Policy and licensing / Alaska

Alaska Chapter 4, SLA 2022: microreactor siting

Alaska's 2022 session law lets a defined microreactor be constructed on land the legislature has not designated, while the opened permit sentence still requires municipal approval or, in an unorganized borough, legislative approval before a permit is issued. The definition is a fission reactor of not more than 50 megawatts electric, tied to a federal definition that was not opened. It is not a permit and not a Nuclear Regulatory Commission license. The current Title 18 compilation was opened and contains those microreactor provisions. No compilation edition date is printed. The department's regulations were not opened.

Category
Laws, rules and executive directives
Status
In effect
Instrument
statute · Chapter 4, SLA 2022 (CSSB 177(RES))
Issued by
Alaska State Legislature
Jurisdiction
Alaska
Affects
Siting
In effect from
22 Aug 2022
Expiry or completion
None recorded
Operative text
Alaska enrolled CSSB 177(RES), Chapter 4 SLA 2022 (Enrolled CSSB 177(RES) PDF, opened 4 October 2026)
Record reviewed · next review
4 Oct 2026 · 15 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)

Legal and geographic scope

Enrolled CSSB 177(RES) opened 4 October 2026, with the legislature's bill history recording it as Chapter 4, SLA 2022, signed into law on 24 May 2022 and effective 22 August 2022. The act amends the nuclear-facility siting statute. The opened permit sentence still says a permit may not be issued until the municipality with jurisdiction approves it or, in an unorganized borough, until the legislature approves it. A new subsection says that, notwithstanding the undesignated-land subsection, a person otherwise compliant with the chapter may construct a microreactor on land the legislature has not designated. Another new subsection says the study requirements of the existing section do not apply to the presence of microreactors. If the Department of Environmental Conservation is notified that a person has applied to the Nuclear Regulatory Commission for a license for a microreactor in the state, the department coordinates and submits the named agencies' comments in that federal licensing process. The act does not issue a state permit or a Nuclear Regulatory Commission license.

Not approved or still pending

The current Title 18 compilation was opened on 4 October 2026 and contains the same microreactor permit exception, study exemption, and 50-megawatt-electric definition. No compilation edition date is printed in the opened header. The pre-existing subsections cross-referenced by the act were not opened, so the notwithstanding clause is not restated as a description of that older text. Department of Environmental Conservation regulations were not opened. 42 U.S.C. 16271 was not opened. The Senate Journal records that enrolling corrected a manifest error by inserting the word 'the' after 'from' on page 2, line 4; the opened enrolled PDF already reads that way. No project is linked. The act does not approve a reactor. (Record checked .)

Dated lifecycle

Definitions in this instrument

Projects or designs named by the source

Sources