precision": "day"
    },
    "revises": "evt-darlington-grid-target-2029-stated-20231130",
    "confidence": "medium",
    "last_checked": "2026-10-21",
    "review_state": "verified",
    "milestone": {
      "key": "grid_connection",
      "scope": "unit1"
    }
  },
  {
    "stable_id": "evt-antares-mark1-nsda-announcement-20261023",
    "name": "Antares reports DOE approval of the Mark-1 safety-design agreement",
    "project_id": "prj-antares-mark1-inl",
    "event_type": "announcement",
    "date": {
      "value": "2026-10-23",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Antares announced that DOE had approved the Mark-1 Nuclear Safety Design Agreement. The company describes it as the first step in DOE's authorization pathway and a framework for design requirements and safety analysis. This date is the announcement day; the approval day is not stated. The NSDA is not itself construction or operating authorization.",
    "reader": {
      "headline": "Antares reports Mark-1 safety-design agreement approval",
      "what": "Antares announced that DOE had approved the Mark-1 Nuclear Safety Design Agreement, the first step in the authorization pathway described by the company.",
      "limit": "Company-reported framework; approval day unknown. It is not construction or operating authorization.",
      "date_label": "Announced"
    },
    "sources": [
      "src-antares-mark1-nsda-20261023"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-24",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-antares-mark1-electricity-target-2027",
    "name": "Antares target: Mark-1 electricity production at INL in 2027",
    "project_id": "prj-antares-mark1-inl",
    "date": {
      "value": "2027",
      "precision": "year",
      "basis": "target"
    },
    "event_type": "electricity_generation",
    "summary": "Antares's 17 February 2026 roadmap says it intends to produce electricity with its full-scale Mark-1 reactor within 2027, in the INL test facility it established for the Mark-0 pilot. A target, not an achieved milestone.",
    "sources": [
      "src-antares-path-to-power-2026"
    ],
    "stated": {
      "value": "2026-02-17",
      "precision": "day"
    },
    "confidence": "medium",
    "last_checked": "2026-10-23",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-antares-mark0-nsda-reported-202510",
    "name": "Antares reports Mark-0 safety-design agreement approval in October 2025",
    "project_id": "prj-antares-mark0-inl",
    "event_type": "other",
    "date": {
      "value": "2025-10",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "Antares' announcement dated 29 October 2025 says DOE approved the safety-design agreement for its first reactor. Its 23 October 2026 retrospective explicitly identifies Mark-0 and places approval in October 2025. The approval month is recorded at month precision because neither statement establishes an approval day, and the company-reported framework is not itself operating authorization.",
    "reader": {
      "headline": "Antares reports Mark-0 safety-design agreement approval in October 2025",
      "what": "A contemporaneous October 2025 announcement reports DOE approval for Antares' first reactor, and the October 2026 retrospective explicitly identifies Mark-0 and its approval month.",
      "limit": "Company reports only, with approval month established but no approval day or operating authority inferred.",
      "date_label": "Reported approval month"
    },
    "sources": [
      "src-antares-mark1-nsda-20261023",
      "src-antares-nsda-original-20251029"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-25",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-radiant-crane-selection-announced-20261020",
    "name": "Radiant announces Navy selection of Kaleidos for Crane",
    "project_id": "prj-navy-crane-microreactor",
    "event_type": "announcement",
    "date": {
      "value": "2026-10-20",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Radiant announced that the Department of the Navy selected it to deploy Kaleidos at Naval Weapons Station Crane. The company lists design refinement, prototype testing, environmental review, site preparation and regulatory coordination before deployment. This selection announcement is not a construction start, regulatory permission or operating milestone; the separate Navy original was identified but could not be opened.",
    "reader": {
      "headline": "Radiant announces Kaleidos selection for Naval Weapons Station Crane",
      "what": "The company identifies the vendor and design for the previously announced Indiana microreactor proposal.",
      "limit": "Company-reported selection; testing, environmental review, site preparation and regulatory coordination remain ahead. No Crane-specific capacity or operating date is inferred.",
      "date_label": "Company announcement"
    },
    "sources": [
      "src-radiant-crane-selection-20261020"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-25",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-linglong-operator-licences-202503",
    "name": "First 34 Linglong One reactor operators licensed",
    "event_type": "other",
    "project_id": "prj-linglong-one",
    "date": {
      "value": "2025-03",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "China News Service reported on 1 October 2026, from a site visit, that in March 2025 the first 34 people received reactor operator licences for the Linglong One demonstration unit. Operator licensing is a staffing step; it is not fuel loading, criticality or an operating licence for the unit.",
    "sources": [
      "src-chinanews-linglong-hft-20261001"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "First Linglong One reactor operators licensed",
      "what": "The first 34 people received operator licences for the Linglong One demonstration unit, as reported from the site by China News Service.",
      "limit": "Operator licences are a staffing step, not an operating licence for the unit."
    }
  },
  {
    "stable_id": "evt-linglong-cold-functional-202510",
    "name": "Linglong One cold functional testing completed",
    "event_type": "other",
    "project_id": "prj-linglong-one",
    "date": {
      "value": "2025-10",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "China News Service reported on 1 October 2026 that cold functional testing of the Linglong One unit was completed in October 2025. The National Energy Administration's China Nuclear Power Development Report 2026 (July 2026) also records cold functional tests completed in 2025. Cold testing precedes hot functional testing, fuel loading, criticality and grid connection, none of which this entry records. China News Service describes cold and hot functional testing as the two key checks a unit passes before grid connection, with fuel loading the next step after hot testing.",
    "sources": [
      "src-chinanews-linglong-hft-20261001",
      "src-nea-china-nuclear-report-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "Linglong One completes cold functional testing",
      "what": "Cold functional testing of the Linglong One unit was completed, the first of the two key system tests before grid connection.",
      "limit": "Hot testing, fuel loading, criticality and grid connection were still ahead."
    }
  },
  {
    "stable_id": "evt-linglong-nnsa-key-issues-20260316",
    "name": "NNSA supervision meeting names key Linglong One review issues",
    "event_type": "regulatory_step",
    "project_id": "prj-linglong-one",
    "date": {
      "value": "2026-03-16",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "A notice published on 16 March 2026 by the Ministry of Ecology and Environment's nuclear power safety supervision department (NNSA) reports a recent supervision activity on the China-Russia cooperation projects and the Hainan small reactor, which studied key problems constraining the projects' entry into operation. For the Hainan small reactor it names main-pump nozzle safety and once-through steam generator flow stability among the key difficult issues in construction and commissioning. The activity is regulatory oversight, not a licence decision.",
    "sources": [
      "src-nnsa-linglong-review-2026-03"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "China's regulator names key Linglong One review issues",
      "what": "An NNSA supervision activity named main-pump nozzle safety and once-through steam generator flow stability among key difficult issues in the Hainan small reactor's construction and commissioning.",
      "limit": "Regulatory oversight, not a licence decision.",
      "date_label": "Notice published"
    }
  },
  {
    "stable_id": "evt-linglong-nnsa-workgroup-20260605",
    "name": "NNSA working group reviews Linglong One safety issues and urges pre-fuel-load preparation",
    "event_type": "regulatory_step",
    "project_id": "prj-linglong-one",
    "date": {
      "value": "2026-06-05",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "A notice published on 5 June 2026 by the NNSA's nuclear power safety supervision department reports a recent meeting of the special review and supervision working group for the Hainan Changjiang small modular reactor demonstration. The operating and design organisations reported construction progress and the handling of safety-significant issues found in review and site commissioning. The notice says the demonstration had entered a critical construction period and urged the operating and design organisations to resolve key technical issues and push ahead rigorously with production-readiness work before fuel loading. The meeting is regulatory oversight, not a fuel-load permit.",
    "sources": [
      "src-nnsa-linglong-workgroup-2026-06"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "Regulator's Linglong One working group urges pre-fuel-load preparation",
      "what": "The NNSA working group for the Changjiang demonstration reviewed safety issues found in review and commissioning and urged the operator to push ahead with production-readiness work before fuel loading.",
      "limit": "Regulatory oversight, not a fuel-load permit.",
      "date_label": "Notice published"
    }
  },
  {
    "stable_id": "evt-linglong-nnsa-commissioning-20260818",
    "name": "NNSA working group reviews Linglong One commissioning anomalies",
    "event_type": "regulatory_step",
    "project_id": "prj-linglong-one",
    "date": {
      "value": "2026-08-18",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "A notice published on 18 August 2026 by the NNSA's nuclear power safety supervision department reports the working group's second 2026 meeting on the Hainan Changjiang small modular reactor demonstration. It covered unclosed review questions, overall review and site-inspection status, commissioning progress and the handling of anomalies found during commissioning, and asked for a full review of instrumentation and control commissioning and verification. The meeting is regulatory oversight, not a licence decision.",
    "sources": [
      "src-nnsa-linglong-commissioning-2026-08"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "Regulator reviews Linglong One commissioning anomalies",
      "what": "The NNSA working group's second 2026 meeting reviewed open review questions, commissioning progress and anomalies found during commissioning.",
      "limit": "Regulatory oversight, not a licence decision.",
      "date_label": "Notice published"
    }
  },
  {
    "stable_id": "evt-linglong-hot-functional-20261001",
    "name": "Linglong One in hot functional testing",
    "event_type": "other",
    "project_id": "prj-linglong-one",
    "date": {
      "value": "2026-10-01",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "China News Service reported from the Changjiang site on 1 October 2026 that the Linglong One unit was in hot functional testing, with civil works complete and equipment installation essentially finished, and that fuel loading and grid connection were targeted within 2026. NucNet relayed the testing status on 7 October 2026. The start date of hot testing is not stated; fuel loading, criticality and grid connection are not recorded as achieved. China News Service describes cold and hot functional testing as the two key checks a unit passes before grid connection, with fuel loading the next step after hot testing.",
    "sources": [
      "src-chinanews-linglong-hft-20261001",
      "src-nucnet-linglong-hft-20261007"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "Linglong One reported in hot functional testing",
      "what": "Linglong One was in hot functional testing, the test after which fuel loading comes next, according to a China News Service site report.",
      "limit": "Fuel loading, criticality and grid connection had not happened; the 2026 dates are targets.",
      "date_label": "Reported"
    }
  },
  {
    "stable_id": "evt-last-energy-caldwell-rep-202607",
    "name": "Last Energy's NRC engagement plan names Caldwell County for its first commercial unit",
    "event_type": "announcement",
    "project_id": "prj-last-energy-caldwell",
    "date": {
      "value": "2026-07",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "Last Energy's regulatory engagement plan, Revision 1.0, dated July 2026 and issued to the NRC on 30 July 2026 according to its record of change, says the company's first commercial PWR-20 unit is planned at a 44-acre site in Caldwell County, Texas, and calls the site its priority for NRC engagement. The plan schedules a limited work authorization application and a docket number for later in 2026; it is a company plan, not an application or permit.",
    "sources": [
      "src-fr-last-energy-submitted-to-d389a5bc"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "Last Energy names Caldwell County, Texas, for its first commercial microreactor",
      "what": "Last Energy's plan for NRC engagement says its first commercial PWR-20 unit is planned at a 44-acre Caldwell County site, its priority for NRC engagement.",
      "limit": "A company engagement plan, not an application or permit.",
      "date_label": "Plan dated"
    }
  },
  {
    "stable_id": "evt-natrium-kemmerer-supplier-awards-20260831",
    "name": "TerraPower announces 12 supplier awards for the Natrium plant and sodium test facility",
    "event_type": "contract",
    "project_id": "prj-natrium-kemmerer",
    "date": {
      "value": "2026-08-31",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "TerraPower's release of 31 August 2026 announced 12 supplier awards to 11 companies, including control rod drive design by BWXT Canada, a plant cyber system by Mirion Technologies and an air-sodium heat exchanger by Thermal Engineering International. It says the awards support construction of the Natrium plant and completion of the sodium test and fill facility, without assigning individual awards to either; seven of the twelve are design scopes and no values are given. These are supplier awards, not an EPC appointment.",
    "sources": [
      "src-fr-terrapower-0003c11a"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "TerraPower names 12 Natrium supplier awards",
      "what": "Twelve equipment and design awards to 11 companies, including BWXT Canada, Mirion Technologies and Thermal Engineering International, support the Natrium plant and its sodium test and fill facility.",
      "limit": "No contract values; awards are not split between the plant and the test facility; not an EPC appointment.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-rr-tusimice-eia-notification-20250506",
    "name": "Czech environment ministry receives ČEZ's assessment notification for a Tušimice SMR plant",
    "event_type": "regulatory_step",
    "project_id": "prj-rr-tusimice",
    "date": {
      "value": "2025-05-06",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The Ministry of the Environment received ČEZ's environmental-assessment notification for a new SMR nuclear source at Tušimice on 6 May 2025 and opened screening the next day. The notification covers one to six light-water SMRs of up to 1,500 MWe net and does not choose a supplier.",
    "sources": [
      "src-fr-ministry-of-the-environm-c12dd8e0",
      "src-cenia-tusimice-eia"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "ČEZ files environmental assessment notification for Tušimice SMRs",
      "what": "The notification covers one to six light-water SMRs of up to 1,500 MWe net at the Tušimice coal-plant site; the supplier is not chosen.",
      "limit": "An environmental assessment step, not a nuclear licence application or permit.",
      "date_label": "Notification received"
    }
  },
  {
    "stable_id": "evt-rr-tusimice-eia-screening-20251222",
    "name": "Czech environment ministry issues screening conclusion for the Tušimice SMR assessment",
    "event_type": "regulatory_step",
    "project_id": "prj-rr-tusimice",
    "date": {
      "value": "2025-12-22",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "The Ministry of the Environment's screening conclusion of 22 December 2025 sets what ČEZ's environmental-impact documentation for Tušimice must cover, including a justification of the site against alternatives in the region. A full assessment is mandatory for nuclear plants under Czech law; the conclusion is not a permit.",
    "sources": [
      "src-fr-ministry-of-the-environm-c12dd8e0"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "Ministry sets the scope of the Tušimice SMR environmental assessment",
      "what": "ČEZ must justify the site against regional alternatives and cover the listed surveys in its environmental-impact documentation.",
      "limit": "A scoping step in the environmental assessment, not a permit or nuclear licence.",
      "date_label": "Conclusion issued"
    }
  },
  {
    "stable_id": "evt-rr-tusimice-preferred-site-20230227",
    "name": "ČEZ names Tušimice a preferred SMR site and begins site exploration",
    "event_type": "announcement",
    "project_id": "prj-rr-tusimice",
    "date": {
      "value": "2023-02-27",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "ČEZ said on 27 February 2023 that, after a preliminary assessment, it had tentatively identified Tušimice and Dětmarovice as preferred sites for further small modular reactors after Temelín, and that exploration of the power-plant sites for active faults, hydrogeology and bedrock had begun in the first half of February. It said suitability would be clear only after further exploration.",
    "sources": [
      "src-cez-smr-preferred-sites-2023"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "ČEZ names Tušimice a preferred SMR site",
      "what": "ČEZ tentatively chose the site after a preliminary assessment and began exploration for faults, groundwater and bedrock.",
      "limit": "Site suitability was not yet established; no vendor, unit count or application.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-rr-detmarovice-preferred-site-20230227",
    "name": "ČEZ names Dětmarovice a preferred SMR site and begins site exploration",
    "event_type": "announcement",
    "project_id": "prj-rr-detmarovice",
    "date": {
      "value": "2023-02-27",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "ČEZ said on 27 February 2023 that, after a preliminary assessment, it had tentatively identified Dětmarovice and Tušimice as preferred sites for further small modular reactors after Temelín, and that exploration of the power-plant sites for active faults, hydrogeology and bedrock had begun in the first half of February. It said suitability would be clear only after further exploration.",
    "sources": [
      "src-cez-smr-preferred-sites-2023"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "reader": {
      "headline": "ČEZ names Dětmarovice a preferred SMR site",
      "what": "ČEZ tentatively chose the site after a preliminary assessment and began exploration for faults, groundwater and bedrock.",
      "limit": "Site suitability was not yet established; no vendor, unit count or application.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-linglong-fuel-grid-target-2026",
    "name": "Reported target: Linglong One fuel loading and grid connection within 2026",
    "project_id": "prj-linglong-one",
    "event_type": "other",
    "date": {
      "value": "2026",
      "precision": "year",
      "basis": "target"
    },
    "stated": {
      "value": "2026-10-01",
      "precision": "day"
    },
    "summary": "China News Service reported from the Changjiang site on 1 October 2026 that the unit was aiming for fuel loading and grid-connected generation within the year; NucNet relayed this as targets before the end of 2026. These are reported targets, not achieved milestones. No fuel-loading approval is shown in the sources reviewed. This entry does not cover commercial operation.",
    "sources": [
      "src-chinanews-linglong-hft-20261001",
      "src-nucnet-linglong-hft-20261007"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-03",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-osge-wloclawek-first-unit-target-2032",
    "name": "OSGE assumption: first BWRX-300 unit commissioned at Włocławek in 2032",
    "project_id": "prj-osge-wloclawek",
    "event_type": "other",
    "date": {
      "value": "2032",
      "precision": "year",
      "basis": "target"
    },
    "stated": {
      "value": "2026-06-29",
      "precision": "day"
    },
    "summary": "OSGE's release of 29 June 2026 on its contract-for-difference application says that, according to its assumptions, the first BWRX-300 unit will be commissioned in 2032 in Włocławek. This is a company assumption, not a permit date or an achieved milestone, and no construction permit is recorded.",
    "sources": [
      "src-osge-cfd-fleet",
      "src-osge-cfd-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "milestone": {
      "key": "first_unit_commissioning",
      "scope": "first_unit"
    }
  },
  {
    "stable_id": "evt-fermi-estonia-first-reactor-target-2035",
    "name": "Fermi Energia application: first reactor could start operating in 2035 at the earliest",
    "project_id": "prj-fermi-estonia",
    "event_type": "other",
    "date": {
      "value": "2035",
      "precision": "year",
      "basis": "target"
    },
    "stated": {
      "value": "2025-05-22",
      "precision": "day"
    },
    "summary": "Estonia's government said on 22 May 2025 that the first of the two planned reactors could, according to Fermi Energia's application, start operating in 2035 at the earliest, assuming smooth processes. Fermi's planning page says the first reactor would produce electricity in the second half of 2035. This is an applicant's earliest case, not a commitment or an achieved milestone, and no site is final.",
    "sources": [
      "src-estonia-spatial-plan-2025",
      "src-fermi-rep"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-03",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-hermes-2-operations-target-2030",
    "name": "Kairos target: Hermes 2 to begin operations in 2030",
    "project_id": "prj-hermes-2",
    "event_type": "other",
    "date": {
      "value": "2030",
      "precision": "year",
      "basis": "target"
    },
    "stated": {
      "value": "2025-08-18",
      "precision": "day"
    },
    "summary": "Kairos Power said on 18 August 2025 that it would raise Hermes 2 output from 28 MW to 50 MW generated by a single reactor, scheduled to begin operations in 2030. This is a company target for a configuration the NRC permits do not reflect. It is not an achieved milestone, and no operating licence is recorded.",
    "sources": [
      "src-kairos-tva-ppa-20250818"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-03",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-radiant-dsa-approval-statement-20261029",
    "name": "Radiant announces DOE approval of the Kaleidos Documented Safety Analysis",
    "event_type": "announcement",
    "project_id": "prj-radiant-kaleidos-inl",
    "date": {
      "value": "2026-10-29",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Company statement of 29 October 2026. Radiant says DOE approved its Documented Safety Analysis, covering operation at power as well as initial criticality, and that DOE's Readiness Review is the next step before nuclear operations can begin. It says fuel loading and a five-phase test campaign follow a successful review. This is Radiant's account; the DOE approval document was not opened. No date is given for the review, fuel loading or criticality, and no startup or criticality is recorded.",
    "sources": [
      "src-radiant-dsa-approval-20261029"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "reader": {
      "headline": "Radiant says DOE approved its Kaleidos safety analysis",
      "what": "Radiant says a DOE Readiness Review comes next, before nuclear operations can begin, with fuel loading and a test campaign to follow.",
      "limit": "This is Radiant's account, and the DOE document was not opened. No date is given, and no startup or criticality is recorded.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-doicesti-ropower-interim-report-target-20261231",
    "name": "Target: interim report on RoPower Nuclear's measures",
    "event_type": "other",
    "project_id": "prj-nuscale-romania",
    "date": {
      "value": "2026-12-31",
      "precision": "day",
      "basis": "target"
    },
    "summary": "The shareholder note for the 29 October 2026 meeting calls for a phased schedule at RoPower Nuclear with an interim report on the steps taken by 31 December 2026; shareholders adopted the note's Section 4 measures on 29 October 2026. A deadline from Nuclearelectrica's note, not a result; whether the report has been made is not recorded.",
    "sources": [
      "src-snn-doicesti-fid-conditions-note-202610",
      "src-snn-gms-resolutions-20261029"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-uiuc-kronos-hyundai-mou-20261027",
    "name": "NANO Nuclear announces a memorandum with Hyundai Engineering on KRONOS at the University of Illinois",
    "event_type": "announcement",
    "project_id": "prj-uiuc-kronos",
    "date": {
      "value": "2026-10-27",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Company statement of 27 October 2026. NANO Nuclear says it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. as a framework for potential collaboration on project-execution planning, site-related work, procurement and supply chain for the University of Illinois reactor. A larger role would depend on later evaluation, university and regulatory requirements and separate definitive agreements. NANO says the memorandum is non-exclusive and does not itself award any work package or commit either party to funding or construction. It is not a construction contract.",
    "reader": {
      "headline": "NANO Nuclear announces a memorandum with Hyundai Engineering on KRONOS",
      "what": "NANO Nuclear said it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. as a framework for potential collaboration on the University of Illinois reactor.",
      "limit": "A larger role depends on later evaluation and separate agreements. NANO says it awards no work package and commits neither party to funding or construction. It is not a construction contract.",
      "date_label": "Announced"
    },
    "sources": [
      "src-nano-hyundai-engineering-mou-20261027"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-arc100-inl-hyundai-mou-20261029",
    "name": "ARC announces a memorandum with Hyundai Engineering on ARC-100 deployment",
    "event_type": "announcement",
    "project_id": "prj-arc100-inl",
    "date": {
      "value": "2026-10-29",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Company statement of 29 October 2026. ARC says it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. to explore support for the first U.S. ARC-100 deployment at Idaho National Laboratory and for design completion and NRC licensing under 10 CFR Part 53. It is a memorandum to explore collaboration, not a construction contract or a licence application.",
    "reader": {
      "headline": "ARC announces a memorandum with Hyundai Engineering on ARC-100 deployment",
      "what": "ARC said it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. to explore support for the first U.S. ARC-100 deployment at Idaho National Laboratory and for NRC licensing.",
      "limit": "It is a memorandum to explore collaboration, not a construction contract or a licence application.",
      "date_label": "Announced"
    },
    "sources": [
      "src-arc-hyundai-engineering-mou-20261029"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-ucri-ien-other-2026-01-21",
    "name": "ANSN meets IEN and Terminus on licensing the critical unit",
    "project_id": "prj-ucri-ien",
    "date": {
      "value": "2026-01-21",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "ANSN reports meeting IEN/CNEN and the designer Terminus on 21 January 2026 on the next licensing steps. Its preliminary evaluation of the site report found points to improve. It states no permission.",
    "sources": [
      "src-ansn-ucri-licensing-meeting-20260121"
    ],
    "confidence": "high",
    "last_checked": "2026-11-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-xuwei-u3-construction-licence-20261102",
    "name": "Xuwei Unit 3 construction licence issued",
    "event_type": "regulatory_step",
    "project_id": "prj-xuwei-htgr-unit3",
    "date": {
      "value": "2026-11-02",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "NNSA's construction-licence record dates licence 国核安证字第2621号 to 2 November 2026. This event is the same decision, not a separate announcement. It is not a construction start.",
    "sources": [
      "src-nnsa-xuwei-u3-construction-licence-2621-20261102"
    ],
    "confidence": "high",
    "last_checked": "2026-11-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-huakun-one-siting-opinion-20261102",
    "name": "Huakun One: regulator siting review opinion issued",
    "project_id": "prj-huakun-one-taipingling",
    "date": {
      "value": "2026-11-02",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "NNSA issued site-selection review opinion No. 2620; a siting opinion, not a construction licence.",
    "sources": [
      "src-nnsa-huakun-site-opinion-2620-20261102"
    ],
    "confidence": "high",
    "last_checked": "2026-11-04",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-longmott-cp-issued-20261109",
    "name": "NRC issues the Long Mott construction permit",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-11-09",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "regulatory_step",
    "summary": "NRC news release 26-083 of 9 November 2026 says the NRC has issued the construction permit for the Long Mott Generating Station. This event is the same decision as the regulatory action, not a separate announcement. The permit authorizes construction but not operation. It is not a construction start. The permit is CPAR-3 (ADAMS ML26301A133); the Federal Register notice of issuance is 91 FR 72925, 12 November 2026.",
    "sources": [
      "src-nrc-news-26-083-longmott-cp-20261109",
      "src-fr-longmott-cpar3-2026",
      "src-nrc-longmott-cpar3-permit-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-11-10",
    "review_state": "verified",
    "reader": {
      "headline": "NRC issues the Long Mott construction permit",
      "what": "The NRC says it has issued the construction permit for the four-reactor Long Mott Generating Station in Texas.",
      "limit": "The permit authorizes construction, not operation. No construction start is recorded."
    }
  },
  {
    "stable_id": "evt-xuwei-u3-first-concrete-20261106",
    "milestone": {
      "key": "first_nuclear_island_concrete",
      "scope": "xuwei_unit3"
    },
    "name": "Xuwei Unit 3 (HTGR) first nuclear-island concrete",
    "project_id": "prj-xuwei-htgr-unit3",
    "date": {
      "value": "2026-11-06",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "first_concrete",
    "summary": "Tsinghua University reported on 10 November 2026 that Xuwei Phase I Unit 3 formally started construction on 6 November with the first nuclear-island concrete poured. China National Nuclear Power's announcement 2026-066, dated 6 November, gave that day as the planned pour date. This follows NNSA construction licence 国核安证字第2621号 of 2 November.",
    "sources": [
      "src-tsinghua-chilong-start-20261110",
      "src-cnnp-xuwei-u3-fcd-notice-20261106"
    ],
    "confidence": "high",
    "last_checked": "2026-11-10",
    "review_state": "verified",
    "reader": {
      "headline": "Xuwei Unit 3 HTGR pours first nuclear-island concrete",
      "what": "Construction of the Unit 3 high-temperature gas-cooled reactor formally started on 6 November 2026 with the first nuclear-island concrete.",
      "limit": "Reported by the technology developer and the owner's parent company; no regulator or IAEA PRIS record of the pour has been read."
    }
  },
  {
    "stable_id": "evt-longmott-final-se-completed-202610",
    "name": "NRC completes the Long Mott safety evaluation",
    "project_id": "prj-long-mott",
    "event_type": "other",
    "milestone": {
      "key": "final_safety_evaluation",
      "scope": "longmott_construction_permit"
    },
    "date": {
      "value": "2026-10",
      "precision": "month",
      "basis": "actual"
    },
    "summary": "NRC news release 26-083 of 9 November 2026 states that staff completed the comprehensive safety evaluation in October, one month ahead of schedule. The source does not give a completion day. This completion is distinct from X-energy's announcement on 30 October and the NRC's separately recorded construction-permit decision on 9 November. A safety evaluation is not a construction permit or operating licence.",
    "reader": {
      "headline": "NRC completes the Long Mott safety evaluation in October",
      "what": "The NRC says staff completed its comprehensive safety evaluation for Long Mott in October 2026, one month ahead of schedule.",
      "limit": "The source gives no completion day. This is the evaluation, not the separately recorded construction permit or an operating licence."
    },
    "sources": [
      "src-nrc-news-26-083-longmott-cp-20261109"
    ],
    "confidence": "high",
    "last_checked": "2026-11-10",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-cascade-enw-fluor-nuclear-island-20261105",
    "name": "X-energy announces Fluor selection for Cascade nuclear-island engineering",
    "event_type": "announcement",
    "project_id": "prj-cascade-enw",
    "date": {
      "value": "2026-11-05",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "X-energy announced on 5 November 2026 that it selected Fluor for engineering, design development, supply chain, estimating and project controls services for the nuclear island of the Cascade facility. The release gives no contract date or value. This is not a construction contract.",
    "reader": {
      "headline": "X-energy selects Fluor for Cascade nuclear-island engineering",
      "what": "X-energy said Fluor will provide design and engineering services for the plant areas containing the Xe-100 reactors.",
      "limit": "An engineering and design contract between X-energy and Fluor, not a construction contract or an NRC application.",
      "date_label": "Announced"
    },
    "sources": [
      "src-xenergy-fluor-cascade-20261105"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-longmott-steam-generator-tubing-order-20261104",
    "name": "X-energy announces first steam-generator tubing order for the Dow plant",
    "event_type": "announcement",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-11-04",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "X-energy, Alleima and Doosan Enerbility announced on 4 November 2026 the first procurement of steam-generator tubing for the Xe-100, for its first deployment, the proposed four-unit plant with Dow in Texas. Alleima is to make the tubing and Doosan is to bend it into helical coils. No quantity or value is stated.",
    "reader": {
      "headline": "X-energy announces first steam-generator tubing order",
      "what": "X-energy said Alleima and Doosan Enerbility will supply steam-generator tubing and coils for the first Xe-100 deployment.",
      "limit": "A long-lead component order. It is not a construction start or a final investment decision.",
      "date_label": "Announced"
    },
    "sources": [
      "src-xenergy-alleima-doosan-20261104"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-elementl-letart-dsip-partnership-loi-20261026",
    "name": "Elementl announces a proposed development partnership covering its Ohio project",
    "event_type": "announcement",
    "project_id": "prj-elementl-letart",
    "date": {
      "value": "2026-10-26",
      "precision": "day",
      "basis": "actual"
    },
    "summary": "Elementl announced on 26 October 2026 a letter of intent and term sheet for a proposed development partnership of up to $750 million with a consortium led by DS Investment Partners. It would fund part of the capital needed to bring up to three projects, including the Ohio project, to a final investment decision.",
    "reader": {
      "headline": "Elementl announces proposed partnership of up to $750 million",
      "what": "Elementl said a consortium led by DS Investment Partners would fund a portion of a partnership supporting up to three projects, including Ohio.",
      "limit": "A preliminary agreement subject to definitive documents and approvals. It is not a final investment decision or committed funding.",
      "date_label": "Announced"
    },
    "sources": [
      "src-elementl-dsip-samsung-20261026"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-doicesti-feed2-work-completed-2025",
    "name": "NuScale reports its FEED Phase 2 work for RoPower was completed in late 2025",
    "event_type": "other",
    "project_id": "prj-nuscale-romania",
    "date": {
      "value": "2025",
      "precision": "year",
      "basis": "actual"
    },
    "summary": "NuScale's third-quarter 2026 results say its work associated with Fluor's front-end engineering and design Phase 2 services for the RoPower project was completed in late 2025, with no comparable activity in 2026. The source gives no completion day.",
    "reader": {
      "headline": "NuScale says FEED Phase 2 work for RoPower finished in late 2025",
      "what": "NuScale said its work supporting Fluor's FEED Phase 2 services for RoPower was completed in late 2025.",
      "limit": "A company statement in a financial release. It does not establish acceptance of the FEED results or that investment-decision conditions were met.",
      "date_label": "Reported"
    },
    "sources": [
      "src-nuscale-q3-2026-results-20261105"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified"
  },
  {
    "stable_id": "evt-osge-wloclawek-first-unit-mid-2030s",
    "name": "OSGE states first Włocławek BWRX-300 unit is to be commissioned in the mid-2030s",
    "project_id": "prj-osge-wloclawek",
    "event_type": "other",
    "date": {
      "value": null,
      "precision": "unknown",
      "basis": "target"
    },
    "summary": "OSGE's release of 22 October 2026 on the umbrella agreement among Orlen, SGE and OSGE says the first BWRX-300 unit at Włocławek is to be commissioned in the mid-2030s. Its 29 June 2026 release had assumed 2032, and a 29 September 2026 release said the first BWRX-300 in Poland may start in 2032 without naming a site. These are company statements, not permit dates.",
    "sources": [
      "src-osge-parasol-20261022",
      "src-osge-cfd-2026",
      "src-osge-bwrx-usa-20260929"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified",
    "stated": {
      "value": "2026-10-22",
      "precision": "day"
    },
    "milestone": {
      "key": "first_unit_commissioning",
      "scope": "first_unit"
    },
    "supersedes": "evt-osge-wloclawek-first-unit-target-2032",
    "revision_note": "OSGE's 22 October 2026 release says mid-2030s, a period with no single year, so no date comparison is made."
  },
  {
    "stable_id": "evt-rr-wylfa-iacc-collaboration-20260325",
    "name": "GBE-N and Isle of Anglesey County Council sign a Collaboration Agreement for Wylfa",
    "project_id": "prj-rr-wylfa",
    "date": {
      "value": "2026-03-25",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Great British Energy - Nuclear and Isle of Anglesey County Council signed a Collaboration Agreement setting out how they will work together to support delivery of SMRs at Wylfa, under general principles covering matters including accountability, communication and sustainable development.",
    "sources": [
      "src-govuk-gben-iacc-collaboration-20260325"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified",
    "reader": {
      "headline": "GBE-N and Anglesey council sign a Collaboration Agreement for Wylfa",
      "what": "The agreement sets out how Great British Energy - Nuclear and Isle of Anglesey County Council will work together to support delivery of SMRs at Wylfa.",
      "limit": "A working agreement with the local authority, not planning consent or a site licence."
    }
  },
  {
    "stable_id": "evt-doicesti-control-body-report-published-20260911",
    "name": "Nuclearelectrica publishes the Prime Minister's Control Body report on the Doicești project",
    "project_id": "prj-nuscale-romania",
    "date": {
      "value": "2026-09-11",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "Nuclearelectrica published the Romanian Prime Minister's Control Body report on its audit of the company from 15 October 2025 to 20 March 2026, in the form submitted by its majority shareholder, the Ministry of Energy, after shareholders approved publication on 11 September 2026. The report concludes that the SMR project's FEED 2 stage ran 20 months late against the original timeline, says Doicești ranked second in Sargent & Lundy's site assessment, and gives a December 2025 cost estimate of USD 6.5 billion. It makes other findings on the project company's set-up, the Doicești site purchase and Nuclearelectrica's oversight, which this record does not summarise.",
    "sources": [
      "src-snn-ccpm-report-20260911"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified",
    "reader": {
      "headline": "Nuclearelectrica publishes the government Control Body's report on the Doicești SMR",
      "what": "The report concludes that the FEED 2 stage ran 20 months late, says Doicești ranked second in the consultant site assessment, and gives a December 2025 cost estimate of USD 6.5 billion.",
      "limit": "An audit body's findings, not a regulator decision or court ruling. It has other findings not summarised here. Nuclearelectrica answered a summary on 28 July 2026. The project stage does not change."
    }
  },
  {
    "stable_id": "evt-darlington-opg-q3-2026-unit1-no-longer-meeting-cod-cost-20261110",
    "name": "OPG says Darlington BWRX-300 Unit 1 is no longer expected to meet its October 2030 commercial-operation target or C$7.7 billion estimate",
    "project_id": "prj-darlington-bwrx",
    "date": {
      "value": "2026-11-10",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "In its third-quarter 2026 results release of 10 November 2026, OPG said that, while it undertakes a comprehensive assessment of the project's cost and schedule, Darlington New Nuclear Project Unit 1 is no longer expected to achieve the previously disclosed commercial operation date target of October 2030 or be completed within the previously disclosed estimated cost of C$7.7 billion, inclusive of required systems and services that would be common to all planned SMRs. OPG said this reflects GE Vernova Hitachi Nuclear Energy's ongoing engineering for its first-of-a-kind SMR, which OPG says affects construction execution and supply-chain performance, and that the assessment is currently expected to be substantially completed by mid-2027. The release gives no replacement date or cost. OPG's 2025 annual MD&A (12 March 2026) gave grid connection by the end of 2030 and a C$7.7 billion budget, and its first-quarter 2026 MD&A (5 May 2026) listed a 2030 in-service date for Unit 1 against the same approved budget. The release does not mention grid connection; October 2030 is a commercial-operation date, not the end-2030 grid-connection target recorded from OPG's earlier statements.",
    "sources": [
      "src-opg-q3-2026-release-20261110",
      "src-opg-fy2025-mda-20260312",
      "src-opg-q1-2026-mda-20260505",
      "src-wnn-opg-revise-20261111"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-13",
    "review_state": "verified",
    "reader": {
      "headline": "OPG: Darlington Unit 1 no longer expected to meet its October 2030 target or C$7.7 billion estimate",
      "what": "OPG said on 10 November 2026 that the first Darlington BWRX-300 is no longer expected to meet its previously disclosed October 2030 commercial-operation target or C$7.7 billion estimate; its assessment should be substantially complete by mid-2027.",
      "limit": "Read as republished by Cantech Letter; OPG's own copy and Q3 MD&A not opened. No new date or cost given. Company outlook, not a CNSC decision; does not itself replace the end-2030 grid target.",
      "date_label": "Announced"
    }
  },
  {
    "stable_id": "evt-longmott-cli-26-15",
    "name": "NRC Commission denies the intervenor's petition for review (CLI-26-15)",
    "project_id": "prj-long-mott",
    "date": {
      "value": "2026-11-06",
      "precision": "day",
      "basis": "actual"
    },
    "event_type": "other",
    "summary": "On 6 November 2026 the Commission denied San Antonio Bay Estuarine Waterkeeper's petition for review of the Licensing Board's rulings, which had rejected or dismissed all of its contentions; the Board had already terminated the proceeding. The order also records that the NRC held its uncontested (mandatory) hearing on 22 September 2026 in Port Lavaca, Texas. An adjudicatory order, not the permit; the construction permit followed on 9 November 2026.",
    "sources": [
      "src-nrc-cli-26-15"
    ],
    "confidence": "high",
    "last_checked": "2026-11-13",
    "review_state": "verified",
    "reader": {
      "headline": "Long Mott: Commission denies the intervenor's petition for review",
      "what": "The Commission denied Waterkeeper's petition for review on 6 November 2026, closing the contested proceeding on the Long Mott construction permit application.",
      "limit": "An adjudicatory order, not the permit. Whether any court challenge has been filed was not searched."
    }
  }
]