Methodology, coverage & attribution
How SMRMap decides what to list, how to read a record, and where its limits are.
- SMRMap lists SMR and microreactor projects and links the sources behind them. It is not a census.
- A stage, a review date or a map pin is a recorded fact. None of them proves current activity.
- Targets are plans, not achievements or commitments. Unknown stays unknown, and is never zero.
- Open a topic below for the full rules.
Coverage limits
SMRMap publishes source-linked SMR and labeled-microreactor projects and proposals reconciled against named source snapshots with a reconciliation cutoff of 2026-10-02, and against the named public inventories and the regulator, government, operator and developer routes of the worldwide coverage pass through 2026-10-06. The coverage page lists those snapshot versions, inventory scopes, rights limits, each country's research status and the United Nations member states that remain unreviewed. Discovery snapshots and unfinished dispositions are recorded separately. It is not a complete worldwide census. Counts include announced, siting, licensing, construction, commissioning, operating, demonstration, canceled and suspended records; they are not counts of operating power plants. A specific source-backed deployment commitment can be a record when the site is undisclosed. Generic country programs, evaluation agreements and unresolved research are not deployment records. Opening a cited source confirms its documented facts, not every possible subsequent development.
Snapshot versions, reconciliation counts, rights limits and remaining gaps are on the coverage and gaps page. Those counts are generated from the research ledger and the publication selection.
The source-snapshot cutoff of 2 October 2026 is separate from research updates through 30 October 2026; the coverage and gaps page prints both, and neither one replaces a record's source date or its verification date.
This release prioritizes deployment projects with regulator, company, or IAEA-linked evidence, plus a companies directory for linked organizations and selected source-backed reactor developers without tracked deployments yet. Vendor concept sheets without a site/project pathway may appear as company/design records only. Entire national large-reactor fleets are intentionally excluded. Fuel-cycle and equipment suppliers are a separate coverage lane from reactor developers.
Company inclusion
- Include organizations that develop, vend, operate, host, or offtake tracked SMR/microreactor deployments in this dataset.
- Also include source-backed direct reactor developers even when no deployment project is tracked yet — say “no projects tracked here,” never “no projects exist.”
- Keep listing status, ownership/control, and organization type as separate fields. State-controlled entities can also be listed; parent tickers are never assigned to subsidiaries by inference.
- Investor, customer, operator, and reactor-developer roles are distinct.
- Do not invent deployments or plot headquarters as reactor sites.
SMR inclusion
SMRMap includes deployment projects for designs that are factory-fabricatable or modularly deployable and generally at or below about 300 MWe per module (some multi-module plants exceed that site total), OR that a competent regulator or IAEA ARIS entry classifies as an SMR/microreactor. Low electrical output alone is not sufficient. Microreactors are labeled separately. A design profile does not need a deployment. A specific source-backed agreement or announcement to deploy a named design, or a described plant, can be published with an undisclosed site and no coordinates. Generic national interest, evaluation or feasibility agreements, non-binding letters and unnamed vendor programs stay context. A company plus a state is enough for an undisclosed-site record only when the source commits to a plant there; it is not a pin and not a named host. One plant record, its planned module count and any unit rows are separate. A configuration count is not a count of built reactors. Program-scope rows are aggregates or non-deployment studies and are not verified deployments. Rolls-Royce SMR (~470 MWe) is included with an explicit capacity-check note.
How to read a record
Use the stage, capacity, dates and cited sources together. A listing describes documented evidence; it does not guarantee that a proposal will be built.
Stages
Stages summarize the activity supported by each project's sources. They are not a required sequence. A demonstration reactor can be under construction, commissioning or operating.
- Announced — A deployment proposal has been made public; later activity is not yet established here.
- Siting — A proposed location is being selected, evaluated or characterized; pre-application regulator engagement alone remains here.
- Licensing — A formal project-specific application has been submitted or is under regulator review; design-only and pre-application advice do not qualify.
- Construction — Sources report physical construction for the project; a permit alone is insufficient.
- Commissioning — Startup, testing or preparation for operation is documented; electricity delivery is not implied.
- Operating — Reactor operation is documented, including heat-only or experimental operation where specified.
- Suspended — Project activity has been paused; resumption is not assumed.
- Canceled — The proposal or project has been ended; its page preserves the historical evidence.
- Deferred — The proposal has been postponed; this does not establish cancellation or a new start date.
A named site with only an intention to apply, pre-application advice or a design review remains Siting. Use Licensing only after a formal project-specific application is submitted or project-specific regulatory review starts; record an issued permission separately. A company announcement alone does not establish application acceptance.
A recorded stage is not today's activity
Read the dates and sources before treating a stage as current. Suspended or canceled proposals, such as CAREM-25, carry a Historical record label.
Source snapshot dates the catalog evidence; Record reviewed dates our check of the record. For Blossom Energy SMR, these are 14 Feb 2025 and 2 Oct 2026. Neither confirms current availability or a deployment.
In a source list, accessed is when we read the source. Where a source's own date has been recorded, it is shown as published, dated, revised or page updated. A page-update date is not the date of the events the page reports. On First American Nuclear's Indiana record, the company's own announcement was published on 4 Nov 2025 and a press report followed on 10 Nov 2025.
Capacity
MWe measures electrical output; MWth measures heat. We do not convert between them. Gross electrical output is before the plant's own use; net is after it. A gross/net unspecified figure does not establish either basis. “Up to” is a stated maximum and “approximately” is an estimate; neither is silently rounded into an exact output. Module ratings and whole-plant totals must be read separately.
HTR-PM Shidaowan and its design profile show totals for the two-module plant: 210 MWe gross and 500 MWth. These are not the output of one reactor module.
Akademik Lomonosov is a two-module floating plant rated at 70 MWe gross. Its KLT-40S design is rated at 35 MWe gross per module. CAREM-25 records 25 MWe net for one module.
The Rolls-Royce SMR module is rated at 470 MWe net, also used for Temelin. Wylfa records 1410 MWe net for a planned three-module plant. The inclusion rule above explains the Rolls-Royce exception; it is not a microreactor cutoff.
Companies, designs, projects, and units
A company develops or operates reactors; a design describes the technology; a project proposes or carries out deployment at a site. A project can cover one unit or several. “No projects tracked here” describes our coverage, not proof that none exists. Modules planned is not a census of built reactors.
Project proposer, parent company, site host, customer and operator are separate relationships. An announcement, land lease or power-purchase negotiation does not establish who will operate a reactor. We leave the operator field empty until a source supports that specific role; other documented relationships appear under Who is involved with their sources.
Darlington BWRX-300 Unit 1 and Darlington BWRX-300 Units 2-4 are separate projects; the first records one unit's capacity.
Purpose
Operating, commissioning and construction projects record a purpose. Power plant: intended to supply electricity or heat to a grid or customer, including first-of-a-kind and demonstration power plants. Research or test reactor: a research, test, experimental, prototype-test or critical-experiment reactor, including a facility licensed or authorized as non-power or as a test reactor. The license or authorization category governs: a company's statement that such a facility will also supply power does not change it. Counts are records, not reactors; one record can cover several units.
Who is involved
Every project page answers the same questions: proposer or applicant, operator, supplier, customer or offtaker, contractor, funding and government decisions, fuel, site host or owner, programs naming the project, and whether a comparable schedule revision is recorded. Each answer names only what a cited source supports, with the terms the source states. A prospective customer under a letter of intent is not a contract; a selection or program listing is not a disbursement; company-wide fundraising counts only when its source ties it to the project, and is then labeled company-level; a design's stated fuel form is not a fuel supply arrangement. A contractor answer may name a preparatory partner; that is not a construction contract or a payment, and a recorded construction role keeps its construction label. “Not recorded” is not a finding that none exists. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed. Who is involved across projects lists every answer and counts the gaps.
Schedule changes
Where a source documents that a milestone's target moved, the earlier and revised targets are shown with the dates they were stated. Belews Creek shows the NRC moving four review milestones earlier in its 29 September 2026 letter. The earlier target no longer counts as upcoming. Only the same milestone is compared, a direction is shown only when both dates have the same precision, and no delay score is derived. All documented schedule changes.
Construction permission is not the project stage
Permission to construct is recorded separately from physical construction. Clinch River has an issued construction permit but remains labeled licensing because a construction start is not recorded. Darlington Unit 1 records both a construction license and construction activity. Design assessment alone permits neither a site nor construction. A completed UK Generic Design Assessment step or Canadian vendor design review is shown as a review completed, not an approval; design reviews and approvals by regulator lists them with each design's project permissions.
Criticality is not a record of electricity
Criticality alone does not demonstrate electricity generation or commercial operation. Antares Mark-0 and Aalo-X record zero-power criticality and remain labeled commissioning. HTR-PM separately records commercial operation.
TMSR-LF1 is an operating experimental reactor with thermal-only output recorded. Ward 250 records demonstrated full-power research operation; its label does not claim continuous operation today or commercial power delivery. An operating label does not always mean a power plant supplying the grid.
A missing pin is not a stage
Projects without a published point remain in the Projects table and the search; the pin line above the table and the map counts them separately as naming a site or town, or naming no site at all. We do not substitute a headquarters or invent a location. Most pins mark a named facility, not the reactor: the pin for TMSR-LF1 marks its industrial-park campus. Marker color shows the recorded project stage, marker shape shows reactor class, a dashed ring marks a site-area point and a hollow marker a town-level point. Location precision explains each step.
Preserved distinctions
- MWe vs MWth; gross vs net vs unspecified nameplate
- Module vs multi-module plant totals
- Design approval vs site preparation vs construction vs operation
- Planned vs achieved dates; source publication dates vs record review dates (
last_checked) vs event dates - Exact, site-area, town-level, region-only and undisclosed locations — HQ is never plotted as a deployment
- Map marker color shows the recorded project stage; shape shows reactor class; a dashed ring marks a site-area point and a hollow marker a town-level point
Location precision
Every site record uses one ladder. With a point, it is the precision of that point; without one, it is the most precise place the project's own sources name. Every pin cites the export row, document, map feature or article that gives its point.
- Exact: a point the regulator, owner or developer publishes for the reactor, unit or its pad.
- Site area: a named plant, laboratory, campus, base, port, industrial park or notified parcel. The pin marks that facility or parcel area, not the reactor, and is drawn with a dashed ring.
- Town or locality: only a town, village or municipality is named, or the only recorded point is a town point. The pin marks the town, is drawn hollow and is labeled approximate.
- Region only: only a state, province, county, economic zone or other region is named. Never pinned.
- No site named: nothing below the country is named. Never pinned.
Attribution & licenses
- Quoted excerpts and linked primary sources remain copyright of their owners.
- Homepage land outline: Natural Earth 110m (public domain).
- NuclearChain exports (reactors, sites, SMR designs and companies CSVs) are labeled CC BY 4.0 at https://www.nuclearchain.net/data/ (re-checked 2026-10-02). Attribution: NuclearChain (nuclearchain.net), CC BY 4.0; fleet data derived from Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release, CC BY 4.0. Site coordinates whose sources include NuclearChain reactors.csv export (unit coordinates) are NuclearChain export unit points for a host facility that the project's own sources name; SMRMap selected them per project and labels them approximate (changes made). Published project facts prefer primary regulator, company and government sources cited per record. Capacity alone does not establish SMR inclusion.
- Global Energy Monitor: GEM's nuclear tracker download page, as archived on 6 December 2025, stated that all GEM tracker data are available under CC BY 4.0 unless otherwise noted, and the current download widget names CC BY 4.0. Downloading the workbook requires GEM's form, which was not submitted, so the workbook and its NOTICE sheet were not read. The public August 2026 map layer, which carries no license notice of its own, was used only as a unit-count and coordinate cross-check and is not republished. GEM wiki pages are CC BY-NC-SA; no wiki text is copied.
- Map tiles in the map view of Projects (/projects/?view=map): OpenStreetMap contributors (ODbL). Leaflet: BSD-2-Clause.
- NEA (2025), The NEA Small Modular Reactor Dashboard: Third Edition, OECD Publishing, Paris, DOI https://doi.org/10.82155/nqz2-hp44, CC BY 4.0. Assessment cutoff 14 February 2025; revised 5 September 2025. Catalog identities and descriptions adapted; third-party images, logos, quoted material and tables are excluded.
- This is an adaptation of an original work by the OECD. The opinions expressed and arguments employed in this adaptation should not be reported as representing the official views of the OECD or of its Member countries.
- Some approximate site coordinates are geocoded from OpenStreetMap data via Nominatim (© OpenStreetMap contributors, ODbL) for a host that the project's own sources name; each such site records the query and returned feature. These are individual, insubstantial extracts, not a copy of the OpenStreetMap database.
- Some approximate site and town points are the coordinate shown on the Wikipedia article for a facility or place that the project's own sources name (Wikipedia contributors, CC BY-SA 4.0); each such site cites the article. These are individual factual extracts; no article text is copied.
- The NEA SMR Digital Dashboard edition 4.0 (2026) was consulted as a discovery source; facts used are paraphrased and linked. No dashboard text, grades, tables or images are republished.
Map library & tiles
The map view of Projects uses Leaflet
(BSD-2-Clause) and OpenStreetMap raster tiles at
https://tile.openstreetmap.org/{z}/{x}/{y}.png, with OpenStreetMap contributor attribution on the map. Leaflet and the tiles
load only when a reader opens the map; the table view and every other page load nothing from these services.
Who builds SMRMap
Fillip Kosorukov leads SMRMap's product development and research workflow. AI tools assist with research, implementation and testing.
The public dataset is available in free CSV and JSON downloads, with attribution and reuse terms alongside the files. Quoted source material retains its own rights.
Update process
Sources are reviewed, records validated, and changes checked before publication.
How sources are found, which ones are checked each day and how complete each kind of record is: how SMRMap finds and updates records.
Each monthly digest also lists what SMRMap itself added, changed or removed that month, by release day: the day (UTC) a change first appeared in a public build. A release day is not the date of the development. The same days are the publication dates in the RSS feed and are published in publication-history.json. History starts with the first public dataset on 1 October 2026; re-checks that change only a record's review dates, reviewer or next trigger are not counted as changes. A change only to a record's evidence references is listed separately and is not counted as a changed record. A record put back after an earlier removal is listed as restored, and a renamed record as removed and new.
The SMR news page lists recent headlines from the trade press, developer newsrooms, regulators and the Federal Register that SMRMap's source checks already read; it adds no sources. A headline is listed when it, or the summary the source publishes with it, uses an SMR or microreactor term (in English or, for some sources, the source's language) or names a tracked project, design or program. Federal Register notices in the dockets of tracked applications and rulemakings, and a reactor developer's own announcements, are listed too. SMRMap does not check these reports, and listing a headline does not add or change a record. Developments SMRMap has reviewed appear in Updates, each with its source and limits; a headline whose address is a source of one of those entries is marked “Reviewed in Updates” and links to it. Headlines from the last 45 days are shown, newest first, and the page is refreshed when the site is rebuilt.
Corrections
See corrections. Dataset license: CC BY 4.0.