Glossary

Plain definitions of the abbreviations and terms used across SMRMap. The first use of an abbreviation in a page heading or opening paragraph is also explained when you hover over or long-press it.

These are short orientation definitions, not legal ones: a regulator's own rules and documents govern what a permit or license allows. 55 terms, from A to V. How small reactor types work.

ARDP (Advanced Reactor Demonstration Program)
A U.S. Department of Energy program, begun in 2020, that shares the cost of building advanced reactor demonstration plants with the companies that develop them.
ARIS (Advanced Reactors Information System)
The IAEA's online database of advanced and small modular reactor design descriptions, supplied mainly by the reactor developers.
ASNR (Autorité de sûreté nucléaire et de radioprotection (French nuclear safety and radiation protection authority))
France's nuclear safety and radiation protection regulator, formed on 1 January 2025 by merging the ASN regulator with the IRSN technical expert body.
BWR (boiling water reactor)
A water-cooled and water-moderated reactor in which water boils in the core and the steam drives the turbine directly. How a boiling water reactor works
CNSC (Canadian Nuclear Safety Commission)
Canada's federal nuclear regulator, which licenses the site preparation, construction and operation of nuclear facilities.
COL (combined license)
A U.S. Nuclear Regulatory Commission license, issued under 10 CFR Part 52, that authorizes both construction and operation of a nuclear plant in one licensing action.
CP (construction permit)
A license to build a nuclear reactor; in the United States the NRC issues it under 10 CFR Part 50, and operation needs a separate operating license.
CPA (construction permit application)
An application to a regulator for a construction permit; filing or accepting the application does not grant the permit.
DOE (U.S. Department of Energy)
The U.S. federal department that funds reactor research and demonstration programs and authorizes test reactors under its own oversight.
DOME (Demonstration of Microreactor Experiments)
A test bed at Idaho National Laboratory, operated by DOE's National Reactor Innovation Center, where developers can run small experimental reactors.
EIA (environmental impact assessment)
A formal study of a proposed project's environmental effects that a government reviews before deciding whether the project may go ahead. In U.S. energy statistics, EIA also stands for the Energy Information Administration, so it is not marked automatically on pages.
EIS (environmental impact statement)
The detailed environmental review document that U.S. federal agencies prepare under the National Environmental Policy Act for major actions, such as some NRC permits.
ESP (early site permit)
An NRC permit that approves a site for one or more future nuclear units and can be issued before a specific reactor design is chosen; it does not allow construction.
FHR (fluoride salt-cooled high-temperature reactor)
A reactor that combines solid TRISO fuel with a molten fluoride salt coolant. How a salt-cooled pebble bed reactor works
FID (final investment decision)
The point at which a project's owners formally commit the money to build it.
FOAK (first of a kind)
The first plant built to a given design; later units of the same design are sometimes called nth of a kind (NOAK).
FONSI (finding of no significant impact)
A U.S. federal agency's conclusion, after an environmental assessment, that an action needs no full environmental impact statement.
GDA (Generic Design Assessment)
The UK's assessment of a reactor design by the Office for Nuclear Regulation and the environment agencies, carried out independently of any specific site; it does not permit construction.
GFR (gas-cooled fast reactor)
A reactor cooled by a gas, usually helium, that uses fast (unmoderated) neutrons. How a gas-cooled fast reactor works
HALEU (high-assay low-enriched uranium)
Uranium enriched to between 5 and 20 percent uranium-235, a fuel that many advanced reactor designs require.
HTGR (high-temperature gas-cooled reactor)
A graphite-moderated reactor cooled by helium, usually fueled with TRISO particles, that can deliver heat at high temperatures. How a high-temperature gas reactor works
IAEA (International Atomic Energy Agency)
The international organization in the United Nations system that promotes peaceful uses of nuclear energy and develops nuclear safety standards.
INB (installation nucléaire de base (basic nuclear installation))
The French legal category for large nuclear facilities, including reactors, whose creation needs a government decree after review by ASNR. INB is also the abbreviation of Indústrias Nucleares do Brasil, Brazil's state nuclear fuel company, so it is not marked automatically on pages.
INL (Idaho National Laboratory)
A U.S. Department of Energy national laboratory in eastern Idaho that hosts several test and demonstration reactor projects.
iPWR (integral pressurized water reactor)
A pressurized water reactor whose primary-circuit components, such as the steam generators, are inside the reactor pressure vessel rather than in separate loops; many small modular reactor designs use this layout. How an integral PWR works
LEU (low-enriched uranium)
Uranium enriched to less than 20 percent uranium-235; most current power reactors use LEU enriched to under 5 percent.
LFR (lead-cooled fast reactor)
A reactor cooled by molten lead or a lead-bismuth alloy that uses fast (unmoderated) neutrons. How a lead-cooled fast reactor works
LOI / LoI (letter of intent)
A letter in which parties state that they intend to reach an agreement; it usually does not bind them to the agreement itself.
LWA (limited work authorization)
NRC permission to carry out specified construction work at a site before a construction permit or combined license is issued.
LWR (light-water reactor)
A reactor cooled and moderated by ordinary water; pressurized water reactors and boiling water reactors are both light-water reactors.
Microreactor
A very small reactor, generally up to about 20 MWe depending on the definition used, that is often designed to be factory-built and transportable; SMRMap labels microreactors separately from other SMRs.
MoU / MOU (memorandum of understanding)
A written statement of shared intent between parties that usually does not commit them to build, buy or pay.
MSNR (Mission de la sûreté nucléaire et de la radioprotection (French ministry nuclear safety unit))
The nuclear safety and radiation protection unit of the French government ministry responsible for nuclear safety, which handles applications for government nuclear decrees and refers them to ASNR for review.
MSR (molten salt reactor)
A reactor that uses molten salt as its coolant and, in many designs, also carries the fuel dissolved in the salt. How a molten salt reactor works
MWe (megawatts electric)
Electrical output in millions of watts; a source may state it gross (at the generator) or net (after the plant's own use), and SMRMap records which when the source says so.
MWt / MWth (megawatts thermal)
The heat produced by a reactor in millions of watts, which is always more than the electrical output the same reactor can deliver.
NEA (Nuclear Energy Agency)
An intergovernmental agency of the Organisation for Economic Co-operation and Development (OECD) that supports nuclear energy policy and publishes data, including on SMRs. In Chinese sources, NEA can instead mean China's National Energy Administration, so it is not marked automatically on pages.
NEPA (National Environmental Policy Act)
The U.S. law that requires federal agencies to assess the environmental effects of their decisions, such as issuing a reactor permit.
NNSA (National Nuclear Safety Administration (China))
China's nuclear safety regulator, administered by the Ministry of Ecology and Environment, which issues siting opinions and construction and operating licenses for nuclear plants. In U.S. sources, NNSA usually means the National Nuclear Security Administration, an agency of the Department of Energy. It is therefore not marked automatically on pages.
NPP (nuclear power plant)
A power station that generates electricity from one or more nuclear reactors.
NRC (U.S. Nuclear Regulatory Commission)
The independent U.S. federal agency that licenses and regulates commercial nuclear reactors and other civilian uses of nuclear materials.
NRIC (National Reactor Innovation Center)
A U.S. Department of Energy program, led by Idaho National Laboratory, that gives reactor developers access to test sites and facilities such as DOME.
NSDA (Nuclear Safety Design Agreement)
An agreement in which DOE accepts the safety design approach for a reactor that DOE itself will authorize, an early step toward DOE authorization rather than an NRC license.
OL (operating license)
A license to load fuel and operate a nuclear reactor; in the two-step U.S. process under 10 CFR Part 50 it follows a construction permit.
ONR (Office for Nuclear Regulation)
The independent regulator of nuclear safety and security at nuclear sites in Great Britain.
PDSA (preliminary documented safety analysis)
The preliminary safety analysis that DOE reviews before it authorizes construction of a nuclear facility under its own oversight, such as a test reactor in its Reactor Pilot Program.
PPA (power purchase agreement)
A contract under which a buyer agrees to purchase electricity from a generator, often for many years on agreed terms.
PRIS (Power Reactor Information System)
The IAEA's database of nuclear power reactors in operation, under construction or shut down, with their status and key dates.
PSAR (preliminary safety analysis report)
The safety analysis an applicant submits with a construction permit application, describing the design and how it meets safety requirements.
PWR (pressurized water reactor)
A reactor cooled and moderated by water kept under high pressure so that it does not boil; it is the most common type of power reactor. How a pressurized water reactor works
RPP (Reactor Pilot Program)
A U.S. Department of Energy program, started in 2025, under which DOE rather than the NRC authorizes selected companies' test reactors.
SFR (sodium-cooled fast reactor)
A reactor cooled by liquid sodium that uses fast (unmoderated) neutrons. How a sodium-cooled fast reactor works
SMR (small modular reactor)
A nuclear fission reactor, generally of up to about 300 MWe per unit, whose main parts are designed to be built in a factory; definitions vary, and SMRMap's inclusion rule is on the Methodology page.
TRISO (tristructural isotropic (fuel particle))
A fuel particle in which a small uranium kernel is coated in layers of carbon and silicon carbide that are designed to retain fission products at high temperatures.
VDR (vendor design review)
An optional review by the Canadian Nuclear Safety Commission of a reactor design before any license application; it is not a license.