    "stable_id": "reg-opg-ltc-2025",
    "name": "OPG licence to construct BWRX-300",
    "action_type": "licence_to_construct",
    "status": "approved",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": "prj-darlington-bwrx",
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2025-04-04",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-darlington",
      "src-cnsc-darlington-ltc-rod-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "CNSC issued licence to construct PRCL 32.00/2035 for one BWRX-300 on 4 April 2025, valid to 31 March 2035, with regulatory hold points. OPG's application was received on 31 October 2022.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "submitted_date": {
      "value": "2022-10-31",
      "precision": "day",
      "basis": "actual"
    },
    "permit_numbers": [
      "PRCL 32.00/2035"
    ],
    "reader": {
      "application": {
        "headline": "OPG applies for the Darlington BWRX-300 construction licence",
        "what": "The recorded application date for the Darlington BWRX-300 construction licence is 31 Oct 2022.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 4 Apr 2025. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-opg-lto-2026",
    "name": "OPG licence to operate application",
    "action_type": "operating_licence",
    "status": "under_review",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": "prj-darlington-bwrx",
    "design_id": "dsn-bwrx-300",
    "submitted_date": {
      "value": "2026-03-25",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-darlington"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "20-year operating licence application for one BWRX-300 and waste structure.",
    "applies_to": "project",
    "permission_stage": "operating_authority"
  },
  {
    "stable_id": "reg-hermes1-cp",
    "name": "Kairos Hermes 1 construction permit",
    "action_type": "construction_permit",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-hermes-1",
    "design_id": "dsn-hermes",
    "decision_date": {
      "value": "2023-12-14",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-fr-hermes1-cptr6-2023",
      "src-fr-hermes1-extension-2026",
      "src-nrc-kairos-hermes",
      "src-det-1c00152982"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "The NRC issued construction permit CPTR-6 for the Hermes non-power test reactor on 14 December 2023. A 13 May 2026 order extended the latest construction completion date from 31 December 2026 to 30 April 2029. Operation needs a separate operating licence.",
    "docket": [
      "50-7513"
    ],
    "permit_numbers": [
      "CPTR-6"
    ],
    "federal_register": [
      {
        "citation": "88 FR 88137",
        "document_number": "2023-27960",
        "published": "2023-12-20"
      },
      {
        "citation": "91 FR 28629",
        "document_number": "2026-09880",
        "published": "2026-05-18"
      }
    ],
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "submitted_date": {
      "value": "2021-09-29",
      "precision": "day",
      "basis": "actual"
    },
    "adams": [
      "ML23338A258"
    ],
    "reader": {
      "application": {
        "headline": "Application for the Hermes 1 construction permit",
        "what": "The recorded application date for the Hermes 1 construction permit is 29 Sep 2021.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 14 Dec 2023. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-hermes2-cp",
    "name": "Kairos Hermes 2 construction permit",
    "action_type": "construction_permit",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-hermes-2",
    "design_id": "dsn-hermes",
    "decision_date": {
      "value": "2024-11-21",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-fr-hermes2-cptr7-8-2024",
      "src-nrc-kairos-hermes",
      "src-det-b1d2a212a5"
    ],
    "confidence": "high",
    "last_checked": "2026-11-04",
    "review_state": "verified",
    "summary": "The NRC issued construction permits CPTR-7 and CPTR-8 for the two-unit Hermes 2 test reactor facility on 21 November 2024. Operation needs separate operating licences.",
    "docket": [
      "50-611",
      "50-612"
    ],
    "permit_numbers": [
      "CPTR-7",
      "CPTR-8"
    ],
    "federal_register": [
      {
        "citation": "89 FR 94767",
        "document_number": "2024-28025",
        "published": "2024-11-29"
      }
    ],
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "submitted_date": {
      "value": "2023-07-14",
      "precision": "day",
      "basis": "actual"
    },
    "adams": [
      "ML24324A021",
      "ML24324A022"
    ],
    "reader": {
      "application": {
        "headline": "Application for the Hermes 2 construction permits",
        "what": "The recorded application date for the Hermes 2 construction permits is 14 Jul 2023.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 21 Nov 2024. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-natrium-cp",
    "name": "TerraPower Natrium construction permit",
    "action_type": "construction_permit",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-natrium-kemmerer",
    "design_id": "dsn-natrium",
    "decision_date": {
      "value": "2026-03-09",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-fr-natrium-cpar1-2026",
      "src-nrc-terrapower",
      "src-det-331ef88455"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "The NRC issued construction permit CPAR-1 on 9 March 2026 to US SFR Owner, LLC (TerraPower) for Kemmerer Power Station Unit 1, after the Commission's 4 March 2026 decision on the uncontested hearing. The permit authorizes construction only; an operating licence is a separate NRC decision.",
    "docket": [
      "50-613"
    ],
    "permit_numbers": [
      "CPAR-1"
    ],
    "adams": [
      "ML26034B247"
    ],
    "federal_register": [
      {
        "citation": "91 FR 12628",
        "document_number": "2026-05067",
        "published": "2026-03-16"
      }
    ],
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "submitted_date": {
      "value": "2024-03-28",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "application": {
        "headline": "Application for the Natrium construction permit",
        "what": "The recorded application date for the Natrium construction permit is 28 Mar 2024.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 9 Mar 2026. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-longmott-cp",
    "name": "Long Mott construction permit",
    "action_type": "construction_permit",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-long-mott",
    "design_id": "dsn-xe-100",
    "submitted_date": {
      "value": "2025-03-31",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-fr-longmott-docketed-2025",
      "src-fr-longmott-hearing-2026",
      "src-nrc-xenergy-dow",
      "src-fr-longmott-ea-fonsi-2026",
      "src-nrc-longmott-page-2026",
      "src-nrc-cli-26-10",
      "src-nrc-longmott-hearing-meeting-2026",
      "src-nrc-acrs-longmott-20261016",
      "src-fr-acrs-739-meeting-2026",
      "src-xenergy-longmott-fser-20261030",
      "src-nrc-news-26-083-longmott-cp-20261109",
      "src-xenergy-dow-longmott-cp-20261109",
      "src-fr-longmott-cpar3-2026",
      "src-nrc-longmott-cpar3-permit-2026",
      "src-nrc-cli-26-15"
    ],
    "confidence": "high",
    "last_checked": "2026-10-11",
    "review_state": "verified",
    "summary": "Long Mott Energy's construction permit application, dated 31 March 2025, was accepted and docketed by the NRC. NRC news release 26-083 of 9 November 2026 states that the NRC has issued the construction permit for the four-reactor Xe-100 Long Mott Generating Station in Calhoun County, Texas, that staff completed the safety evaluation in October, and that the permit authorizes building the facility but not operation; a separate operating licence is required before fuel loading. The release gives no permit number; the permit itself is Construction Permit No. CPAR-3 (ADAMS ML26301A133), issued 9 November 2026, and the Federal Register notice of issuance (91 FR 72925, 12 November 2026) says it is immediately effective and authorizes construction of a power reactor facility in Calhoun County, Texas. The permit sets the earliest construction completion date as 1 July 2033 and the latest as 31 December 2033 and expires on that date. Its conditions include that Long Mott Energy notify the NRC when the site grading design and the passive engineered flooding protection design that may impact site grading are available for NRC staff examination, and that it perform geologic mapping of each foundation excavation for safety-related structures, evaluate it against the site characterization and notify the NRC when it is available for examination; the permit also incorporates an environmental protection plan. It says a licence authorizing operation will not be issued unless the applicant submits the complete final safety analysis report, the Commission makes the stated findings on final design and environmental requirements, and the applicant submits proof of financial protection and executes an indemnity agreement. The NRC's project page, updated 12 November 2026, lists the hearing as held on 22 September 2026 and the construction permit decision as 8 November 2026; the permit and the Federal Register notice date issuance to 9 November 2026, and the one-day difference is unexplained in the sources read. Earlier steps: the uncontested (mandatory) hearing was held on 22 September 2026 in Port Lavaca; the Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review supports issuance; NRC issued an environmental assessment and finding of no significant impact plus related exemptions on 18 May 2026. In the contested proceeding, both admitted contentions were dismissed as moot in 2026 and on 7 August 2026 the Commission dismissed the applicant's appeal as moot; on 6 November 2026 the Commission denied the intervenor's separate petition for review (CLI-26-15). The permit is not an operating licence. No construction start is recorded; a permit is not a physical construction start.",
    "docket": [
      "50-614"
    ],
    "permit_numbers": [
      "CPAR-3"
    ],
    "adams": [
      "ML26301A133"
    ],
    "federal_register": [
      {
        "citation": "90 FR 24428",
        "document_number": "2025-10505",
        "published": "2025-06-10"
      },
      {
        "citation": "91 FR 53900",
        "document_number": "2026-16975",
        "published": "2026-08-20"
      },
      {
        "citation": "91 FR 72925",
        "document_number": "2026-23029",
        "published": "2026-11-12"
      }
    ],
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "decision_date": {
      "value": "2026-11-09",
      "precision": "day",
      "basis": "actual"
    },
    "date_sources": {
      "decision_date": "src-nrc-longmott-cpar3-permit-2026"
    },
    "reader": {
      "decision": {
        "headline": "Construction permit issued for the Long Mott Xe-100 station",
        "what": "The NRC says it has issued a construction permit for Long Mott Energy's four-reactor Xe-100 station at Dow's Seadrift site in Texas. It authorizes construction but not operation.",
        "limit": "No construction start is recorded; a permit is not a physical construction start.",
        "dates_note": "NRC news release and Construction Permit No. CPAR-3: 9 November 2026. Federal Register notice: 12 November 2026 (91 FR 72925). Application dated 31 March 2025."
      },
      "application": {
        "headline": "Application for the Long Mott construction permit",
        "what": "Long Mott Energy's construction permit application for four Xe-100 modules at Dow's Seadrift site is dated 31 Mar 2025 and was accepted and docketed by the NRC.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 9 Nov 2026. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-longmott-ea-fonsi-2026",
    "name": "Long Mott environmental assessment, FONSI and review exemptions",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Nuclear Regulatory Commission",
    "country": "US",
    "project_id": "prj-long-mott",
    "design_id": "dsn-xe-100",
    "decision_date": {
      "value": "2026-05-18",
      "precision": "day",
      "basis": "actual"
    },
    "federal_register": [
      {
        "citation": "91 FR 29515",
        "document_number": "2026-10073",
        "published": "2026-05-20"
      }
    ],
    "sources": [
      "src-fr-longmott-ea-fonsi-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified",
    "summary": "The NRC notice says the Long Mott construction-permit environmental assessment and finding of no significant impact were available on 18 May 2026 and that exemptions permitting this review in place of an environmental impact statement were issued the same day. The construction-permit application remains under review; this decision is not a construction permit or authority to operate.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-nb-ltps",
    "name": "NB Power licence to prepare site application",
    "action_type": "licence_to_prepare_site",
    "status": "under_review",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": "prj-arc100-lepreau",
    "design_id": "dsn-arc-100",
    "submitted_date": {
      "value": "2023-06-30",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-nbpower"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "Site preparation licence application for ARC-100.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-rr-gda",
    "name": "Rolls-Royce SMR Generic Design Assessment",
    "action_type": "generic_design_assessment",
    "status": "under_review",
    "regulator": "ONR/EA (UK)",
    "country": "GB",
    "project_id": null,
    "design_id": "dsn-rr-smr",
    "sources": [
      "src-onr-rr-gda"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "Generic Design Assessment of the Rolls-Royce SMR design by the UK regulators. ONR's page (read 3 October 2026) shows Step 1 from April 2022 to April 2023, Step 2 to July 2024 with published Step 2 statements, and Step 3 under way since July 2024. A GDA assesses the generic design only; it is not permission for any site, construction or operation, and no Step 3 conclusion is recorded here. The reactors index, fetched 5 October 2026, still lists this as the active assessment and does not record a Step 3 conclusion. Re-read on 28 October 2026, ONR's page still describes the assessment as ongoing.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Step 3 under way since July 2024."
  },
  {
    "stable_id": "reg-bapeten-kelasa-2025",
    "name": "BAPETEN Kelasa site-evaluation approval",
    "action_type": "other",
    "status": "approved",
    "regulator": "BAPETEN",
    "country": "ID",
    "project_id": "prj-thorcon-kelasa",
    "design_id": "dsn-thorcon-500",
    "decision_date": {
      "value": "2025-07-30",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-bapeten-kelasa-2025",
      "src-bapeten-kelasa-lek"
    ],
    "confidence": "high",
    "last_checked": "2026-10-01",
    "review_state": "verified",
    "summary": "Decision 00003.556.1.300725 authorizes PT Thorcon Power Indonesia to conduct site evaluation under its PET and SMET. It is not a construction licence.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-clinch-cp-20260929",
    "name": "Clinch River Unit 1 construction permit",
    "summary": "The Federal Register published this notice on 5 October 2026 at 91 FR 63311. It states that construction permit CPAR-2 was issued to TVA on 28 September 2026 for Clinch River Nuclear Unit 1, is immediately effective, and authorizes construction of a power reactor facility in Roane County, Tennessee. The notice says the conditions in early site permit ESP-006 had been met except those listed in the construction permit. The permit sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, expires on that latest date and does not restate an output rating. TVA announced the permit on 29 September 2026. The permit is not an operating licence. No construction start is recorded; a permit is not a physical construction start.",
    "sources": [
      "src-fr-clinch-cpar2-2026",
      "src-parent-clinch-permit",
      "src-nrc-clinch-river-cpa",
      "src-nrc-clinch-cpar2-permit-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "action_type": "construction_permit",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-clinch-river-bwrx",
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2026-09-28",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "50-615"
    ],
    "permit_numbers": [
      "CPAR-2"
    ],
    "federal_register": [
      {
        "citation": "91 FR 63311",
        "document_number": "2026-20345",
        "published": "2026-10-05"
      }
    ],
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "submitted_date": {
      "value": "2025-04-28",
      "precision": "day",
      "basis": "actual"
    },
    "adams": [
      "ML26244A257",
      "ML26243A056"
    ],
    "reader": {
      "decision": {
        "headline": "Construction permit issued for TVA's Clinch River Unit 1",
        "what": "A construction permit was issued to TVA for Clinch River Nuclear Unit 1. It is immediately effective and authorizes construction of a power reactor facility in Roane County, Tennessee.",
        "limit": "No construction start is recorded; a permit is not a physical construction start.",
        "dates_note": "Federal Register notice: 5 October 2026. Construction completion: earliest 1 October 2031, latest 30 September 2032."
      },
      "application": {
        "headline": "Application for the Clinch River Unit 1 construction permit",
        "what": "The NRC milestone table records the environmental report (part one) as submitted on 28 Apr 2025 and the preliminary safety analysis report (part two) on 20 May 2025.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 28 Sep 2026. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-acu-msrr-cp-2024",
    "name": "ACU Molten Salt Research Reactor construction permit",
    "action_type": "construction_permit",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-natura-msr-1-acu",
    "design_id": "dsn-msr-1",
    "decision_date": {
      "value": "2024-09-16",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "50-610"
    ],
    "permit_numbers": [
      "CPRR-124"
    ],
    "adams": [
      "ML24243A040"
    ],
    "federal_register": [
      {
        "citation": "89 FR 77197",
        "document_number": "2024-21468",
        "published": "2024-09-20"
      }
    ],
    "sources": [
      "src-fr-acu-cprr124-2024",
      "src-fr-acu-ea-2024",
      "src-fr-acu-cp-docketing-2022"
    ],
    "confidence": "high",
    "last_checked": "2026-10-03",
    "review_state": "verified",
    "summary": "The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center on its Abilene campus. ACU's application is dated 12 August 2022; the NRC notified ACU by letter dated 18 November 2022 that it was acceptable for docketing. Operation needs a separate operating licence.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "submitted_date": {
      "value": "2022-08-12",
      "precision": "day",
      "basis": "actual"
    },
    "date_sources": {
      "submitted_date": "src-fr-acu-ea-2024"
    },
    "reader": {
      "application": {
        "headline": "ACU applies for its molten salt research reactor construction permit",
        "what": "Abilene Christian University's construction permit application is dated 12 Aug 2022. The NRC notified ACU by letter dated 18 Nov 2022 that it was acceptable for docketing.",
        "limit": "The date is the application's own date, not an NRC receipt date. The application itself is not an issued permission.",
        "date_label": "Application dated",
        "dates_note": "Later decision: 16 Sep 2024. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-pioneer-cp-lwa-application-2026",
    "name": "Pioneer Units 1 and 2 phased construction permit application (with limited work authorization request)",
    "action_type": "construction_permit",
    "status": "under_review",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-holtec-palisades",
    "design_id": "dsn-smr-300",
    "submitted_date": {
      "value": "2025-12-31",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "50-616",
      "50-617"
    ],
    "federal_register": [
      {
        "citation": "91 FR 62565",
        "document_number": "2026-20094",
        "published": "2026-10-01"
      },
      {
        "citation": "91 FR 66740",
        "document_number": "2026-21588",
        "published": "2026-10-22"
      },
      {
        "citation": "91 FR 72577",
        "document_number": "2026-22884",
        "published": "2026-11-10"
      }
    ],
    "sources": [
      "src-fr-pioneer-cp-lwa-2026",
      "src-nrc-holtec-pioneer-lwa",
      "src-holtec-pioneer-regulatory-2026",
      "src-fr-pioneer-fourth-receipt-20261022",
      "src-fr-pioneer-part2-receipt-20261110",
      "src-nrc-holtec-pioneer-page"
    ],
    "confidence": "high",
    "last_checked": "2026-10-25",
    "review_state": "verified",
    "summary": "Holtec filed Part 1 of a phased construction permit application for two SMR-300 units (Pioneer 1 and 2) at the Palisades Energy Center on 31 December 2025, including a limited work authorization request. The NRC accepted it for docketing in February 2026 and began weekly notices of receipt on 1 October 2026. Its fourth notice, published 22 October, again records receipt and availability; it does not grant an LWA or construction permit. Part 2 (a complete preliminary safety analysis report, with an updated Quality Assurance Topical Report and exemption requests) was filed on 30 September 2026, according to the NRC's notice of receipt dated 5 November and published 10 November 2026 (91 FR 72577; ADAMS package ML26273A416), which began a second series of four weekly notices. The notice says the NRC staff was then undertaking its acceptance review of Part 2; no acceptance or docketing of Part 2 is recorded. The application remains recorded as under review; this receipt notice is not a new permission decision.",
    "applies_to": "project",
    "permission_stage": "construction_permission"
  },
  {
    "stable_id": "reg-pioneer-excavation-walls-exemption-2026",
    "name": "NRC exemption for specified Pioneer support-of-excavation walls before LWA",
    "action_type": "other",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-holtec-palisades",
    "design_id": "dsn-smr-300",
    "decision_date": {
      "value": "2026-08-28",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "50-616",
      "50-617"
    ],
    "federal_register": [
      {
        "citation": "91 FR 55628",
        "document_number": "2026-17626",
        "published": "2026-08-28"
      }
    ],
    "sources": [
      "src-fr-pioneer-excavation-exemption-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-09",
    "review_state": "verified",
    "summary": "The NRC issued a narrow exemption on 28 August 2026 allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization. The notice does not issue or commit to an LWA or construction permit. The exemption does not show that physical work began or authorize all construction.",
    "applies_to": "project",
    "permission_stage": "other",
    "reader": {
      "decision": {
        "headline": "NRC allows specified Pioneer excavation walls before a limited work authorization",
        "what": "The NRC issued a narrow exemption allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization.",
        "limit": "It does not issue or commit to a limited work authorization or construction permit, or show that physical work began."
      }
    }
  },
  {
    "stable_id": "reg-pioneer-excavation-ea-fonsi-2026",
    "name": "NRC environmental assessment and FONSI for Pioneer excavation-wall exemption",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-holtec-palisades",
    "design_id": "dsn-smr-300",
    "decision_date": {
      "value": "2026-08-25",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "50-616",
      "50-617"
    ],
    "federal_register": [
      {
        "citation": "91 FR 54890",
        "document_number": "2026-17253",
        "published": "2026-08-25"
      }
    ],
    "sources": [
      "src-fr-pioneer-excavation-ea-fonsi-2026",
      "src-fr-pioneer-excavation-exemption-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-09",
    "review_state": "verified",
    "summary": "The NRC made an environmental assessment and finding of no significant impact available on 24 August 2026; its later exemption notice describes the finding as issued on 25 August. It addresses environmental effects of the requested support-of-excavation-wall exemption; it is not the 28 August exemption and does not issue an LWA or construction permit.",
    "applies_to": "project",
    "permission_stage": "environmental_decision",
    "reader": {
      "decision": {
        "headline": "NRC finds no significant environmental impact for Pioneer excavation-wall exemption",
        "what": "The NRC issued an environmental assessment and finding of no significant impact covering the environmental effects of the requested Pioneer support-of-excavation-wall exemption.",
        "limit": "It is not the 28 August exemption and does not issue a limited work authorization or construction permit.",
        "dates_note": "Made available: 24 August 2026. The later exemption notice describes it as issued on 25 August."
      }
    }
  },
  {
    "stable_id": "reg-doe-cx-271002-aalo",
    "name": "DOE Idaho categorical exclusion CX-271002 for the Aalo-X critical assembly",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Energy, Idaho Operations Office",
    "country": "US",
    "project_id": "prj-aalo-x-inl",
    "design_id": "dsn-aalo-x",
    "decision_date": {
      "value": "2026-04-14",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-doe-cx-271002-pdf"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified",
    "summary": "Approved 14 April 2026 under posting DOE-ID-INL-26-013. Covers installation and zero-power operation of the critical assembly at no more than 10 watts thermal. It is an environmental categorical exclusion, not a construction permit or operating licence, and it does not authorize a later power reactor.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-doe-cx-035340-mark0",
    "name": "DOE Idaho categorical exclusion CX-035340 for the Antares Mark-0 experiment",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Energy, Idaho Operations Office",
    "country": "US",
    "project_id": "prj-antares-mark0-inl",
    "design_id": "dsn-mark-0",
    "decision_date": {
      "value": "2026-01-26",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-doe-cx-035340-pdf"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified",
    "summary": "Approved 26 January 2026 under posting DOE-ID-INL-25-037. Covers the zero-power Mark-0 heat-pipe experiment in MFC-793. No measurable thermal output is claimed. This is not an operating licence, and it does not approve the later Mark-1 reactor.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-doe-cx-271007-unity",
    "name": "DOE Idaho categorical exclusion CX-271007 for the Unity zero-power test",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Energy, Idaho Operations Office",
    "country": "US",
    "project_id": "prj-unity-inl",
    "design_id": "dsn-unity",
    "decision_date": {
      "value": "2026-04-15",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-doe-cx-271007-pdf"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified",
    "summary": "Approved 15 April 2026 under posting DOE-ID-INL-26-011. Covers a zero-power criticality test bounded at 0 MWth and 0 kWe. It does not authorize the future 1 MWe configuration and is not an operating licence.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-doe-cx-271015-ward",
    "name": "DOE categorical exclusion CX-271015 for the Ward250 research reactor",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Energy, Office of Nuclear Energy",
    "country": "US",
    "project_id": "prj-ward-250",
    "design_id": "dsn-ward-250",
    "decision_date": {
      "value": "2026-04-22",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-doe-cx-271015-pdf"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-04",
    "review_state": "verified",
    "summary": "Signed 22 April 2026 under NEPA identification DOE-ID-26-005. Determines that the 250 kWth Ward250 research reactor at USREL fits a categorical exclusion. It states no authorization number and no electrical output, and it does not confirm the company's later electricity claim.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-nrc-uiuc-kronos-cp-2026",
    "name": "NRC construction permit application for the University of Illinois KRONOS MMR",
    "action_type": "construction_permit",
    "status": "under_review",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-uiuc-kronos",
    "design_id": "dsn-kronos-mmr",
    "submitted_date": {
      "value": "2026-03-31",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nrc-uiuc-kronos-2026",
      "src-fr-uiuc-cp-receipt-2026",
      "src-fr-uiuc-cp-docketing-2026"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-03",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "The university applied for a construction permit for one research reactor by letter dated 27 March 2026; the NRC records it as tendered on 31 March 2026, accepted it for docketing on 18 May 2026 as Docket No. 50-618 and published the hearing opportunity on 26 May 2026. The stated application power level is 45 MWth. No permit has been issued; target review dates in 2027 are not decisions.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "docket": [
      "50-618"
    ],
    "adams": [
      "ML26090A463",
      "ML26120A548"
    ],
    "federal_register": [
      {
        "citation": "91 FR 21321",
        "document_number": "2026-07677",
        "published": "2026-04-21"
      },
      {
        "citation": "91 FR 30730",
        "document_number": "2026-10419",
        "published": "2026-05-26"
      }
    ]
  },
  {
    "stable_id": "reg-asnr-jimmy-dac-2024",
    "name": "Jimmy Bazancourt creation-authorization application",
    "action_type": "other",
    "status": "under_review",
    "regulator": "ASNR",
    "country": "FR",
    "project_id": "prj-jimmy-bazancourt",
    "design_id": "dsn-jimmy-heat",
    "submitted_date": {
      "value": "2024",
      "precision": "year",
      "basis": "actual"
    },
    "sources": [
      "src-asnr-prm-20261005",
      "src-asnr-annual-report-2024-jimmy"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified",
    "summary": "ASNR records Jimmy's 2024 creation-authorization application for an industrial-heat reactor at a Cristal Union factory in Bazancourt. Published filing dates differ across the project sources, so the stored submission date remains at year precision. MSNR requested further information on 13 February 2025. Jimmy submitted an updated design and the remaining answers on 23 July 2026, and MSNR referred that updated file to ASNR for review on 24 July 2026. These sources do not record an issued creation authorization.",
    "applies_to": "project",
    "permission_stage": "construction_permission"
  },
  {
    "stable_id": "reg-asnr-stellaria-alpha-2025",
    "name": "Stellaria INB Alpha creation-authorization application",
    "action_type": "other",
    "status": "under_review",
    "regulator": "ASNR",
    "country": "FR",
    "project_id": "prj-stellaria-alvin-cadarache",
    "submitted_date": {
      "value": "2025-12-19",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-asnr-prm-20261005",
      "src-asnr-prm-20261014"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "summary": "ASNR states that Stellaria filed a creation-authorization application on 19 December 2025 for INB Alpha, including the ALVIN research reactor at CEA Cadarache. MSNR referred it to ASNR on 22 December 2025. Following ASNR analysis, MSNR requested further information on 16 June 2026. The page updated 14 October says technical review is suspended pending that information; it does not separately date the suspension. No creation authorization is recorded.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "design_id": "dsn-alvin",
    "status_note": "ASNR says technical review is suspended pending further information requested on 16 June 2026."
  },
  {
    "stable_id": "reg-asnr-calogena-options-2024",
    "name": "Calogena CAL30 safety-options requests",
    "action_type": "other",
    "status": "under_review",
    "regulator": "ASNR",
    "country": "FR",
    "project_id": null,
    "design_id": "dsn-catalogue-cal-30",
    "submitted_date": {
      "value": "2024-10-31",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-asnr-prm-20261005",
      "src-asnr-prm-20261014",
      "src-asnr-cal30-opinion-2026-av027"
    ],
    "confidence": "high",
    "last_checked": "2026-10-27",
    "review_state": "verified",
    "summary": "ASNR records a CAL30 safety-options request on 31 October 2024 and further requests through 28 August 2026. Its 19 May 2026 opinion concerns shutdown-system diversification: principles are broadly satisfactory, with stronger electrical diversification, detailed design and qualification evidence, and a simple, robust alternative shutdown means required for possible common-mode rod blockage. These are requirements for a possible future creation-authorization application, not whole-design approval or a Cadarache site permission. The opinion dates the amended letter 19 June 2025, while the earlier listing records 20 June 2025.",
    "applies_to": "design",
    "permission_stage": "design_assessment"
  },
  {
    "stable_id": "reg-asnr-lfr-as-30-options-2025",
    "name": "newcleo LFR-AS-30 safety-options request",
    "action_type": "other",
    "status": "submitted",
    "regulator": "ASNR",
    "country": "FR",
    "project_id": null,
    "design_id": "dsn-catalogue-lfr-as-30",
    "submitted_date": {
      "value": "2025-12-19",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-asnr-prm-20261005"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "summary": "ASNR states that newcleo filed a safety-options request on 19 December 2025 for LFR-AS-30. The page does not record an opinion or a creation authorization.",
    "applies_to": "design",
    "permission_stage": "design_assessment"
  },
  {
    "stable_id": "reg-asnr-otrera-one-options-2026",
    "name": "OTRERA ONE safety-options request",
    "action_type": "other",
    "status": "submitted",
    "regulator": "ASNR",
    "country": "FR",
    "project_id": null,
    "design_id": "dsn-otrera-one",
    "submitted_date": {
      "value": "2026-07-30",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-asnr-prm-20261005"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "summary": "ASNR states that Otrera filed a safety-options request on 30 July 2026 for OTRERA ONE, listed on the 14 October 2026 page as a 200 MWth sodium-cooled demonstrator/prototype. The page does not record an opinion or a creation authorization. This is not a sited project.",
    "applies_to": "design",
    "permission_stage": "design_assessment"
  },
  {
    "stable_id": "reg-nrc-belews-creek-esp-2025",
    "name": "Belews Creek early site permit application",
    "action_type": "other",
    "status": "under_review",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-belews-creek",
    "submitted_date": {
      "value": "2025-12-30",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "52-055"
    ],
    "adams": [
      "ML25364A004",
      "ML26016A624",
      "ML26259A008",
      "ML26274A437"
    ],
    "federal_register": [
      {
        "citation": "91 FR 5787",
        "document_number": "2026-02521",
        "published": "2026-02-09"
      },
      {
        "citation": "91 FR 542",
        "document_number": "2026-00090",
        "published": "2026-01-07"
      },
      {
        "citation": "91 FR 22549",
        "document_number": "2026-08155",
        "published": "2026-04-27"
      },
      {
        "citation": "91 FR 50896",
        "document_number": "2026-16044",
        "published": "2026-08-06"
      }
    ],
    "sources": [
      "src-fr-belews-esp-docketed-2026",
      "src-fr-belews-esp-receipt-2026",
      "src-fr-belews-esp-eis-scoping-2026",
      "src-fr-belews-esp-hearing-2026",
      "src-nrc-belews-creek-esp-page",
      "src-nrc-belews-esp-fee-schedule-20260929",
      "src-duke-belews-esp-rev2-20261001"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "summary": "Duke Energy Carolinas applied on 30 December 2025 for an early site permit for the Belews Creek site in Stokes and Forsyth counties, North Carolina. The NRC accepted and docketed the application in February 2026 under Docket No. 52-055, and it is under review. If issued, an early site permit approves a site independent of a specific plant design. It is not a construction permit or a combined licence, and no reactor design is selected. The NRC gave notice on 27 April 2026 that it will prepare an environmental impact statement, and its project page marks the uncontested hearing of 17 September 2026 as held. On 29 September 2026, NRC letter ML26259A008 set a $2,178,000 cap on NRC review fees. That cap is not a project cost or a permit. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The letter accelerates the 8 February 2026 schedule. NRC targets, not completed: advanced final safety evaluation report without open items December 2026 (from March 2027), draft environmental impact statement December 2026 (from February 2027), final safety evaluation February 2027 (from May 2027), and final environmental impact statement March 2027 (from May 2027). The decision date is listed as to be determined. Duke Energy Carolinas' Revision 2 cover letter (ML26274A437), dated 1 October 2026, states that Duke is not requesting a limited work authorization. The NRC project page lists the Revision 2 package as ML26274A436.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-dod-pele-rod-2022",
    "name": "Project Pele record of decision (prototype mobile microreactor environmental impact statement)",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Defense, Strategic Capabilities Office",
    "country": "US",
    "project_id": "prj-pele-inl",
    "design_id": "dsn-pele",
    "decision_date": {
      "value": "2022-04-05",
      "precision": "day",
      "basis": "actual"
    },
    "federal_register": [
      {
        "citation": "87 FR 22521",
        "document_number": "2022-08039",
        "published": "2022-04-15"
      }
    ],
    "sources": [
      "src-fr-pele-rod-2022"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified",
    "summary": "Signed 5 April 2022 and published 15 April 2022 at 87 FR 22521. The Strategic Capabilities Office decided to implement the proposed action of its final environmental impact statement: fabricate the prototype mobile microreactor and its fuel at existing off-site commercial facilities and demonstrate it at the Idaho National Laboratory Site. This is a National Environmental Policy Act decision. This record addresses the environmental decision; it does not establish the status of any separate DOE safety authorization. No such authorization document was opened.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-doe-marvel-fonsi-2021",
    "name": "DOE finding of no significant impact for MARVEL (DOE/EA-2146)",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Energy, Idaho Operations Office",
    "country": "US",
    "project_id": "prj-inl-marvel",
    "design_id": "dsn-aris-marvel",
    "decision_date": {
      "value": "2021-11-12",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-doe-ea-2146-fonsi-2021"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified",
    "summary": "Issued at Idaho Falls on 12 November 2021 for environmental assessment DOE/EA-2146. DOE found that designing and demonstrating MARVEL in the north high bay of the Transient Reactor Test facility would not significantly affect the human environment, so no environmental impact statement is required. It is an environmental finding. It is not approval of a safety analysis and not authority to load fuel or operate. The 2021 text describes about 20 kW electric; DOE's current project page gives 85 kW thermal and about 10 kW electric.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-nrc-aurora-col-2020-denied",
    "name": "Oklo Aurora custom combined licence application (2020), denied without prejudice",
    "action_type": "other",
    "status": "denied",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-aurora-inl",
    "submitted_date": {
      "value": "2020-03-11",
      "precision": "day",
      "basis": "actual"
    },
    "decision_date": {
      "value": "2022-01-06",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "52-049"
    ],
    "adams": [
      "ML20075A001",
      "ML21357A034"
    ],
    "federal_register": [
      {
        "citation": "87 FR 1441",
        "document_number": "2022-00339",
        "published": "2022-01-11"
      }
    ],
    "sources": [
      "src-fr-oklo-aurora-col-denial-2022",
      "src-nrc-oklo-aurora-preapp"
    ],
    "confidence": "high",
    "last_checked": "2026-10-05",
    "review_state": "verified",
    "summary": "Oklo Power applied on 11 March 2020 for a custom combined licence, which covers construction and operation, for one Aurora microreactor at Idaho National Laboratory. The NRC denied it without prejudice by letter of 6 January 2022 because requested information was not provided, and said Oklo may resubmit. This is an earlier application than the current Aurora powerhouse, which is following DOE authorization under the Reactor Pilot Program. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only (project 99902095) and no docketed application.",
    "applies_to": "project",
    "permission_stage": "other",
    "reader": {
      "application": {
        "headline": "Application for the Aurora combined licence",
        "what": "The recorded application date for the Aurora combined licence is 11 Mar 2020.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later denial decision: 6 Jan 2022. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-haiyang-small-reactor-siting-opinion-2024",
    "name": "NNSA site-selection review opinion No. 2414, Haiyang integrated small reactor demonstration",
    "action_type": "other",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-haiyang-integrated-small-reactor",
    "design_id": null,
    "decision_date": {
      "value": "2024-09-10",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nnsa-haiyang-siting-opinion-2024"
    ],
    "confidence": "high",
    "last_checked": "2026-10-06",
    "review_state": "verified",
    "summary": "The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2414号) on 10 September 2024 for one 200 MWt integrated natural-circulation small PWR and auxiliary facilities at the southwest corner of the Haiyang nuclear plant site. The opinion agrees that design work may proceed on the stated site parameters.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-doe-aurora-nepa-20260720",
    "name": "DOE Aurora-INL B5.26 environmental categorical exclusion",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Energy, Idaho Operations Office",
    "country": "US",
    "project_id": "prj-aurora-inl",
    "design_id": "dsn-aurora",
    "decision_date": {
      "value": "2026-07-20",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-doe-id-inl-26-018-aurora-20260720"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified",
    "summary": "DOE Idaho approved environmental determination DOE-ID-INL-26-018 on 20 July 2026 for the proposed Aurora-INL reactor construction, installation and operation scope under B5.26. The document describes anticipated activities and a planned construction period; it is an environmental determination, not evidence that reactor construction occurred, an approval of the preliminary safety analysis, or authority to load fuel or operate.",
    "applies_to": "project",
    "permission_stage": "environmental_decision"
  },
  {
    "stable_id": "reg-doe-pwr5-phase1-nepa-20260930",
    "name": "DOE PWR-5 Phase 1 environmental categorical exclusion",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "U.S. Department of Energy, Office of Nuclear Energy",
    "country": "US",
    "project_id": "prj-last-energy-rellis",
    "design_id": "dsn-pwr-5",
    "decision_date": {
      "value": "2026-09-30",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-doe-id-26-008-pwr5-20260930"
    ],
    "confidence": "high",
    "last_checked": "2026-10-08",
    "review_state": "verified",
    "summary": "DOE approved NEPA determination DOE-ID-26-008 on 30 September 2026 for proposed PWR-5 Phase 1 initial criticality and low-power testing at RELLIS. The Phase 1 research configuration is bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export. The 19.5 MWth PWR-5 design point applies to later phases. This environmental decision is not DOE startup authorization, proof of achieved criticality, or authorization for later phases.",
    "applies_to": "project",
    "permission_stage": "environmental_decision",
    "reader": {
      "decision": {
        "headline": "DOE approves environmental determination for PWR-5 Phase 1 testing at RELLIS",
        "what": "DOE approved a NEPA determination for proposed PWR-5 Phase 1 initial criticality and low-power testing, bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export.",
        "limit": "This is not DOE startup authorization or proof that criticality occurred."
      }
    }
  },
  {
    "stable_id": "reg-cncan-doicesti-siting-application",
    "name": "Doicești NuScale siting licence application",
    "action_type": "licence_to_prepare_site",
    "status": "under_review",
    "regulator": "CNCAN",
    "country": "RO",
    "project_id": "prj-nuscale-romania",
    "design_id": "dsn-voygr",
    "sources": [
      "src-cncan-national-report-2025",
      "src-dcbusiness-cncan-doicesti-2026",
      "src-snn-doicesti-fid-conditions-note-202610"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified",
    "summary": "CNCAN's August 2025 national report says an application for the NuScale VOYGR-6 design and Doicești siting licences was submitted with only part of the supporting documents, and regulatory review was ongoing. The report does not date the filing or grant a licence. A June 2026 report quoting CNCAN says no approval or permit had been issued. Nuclearelectrica's note for its 29 October 2026 shareholder meeting says the start of site-characterisation studies required to obtain the site licence has been delayed; that is the company's statement and reports no CNCAN decision. This action tracks the site application, not design certification or construction authority.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-nrc-blue-energy-cp-lwa-part1-2026",
    "name": "Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application, Part 1 (with limited work authorization request)",
    "action_type": "construction_permit",
    "status": "submitted",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-blue-energy-victoria",
    "design_id": "dsn-bwrx-300",
    "submitted_date": {
      "value": "2026-09-15",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "99902137"
    ],
    "adams": [
      "ML26265A371",
      "ML26258A339"
    ],
    "federal_register": [
      {
        "citation": "91 FR 64409",
        "document_number": "2026-20678",
        "published": "2026-10-08"
      }
    ],
    "sources": [
      "src-fr-blue-energy-cp-lwa-receipt-2026",
      "src-blue-energy-cpa-part1-20260915",
      "src-govinfo-blue-energy-cp-lwa-receipt-20261019"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "review_state": "verified",
    "summary": "Blue Energy filed Part 1 of a phased construction permit application on 15 September 2026 for one BWRX-300 unit, Blue Energy Center–Port of Victoria Nuclear Unit 1, in Victoria, Texas. Part 1 includes a limited work authorization request, two related exemption requests and an environmental report. The NRC published a notice of receipt on 8 October 2026 (91 FR 64409). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction. The applicant intends to file the full construction permit application within 18 months of Part 1.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "reader": {
      "application": {
        "headline": "Blue Energy files Part 1 of a construction permit application for Port of Victoria",
        "what": "Blue Energy filed Part 1 of a phased construction permit application for one BWRX-300 unit in Victoria, Texas. It includes a limited work authorization request, two exemption requests and an environmental report.",
        "why": "It is the first part of a phased application; the applicant intends to file the full application within 18 months of Part 1.",
        "limit": "The NRC has reported receipt only, not acceptance for docketing, a limited work authorization or a construction permit.",
        "dates_note": "NRC notice of receipt: 8 October 2026. Blue Energy asked for acceptance review of specified items by 20 November 2026."
      }
    }
  },
  {
    "stable_id": "reg-nrc-us460-sda-2025",
    "name": "NRC standard design approval for the NuScale US460",
    "action_type": "standard_design_approval",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": null,
    "design_id": "dsn-voygr",
    "decision_date": {
      "value": "2025-05-29",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-fr-us460-sda-2025",
      "src-fr-us460-sda-receipt-2023",
      "src-fr-us460-sda-docketing-2023"
    ],
    "confidence": "high",
    "last_checked": "2026-10-10",
    "review_state": "verified",
    "summary": "The NRC issued a standard design approval to NuScale Power for the US460 small modular reactor design on 29 May 2025, completing its staff technical review. NuScale submitted the application in stages: the first part by letter dated 23 November 2022 and the remaining portions in stages between 29 November and 31 December 2022. The NRC notified NuScale by letter dated 31 July 2023 that the application was acceptable for docketing. The approval lets an applicant reference the design in a construction permit, operating licence, combined licence or manufacturing licence application. It is a design approval only: it grants no permission for any site, construction or operation.",
    "adams": [
      "ML25129A004",
      "ML25086A073"
    ],
    "federal_register": [
      {
        "citation": "90 FR 23716",
        "document_number": "2025-10123",
        "published": "2025-06-04"
      }
    ],
    "applies_to": "design",
    "permission_stage": "design_assessment"
  },
  {
    "stable_id": "reg-nnsa-xuwei-u3-cl-review-2025",
    "name": "NNSA construction licence 国核安证字第2621号 for Xuwei Phase I Unit 3 (HTGR)",
    "action_type": "construction_permit",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-xuwei-htgr-unit3",
    "design_id": null,
    "sources": [
      "src-nnsa-xuwei-unit3-review-2025",
      "src-nnsa-xuwei-inspection-20261009",
      "src-nnsa-xuwei-u3-construction-licence-2621-20261102"
    ],
    "confidence": "high",
    "last_checked": "2026-11-04",
    "review_state": "verified",
    "summary": "China's nuclear regulator reported on 26 June 2025 that it had started the construction-licence review for Unit 3 of the Xuwei nuclear heating and power plant, covering the preliminary safety analysis report and the construction-stage environmental impact report, with CNNC Sueneng Nuclear Power presenting the high-temperature gas-cooled reactor. That notice gives no filing day and no licence decision. The 9 October 2026 pre-construction inspection report found that preparations met the conditions for issuing a construction licence and set seven corrective requirements; it does not itself issue the licence. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction licence 国核安证字第2621号 for Unit 3 to CNNC Sueneng, valid to 1 November 2036, and says the company may begin pouring the first concrete for the nuclear-island foundation. The licence requires an operating-licence application before first fuel loading. It is not an operating licence. No construction start is recorded; a permit is not a physical construction start.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "decision_date": {
      "value": "2026-11-02",
      "precision": "day",
      "basis": "actual"
    },
    "permit_numbers": [
      "国核安证字第2621号"
    ],
    "date_sources": {
      "decision_date": "src-nnsa-xuwei-u3-construction-licence-2621-20261102"
    },
    "reader": {
      "decision": {
        "headline": "Construction licence issued for Xuwei Unit 3",
        "what": "NNSA issued construction licence No. 2621 to CNNC Sueneng on 2 November 2026, valid to 1 November 2036, and said the company may begin pouring first concrete for the nuclear-island foundation.",
        "limit": "No construction start is recorded; a permit is not a physical construction start. It is not an operating licence."
      }
    }
  },
  {
    "stable_id": "reg-nnsa-xuwei-htgr-design-criteria-2026",
    "name": "NNSA approval of the Xuwei HTGR safety design criteria",
    "action_type": "other",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-xuwei-htgr-unit3",
    "design_id": null,
    "decision_date": {
      "value": "2026-08-31",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nnsa-xuwei-htgr-criteria-2026",
      "src-nnsa-xuwei-criteria-instrument-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "summary": "NNSA instrument 国核安发〔2026〕161号, signed 31 August 2026, approves B-version safety design criteria for the Xuwei HTGR. Its later 29 September announcement describes a small nuclear power reactor with multiple modules and one turbine. The criteria guide safety review and are not a construction licence.",
    "applies_to": "project",
    "permission_stage": "other",
    "reader": {
      "decision": {
        "headline": "NNSA approves safety design criteria for the Xuwei high-temperature reactor",
        "what": "NNSA approved B-version safety design criteria for the Xuwei HTGR. Its later announcement describes a small nuclear power reactor with multiple modules and one turbine.",
        "limit": "The criteria guide safety review; they are not a construction licence."
      }
    }
  },
  {
    "stable_id": "reg-se-gov-approval-malma-2026",
    "name": "Swedish Government approval application for a nuclear facility at Målma, Valdemarsvik",
    "action_type": "other",
    "status": "under_review",
    "regulator": "Government of Sweden",
    "country": "SE",
    "project_id": "prj-knxt-valdemarsvik",
    "design_id": null,
    "submitted_date": {
      "value": "2026-03-23",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-se-gov-provning-20261002",
      "src-se-gov-malma-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "Refirm Målma AB applied on 23 March 2026 for the Government's approval of a nuclear facility at Målma in Valdemarsvik municipality, the first application under the new law; on 7 May 2026 the Government assigned the Östergötland county administrative board to draft a facility plan. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, licence or construction is established.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-se-gov-approval-norrsundet-2026",
    "name": "Swedish Government approval application for a nuclear facility at Norrsundet, Gävle",
    "action_type": "other",
    "status": "under_review",
    "regulator": "Government of Sweden",
    "country": "SE",
    "project_id": "prj-sealer-norrsundet",
    "design_id": null,
    "submitted_date": {
      "value": "2026-05-18",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-se-gov-provning-20261002",
      "src-se-gov-norrsundet-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "Blykalla AB applied on 18 May 2026 for the Government's approval of a nuclear facility at Norrsundet in Gävle municipality; on 28 May 2026 the Government assigned the Gävleborg county administrative board to draft a facility plan by 31 December 2026. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, licence or construction is established.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-se-gov-approval-studsvik-2026",
    "name": "Swedish Government approval application for a nuclear facility at Studsvik, Nyköping",
    "action_type": "other",
    "status": "under_review",
    "regulator": "Government of Sweden",
    "country": "SE",
    "project_id": "prj-studsvik-nykoping",
    "design_id": null,
    "submitted_date": {
      "value": "2026-05-25",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-se-gov-provning-20261002",
      "src-se-gov-studsvik-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "Studsvik AB applied on 25 May 2026 for the Government's approval of a nuclear facility for two to four light-water reactors of about 600-1,400 MW in total at Studsvik in Nyköping municipality; on 9 June 2026 the Government assigned the Södermanland county administrative board to draft a facility plan by 31 December 2026. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, licence or construction is established.",
    "applies_to": "project",
    "permission_stage": "site_permission"
  },
  {
    "stable_id": "reg-se-gov-approval-untra-2026",
    "name": "Swedish Government approval application for a nuclear facility at Untra, Tierp",
    "action_type": "other",
    "status": "under_review",
    "regulator": "Government of Sweden",
    "country": "SE",
    "project_id": "prj-sealer-untra",
    "design_id": null,
    "submitted_date": {
      "value": "2026-08-25",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-se-gov-provning-20261002",
      "src-se-gov-untra-plan-2026"
    ],
    "confidence": "high",
    "last_checked": "2026-11-03",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "Blykalla AB applied on 25 August 2026 (recorded as received on 26 August) for the Government's approval of eight lead-cooled small modular reactors of about 440 MW in total at Untra in Tierp municipality; on 28 August 2026 the Government assigned the Uppsala county administrative board to draft a facility plan by 30 April 2027. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, licence or construction is established.",
    "applies_to": "project",
    "permission_stage": "site_permission",
    "reader": {
      "application": {
        "headline": "Blykalla applies for Government approval of eight lead-cooled SMRs at Untra, Tierp",
        "what": "Blykalla AB applied for the Government's approval of eight lead-cooled small modular reactors of about 440 MW in total at Untra in Tierp municipality.",
        "why": "Approval would replace the Environmental Code permissibility review, but not licensing under the Environmental Code and the Nuclear Activities Act.",
        "limit": "Approval needs municipal consent and a facility plan in force.",
        "dates_note": "Received 26 August. Facility plan assigned 28 August to Uppsala county administrative board, due 30 April 2027."
      }
    }
  },
  {
    "stable_id": "reg-nnsa-tmsr-lf1-operating-2023",
    "name": "TMSR-LF1 operating licence 2307",
    "summary": "NNSA issued operating licence 国核安证字第2307号 to SINAP on 7 June 2023, expiring 6 June 2033. The instrument includes separate commissioning hold points; it does not prove their release.",
    "sources": [
      "src-nnsa-tmsr-lf1-operating-2023"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-13",
    "review_state": "verified",
    "action_type": "operating_licence",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-tmsr-lf1-wuwei",
    "design_id": "dsn-tmsr-lf1",
    "applies_to": "project",
    "permission_stage": "operating_authority",
    "decision_date": {
      "value": "2023-06-07",
      "precision": "day",
      "basis": "actual"
    },
    "docket": "国核安证字第2307号"
  },
  {
    "stable_id": "reg-ansn-ucri-request-2025",
    "name": "Reported IEN request to construct the UCRI critical unit",
    "summary": "CNEN reports an IEN letter to ANSN dated 2 December 2025 seeking construction permission and use of Argonauta facilities for the critical experiment. This is a reported submission; the letter, acceptance and a permission decision are not recorded.",
    "sources": [
      "src-cnen-ucri-licensing-20251215"
    ],
    "confidence": "medium",
    "last_checked": "2026-11-11",
    "review_state": "verified",
    "action_type": "other",
    "status": "submitted",
    "regulator": "ANSN",
    "country": "BR",
    "project_id": "prj-ucri-ien",
    "design_id": null,
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "submitted_date": {
      "value": "2025-12-02",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "reg-darlington-bwrx-cnsc-consent-to-remove-regulatory-hold-point",
    "name": "CNSC consent to remove Regulatory Hold Point 1 (reactor building foundation)",
    "action_type": "other",
    "status": "approved",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": "prj-darlington-bwrx",
    "sources": [
      "src-det-711174994e"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "Submitted date is OPG's request letter of 25 March 2026 cited as reference [1] in the CNSC letter.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2026-03-30",
      "precision": "day",
      "basis": "actual"
    },
    "submitted_date": {
      "value": "2026-03-25",
      "precision": "day",
      "basis": "actual"
    },
    "permit_numbers": [
      "PRCL 32.01/2035"
    ],
    "reader": {
      "application": {
        "headline": "Request to remove Darlington Regulatory Hold Point 1",
        "what": "The recorded application date for removal of Darlington Regulatory Hold Point 1 is 25 Mar 2026.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 30 Mar 2026. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-darlington-bwrx-renewal-of-darlington-new-nuclear-project-si",
    "name": "Renewal of Darlington New Nuclear Project site preparation licence (PRSL 18.00/2031)",
    "action_type": "licence_to_prepare_site",
    "status": "approved",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": "prj-darlington-bwrx",
    "sources": [
      "src-det-10a0d119bb"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "Record of Decision DEC 21-H4; application received 29 June 2020.",
    "applies_to": "project",
    "permission_stage": "site_permission",
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2021-10-12",
      "precision": "day",
      "basis": "actual"
    },
    "submitted_date": {
      "value": "2020-06-29",
      "precision": "day",
      "basis": "actual"
    },
    "permit_numbers": [
      "PRSL 18.00/2031"
    ],
    "reader": {
      "application": {
        "headline": "Application to renew the Darlington site preparation licence",
        "what": "The recorded application date for renewal of the Darlington site preparation licence is 29 Jun 2020.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 12 Oct 2021. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-darlington-bwrx-original-darlington-new-nuclear-project-site",
    "name": "Original Darlington New Nuclear Project site preparation licence (PRSL 18.00/2022)",
    "action_type": "licence_to_prepare_site",
    "status": "superseded",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": "prj-darlington-bwrx",
    "sources": [
      "src-det-10a0d119bb",
      "src-cnsc-darlington-timeline-20261031"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "CNSC's project timeline records that Ontario Power Generation applied for a licence to prepare site in September 2006, for the original Darlington New Nuclear Project. The 2021 renewal decision says the licence was issued in 2012. The project timeline says the Joint Review Panel, as a panel of the Commission, issued a 10-year site preparation licence in 2012. The licence document itself was not opened, so the stored decision date stays at year precision.",
    "applies_to": "project",
    "permission_stage": "site_permission",
    "submitted_date": {
      "value": "2006-09",
      "precision": "month",
      "basis": "actual"
    },
    "date_sources": {
      "submitted_date": "src-cnsc-darlington-timeline-20261031"
    },
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2012",
      "precision": "year",
      "basis": "actual"
    },
    "permit_numbers": [
      "PRSL 18.00/2022"
    ],
    "reader": {
      "application": {
        "headline": "OPG applies for the original Darlington site preparation licence",
        "what": "CNSC's project timeline records that Ontario Power Generation applied for a licence to prepare site in Sep 2006, for the original Darlington New Nuclear Project.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: licence issued in 2012. The same timeline records OPG submitting its environmental impact statement and licence documentation in Sep 2009. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-clinch-river-bwrx-clinch-river-nuclear-site-early-site-permi",
    "name": "Clinch River Nuclear Site early site permit ESP-006",
    "action_type": "other",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-clinch-river-bwrx",
    "sources": [
      "src-det-88ab73b4f7"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "NRC: application for two or more SMR modules (up to 800 MWe, 2420 MWt) submitted 12 May 2016, docketed 30 Dec 2016; Commission decision 17 Dec 2019.",
    "applies_to": "project",
    "permission_stage": "site_permission",
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2019-12-19",
      "precision": "day",
      "basis": "actual"
    },
    "submitted_date": {
      "value": "2016-05-12",
      "precision": "day",
      "basis": "actual"
    },
    "permit_numbers": [
      "ESP-006"
    ],
    "reader": {
      "application": {
        "headline": "Application for the Clinch River early site permit",
        "what": "The recorded application date for the Clinch River early site permit is 12 May 2016.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 19 Dec 2019. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-ritm-jizzakh-permit-to-use-the-site-for-nuclear-installation",
    "name": "Permit to use the site for nuclear installations (Farish district NPP site)",
    "action_type": "other",
    "status": "approved",
    "regulator": "Committee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of the Republic of Uzbekistan",
    "country": "UZ",
    "project_id": "prj-ritm-jizzakh",
    "sources": [
      "src-det-4f21824b31"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "Regulator's own news item dated 4 June 2026 states the permit was issued on 23 March 'of the current year'. The notice reports permission to use the site designated for nuclear installations for NPP construction. It does not give a permit number.",
    "applies_to": "project",
    "permission_stage": "site_permission",
    "design_id": "dsn-ritm-200n",
    "decision_date": {
      "value": "2026-03-23",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "reg-ritm-jizzakh-licence-for-construction-of-an-npp-power-unit-w",
    "name": "Licence for construction of an NPP power unit with a RITM-200N reactor",
    "action_type": "licence_to_construct",
    "status": "approved",
    "regulator": "Committee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of the Republic of Uzbekistan",
    "country": "UZ",
    "project_id": "prj-ritm-jizzakh",
    "sources": [
      "src-det-4f21824b31",
      "src-d3-uzatom-first-concrete-20260604"
    ],
    "confidence": "high",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "Council of the Committee decided 'today' (item dated 2026-06-04) to issue the licence for construction of one power unit (singular 'энергоблока'); the Committee's notice states no licence number or holder. Uzatom states that the licence was issued to the state institution Directorate for the Construction of the Nuclear Power Plant; the licence number is not published.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "design_id": "dsn-ritm-200n",
    "decision_date": {
      "value": "2026-06-04",
      "precision": "day",
      "basis": "actual"
    }
  },
  {
    "stable_id": "reg-htr10-inet-nnsa-first-fuel-loading-licence-for-htr-10",
    "name": "NNSA first fuel loading licence for HTR-10",
    "action_type": "other",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-htr10-inet",
    "sources": [
      "src-nnsa-htr10-2014"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-14",
    "review_state": "verified",
    "summary": "Reported in NNSA's own 2014 letter attachment; the 2000 licence instrument itself was not opened, so no licence number.",
    "applies_to": "project",
    "permission_stage": "operating_authority",
    "design_id": "dsn-aris-htr-10",
    "decision_date": {
      "value": "2000",
      "precision": "year",
      "basis": "actual"
    }
  },
  {
    "stable_id": "reg-nnsa-htrpm-ol-2119",
    "name": "NNSA operating licence for the Shidaowan HTR-PM demonstration",
    "action_type": "operating_licence",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-htr-pm-shidaowan",
    "design_id": "dsn-htr-pm",
    "decision_date": {
      "value": "2021-08-20",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nnsa-htrpm-ol-2119-20210820",
      "src-nnsa-shidaowan-ol-db-20230329"
    ],
    "confidence": "high",
    "last_checked": "2026-10-15",
    "review_state": "verified",
    "summary": "NNSA issued operating licence 国核安证字第2119号 on 20 August 2021 for the high-temperature gas-cooled demonstration (CN-44) at Ningjin Town, Rongcheng, Shandong. The holder and operating organization is Huaneng Shandong Shidao Bay Nuclear Power Company, Ltd. Validity runs through 19 August 2061. First fuel loading is the start of operation. Condition 23 sets control points at 15 percent and 65 percent of plant rated electrical power and states no megawatt number. The legal representative named on the licence is not stored.",
    "applies_to": "project",
    "permission_stage": "operating_authority",
    "permit_numbers": [
      "国核安证字第2119号"
    ]
  },
  {
    "stable_id": "reg-nnsa-htr10-ol-1405",
    "name": "HTR-10 operating licence issued in 2014, valid through June 2024",
    "action_type": "operating_licence",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-htr10-inet",
    "design_id": "dsn-aris-htr-10",
    "decision_date": {
      "value": "2014-07-15",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nnsa-htr10-ol-notice-20140715",
      "src-nnsa-htr10-ol-1405"
    ],
    "confidence": "high",
    "last_checked": "2026-10-15",
    "review_state": "verified",
    "summary": "NNSA notice 国核安发〔2014〕158号, dated 15 July 2014, issued operating licence 国核安证字1405号 to Tsinghua University's Institute of Nuclear and New Energy Technology for the 10 MW high-temperature gas-cooled experimental reactor. The licence is valid through 30 June 2024. Continued operation after that date requires a new application twelve months before expiry. No successor instrument was opened. The extracted licence pages do not print a separate issue date; the decision-letter date is used. Personal names on the licence are not stored.",
    "applies_to": "project",
    "permission_stage": "operating_authority",
    "permit_numbers": [
      "国核安证字1405号"
    ],
    "reader": {
      "decision": {
        "headline": "HTR-10 operating licence valid through June 2024; operation listed, not confirmed",
        "what": "NNSA's notice of 15 July 2014 issued the reactor's operating licence, valid through 30 June 2024. Operation after that date required a new application twelve months before expiry.",
        "limit": "No successor licence was opened and no dated recent power run was found, so operation is listed rather than confirmed. The stage is unchanged, and the reactor is not recorded as stopped."
      }
    }
  },
  {
    "stable_id": "reg-nra-httr-installation-change-2020-06-03",
    "name": "NRA decision to grant the HTTR installation-change permit",
    "action_type": "other",
    "status": "approved",
    "regulator": "NRA",
    "country": "JP",
    "project_id": "prj-httr-oarai",
    "design_id": "dsn-catalogue-httr",
    "decision_date": {
      "value": "2020-06-03",
      "precision": "day",
      "basis": "actual"
    },
    "submitted_date": {
      "value": "2014-11-26",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nra-httr-installation-change-20200603"
    ],
    "confidence": "high",
    "last_checked": "2026-10-15",
    "review_state": "verified",
    "summary": "On 3 June 2020 the Nuclear Regulation Authority decided that the application to change the HTTR installation at Oarai meets the permit criteria and that the installation-change permit shall be granted under article 26(1) of the Reactor Regulation Act. The application was received on 26 November 2014. The draft letter has a blank number and a blank date, so no permit number is stored. This decision is not an operating licence and is distinct from the July 2021 restart.",
    "applies_to": "project",
    "permission_stage": "other",
    "reader": {
      "application": {
        "headline": "Application for the HTTR installation-change permit",
        "what": "The recorded application date for the HTTR installation-change permit is 26 Nov 2014.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 3 Jun 2020. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-asnr-hexana-options-2026",
    "name": "HEXANA first safety-options request",
    "action_type": "other",
    "status": "submitted",
    "regulator": "ASNR",
    "country": "FR",
    "project_id": null,
    "design_id": "dsn-catalogue-hexana",
    "submitted_date": {
      "value": "2026-09-30",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-asnr-prm-20261014"
    ],
    "confidence": "high",
    "last_checked": "2026-11-11",
    "review_state": "verified",
    "summary": "ASNR reports that Hexana requested an opinion on a first safety option for its small modular reactor on 30 September 2026. The page places this in pre-instruction safety-options exchanges. This is a design assessment request, not a Gard Rhodanien site application, construction permission or issued opinion.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "reader": {
      "application": {
        "headline": "Hexana asks ASNR for an opinion on a first safety option for its SMR",
        "what": "ASNR reports that Hexana requested an opinion on a first safety option for its small modular reactor. ASNR places this in pre-instruction safety-options exchanges.",
        "limit": "This is a design assessment request, not a Gard Rhodanien site application or an issued opinion."
      }
    }
  },
  {
    "stable_id": "reg-kr-smart100-sda-2024",
    "name": "Korean standard design approval for SMART100",
    "action_type": "standard_design_approval",
    "status": "approved",
    "regulator": "NSSC (Republic of Korea)",
    "country": "KR",
    "project_id": null,
    "design_id": "dsn-catalogue-smart100",
    "submitted_date": {
      "value": "2019-12-30",
      "precision": "day",
      "basis": "actual"
    },
    "decision_date": {
      "value": "2024-09-26",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nssc-smart100-review-2024",
      "src-nssc-201-smart100-minutes-2024",
      "src-kaeri-smart100-sda-2024"
    ],
    "confidence": "high",
    "last_checked": "2026-10-15",
    "review_state": "verified",
    "summary": "The NSSC's 201st meeting approved SMART100's standard design on 26 September 2024. Printed minutes pp.121–123 distinguish standard-design approval from construction permission, direct administrative follow-up on power-system review during later licensing and continued verification improvements, and remove disputed wording asserting that a single off-site power circuit presents no safety impediment. The application date is recorded in the technical agenda. This does not authorize any project, construction or operation, does not approve SMART-C, and is not a Saudi or Canadian licence. No separate issued certificate number was opened.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "reader": {
      "application": {
        "headline": "Application for SMART100 standard-design approval",
        "what": "The recorded application date for SMART100 standard-design approval is 30 Dec 2019.",
        "limit": "The application itself is not an issued permission.",
        "dates_note": "Later decision: 26 Sep 2024. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-mee-xuwei-phase1-siting-eia-2024-04-17",
    "name": "MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit)",
    "action_type": "environmental_decision",
    "status": "approved",
    "regulator": "MEE",
    "country": "CN",
    "project_id": "prj-xuwei-htgr-unit3",
    "design_id": null,
    "decision_date": {
      "value": "2024-04-17",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-mee-xuwei-phase1-siting-eia-approval-20240417"
    ],
    "confidence": "high",
    "last_checked": "2026-10-16",
    "review_state": "verified",
    "applies_to": "project",
    "permission_stage": "environmental_decision",
    "summary": "The Ministry of Ecology and Environment approved the siting-stage environmental impact report for Xuwei Phase I on 17 April 2024 (环审〔2024〕43号). The approval describes Phase I as two Hualong One pressurized-water units and one HTR-PM600S high-temperature gas-cooled reactor unit with supporting facilities at Xizoushan, Xuwei New Area, Lianyungang. It is an environmental decision for the siting stage covering the whole Phase I project, of which Unit 3 is the HTGR; it is not a construction licence. The Hualong One units are outside SMRMap's scope."
  },
  {
    "stable_id": "reg-nnsa-linglong-construction-licence-2117-2021",
    "name": "NNSA construction licence 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One)",
    "action_type": "licence_to_construct",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-linglong-one",
    "design_id": "dsn-acp100",
    "decision_date": {
      "value": "2021-07-01",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nnsa-linglong-construction-licence-2117-20210701"
    ],
    "confidence": "high",
    "last_checked": "2026-10-17",
    "review_state": "verified",
    "summary": "NNSA issued construction licence 国核安证字第2117号 on 1 July 2021, valid to 30 June 2031, after reviewing the construction application and inspecting readiness for the first nuclear-island concrete. The licence names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations. IAEA PRIS reports a different construction-licence date, 15 July 2019; the licence document carries 1 July 2021, so the PRIS date is kept visible as a conflicting statement and is not treated as the licence date. This is a construction licence, not an operating licence.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "permit_numbers": [
      "国核安证字第2117号"
    ]
  },
  {
    "stable_id": "reg-natrium-kemmerer-energy-island-exemption-20250507",
    "name": "Kemmerer Unit 1 exemption for energy-island work before a construction permit",
    "summary": "The Federal Register notice (90 FR 20692, 15 May 2025) states that the NRC issued an exemption on 7 May 2025, in response to TerraPower's 28 February 2025 request for US SFR Owner, LLC, modifying the definition of construction for Kemmerer Unit 1. It allows specified work for non-safety-related structures, systems and components on the energy island, such as pile driving and foundations, before a construction permit and without a limited work authorization. It is not a construction permit or operating authority.",
    "sources": [
      "src-d1-fr-kemmerer-exemption-2025"
    ],
    "confidence": "high",
    "last_checked": "2026-10-18",
    "review_state": "verified",
    "action_type": "other",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-natrium-kemmerer",
    "design_id": "dsn-natrium",
    "decision_date": {
      "value": "2025-05-07",
      "precision": "day",
      "basis": "actual"
    },
    "docket": [
      "50-613"
    ],
    "federal_register": [
      {
        "citation": "90 FR 20692",
        "document_number": "2025-08628",
        "published": "2025-05-15"
      }
    ],
    "applies_to": "project",
    "permission_stage": "other",
    "submitted_date": {
      "value": "2025-02-28",
      "precision": "day",
      "basis": "actual"
    },
    "reader": {
      "decision": {
        "headline": "NRC allows early energy-island work at Kemmerer before a construction permit",
        "what": "The NRC exempted specified non-safety-related energy-island work, such as piles and foundations, from the rule against construction before a permit.",
        "limit": "It did not authorize nuclear construction; the construction permit came separately in March 2026.",
        "dates_note": "Federal Register notice: 15 May 2025."
      },
      "application": {
        "headline": "Request for an energy-island construction exemption at Kemmerer Unit 1",
        "what": "The recorded request date for the Kemmerer Unit 1 energy-island exemption is 28 Feb 2025. TerraPower filed it for US SFR Owner.",
        "limit": "The request itself is not an issued permission.",
        "dates_note": "Later decision: 7 May 2025."
      }
    }
  },
  {
    "stable_id": "reg-uk-gda-bwrx300-2025",
    "name": "BWRX-300 UK Generic Design Assessment (two steps)",
    "action_type": "generic_design_assessment",
    "status": "completed",
    "regulator": "ONR/EA (UK)",
    "country": "GB",
    "project_id": null,
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2025-12",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-onr-bwrx-gda-20261005",
      "src-ea-reactor-design-assessments-20260616"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Step 2 statement issued December 2025. No Step 3 or design acceptance recorded."
  },
  {
    "stable_id": "reg-uk-gda-smr300-2026",
    "name": "Holtec SMR-300 UK Generic Design Assessment (two steps)",
    "action_type": "generic_design_assessment",
    "status": "completed",
    "regulator": "ONR/EA (UK)",
    "country": "GB",
    "project_id": null,
    "design_id": "dsn-smr-300",
    "decision_date": {
      "value": "2026-03-31",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-ea-reactor-design-assessments-20260616",
      "src-onr-holtec-gda-20261005",
      "src-ea-holtec-gda-step1-summary-20240801"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in January 2023, according to the Environment Agency's Step 1 summary; it was renamed SMR-300 in January 2024. The UK regulators began a two-step Generic Design Assessment of Holtec's SMR-300 on 18 October 2023 at the government's request. Step 1 ran from October 2023 to August 2024 and Step 2 from August 2024 to March 2026. The Environment Agency records completing Step 2 on 31 March 2026, and ONR's page records the assessment as completed that month with no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "submitted_date": {
      "value": "2023-01",
      "precision": "month",
      "basis": "actual"
    },
    "date_sources": {
      "submitted_date": "src-ea-holtec-gda-step1-summary-20240801"
    },
    "status_note": "Step 2 completed 31 March 2026. No Step 3 or design acceptance recorded.",
    "reader": {
      "application": {
        "headline": "Holtec submits its design to the UK government for Generic Design Assessment",
        "what": "Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in Jan 2023, according to the Environment Agency. The regulators began the assessment on 18 Oct 2023.",
        "limit": "Entering design assessment is not an issued permission, nor an application for a site, construction or operating permission.",
        "dates_note": "Step 2 completed 31 Mar 2026. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-uk-gda-rr-smr-step2-2024",
    "name": "Rolls-Royce SMR UK Generic Design Assessment, Step 2",
    "action_type": "generic_design_assessment",
    "status": "completed",
    "regulator": "ONR/EA (UK)",
    "country": "GB",
    "project_id": null,
    "design_id": "dsn-rr-smr",
    "decision_date": {
      "value": "2024-07-30",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-ea-reactor-design-assessments-20260616",
      "src-onr-rr-gda",
      "src-ea-rr-smr-gda-step2-20240730"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "The UK regulators completed Step 2 of their three-step Generic Design Assessment of the Rolls-Royce SMR on 30 July 2024 and issued Step 2 statements. Step 2 began on 3 April 2023, after Step 1 from April 2022 to April 2023. Step 3, the detailed assessment, began in July 2024 and is recorded separately as under way. Completing Step 2 is not a Design Acceptance Confirmation or permission for any site.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Step 2 completed 30 July 2024. Step 3 is listed separately as under way."
  },
  {
    "stable_id": "reg-uk-gda-natrium-2026",
    "name": "Natrium UK Generic Design Assessment",
    "action_type": "generic_design_assessment",
    "status": "under_review",
    "regulator": "ONR/EA (UK)",
    "country": "GB",
    "project_id": null,
    "design_id": "dsn-natrium",
    "sources": [
      "src-ea-reactor-design-assessments-20260616"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "The UK regulators began a three-step Generic Design Assessment of TerraPower's Natrium on 5 June 2026, after ministers at the Department for Energy Security and Net Zero asked them to, following the department's review of TerraPower's application. Step 1 is preparatory. No step is recorded as completed, and the assessment is not permission for any UK site.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Step 1 began 5 June 2026."
  },
  {
    "stable_id": "reg-uk-gda-xe100-2026",
    "name": "Xe-100 UK Generic Design Assessment (requested)",
    "action_type": "generic_design_assessment",
    "status": "submitted",
    "regulator": "ONR/EA (UK)",
    "country": "GB",
    "project_id": null,
    "design_id": "dsn-xe-100",
    "sources": [
      "src-onr-xe100-gda-request-20260915"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "On 15 September 2026 ONR said the Department for Energy Security and Net Zero had asked it, the Environment Agency and Natural Resources Wales to begin a three-step Generic Design Assessment of X-energy UK Holdings Ltd's Xe-100 after a readiness review. The assessment begins once timescale and resource arrangements are in place, so no step is recorded as started. ONR's page, updated 28 September 2026 and re-read on 28 October 2026, still says so.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "ONR said on 15 September 2026 that regulators were asked to begin. Not started at its 28 September update."
  },
  {
    "stable_id": "reg-cnsc-vdr-bwrx300-2023",
    "name": "CNSC vendor design review, Phases 1 and 2 (BWRX-300)",
    "action_type": "vendor_design_review",
    "status": "completed",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-bwrx-300",
    "decision_date": {
      "value": "2023-03",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-vendor-review-list-20261014",
      "src-cnsc-bwrx300-vdr-summary-20230315"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions. The Darlington licence to construct is a separate, site-specific permission.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Combined Phases 1 and 2.",
    "reader": {
      "decision": {
        "headline": "CNSC lists a completed vendor design review of the BWRX-300",
        "what": "CNSC lists combined Phases 1 and 2 of its pre-licensing vendor design review of the BWRX-300 as completed, with an executive summary dated March 2023.",
        "limit": "A vendor design review does not certify a design or issue a licence.",
        "date_label": "Executive summary dated"
      }
    }
  },
  {
    "stable_id": "reg-cnsc-vdr-xe100-2023",
    "name": "CNSC vendor design review, Phases 1 and 2 (Xe-100)",
    "action_type": "vendor_design_review",
    "status": "completed",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-xe-100",
    "decision_date": {
      "value": "2023-12",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-vendor-review-list-20261014",
      "src-cnsc-xe100-vdr-summary-20240117"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of X-energy's Xe-100 among its completed reviews, with an executive summary dated December 2023. CNSC entered into the agreement with X-energy to conduct the review on 20 July 2020; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Combined Phases 1 and 2.",
    "reader": {
      "decision": {
        "headline": "CNSC lists a completed vendor design review of the Xe-100",
        "what": "CNSC lists combined Phases 1 and 2 of its pre-licensing vendor design review of the Xe-100 as completed, with an executive summary dated December 2023.",
        "limit": "A vendor design review does not certify a design or issue a licence.",
        "date_label": "Executive summary dated"
      }
    }
  },
  {
    "stable_id": "reg-cnsc-vdr-arc100-2025",
    "name": "CNSC vendor design review, Phase 2 (ARC-100)",
    "action_type": "vendor_design_review",
    "status": "completed",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-arc-100",
    "decision_date": {
      "value": "2025-07",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-vendor-review-list-20261014",
      "src-cnsc-arc100-vdr-phase2-202507"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "CNSC lists Phase 1 (executive summary dated October 2019) and Phase 2 (executive summary dated July 2025) of its pre-licensing vendor design review of ARC Clean Technology's ARC-100 among completed reviews. CNSC entered into the Phase 2 agreement with ARC on 9 March 2022; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barriers to licensing at that time and listed further design work. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions. NB Power's Point Lepreau site application is a separate process.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Phase 2. Phase 1 summary dated October 2019.",
    "reader": {
      "decision": {
        "headline": "CNSC lists Phase 2 of its ARC-100 vendor design review as completed",
        "what": "CNSC lists Phase 2 of its pre-licensing vendor design review of the ARC-100 as completed, with an executive summary dated July 2025.",
        "limit": "A vendor design review does not certify a design or issue a licence.",
        "date_label": "Executive summary dated"
      }
    }
  },
  {
    "stable_id": "reg-cnsc-vdr-imsr-2023",
    "name": "CNSC vendor design review, Phase 2 (IMSR400)",
    "action_type": "vendor_design_review",
    "status": "completed",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-imsr",
    "decision_date": {
      "value": "2023-04",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-vendor-review-list-20261014",
      "src-cnsc-imsr400-vdr2-20230418"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "CNSC lists Phase 1 (executive summary dated November 2017) and Phase 2 (executive summary dated April 2023) of its pre-licensing vendor design review of Terrestrial Energy's IMSR400 among completed reviews. CNSC entered into the Phase 2 agreement with Terrestrial Energy on 9 May 2018; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barrier to licensing within the reviewed topics and required further design and safety work. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Phase 2. Phase 1 summary dated November 2017.",
    "reader": {
      "decision": {
        "headline": "CNSC lists Phase 2 of its IMSR400 vendor design review as completed",
        "what": "CNSC lists Phase 2 of its pre-licensing vendor design review of the IMSR400 as completed, with an executive summary dated April 2023.",
        "limit": "A vendor design review does not certify a design or issue a licence.",
        "date_label": "Executive summary dated"
      }
    }
  },
  {
    "stable_id": "reg-cnsc-vdr-ssrw-2021",
    "name": "CNSC vendor design review, Phase 1 (SSR-W)",
    "action_type": "vendor_design_review",
    "status": "completed",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-catalogue-ssr-w",
    "decision_date": {
      "value": "2021-05",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-vendor-review-list-20261014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "CNSC lists Phase 1 of its pre-licensing vendor design review of Moltex Energy's SSR-W300 among completed reviews, with an executive summary dated May 2021. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Phase 1. No later phase listed.",
    "reader": {
      "decision": {
        "headline": "CNSC lists Phase 1 of its SSR-W vendor design review as completed",
        "what": "CNSC lists Phase 1 of its pre-licensing vendor design review of Moltex's SSR-W300 as completed, with an executive summary dated May 2021.",
        "limit": "A vendor design review does not certify a design or issue a licence.",
        "date_label": "Executive summary dated"
      }
    }
  },
  {
    "stable_id": "reg-cnsc-vdr-smr160-2020",
    "name": "CNSC vendor design review, Phase 1 (SMR-160)",
    "action_type": "vendor_design_review",
    "status": "completed",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-holtec-smr-160",
    "decision_date": {
      "value": "2020-08",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-vendor-review-list-20261014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "CNSC lists Phase 1 of its pre-licensing vendor design review of the SMR-160 by SMR, LLC (Holtec International) among completed reviews, with an executive summary dated August 2020. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Phase 1. No later phase listed.",
    "reader": {
      "decision": {
        "headline": "CNSC lists Phase 1 of its SMR-160 vendor design review as completed",
        "what": "CNSC lists Phase 1 of its pre-licensing vendor design review of Holtec's SMR-160 as completed, with an executive summary dated August 2020.",
        "limit": "A vendor design review does not certify a design or issue a licence.",
        "date_label": "Executive summary dated"
      }
    }
  },
  {
    "stable_id": "reg-cnsc-vdr-evinci-2023",
    "name": "CNSC vendor design review, Phase 2 (eVinci)",
    "action_type": "vendor_design_review",
    "status": "on_hold",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-evinci",
    "sources": [
      "src-cnsc-vendor-review-list-20261014"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "status_checked": "2026-10-31",
    "review_state": "verified",
    "summary": "CNSC's table of current vendor design review agreements lists Westinghouse's eVinci (about 5 MWe) for Phase 2, with the review starting in June 2023 and its status on hold; Phase 1 objectives are addressed within the Phase 2 scope. The Canadian status does not describe eVinci's separate US test and deployment paths. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Phase 2 started June 2023 and is on hold."
  },
  {
    "stable_id": "reg-nrc-us600-dc-2023",
    "name": "NRC design certification of the NuScale US600",
    "action_type": "design_certification",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": null,
    "design_id": "dsn-nuscale-us600",
    "decision_date": {
      "value": "2023-01-19",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-ecfr-part52-appendix-g-20261028",
      "src-nrc-nuscale-us600-20261028",
      "src-nrc-design-certifications-20261028",
      "src-fr-us600-dc-docketing-2017"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "The NRC lists the NuScale US600 among its issued design certifications. NuScale filed the application by letter dated 31 December 2016; the NRC lists it as tendered in December 2016, with the submission completed in January 2017. The certification rule, Appendix G to 10 CFR Part 52, was published on 19 January 2023 (88 FR 3306) and may be referenced for 40 years from 21 February 2023. The US600 is NuScale's earlier configuration of up to twelve modules of 50 MWe and 160 MWt each, which also received a standard design approval on 11 September 2020; the later US460 holds its own 2025 standard design approval. A design certification approves a design independent of any site and is not permission to build or operate.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Certification rule published 19 January 2023, effective 21 February 2023."
  },
  {
    "stable_id": "reg-kr-smart-sda-2012",
    "name": "Korean standard design approval for SMART",
    "action_type": "standard_design_approval",
    "status": "approved",
    "regulator": "NSSC (Republic of Korea)",
    "country": "KR",
    "project_id": null,
    "design_id": "dsn-aris-smart",
    "decision_date": {
      "value": "2012-07-04",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-kaeri-smart-sda-2012"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "KAERI's release says the Nuclear Safety and Security Commission issued a standard design approval for the original SMART (100 MWe, 330 MWth) on 4 July 2012 under Article 12 of the Nuclear Safety Act, after KAERI and KEPCO applied on 30 December 2010. The approval document itself was not opened. SMART100 holds a separate 2024 approval. A standard design approval is not a construction or operating permission.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "submitted_date": {
      "value": "2010-12-30",
      "precision": "day",
      "basis": "actual"
    },
    "status_note": "Original SMART design. SMART100 has its own 2024 approval.",
    "reader": {
      "application": {
        "headline": "KAERI and KEPCO apply for a standard design approval of SMART",
        "what": "KAERI's release says KAERI and KEPCO applied for a standard design approval of the original SMART on 30 Dec 2010.",
        "limit": "This is the applicants' own account; the approval document itself was not opened. The application itself is not an issued permission.",
        "dates_note": "Later decision: 4 Jul 2012. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-nrc-us600-sda-2020",
    "name": "NRC standard design approval for the NuScale US600",
    "action_type": "standard_design_approval",
    "status": "approved",
    "regulator": "NRC",
    "country": "US",
    "project_id": null,
    "design_id": "dsn-nuscale-us600",
    "decision_date": {
      "value": "2020-09-11",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nrc-nuscale-us600-20261028"
    ],
    "confidence": "high",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "The NRC records that NuScale requested a standard design approval for the US600 on 13 July 2020 and that it was approved on 11 September 2020 (ML20247J564). The design was later certified by rule in January 2023. A standard design approval approves a design independent of any site; it is not permission to build or operate.",
    "adams": [
      "ML20247J564"
    ],
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "submitted_date": {
      "value": "2020-07-13",
      "precision": "day",
      "basis": "actual"
    },
    "status_note": "Approved 11 September 2020, before the 2023 certification.",
    "reader": {
      "application": {
        "headline": "NuScale requests a standard design approval for the US600",
        "what": "The NRC records that NuScale requested a standard design approval for the US600 on 13 Jul 2020.",
        "limit": "The application itself is not an issued permission. A standard design approval is not permission to build or operate.",
        "dates_note": "Later decision: 11 Sep 2020. Details are in Checking notes."
      }
    }
  },
  {
    "stable_id": "reg-cnsc-vdr-mmr-2019",
    "name": "CNSC vendor design review, Phase 1 (USNC MMR)",
    "action_type": "vendor_design_review",
    "status": "completed",
    "regulator": "CNSC",
    "country": "CA",
    "project_id": null,
    "design_id": "dsn-gfp-mmr",
    "decision_date": {
      "value": "2019-02",
      "precision": "month",
      "basis": "actual"
    },
    "sources": [
      "src-cnsc-vendor-review-list-20261014",
      "src-parent-cnsc-chalk"
    ],
    "confidence": "medium",
    "last_checked": "2026-10-28",
    "review_state": "verified",
    "summary": "CNSC lists Phase 1 of its pre-licensing vendor design review of the MMR by USNC-Power Ltd. (Ultra Safe Nuclear Corporation) among completed reviews, with an executive summary dated February 2019. No later phase is listed. CNSC's Chalk River project page names Ultra Safe Nuclear Corporation as the parent of Global First Power, whose proposed micro modular reactor this profile records. CNSC staff paused the Chalk River environmental assessment and licence-to-prepare-site application review as of August 2024. CNSC says a vendor design review does not certify a design, issue a licence or bind later Commission decisions.",
    "applies_to": "design",
    "permission_stage": "design_assessment",
    "status_note": "Phase 1. No later phase listed.",
    "reader": {
      "decision": {
        "headline": "CNSC lists Phase 1 of its USNC MMR vendor design review as completed",
        "what": "CNSC lists Phase 1 of its pre-licensing vendor design review of the MMR by USNC-Power Ltd. as completed, with an executive summary dated February 2019.",
        "limit": "A vendor design review does not certify a design or issue a licence.",
        "date_label": "Executive summary dated"
      }
    }
  },
  {
    "stable_id": "reg-huakun-one-siting-opinion-2026",
    "name": "NNSA site-selection review opinion No. 2620, Huakun One science and technology demonstration project",
    "action_type": "other",
    "status": "approved",
    "regulator": "NNSA",
    "country": "CN",
    "project_id": "prj-huakun-one-taipingling",
    "design_id": "dsn-huakun-one",
    "decision_date": {
      "value": "2026-11-02",
      "precision": "day",
      "basis": "actual"
    },
    "sources": [
      "src-nnsa-huakun-site-opinion-2620-20261102"
    ],
    "confidence": "high",
    "last_checked": "2026-11-04",
    "review_state": "verified",
    "summary": "The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2620号) on 2 November 2026 to CGN Ocean Energy for the Huakun One floating reactor platform and maintenance base at the Taipingling nuclear base in Huidong county. The review found no disqualifying site factor affecting safety that engineering measures could not resolve, and the opinion agrees that design work may proceed on the stated site parameters. It is not a construction licence: before holding one the company may not pour seismic Category I foundation concrete or build other safety-important structures.",
    "applies_to": "project",
    "permission_stage": "site_permission",
    "permit_numbers": [
      "国核安证字第2620号"
    ],
    "reader": {
      "decision": {
        "headline": "NNSA issues site-selection opinion for Huakun One",
        "what": "NNSA's site-selection opinion No. 2620 of 2 November 2026 found no disqualifying site factor that engineering measures could not resolve, and agrees design work may proceed on the site parameters.",
        "limit": "It is not a construction licence. Until it holds one, the company may not pour seismic Category I foundation concrete or build other safety-important structures."
      }
    }
  },
  {
    "stable_id": "reg-nrc-last-energy-caldwell-cp-lwa-part1-2026",
    "name": "Last Energy Caldwell site phased construction permit application, Part 1 (with limited work authorization request)",
    "action_type": "construction_permit",
    "status": "submitted",
    "regulator": "NRC",
    "country": "US",
    "project_id": "prj-last-energy-caldwell",
    "design_id": "dsn-pwr-20",
    "submitted_date": {
      "value": "2026-10-20",
      "precision": "day",
      "basis": "actual"
    },
    "date_sources": {
      "submitted_date": "src-gpo-last-energy-caldwell-lwa-receipt-20261105"
    },
    "docket": [
      "99902140"
    ],
    "adams": [
      "ML26294A162"
    ],
    "federal_register": [
      {
        "citation": "91 FR 69895",
        "document_number": "2026-22577",
        "published": "2026-11-05"
      }
    ],
    "sources": [
      "src-gpo-last-energy-caldwell-lwa-receipt-20261105"
    ],
    "confidence": "high",
    "last_checked": "2026-11-10",
    "review_state": "verified",
    "summary": "Last Energy filed Part 1 of a two-part phased construction permit application on 20 October 2026 for a PWR-20 facility at the Caldwell Site in Caldwell County, Texas. Part 1 includes a limited work authorization request under 10 CFR 50.10(d) covering early foundation work, with financial information, a preliminary safety analysis report for the LWA scope, an environmental report and a site redress plan. The NRC published a notice of receipt on 5 November 2026 (91 FR 69895). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction.",
    "applies_to": "project",
    "permission_stage": "construction_permission",
    "reader": {
      "application": {
        "headline": "Last Energy files for a limited work authorization at its Caldwell site",
        "what": "Last Energy filed Part 1 of a phased construction permit application, including a limited work authorization request, for a PWR-20 plant in Caldwell County, Texas.",
        "limit": "A notice of receipt only; the NRC has not yet said whether it will docket the application, and nothing is authorized.",
        "dates_note": "Filed 20 October 2026. Federal Register notice of receipt: 5 November 2026."
      }
    }
  }
]