Updates
Source-linked developments in SMR projects, permissions and policy: what changed, why it matters and what it does not show.
Last updated . In the 7 days to then, SMRMap added 26 developments: 4 dated that week and 22 dated earlier. Of these, 6 are policy measures. Latest additions and changes on SMRMap →
How to read these entries
Each entry is dated when the development happened unless its label says otherwise, such as “Announced” or “Report dated”. A date recorded only to a month, quarter or year is shown that way. Targets are plans, not achievements or commitments. A routine recheck, a new database row or a webpage edit is not listed. An “Agreement or program announced” entry marks the day an agreement, plan or program recorded under Agreements was announced or first reported. It is not evidence that the work it describes has started or been completed.
A target is a plan, not an achieved step. Read the dated source and the scope of each development:
- Application or permission? Filing an application or starting a review does not grant permission. A decision covers only the activity it names: a site or environmental decision is not automatically permission to build or operate.
- Design or project? A design review does not authorize a particular site. National program readiness is different again; the IAEA Milestones Approach is not a project licensing checklist.
- Testing or operation? Construction, commissioning tests, grid connection and commercial operation are different steps. One does not prove the next is complete.
Requirements and sequences differ by country. Compare the named activity and its source, not just a stage label. How to read permissions · Schedule changes and targets.
Since your saved visit
This counts only entries newly added to Updates, by the day SMRMap first published them. Edits to existing entries, new or changed records and stage changes are not counted; see Latest additions and changes on SMRMap. Your saved visit stays only in this browser: SMRMap does not receive it, and loading pages still makes ordinary web requests.
Changes to SMRMap’s pages and downloads are listed separately.
Monthly digests: November 2026 · October 2026 · September 2026 · August 2026 · All months · Latest additions and changes on SMRMap · RSS feed (every project; the filters below do not change the feed)
925 recorded developments and 77 targets listed
No developments match these filters.
Recorded developments
Newest first. An announcement records the announcement, not proof that the announced step occurred.
Announced · Recorded development
OPG: Darlington Unit 1 no longer expected to meet its October 2030 target or C$7.7 billion estimate #
OPG said on 10 November 2026 that the first Darlington BWRX-300 is no longer expected to meet its previously disclosed October 2030 commercial-operation target or C$7.7 billion estimate; its assessment should be substantially complete by mid-2027. Read as republished by Cantech Letter; OPG's own copy and Q3 MD&A not opened. No new date or cost given. Company outlook, not a CNSC decision; does not itself replace the end-2030 grid target.
Checking notes
In its third-quarter 2026 results release of 10 November 2026, OPG said that, while it undertakes a comprehensive assessment of the project's cost and schedule, Darlington New Nuclear Project Unit 1 is no longer expected to achieve the previously disclosed commercial operation date target of October 2030 or be completed within the previously disclosed estimated cost of C$7.7 billion, inclusive of required systems and services that would be common to all planned SMRs. OPG said this reflects GE Vernova Hitachi Nuclear Energy's ongoing engineering for its first-of-a-kind SMR, which OPG says affects construction execution and supply-chain performance, and that the assessment is currently expected to be substantially completed by mid-2027. The release gives no replacement date or cost. OPG's 2025 annual MD&A (12 March 2026) gave grid connection by the end of 2030 and a C$7.7 billion budget, and its first-quarter 2026 MD&A (5 May 2026) listed a 2030 in-service date for Unit 1 against the same approved budget. The release does not mention grid connection; October 2030 is a commercial-operation date, not the end-2030 grid-connection target recorded from OPG's earlier statements.
· Comment period closed
Comments close on NRC licensing, decommissioning and oversight proposal #
Comments closed on 9 November 2026 on the proposal published on 24 September 2026. The proposed changes are not in effect.
Checking notes
NRC published a separate proposal on 24 September 2026 for reactor licensing, decommissioning and operational oversight; comments closed on 9 November. The proposed changes are not in effect. No reactor application, construction permission or operating authority follows from this proposal.
· Regulatory step
NRC issues the Long Mott construction permit #
The NRC says it has issued the construction permit for the four-reactor Long Mott Generating Station in Texas. The permit authorizes construction, not operation. No construction start is recorded.
Checking notes
NRC news release 26-083 of 9 November 2026 says the NRC has issued the construction permit for the Long Mott Generating Station. This event is the same decision as the regulatory action, not a separate announcement. The permit authorizes construction but not operation. It is not a construction start. The permit is CPAR-3 (ADAMS ML26301A133); the Federal Register notice of issuance is 91 FR 72925, 12 November 2026.
· Construction permission recorded
Construction permit issued for the Long Mott Xe-100 station #
The NRC says it has issued a construction permit for Long Mott Energy's four-reactor Xe-100 station at Dow's Seadrift site in Texas. It authorizes construction but not operation. No construction start is recorded; a permit is not a physical construction start.
NRC news release and Construction Permit No. CPAR-3: 9 November 2026. Federal Register notice: 12 November 2026 (91 FR 72925). Application dated 31 March 2025.
Checking notes
Long Mott Energy's construction permit application, dated 31 March 2025, was accepted and docketed by the NRC. NRC news release 26-083 of 9 November 2026 states that the NRC has issued the construction permit for the four-reactor Xe-100 Long Mott Generating Station in Calhoun County, Texas, that staff completed the safety evaluation in October, and that the permit authorizes building the facility but not operation; a separate operating license is required before fuel loading. The release gives no permit number; the permit itself is Construction Permit No. CPAR-3 (ADAMS ML26301A133), issued 9 November 2026, and the Federal Register notice of issuance (91 FR 72925, 12 November 2026) says it is immediately effective and authorizes construction of a power reactor facility in Calhoun County, Texas. The permit sets the earliest construction completion date as 1 July 2033 and the latest as 31 December 2033 and expires on that date. Its conditions include that Long Mott Energy notify the NRC when the site grading design and the passive engineered flooding protection design that may impact site grading are available for NRC staff examination, and that it perform geologic mapping of each foundation excavation for safety-related structures, evaluate it against the site characterization and notify the NRC when it is available for examination; the permit also incorporates an environmental protection plan. It says a license authorizing operation will not be issued unless the applicant submits the complete final safety analysis report, the Commission makes the stated findings on final design and environmental requirements, and the applicant submits proof of financial protection and executes an indemnity agreement. The NRC's project page, updated 12 November 2026, lists the hearing as held on 22 September 2026 and the construction permit decision as 8 November 2026; the permit and the Federal Register notice date issuance to 9 November 2026, and the one-day difference is unexplained in the sources read. Earlier steps: the uncontested (mandatory) hearing was held on 22 September 2026 in Port Lavaca; the Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review supports issuance; NRC issued an environmental assessment and finding of no significant impact plus related exemptions on 18 May 2026. In the contested proceeding, both admitted contentions were dismissed as moot in 2026 and on 7 August 2026 the Commission dismissed the applicant's appeal as moot; on 6 November 2026 the Commission denied the intervenor's separate petition for review (CLI-26-15). The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
· First concrete
Xuwei Unit 3 HTGR pours first nuclear-island concrete #
Construction of the Unit 3 high-temperature gas-cooled reactor formally started on 6 November 2026 with the first nuclear-island concrete. Reported by the technology developer and the owner's parent company; no regulator or IAEA PRIS record of the pour has been read.
Checking notes
Tsinghua University reported on 10 November 2026 that Xuwei Phase I Unit 3 formally started construction on 6 November with the first nuclear-island concrete poured. China National Nuclear Power's announcement 2026-066, dated 6 November, gave that day as the planned pour date. This follows NNSA construction license 国核安证字第2621号 of 2 November.
· Recorded development
Long Mott: Commission denies the intervenor's petition for review #
The Commission denied Waterkeeper's petition for review on 6 November 2026, closing the contested proceeding on the Long Mott construction permit application. An adjudicatory order, not the permit. Whether any court challenge has been filed was not searched.
Checking notes
On 6 November 2026 the Commission denied San Antonio Bay Estuarine Waterkeeper's petition for review of the Licensing Board's rulings, which had rejected or dismissed all of its contentions; the Board had already terminated the proceeding. The order also records that the NRC held its uncontested (mandatory) hearing on 22 September 2026 in Port Lavaca, Texas. An adjudicatory order, not the permit; the construction permit followed on 9 November 2026.
· Comment period closed
Comments close on NRC draft non-light-water reactor materials guidance #
The comment period on draft DANU-ISG-2023-01, Revision 1, closed on 5 November 2026. The draft is not adopted guidance.
Checking notes
NRC published a request for comment on 21 September 2026 on draft DANU-ISG-2023-01, Revision 1, covering material compatibility for non-light-water reactors. This record establishes the consultation notice, not the contents or adoption of the underlying guidance.
Announced · Announcement
X-energy selects Fluor for Cascade nuclear-island engineering #
X-energy said Fluor will provide design and engineering services for the plant areas containing the Xe-100 reactors. An engineering and design contract between X-energy and Fluor, not a construction contract or an NRC application.
Checking notes
X-energy announced on 5 November 2026 that it selected Fluor for engineering, design development, supply chain, estimating and project controls services for the nuclear island of the Cascade facility. The release gives no contract date or value. This is not a construction contract.
Announced · Announcement
X-energy announces first steam-generator tubing order #
X-energy said Alleima and Doosan Enerbility will supply steam-generator tubing and coils for the first Xe-100 deployment. A long-lead component order. It is not a construction start or a final investment decision.
Checking notes
X-energy, Alleima and Doosan Enerbility announced on 4 November 2026 the first procurement of steam-generator tubing for the Xe-100, for its first deployment, the proposed four-unit plant with Dow in Texas. Alleima is to make the tubing and Doosan is to bend it into helical coils. No quantity or value is stated.
Published · Published
NRC publishes new pathways for contested licensing hearings #
The final rule sets Standard, Focused and Expedited pathways for contested adjudications in NRC licensing proceedings. Effective 3 December 2026 for proceedings noticed on or after that date; it decides no project application.
Checking notes
NRC published a final rule on 3 November 2026 to streamline contested adjudications in its licensing proceedings, in response to the ADVANCE Act and Executive Order 14300. It sets Standard, Focused and Expedited hearing pathways, which the Commission says are not rigid designations. It takes effect on 3 December 2026 for contested proceedings noticed on or after that date. It is separate from the mandatory (uncontested) hearing rule of April 2026.
· Construction permission recorded
Construction license issued for Xuwei Unit 3 #
NNSA issued construction license No. 2621 to CNNC Sueneng on 2 November 2026, valid to 1 November 2036, and said the company may begin pouring first concrete for the nuclear-island foundation. No construction start is recorded; a permit is not a physical construction start. It is not an operating license.
Checking notes
China's nuclear regulator reported on 26 June 2025 that it had started the construction-license review for Unit 3 of the Xuwei nuclear heating and power plant, covering the preliminary safety analysis report and the construction-stage environmental impact report, with CNNC Sueneng Nuclear Power presenting the high-temperature gas-cooled reactor. That notice gives no filing day and no license decision. The 9 October 2026 pre-construction inspection report found that preparations met the conditions for issuing a construction license and set seven corrective requirements; it does not itself issue the license. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction license 国核安证字第2621号 for Unit 3 to CNNC Sueneng, valid to 1 November 2036, and says the company may begin pouring the first concrete for the nuclear-island foundation. The license requires an operating-license application before first fuel loading. It is not an operating license. No construction start is recorded; a permit is not a physical construction start.
· Site permission recorded
NNSA issues site-selection opinion for Huakun One #
NNSA's site-selection opinion No. 2620 of 2 November 2026 found no disqualifying site factor that engineering measures could not resolve, and agrees design work may proceed on the site parameters. It is not a construction license. Until it holds one, the company may not pour seismic Category I foundation concrete or build other safety-important structures.
Checking notes
The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2620号) on 2 November 2026 to CGN Ocean Energy for the Huakun One floating reactor platform and maintenance base at the Taipingling nuclear base in Huidong county. The review found no disqualifying site factor affecting safety that engineering measures could not resolve, and the opinion agrees that design work may proceed on the stated site parameters. It is not a construction license: before holding one the company may not pour seismic Category I foundation concrete or build other safety-important structures.
Announced · Announcement
Long Mott: X-energy says the NRC has completed its final safety evaluation #
X-energy announced on 30 October 2026 that the NRC's final safety evaluation report for the Long Mott construction-permit application is complete. Reported by the company; the NRC's project page still showed a November target on 1 November. A safety evaluation is not a construction permit.
Checking notes
X-energy announced on 30 October 2026 that the NRC had completed its final safety evaluation report for the Long Mott construction-permit application, documenting the staff's conclusion that the proposed plant and site provide the safety basis to begin construction. The release gives no NRC document number or issue date. When checked on 1 November, the NRC had posted no news release about it, and its Long Mott page (last updated 14 September) still listed the final evaluation as a November 2026 target. A safety evaluation is not a construction permit; as of that 1 November reading, the hearing outcome and permit decision had not been recorded here. The later NRC release of 9 November separately confirms October completion and issuance of the construction permit; those developments have their own records.
Announced · Announcement
Radiant says DOE approved its Kaleidos safety analysis #
Radiant says a DOE Readiness Review comes next, before nuclear operations can begin, with fuel loading and a test campaign to follow. This is Radiant's account, and the DOE document was not opened. No date is given, and no startup or criticality is recorded.
Checking notes
Company statement of 29 October 2026. Radiant says DOE approved its Documented Safety Analysis, covering operation at power as well as initial criticality, and that DOE's Readiness Review is the next step before nuclear operations can begin. It says fuel loading and a five-phase test campaign follow a successful review. This is Radiant's account; the DOE approval document was not opened. No date is given for the review, fuel loading or criticality, and no startup or criticality is recorded.
· Recorded development
Nuclearelectrica shareholders adopt RoPower measures #
Shareholders took note of the Doicești conditions and strategy update without a vote, and adopted the measures in the meeting's note with about 90 percent of the votes present or represented. The resolution does not repeat the measures, and whether RoPower has carried them out is not recorded.
Checking notes
Extraordinary meeting held on 29 October 2026. Shareholders took note, without a vote, of the status of the February 2026 investment-decision conditions and the strategy update. They adopted the measures in Section 4 of the meeting's note, with 90.13 percent of the votes of shareholders present or represented, and authorized Nuclearelectrica's representative to vote for them at RoPower Nuclear's own meeting. The note says RoPower's plan should aim, at the least, to cut the staff working on the project by at least 60 percent, keeping only critical staff, over about six months, and asks RoPower for that plan within a month of the meeting; the resolution refers to the note and does not repeat it. Whether RoPower has carried the measures out is not recorded.
Announced · Announcement
ARC announces a memorandum with Hyundai Engineering on ARC-100 deployment #
ARC said it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. to explore support for the first U.S. ARC-100 deployment at Idaho National Laboratory and for NRC licensing. It is a memorandum to explore collaboration, not a construction contract or a license application.
Checking notes
Company statement of 29 October 2026. ARC says it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. to explore support for the first U.S. ARC-100 deployment at Idaho National Laboratory and for design completion and NRC licensing under 10 CFR Part 53. It is a memorandum to explore collaboration, not a construction contract or a license application.
Announced · Announcement
NANO Nuclear announces a memorandum with Hyundai Engineering on KRONOS #
NANO Nuclear said it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. as a framework for potential collaboration on the University of Illinois reactor. A larger role depends on later evaluation and separate agreements. NANO says it awards no work package and commits neither party to funding or construction. It is not a construction contract.
Checking notes
Company statement of 27 October 2026. NANO Nuclear says it signed a memorandum of understanding with Hyundai Engineering Co., Ltd. as a framework for potential collaboration on project-execution planning, site-related work, procurement and supply chain for the University of Illinois reactor. A larger role would depend on later evaluation, university and regulatory requirements and separate definitive agreements. NANO says the memorandum is non-exclusive and does not itself award any work package or commit either party to funding or construction. It is not a construction contract.
Announced or first reported · Agreement or program announced
USTDA-funded SMR assessment and roadmap for TÜPRAŞ refining operations #
USTDA said on 26 October 2026 that it signed an agreement with TÜPRAŞ to fund technical assistance assessing SMRs to supply electricity, heat and steam for its refining processes, and a roadmap for evaluating whether and how SMRs could be deployed. No refinery, site or reactor is named.
Published · Published
NRC publishes a pathway for using prior DOE or defense reactor evidence #
The final rule permits relevant evidence from previously authorized facilities that have been tested and demonstrated safe functioning to support NRC commercial reactor licensing applications. Effective 25 November 2026. Applicants must demonstrate NRC compliance; the rule grants no project license or construction or operating permission.
Checking notes
NRC published a final rule allowing applicants to use relevant evidence from previously DOE- or Defense-authorized reactors that have been tested and demonstrated safe functioning. It takes effect on 25 November 2026. Applicants must show how that evidence satisfies NRC requirements and address differences in the commercial application. NRC retains independent review and licensing authority. The rule is an evidentiary pathway, not an automatic project approval.
· Took effect
NRC modernization rule takes effect #
The NRC Modernization direct final rule took effect on 26 October 2026, as confirmed in a Federal Register notice of 30 September 2026. The NRC calls the changes administrative; the rule licenses no reactor.
Checking notes
Effective date confirmed by FR Doc. 2026-19963, published 30 September 2026.
Announced · Announcement
Elementl announces proposed partnership of up to $750 million #
Elementl said a consortium led by DS Investment Partners would fund a portion of a partnership supporting up to three projects, including Ohio. A preliminary agreement subject to definitive documents and approvals. It is not a final investment decision or committed funding.
Checking notes
Elementl announced on 26 October 2026 a letter of intent and term sheet for a proposed development partnership of up to $750 million with a consortium led by DS Investment Partners. It would fund part of the capital needed to bring up to three projects, including the Ohio project, to a final investment decision.
Announced or first reported · Agreement or program announced
Blykalla and NEEXT SEALER basic-design engineering cooperation #
Blykalla announced on 26 October 2026 an agreement signed on 2 October expanding NEEXT's engineering support for SEALER conventional-island basic design. NEEXT's design and digital-modeling engineers are being integrated into Blykalla's engineering organization. References to Swedish reactor parks provide context and do not establish a separate construction contract for each site.
Announced · Announcement
Antares reports Mark-1 safety-design agreement approval #
Antares announced that DOE had approved the Mark-1 Nuclear Safety Design Agreement, the first step in the authorization pathway described by the company. Company-reported framework; approval day unknown. It is not construction or operating authorization.
Checking notes
Antares announced that DOE had approved the Mark-1 Nuclear Safety Design Agreement. The company describes it as the first step in DOE's authorization pathway and a framework for design requirements and safety analysis. This date is the announcement day; the approval day is not stated. The NSDA is not itself construction or operating authorization.
Announced or first reported · Agreement or program announced
Dairyland Power and Applied Atomics letter of intent to evaluate SMRs at the Genoa site (Wisconsin) #
Dairyland Power Cooperative and Applied Atomics announced on 22 October 2026 a letter of intent to evaluate deploying one or more Applied Atomics small modular reactors at Dairyland's Genoa site in southwest Wisconsin, with Dairyland to explore buying the power through a power purchase agreement. Applied Atomics says it holds the exclusive land-based license to BWXT's mPower design and describes its units as 100 MWe each. The site formerly hosted a 50 MW nuclear plant and a coal plant retired in 2021, and no unit count, order or license application is stated.
Announced or first reported · Agreement or program announced
Rosatom and PT Pembangkit Listrik Nuklir floating power agreement for northern Halmahera #
Rosatom's 20 October newsletter reports an agreement with PT Pembangkit Listrik Nuklir to supply northern Halmahera using two FPU-100 units, 200 MW combined as stated. First electricity is expected as early as five years after key electricity-supply contract terms take effect, without a fixed year. The signing date, precise berth and operator are unestablished, and this is not a permission or a construction start.
Company announcement · Announcement
Radiant announces Kaleidos selection for Naval Weapons Station Crane #
The company identifies the vendor and design for the previously announced Indiana microreactor proposal. Company-reported selection; testing, environmental review, site preparation and regulatory coordination remain ahead. No Crane-specific capacity or operating date is inferred.
Checking notes
Radiant announced that the Department of the Navy selected it to deploy Kaleidos at Naval Weapons Station Crane. The company lists design refinement, prototype testing, environmental review, site preparation and regulatory coordination before deployment. This selection announcement is not a construction start, regulatory permission or operating milestone; the separate Navy original was identified but could not be opened.
· Application submitted
Last Energy files for a limited work authorization at its Caldwell site #
Last Energy filed Part 1 of a phased construction permit application, including a limited work authorization request, for a PWR-20 plant in Caldwell County, Texas. A notice of receipt only; the NRC has not yet said whether it will docket the application, and nothing is authorized.
Filed 20 October 2026. Federal Register notice of receipt: 5 November 2026.
Checking notes
Last Energy filed Part 1 of a two-part phased construction permit application on 20 October 2026 for a PWR-20 facility at the Caldwell Site in Caldwell County, Texas. Part 1 includes a limited work authorization request under 10 CFR 50.10(d) covering early foundation work, with financial information, a preliminary safety analysis report for the LWA scope, an environmental report and a site redress plan. The NRC published a notice of receipt on 5 November 2026 (91 FR 69895). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction.
Announced or first reported · Agreement or program announced
Deep Fission and GPDA commercial power agreement at Great Plains Industrial Park #
Deep Fission announced a definitive master energy purchase agreement with GPDA for a commercial Gravity project at its Parsons pilot site, distinct from the pilot itself. The company anticipates 150 MW initially and commercial operation on 30 September 2028, with later phases to 2,000 MW depending on demand. Under the agreement, GPDA would purchase available electricity for park tenants with no minimum obligation or disclosed price, and licensing, Kansas approvals and delivery arrangements remain conditions.
Announced or first reported · Agreement or program announced
National Tsing Hua University and NuCube Energy assessment of a microreactor on the NTHU campus #
National Tsing Hua University and NuCube Energy signed an agreement on 19 October 2026 to exchange information on and assess micro modular reactor development, research uses and deployment feasibility, including the possibility of a unit on the NTHU campus. NTHU's THOR research reactor is due to be decommissioned in 2040. NTHU hopes for installation within two years after NuCube's reactor reaches commercial operation in the US. No order, site decision or license application is established.
Announced or first reported · Agreement or program announced
AEP, Amazon and X-energy exploration agreement for the former Breed station in Indiana #
Amazon's 19 October 2026 announcement describes an agreement with AEP and X-energy to explore Xe-100 deployment at the former Breed station in Sullivan County, Indiana, targeting 12 reactors and up to 960 MW as stated. Amazon is a prospective first power customer and development funder. X-energy describes an AEP/X-energy JDA for feasibility work and milestone-based Amazon capital. No amount, disbursement, formal operator appointment, construction permission or final investment decision is established.
· Regulatory step
Long Mott: NRC's safety advisory committee supports issuing the construction permit #
The NRC's Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review of the Long Mott construction-permit application supports issuance of the permit. An advisory report, not a permit decision; the committee lists important work still needed for an operating license.
Checking notes
The NRC's Advisory Committee on Reactor Safeguards wrote to the NRC Chairman on 16 October 2026 that it had completed its review of the Long Mott construction-permit application and the staff's safety evaluation at its 6–9 October meeting (the Long Mott session was scheduled for 7 October), and that its review supports issuance of the construction permit. It listed important work remaining for an operating license application, including fuel and material performance at peak accident temperatures. This is an advisory report, not a permit decision.
Announced or first reported · Agreement or program announced
Thorizon–TNO molten-salt reactor materials program #
Thorizon and TNO announced a TNO-led materials and corrosion program to generate experimental data and predictive models for PIONEER licensing and later Thorizon One deployment. Initial work is under way in Amsterdam and Petten, with wider Dutch and international partners still prospective. This research agreement establishes no completed material qualification, reactor order, new site commitment or permission.
Announced or first reported · Agreement or program announced
SÚJB and SSM memorandum on regulatory cooperation for the Rolls-Royce SMR #
The Czech regulator SÚJB signed a memorandum of understanding with the Swedish regulator SSM on 14 October 2026, mainly on cooperation for future deployment of the Rolls-Royce small modular reactor. SÚJB says both regulators have similar agreements with the UK's ONR, making the cooperation trilateral. The memorandum is not a licensing decision, and SÚJB's notice names no Czech or Swedish project or site.
Announced or first reported · Agreement or program announced
FANCO–Floral Energy integrated-power opportunity evaluation #
FANCO announced a strategic partnership with Floral Energy to evaluate UK opportunities and potential US projects combining near-term generation with a future EAGL-1 pathway. Work covers site evaluation, technical integration and development planning. Oldbury is a potential site subject to access, feasibility and approvals. Floral’s initial Power Blocks are gas-fired. Their capacity is not a nuclear commitment. Individual projects still require commercial arrangements, financing and approvals. The announcement does not specify which US projects may participate.
Announced or first reported · Agreement or program announced
Port of Rotterdam preliminary SMR supply-chain study #
On 12 October 2026 Tractebel announced an exploratory study by Tractebel and Technopolis Group, commissioned by SmartPort, Deltalinqs, the Port of Rotterdam Authority, the Municipality of Rotterdam and the Province of South Holland. It assesses the port's potential role in a future SMR supply chain. It identifies no selected reactor, deployment site, design or developer. This records a study, not a deployment.
Report dated · Recorded development
Xuwei preparations meet construction-license conditions #
NNSA's inspection team found that site management and technical preparations met the conditions for issuing a construction license, while setting seven corrective requirements. The report itself does not issue that license or establish that first concrete occurred.
Inspection: 15–18 September. Report published: 12 October.
Checking notes
NNSA's report on its 15–18 September 2026 inspection before first concrete for Unit 3, signed 9 October and published 12 October, says the inspection team found that site management and technical preparations met the conditions for issuing a construction license. It also sets seven corrective requirements. The report does not itself issue a construction license or establish that first concrete occurred.
Consultation opened · Regulatory step
Consultation opens on the proposed Norrsundet facility plan #
The Gävleborg county board opened consultation on its proposed facility plan and environmental impact statement for the six-reactor Norrsundet park, running from 9 October to 13 November 2026. A draft plan under consultation; it is not Government approval or a license to build.
Checking notes
The Gävleborg county administrative board opened consultation on its proposed facility plan and environmental impact statement for the Norrsundet nuclear facility, running from 9 October to 13 November 2026. The plan covers about 40 hectares within the property Norrsundet 15:28; the board must submit its proposal to the Government by 31 December 2026.
· Took effect
Poland's 2026 nuclear power program takes effect #
The resolution updating the Polish Nuclear Power Programme took effect on 7 October 2026, the day after its publication. A program resolution directs the administration; it funds, licenses or sites no SMR project.
Checking notes
§ 5: in force the day after publication.
Announced · Announcement
Last Energy says DOE approved its PWR-5 final safety analysis #
Last Energy said DOE approved its final Documented Safety Analysis for the PWR-5 pilot at Texas A&M-RELLIS. The company says DOE readiness review and startup authorization are still ahead. The announcement does not establish operating authority or criticality.
Checking notes
On 7 October Last Energy said DOE approved its final Documented Safety Analysis. The DOE letter and exact decision date were not opened. The company says DOE readiness review and startup authorization are still ahead; this announcement does not establish operating authority or criticality.
Reported · Recorded development
BREST-OD-300 turbine hall receives separator-superheaters #
Rosatom said two separator-superheaters were installed in the turbine hall; concreting of the turbine foundation began in May 2026. This is non-nuclear turbine-hall work; it does not change the operation schedule.
Checking notes
World Nuclear News reported on 7 October 2026, relaying Rosatom, that two separator-superheaters had been installed in the turbine hall, that concreting of the turbine-generator foundation began in May 2026, and that the turbine-unit foundation is to be completed by the end of 2026. The date is the report date; the installation day is not given.
· Published
Poland publishes its 2026 nuclear power program in Monitor Polski #
The Council of Ministers resolution updating the Polish Nuclear Power Programme was published in Monitor Polski, 2026 item 977. A program resolution directs the administration; it funds, licenses or sites no SMR project.
Checking notes
Monitor Polski, Warszawa, dnia 6 października 2026 r., poz. 977.
Release dated · Recorded development
INL reports DOE approval of MARVEL's final documented safety analysis #
INL says DOE's Idaho Operations Office approved MARVEL's final documented safety analysis just before the primary coolant system arrived at INL in mid-September 2026. INL describes it as a key safety document authorizing a dry criticality configuration at near-zero power with no coolant. Criticality in December is a target; the release does not report achieved criticality.
The release gives no approval day.
Checking notes
INL's release of 6 October 2026 says DOE's Idaho Operations Office approved MARVEL's final documented safety analysis just before the primary coolant system arrived at INL in mid-September 2026, and describes it as a key safety document authorizing a dry criticality configuration at near-zero power with no coolant. The date shown is the release date, a report date; no approval day is given and the DOE approval document was not opened. The release anticipates criticality in December, a target. It does not identify a separate startup authorization or report achieved criticality.
Announced · Announcement
BWXT announces BANR selection for Belledune transportable plant #
BWXT announced the selection of BANR, with two reactors planned for the up to 50 MWe transportable plant. New Brunswick signed a letter of intent to buy power. This announcement is not a license or a construction start.
Checking notes
BWXT announces BANR selection and two planned reactors for the up to 50 MWe transportable plant; New Brunswick signed a letter of intent to buy power. Planned count is not constructed units, and this announcement is not a license or construction start.
· Provision took effect
Fixed NRC review-fee caps start applying to new applications #
The fixed fee caps in 10 CFR 170.33 apply to complete applications the NRC accepts for review on or after 1 October 2026. A fee cap decides no application; it licenses no reactor.
Checking notes
Table 1 fixed fee caps apply to complete applications accepted for review on or after this date (10 CFR 170.33(b)).
Reported · Recorded development
Linglong One reported in hot functional testing #
Linglong One was in hot functional testing, the test after which fuel loading comes next, according to a China News Service site report. Fuel loading, criticality and grid connection had not happened; the 2026 dates are targets.
Checking notes
China News Service reported from the Changjiang site on 1 October 2026 that the Linglong One unit was in hot functional testing, with civil works complete and equipment installation essentially finished, and that fuel loading and grid connection were targeted within 2026. NucNet relayed the testing status on 7 October 2026. The start date of hot testing is not stated; fuel loading, criticality and grid connection are not recorded as achieved. China News Service describes cold and hot functional testing as the two key checks a unit passes before grid connection, with fuel loading the next step after hot testing.
Letter dated · Regulatory step
Duke files Revision 2 of its Belews Creek early site permit application #
Duke Energy Carolinas submitted Revision 2 of the Belews Creek early site permit application in response to regulatory-audit questions. Duke states it is not requesting a limited work authorization. Revision 2 is an applicant filing, not an NRC permit, a design selection or a construction start.
Checking notes
Duke Energy Carolinas letter RA-26-0157 (ML26274A437), dated 1 October 2026, submits Revision 2 of the Belews Creek early site permit application in response to regulatory-audit questions. The letter states that Duke is not requesting a limited work authorization, so no Site Redress Plan under 10 CFR 52.17(c) is provided. Parts 2, 3, 5 and 10 were revised for audit items; Parts 7 and 8 were unchanged. Revision 2 is an applicant filing, not an NRC permit, a design selection or a construction start.
· Regulatory step
ČEZ submits EIA documentation for the Temelín Rolls-Royce SMR #
ČEZ submitted EIA documentation for the Temelín Rolls-Royce SMR to the Ministry of the Environment.
Checking notes
ČEZ submits EIA documentation for the Temelín Rolls-Royce SMR to the Ministry of the Environment.
· Recorded development
NRC completes the Long Mott safety evaluation in October #
The NRC says staff completed its comprehensive safety evaluation for Long Mott in October 2026, one month ahead of schedule. The source gives no completion day. This is the evaluation, not the separately recorded construction permit or an operating license.
Checking notes
NRC news release 26-083 of 9 November 2026 states that staff completed the comprehensive safety evaluation in October, one month ahead of schedule. The source does not give a completion day. This completion is distinct from X-energy's announcement on 30 October and the NRC's separately recorded construction-permit decision on 9 November. A safety evaluation is not a construction permit or operating license.
Notice updated · Recorded development
Véron newcleo proposal: CNDP says the debate reports are available #
A CNDP notice says the debate reports are available. It gives newcleo and RTE until 30 December to explain how they take the debate into account and communicate their decision. The 30 December date is not a regulator's licensing-decision deadline.
Notice posted 29 September, updated 30 September 2026. Chairman's assessment dated 1 October 2026.
Checking notes
The CNDP notice, posted on 29 September and updated on 30 September 2026, says the debate reports are available. This event dates the notice update, not the publication of each report. The linked chairman's assessment separately bears 1 October 2026. The notice gives newcleo and RTE until 30 December to explain how they take the debate into account and communicate their decision; this is not a regulator's licensing-decision deadline.
Published · Announcement
INL reports Radiant completed the first DOME test #
INL published a statement reporting that Radiant completed the first DOME test. INL gives no completion day, achieved power or scope of completion.
Checking notes
This is the publication date of INL’s statement, not the physical completion date. INL supplies no completion day, achieved power or scope of completion; no operating-stage promotion or final authorization is inferred.
Announcement dated · Published
ONR explains how inspectors use relevant good practice #
A new inspector policy explains how established practices can inform assessments against goal-setting legal duties. Guidance does not replace the legal test or grant project permission; the exact release day of issue 1.1 is not established.
Checking notes
ONR's announcement date; the opened issue 1.1 gives only September 2026 as its publication date.
· Environmental decision recorded
DOE approves environmental determination for PWR-5 Phase 1 testing at RELLIS #
DOE approved a NEPA determination for proposed PWR-5 Phase 1 initial criticality and low-power testing, bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export. This is not DOE startup authorization or proof that criticality occurred.
Checking notes
DOE approved NEPA determination DOE-ID-26-008 on 30 September 2026 for proposed PWR-5 Phase 1 initial criticality and low-power testing at RELLIS. The Phase 1 research configuration is bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export. The 19.5 MWth PWR-5 design point applies to later phases. This environmental decision is not DOE startup authorization, proof of achieved criticality, or authorization for later phases.
· Recorded development
Holtec says Pioneer safety analysis report completes permit application part 2 #
Holtec reported that the preliminary safety analysis report completed the second part of its phased construction-permit application for Pioneer Units 1 and 2. No limited work authorization or construction permit is recorded.
NRC draft safety evaluation report: 31 August 2026. Press anticipated an LWA safety evaluation in December 2026.
Checking notes
Holtec reported that the preliminary safety analysis report completed the second part of its phased construction-permit application. Press anticipated a later limited-work-authorization safety evaluation in December 2026, while the NRC milestone table already lists a draft safety evaluation report with information gaps on 31 August 2026; these are dated reports, not a new permission. No LWA or construction permit is recorded. The NRC's notice of receipt published 10 November 2026 confirms it received Part 2 on 30 September 2026 and says its staff was then undertaking its acceptance review; acceptance for docketing would be a later, separate step.
· Application submitted
Hexana asks ASNR for an opinion on a first safety option for its SMR #
ASNR reports that Hexana requested an opinion on a first safety option for its small modular reactor. ASNR places this in pre-instruction safety-options exchanges. This is a design assessment request, not a Gard Rhodanien site application or an issued opinion.
Checking notes
ASNR reports that Hexana requested an opinion on a first safety option for its small modular reactor on 30 September 2026. The page places this in pre-instruction safety-options exchanges. This is a design assessment request, not a Gard Rhodanien site application, construction permission or issued opinion.
Announced · Announcement
INL names DOME as host for Unity's planned 2027 full-power test #
INL named DOME as the host for Unity's planned 2027 full-power test. The self-funded slot is conditional on readiness, fuel and regulatory milestones. Selection is not authorization.
Checking notes
INL names DOME as the host for Unity’s planned 2027 full-power test. The self-funded slot is conditional on readiness, fuel and regulatory milestones; selection is not authorization.
Announced · Announcement
TVA announces NRC construction permit for Clinch River Unit 1 #
TVA announced that the NRC had issued a construction permit for Clinch River Unit 1. The announcement is not a construction start.
The NRC notice dates the permit 28 September 2026.
Checking notes
TVA announced on 29 September 2026 that the NRC had issued a construction permit for Clinch River Unit 1. The NRC notice dates the permit 28 September 2026. The announcement is not a construction start.
· Issued
Poland adopts its 2026 nuclear power program update #
Poland's Council of Ministers adopted Resolution No. 198 updating the Polish Nuclear Power Programme, which centers on large reactors and promises an SMR roadmap with case-by-case, technology-neutral support decisions. A program resolution directs the administration; it funds, licenses or sites no SMR project.
Checking notes
Uchwała nr 198 Rady Ministrów z dnia 29 września 2026 r.
Letter dated · Schedule change
NRC caps Belews Creek review fees and brings forward its review schedule #
An NRC letter sets a $2,178,000 fixed cap on NRC review fees for the Belews Creek early site permit, a service-fee limit rather than a project cost, and accelerates the review schedule. The revised review dates remain targets.
Moved earlier: advanced final safety evaluation report and draft environmental impact statement to December 2026; final safety evaluation report to February 2027; final environmental impact statement to March 2027.
Checking notes
NRC letter ML26259A008, dated 29 September 2026 and signed by Michelle W. Hayes, sets a $2,178,000 fixed cap on NRC review fees for the Belews Creek early site permit. The cap is a service-fee limit, not a project cost, a permit or a design selection. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The same letter accelerates the 8 February 2026 acceptance-letter schedule (ML26016A624): advanced final safety evaluation report without open items from March 2027 to December 2026; final safety evaluation report from May 2027 to February 2027; draft environmental impact statement from February 2027 to December 2026; final environmental impact statement from May 2027 to March 2027. The revised dates remain targets.
· Construction permission recorded
Construction permit issued for TVA's Clinch River Unit 1 #
A construction permit was issued to TVA for Clinch River Nuclear Unit 1. It is immediately effective and authorizes construction of a power reactor facility in Roane County, Tennessee. No construction start is recorded; a permit is not a physical construction start.
Federal Register notice: 5 October 2026. Construction completion: earliest 1 October 2031, latest 30 September 2032.
Checking notes
The Federal Register published this notice on 5 October 2026 at 91 FR 63311. It states that construction permit CPAR-2 was issued to TVA on 28 September 2026 for Clinch River Nuclear Unit 1, is immediately effective, and authorizes construction of a power reactor facility in Roane County, Tennessee. The notice says the conditions in early site permit ESP-006 had been met except those listed in the construction permit. The permit sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, expires on that latest date and does not restate an output rating. TVA announced the permit on 29 September 2026. The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Announced or first reported · Agreement or program announced
Busan Metropolitan City plan for an SMR special zone and marine SMR industry (2026) #
Busan is studying the feasibility of an SMR special zone under the SMR Special Act that took effect in September 2026, aiming at a demonstration-and-export hub, and plans a zone-planning study in 2027. It also promotes marine SMRs for floating plants and ships. The plan names no reactor site, design or developer.
· Proposed
NRC proposes changes to reactor licensing, decommissioning and operational oversight #
The NRC published a proposal for reactor licensing, decommissioning and operational oversight, with comments due on 9 November. The proposed changes are not in effect.
Checking notes
NRC published a separate proposal on 24 September 2026 for reactor licensing, decommissioning and operational oversight; comments closed on 9 November. The proposed changes are not in effect. No reactor application, construction permission or operating authority follows from this proposal.
Published · Recorded development
Second RITM-200S completed at ZiO-Podolsk for the first PEB-106 #
The second RITM-200S was completed at ZiO-Podolsk, completing the reactor set for the first PEB-106 floating unit for Baim / Cape Nagloynyn.
Completion day not stated.
Checking notes
Second RITM-200S completed at ZiO-Podolsk, completing the reactor set for the first PEB-106. Date is the publication date; completion day not stated.
· Recorded development
Atucha shareholders reportedly authorize a tender for a privately financed reactor #
Shareholders reportedly declared the reactor initiative of business interest and authorized the board to call a public tender for a privately financed reactor over 12 hectares of land reserved for the canceled Atucha III. Authorizing a tender is not an award.
Checking notes
Reported shareholders' meeting decision: the reactor initiative declared of business interest and the board authorized to call a public tender for a privately financed reactor over 12 hectares of the land reserved for the canceled Atucha III. Not an award.
Announced or first reported · Agreement or program announced
SGE, GE Vernova, Hitachi and Samsung C&T cooperation on BWRX-300 fleet deployment in Central and Eastern Europe and… #
Synthos Green Energy (SGE) and Samsung C&T signed a memorandum in December 2025 to explore partnership on BWRX-300 fleet deployment in Central and Eastern Europe, including studies for SGE's Polish project and a possible Samsung C&T investment. On 22 September 2026 SGE, GE Vernova, Hitachi and Samsung C&T signed a broader framework memorandum on BWRX-300 market development in Central and Eastern Europe and the UK, linked to the July 2026 US-Japan-Korea memorandum. Neither names a new site or order.
· Comment period closed
Comments close on NRC draft training-review guidance #
After a one-month extension, the comment period on draft NUREG-1220, Revision 2, closed on 21 September 2026. This is not adopted guidance or a training-program approval.
Checking notes
Extended from 21 August 2026 by 91 FR 54407.
Notice published · Published
NRC seeks comments on draft reactor materials guidance #
The notice concerns draft DANU-ISG-2023-01, Revision 1, for non-light-water reactors. The underlying draft guidance was not opened; the notice establishes no effective guidance or permission.
Checking notes
Publication of the instrument described here. Later final disposition not established.
Announced · Announcement
Ameresco picked to negotiate Aberdeen Proving Ground power lease, with an IMSR planned #
The Army selected Ameresco to negotiate a long-term lease for a power campus at Aberdeen Proving Ground in Maryland. Ameresco says it is working with Terrestrial Energy on an IMSR for the campus's Phase 2 site. The lease is still under negotiation; this is not a license application, permit or construction start.
Checking notes
Ameresco said the Army competitively selected it to negotiate a long-term lease for a power campus at Aberdeen Proving Ground and that it is working with Terrestrial Energy on an IMSR for the Phase 2 site. The lease is not yet signed and no construction will begin before environmental and regulatory reviews.
· Recorded development
FLiBe coolant salt arrives at Natura's MSR-1 facility at Abilene Christian University #
DOE says more than 4,700 pounds of FLiBe salt, once the coolant of Oak Ridge's Molten Salt Reactor Experiment, arrived at Natura's facility for MSR-1, shipped with Oak Ridge and Idaho national laboratories. A salt delivery is not fuel loading, criticality or operation.
Checking notes
DOE says more than 4,700 pounds of FLiBe salt, once the coolant of Oak Ridge's Molten Salt Reactor Experiment, arrived at Natura's facility at Abilene Christian University on 18 September 2026 for MSR-1, shipped with Oak Ridge and Idaho national laboratories; Natura's release gives the same delivery date. A salt delivery is not fuel loading, criticality or operation.
· Recorded development
NRC holds uncontested hearing on the Belews Creek early site permit application #
The NRC scheduled the uncontested hearing for 17 September 2026 in Danbury, North Carolina, and its project page marks the hearing as held. The permit decision date is listed as to be determined. A hearing is a review step, not a decision.
Hearing notice: 6 August 2026.
Checking notes
The NRC's notice of 6 August 2026 (91 FR 50896) scheduled the uncontested hearing for 17 September 2026 in Danbury, North Carolina, and the NRC's project page marks that hearing as held. A hearing is a review step, not a decision. The permit decision date is listed as to be determined.
Announced · Announcement
Idaho State University names site for its Advanced Research and Test Reactor #
An Idaho State University announcement identifies the Business and Research Park as the site of the future Advanced Research and Test Reactor. The announcement establishes no nuclear permission.
Checking notes
University announcement identifies the future Advanced Research and Test Reactor site at the Business and Research Park. No numerical reactor coordinates or nuclear permission are established.
Announced · Announcement
Blue Energy says it submitted Part 1 of an NRC construction permit application #
Blue Energy statements say the first part of a construction permit application for the Port of Victoria project was submitted to the NRC. A submitted application part is not a permit.
Checking notes
Company statements of 16 September 2026 say the first part of a construction permit application for the Port of Victoria project was submitted to the NRC. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only, and no Federal Register notice was found on 5 October 2026. A submitted application part is not a permit.
Announced or first reported · Agreement or program announced
Universidad Nacional-led study of SMR viability in Colombia's Eje Cafetero (coffee region) #
Researchers led by the Universidad Nacional de Colombia, with the Universities of Caldas and Quindío, the Quindío departmental government and other partners, are studying whether small modular reactors could be viable in Colombia's Eje Cafetero region, using computer simulations of technical, economic and social factors. The project was in final evaluation for national royalties funding in September 2026, it names no site and is not a plan to build.
· Application submitted
Blue Energy files Part 1 of a construction permit application for Port of Victoria #
Blue Energy filed Part 1 of a phased construction permit application for one BWRX-300 unit in Victoria, Texas. It includes a limited work authorization request, two exemption requests and an environmental report. It is the first part of a phased application; the applicant intends to file the full application within 18 months of Part 1. The NRC has reported receipt only, not acceptance for docketing, a limited work authorization or a construction permit.
NRC notice of receipt: 8 October 2026. Blue Energy asked for acceptance review of specified items by 20 November 2026.
Checking notes
Blue Energy filed Part 1 of a phased construction permit application on 15 September 2026 for one BWRX-300 unit, Blue Energy Center–Port of Victoria Nuclear Unit 1, in Victoria, Texas. Part 1 includes a limited work authorization request, two related exemption requests and an environmental report. The NRC published a notice of receipt on 8 October 2026 (91 FR 64409). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction. The applicant intends to file the full construction permit application within 18 months of Part 1.
Announced or first reported · Agreement or program announced
EGAT SMR feasibility study funded by the US Trade and Development Agency (about 600 MWe) #
On 14 September 2026 EGAT and USTDA signed an agreement for a US-funded feasibility study on deploying US SMR technologies in Thailand, assessing locations, costs and regulatory steps for about 600 MWe. The vendor-neutral study is to consider designs from seven US companies. It is a study, not a site or technology selection.
Release dated · Recorded development
TVEL: first stage of concreting BREST-OD-300 reactor-vessel inner cavity completed #
TVEL said the first stage of concreting the BREST-OD-300 reactor-vessel inner cavity at Seversk was completed.
The release does not give the completion day.
Checking notes
First stage of concreting the BREST-OD-300 reactor-vessel inner cavity completed (TVEL release). Date is the release date; the release does not give the completion day. Company statement relayed by atomic-energy.ru.
· Took effect
South Korea's SMR Special Act takes effect #
South Korea's Special Act on the Promotion of and Support for SMR Development took effect on 11 September 2026, requiring a five-year SMR development plan and a promotion committee, according to the science ministry. The Act licenses or approves no reactor or project.
Checking notes
In force 11 September 2026, together with its Enforcement Decree per the Ministry of Science and ICT.
· Recorded development
Nuclearelectrica publishes the government Control Body's report on the Doicești SMR #
The report concludes that the FEED 2 stage ran 20 months late, says Doicești ranked second in the consultant site assessment, and gives a December 2025 cost estimate of USD 6.5 billion. An audit body's findings, not a regulator decision or court ruling. It has other findings not summarized here. Nuclearelectrica answered a summary on 28 July 2026. The project stage does not change.
Checking notes
Nuclearelectrica published the Romanian Prime Minister's Control Body report on its audit of the company from 15 October 2025 to 20 March 2026, in the form submitted by its majority shareholder, the Ministry of Energy, after shareholders approved publication on 11 September 2026. The report concludes that the SMR project's FEED 2 stage ran 20 months late against the original timeline, says Doicești ranked second in Sargent & Lundy's site assessment, and gives a December 2025 cost estimate of USD 6.5 billion. It makes other findings on the project company's set-up, the Doicești site purchase and Nuclearelectrica's oversight, which this record does not summarize.
In force · Amended
Japan's NRA amends its rule on power-reactor location and structure standards #
NRA Rule No. 7 of 2026 amended the 2013 rule on the location, structure and equipment of commercial power reactors, in force 11 September 2026. The content of the amendment was not reviewed; the rule approves no site.
Checking notes
NRA Rule No. 7 of 2026, enforced the same day; its content was not reviewed.
· Comment period closed
Comment period closes on the NRC modernization direct final rule #
The public comment period on the NRC Modernization direct final rule closed. A closed comment period does not change what the rule does; it licenses no reactor.
Checking notes
NRC rule in force since 26 October 2026, taken in response to Executive Order 14300. It simplifies how applicants ask the NRC to withhold proprietary information, makes some post-rule comment periods optional, aligns advisory committee rules with government-wide standards and updates security eligibility criteria. The NRC calls the changes administrative. It licenses no reactor.
Announced or first reported · Agreement or program announced
Senegal nuclear power program focused on small modular reactors (launched September 2026) #
At a national workshop opened on 7 September 2026, Senegal's energy minister declared that the political decision for nuclear power had been taken and that implementation would follow the IAEA's phased approach under the Sénégal 2050 agenda, with small modular reactors as the chosen route. A ministry presentation said three 300 MW SMRs could cover about 20% of national needs in 2050, no design, vendor, site or financing has been decided.
· Published
Finland publishes its new Nuclear Energy Act #
The Nuclear Energy Act 775/2026 was published on 7 September 2026. It takes effect on 1 January 2027. The Act is not yet in effect and approves no project.
Checking notes
Finlex julkaisupäivä 7.9.2026.
· Comment period closed
Comments close on India's draft SHANTI Rules #
The comment period on the Department of Atomic Energy's draft SHANTI Rules closed on 4 September 2026. The draft rules are not in effect.
Checking notes
Deadline for submission: 8:00 PM on 4 September 2026.
· Comment period closed
Comments close on India's draft SHANTI Regulations #
The comment period on the draft SHANTI Regulations closed on 4 September 2026. The draft regulations are not in effect.
Checking notes
Deadline for submission: 8:00 PM on 4 September 2026.
· Issued
Finland issues a new Nuclear Energy Act, in force from 1 January 2027 #
Finland's Nuclear Energy Act 775/2026 was issued on 4 September 2026. From 1 January 2027 it replaces the 1987 Act and sets decisions-in-principle, Government licensing of nuclear power plants, and site and protective-zone rules. The Act is not yet in effect and approves no project.
Checking notes
Finlex antopäivä 4.9.2026.
· Contract
Studsvik selects GE Vernova Hitachi and Samsung C&T for a four-unit BWRX-300 project #
Studsvik selected GE Vernova Hitachi and Samsung C&T as strategic partners for an initial four-unit BWRX-300 project of up to 1.2 GW at Nyköping or Målma. The first site is still to be decided. This is not an investment decision.
Checking notes
Strategic partners selected for an initial four-unit BWRX-300 project of up to 1.2 GW at Nyköping or Målma; the first site is still to be decided. Not an investment decision.
· Recorded development
Studsvik selects GE Vernova Hitachi and Samsung C&T for four-unit BWRX-300 project #
Studsvik selected GE Vernova Hitachi and Samsung C&T for an initial four-unit BWRX-300 project.
Checking notes
Studsvik selects GE Vernova Hitachi and Samsung C&T for an initial four-unit BWRX-300 project.
· Provision took effect
Poland's Atomic Law amendment adds a license for preliminary nuclear construction works #
Amendments of 3 July 2026, published on 18 August, took effect on 2 September 2026, adding a separate license from the National Atomic Energy Agency for preliminary construction works at a nuclear power facility. The amendment licenses no site, design or project.
Checking notes
Art. 2 of the Act of 3 July 2026 (new art. 36l) in force 14 days after publication on 18 August 2026 (Art. 9), recorded by the Sejm ELI service as 2 September 2026.
· Provision took effect
Poland's nuclear investments act adds an early permit for preliminary construction works #
Amendments of 3 July 2026 to Poland's 2011 special act took effect on 2 September 2026, adding an earlier building permit for preliminary construction works at a nuclear power facility. It approves no SMR project or design.
Checking notes
Art. 1 of the Act of 3 July 2026 (definition, decision in principle, arts. 17a-17c) in force 14 days after publication on 18 August 2026 (Art. 9), recorded by the Sejm ELI service as 2 September 2026.
Announced · Announcement
Belledune: First Nations and Prodigy transportable nuclear proposal of up to 50 MWe #
The Pabineau and Eel River Bar First Nations and Prodigy propose a transportable nuclear plant of up to 50 MWe at Belledune. The packaging platform is not a selected reactor design. No construction start or precise parcel is established.
Checking notes
Pabineau and Eel River Bar First Nations / Prodigy proposal for up to 50 MWe. The packaging platform is not a selected reactor design. No construction start or precise parcel is established.
Notice published · Published
Army publishes adoption of DOE advanced-reactor categorical exclusion #
The Army adopted DOE categorical exclusion B5.26 as an available environmental-review procedure. No installation is named and no reactor site, construction or operation is approved.
Checking notes
Publication of the instrument described here. Later final disposition not established.
Available for Army use · Effective date recorded
Army can use the adopted advanced-reactor categorical exclusion #
The adoption notice states that DOE categorical exclusion B5.26 is available for Army use from 1 September 2026. No installation is named and no reactor site, construction or operation is approved.
Checking notes
Availability of the adopted exclusion for Army use, not approval of a particular project.
Announced or first reported · Agreement or program announced
USTDA-funded SMR deployment roadmap study for TÜNAŞ #
In September 2026 USTDA signed an agreement with state-owned TÜNAŞ to fund technical assistance for a regulatory, institutional and financial roadmap for SMR deployment by Turkish private companies, including a year-long review of US SMR and advanced designs. No site or plant is involved.
Company timeline · Recorded development
BWXT says Pele core barrel cartridge installation is complete #
BWXT's program page lists core barrel cartridge installation for the Pele reactor as complete in September 2026. The reactor has not yet shipped to INL or been loaded with fuel.
Checking notes
BWXT's program page lists core barrel cartridge installation as complete in September 2026, at its Lynchburg facility. This is a company statement about factory assembly, not shipment, fuel loading or operation.
Reported · Contract
Bechtel steps away from Natrium Kemmerer Unit 1; TerraPower to rebid EPC contract #
Bechtel and TerraPower said in September 2026 that they would move forward separately; Bechtel will finish the on-site Sodium Test & Fill Facility. TerraPower said it would rebid the engineering, procurement and construction contract. No replacement contractor is named; the company's statement that the schedule is unaffected is not a verified milestone.
Checking notes
Reported on 22 September 2026: Bechtel and TerraPower said they would move forward separately after considering the next phase of the project. Bechtel said its work had been under an earlier contract phase, before full EPC scope, and that it would remain on site to complete the Sodium Test & Fill Facility. TerraPower said it would rebid the EPC contract and manage the transition to protect the schedule.
· Other regulatory action recorded
NNSA approves safety design criteria for the Xuwei high-temperature reactor #
NNSA approved B-version safety design criteria for the Xuwei HTGR. Its later announcement describes a small nuclear power reactor with multiple modules and one turbine. The criteria guide safety review; they are not a construction license.
Checking notes
NNSA instrument 国核安发〔2026〕161号, signed 31 August 2026, approves B-version safety design criteria for the Xuwei HTGR. Its later 29 September announcement describes a small nuclear power reactor with multiple modules and one turbine. The criteria guide safety review and are not a construction license.
· Comment period closed
Comments close on NRC proposal to modernize reactor licensing, oversight and siting #
Comments closed on the NRC proposal, published on 16 July 2026 under the Commission's revision of its rules ordered by Executive Order 14300. The proposal is not in effect.
Checking notes
NRC proposal published 16 July 2026 under the Commission's revision of its rules ordered by Executive Order 14300; comments closed 31 August 2026. It is not in effect.
Announced · Contract
TerraPower names 12 Natrium supplier awards #
Twelve equipment and design awards to 11 companies, including BWXT Canada, Mirion Technologies and Thermal Engineering International, support the Natrium plant and its sodium test and fill facility. No contract values; awards are not split between the plant and the test facility; not an EPC appointment.
Checking notes
TerraPower's release of 31 August 2026 announced 12 supplier awards to 11 companies, including control rod drive design by BWXT Canada, a plant cyber system by Mirion Technologies and an air-sodium heat exchanger by Thermal Engineering International. It says the awards support construction of the Natrium plant and completion of the sodium test and fill facility, without assigning individual awards to either; seven of the twelve are design scopes and no values are given. These are supplier awards, not an EPC appointment.
· Recorded development
NRC completes draft safety evaluation report for Pioneer, with information gaps #
The NRC completed a draft safety evaluation report, with information gaps, for Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades).
Checking notes
NRC draft safety evaluation report (with information gaps) completed.
· Recorded development
Untra Nuclear Power AB applies for Swedish state support #
Untra Nuclear Power AB applied for Swedish state support.
Checking notes
Untra Nuclear Power AB applies for Swedish state support.
· Other regulatory action recorded
NRC allows specified Pioneer excavation walls before a limited work authorization #
The NRC issued a narrow exemption allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization. It does not issue or commit to a limited work authorization or construction permit, or show that physical work began.
Checking notes
The NRC issued a narrow exemption on 28 August 2026 allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization. The notice does not issue or commit to an LWA or construction permit. The exemption does not show that physical work began or authorize all construction.
· Recorded development
Government assigns Uppsala county administrative board to draft Untra facility plan #
The Government assigned the Uppsala county administrative board to draft a facility plan for Untra.
Checking notes
Government assigns Uppsala county administrative board to draft a facility plan for Untra.
· Environmental decision recorded
NRC finds no significant environmental impact for Pioneer excavation-wall exemption #
The NRC issued an environmental assessment and finding of no significant impact covering the environmental effects of the requested Pioneer support-of-excavation-wall exemption. It is not the 28 August exemption and does not issue a limited work authorization or construction permit.
Made available: 24 August 2026. The later exemption notice describes it as issued on 25 August.
Checking notes
The NRC made an environmental assessment and finding of no significant impact available on 24 August 2026; its later exemption notice describes the finding as issued on 25 August. It addresses environmental effects of the requested support-of-excavation-wall exemption; it is not the 28 August exemption and does not issue an LWA or construction permit.
Announced · Announcement
Blykalla reports application for up to eight SEALER units at Untra, Tierp #
Blykalla reports an application for up to eight units and up to 440 MWe in total. Operation in the first half of the 2030s is conditional on approvals. No construction is established.
Checking notes
Company reports an application for up to eight units and up to 440 MWe total. First-half-2030s operation is conditional on approvals; no construction is established.
· Application submitted
Blykalla applies for Government approval of eight lead-cooled SMRs at Untra, Tierp #
Blykalla AB applied for the Government's approval of eight lead-cooled small modular reactors of about 440 MW in total at Untra in Tierp municipality. Approval would replace the Environmental Code permissibility review, but not licensing under the Environmental Code and the Nuclear Activities Act. Approval needs municipal consent and a facility plan in force.
Received 26 August. Facility plan assigned 28 August to Uppsala county administrative board, due 30 April 2027.
Checking notes
Blykalla AB applied on 25 August 2026 (recorded as received on 26 August) for the Government's approval of eight lead-cooled small modular reactors of about 440 MW in total at Untra in Tierp municipality; on 28 August 2026 the Government assigned the Uppsala county administrative board to draft a facility plan by 30 April 2027. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.
Reported · Recorded development
Report: Rosatom expects Myanmar survey contract by end of 2026, site work in 2027 #
Atomic Energy 2.0, relaying Strana Rosatom, reported that Rosatom expects to sign a contract for primary engineering surveys by the end of 2026 and begin site work in 2027. These remain plans; the site is not named.
The report describes an 18 August government meeting but does not separately date the Rosatom statement.
Checking notes
Atomic Energy 2.0 reported on 24 August 2026, relaying Strana Rosatom, that Rosatom expects to sign a contract for primary engineering surveys by the end of 2026 and begin site work in 2027. The report describes the 18 August government meeting but does not separately date the Rosatom statement. The first stage is two RITM-200N reactors of 55 MW each, with possible later expansion to 330 MW. These remain plans; the site is not named. The event date is the report date.
· Recorded development
Myanmar: Russian prime minister says implementation of the agreements is starting #
The Russian prime minister said during the Myanmar president's visit that implementation of the agreements is starting. The site is still not named.
Checking notes
Statement by the Russian prime minister during the Myanmar president's visit; the site is still not named.
Notice published · Regulatory step
Regulator reviews Linglong One commissioning anomalies #
The NNSA working group's second 2026 meeting reviewed open review questions, commissioning progress and anomalies found during commissioning. Regulatory oversight, not a license decision.
Checking notes
A notice published on 18 August 2026 by the NNSA's nuclear power safety supervision department reports the working group's second 2026 meeting on the Hainan Changjiang small modular reactor demonstration. It covered unclosed review questions, overall review and site-inspection status, commissioning progress and the handling of anomalies found during commissioning, and asked for a full review of instrumentation and control commissioning and verification. The meeting is regulatory oversight, not a license decision.
· Took effect
NRC's fiscal 2026 fee rule takes effect, with fixed review-fee caps #
The NRC fee rule for fiscal year 2026 took effect, setting $337 an hour for full-cost reviews and $154 for eligible advanced reactor applicants, and adding fixed caps on review fees under Executive Order 14300. It licenses no reactor and decides no applicant's eligibility.
Checking notes
NRC fee rule for fiscal year 2026, in force since 17 August 2026. It sets the full-cost review rate at $337 an hour and the reduced rate for advanced reactor applicants at $154, and adds fixed caps on review fees under Executive Order 14300 for applications that end in a final safety evaluation. It licenses no reactor and decides no applicant's eligibility.
· Proposed
India's atomic energy department proposes draft SHANTI Rules #
The Department of Atomic Energy put draft SHANTI Rules dated 14 August 2026 out for comment. They would require design approval and stage-by-stage safety authorizations from the regulator. A draft has no legal effect.
Checking notes
Draft dated 14 August 2026 and placed on the Department's consultation page.
· Proposed
India publishes draft SHANTI Regulations on nuclear siting authorization #
Draft SHANTI Regulations of the Atomic Energy Regulatory Board, dated 14 August 2026, were put out for comment. They would require a separate safety authorization for siting a nuclear power plant or reactor. A draft has no legal effect.
Checking notes
Draft dated 14 August 2026 and placed on the Department of Atomic Energy's consultation page.
· Recorded development
NRC holds mandatory hearing on Clinch River construction permit #
The NRC held a mandatory hearing on the Clinch River construction permit for TVA's BWRX-300.
Checking notes
NRC mandatory hearing on Clinch River construction permit.
Announced or first reported · Agreement or program announced
TRISO-X–ORNL fuel-research agreement extension #
TRISO-X announced a 30-month extension of its ORNL cooperative research relationship, continuing its existing pilot facility and work on fuel-fabrication quality, yield and characterization. This research aims to develop manufacturing processes. It establishes no delivered commercial fuel, completed fuel qualification or reactor order.
· Published
NRC publishes an administrative modernization rule under Executive Order 14300 #
The NRC published a direct final rule simplifying requests to withhold proprietary information, making some post-rule comment periods optional, aligning advisory committee rules and updating security eligibility criteria. The NRC calls the changes administrative; the rule licenses no reactor.
Checking notes
NRC rule in force since 26 October 2026, taken in response to Executive Order 14300. It simplifies how applicants ask the NRC to withhold proprietary information, makes some post-rule comment periods optional, aligns advisory committee rules with government-wide standards and updates security eligibility criteria. The NRC calls the changes administrative. It licenses no reactor.
· Recorded development
Long Mott: Commission dismisses applicant's appeal after contentions ruled moot #
The Commission dismissed Long Mott Energy's appeal of the Licensing Board's January 2026 ruling admitting an intervenor, because the Board had since dismissed both admitted contentions as moot. An adjudicatory order, not a permit decision. The petition for review was later denied (CLI-26-15, 6 Nov 2026) and the permit issued 9 Nov 2026.
Checking notes
The Commission dismissed Long Mott Energy's appeal of the Licensing Board's January 2026 ruling admitting an intervenor, because the Board had since dismissed both admitted contentions as moot. It took no position on the intervenor's separate petition for review. This is an adjudicatory order, not a permit decision; the construction-permit application was still under review at that date. The Commission later denied the intervenor's petition for review (CLI-26-15, 6 November 2026) and the NRC issued the construction permit on 9 November 2026.
Announced · Regulatory step
Deep Fission announces DOE approval of its Gravity pilot NSDA #
Deep Fission announced approval of the NSDA for its Gravity pilot at Parsons. The agreement defines an early safety framework and separate later readiness, startup and operating steps. The announcement is not an NRC license or evidence of operating authority.
A later public NSDA cover attributes the approval to a DOE letter dated 14 July.
Checking notes
Deep Fission announced NSDA approval on 6 August 2026. Its later public NSDA cover attributes approval to DOE letter CLN260841 dated 14 July, which was not opened. The agreement defines an early safety framework and separate later readiness, startup and operating steps. This announcement is not an NRC license or evidence of operating authority.
Announced or first reported · Agreement or program announced
METI next-generation reactor support: MHI domestic small light-water reactor (SMR) development (2026) #
In August 2026 MHI said METI selected three of its proposals under a supplementary-budget program supporting next-generation reactors, including development of a small light-water reactor using domestic technology. MHI noted that Japan's 31 July 2026 nuclear policy guideline placed small light-water reactors (SMRs) at the social-implementation stage. This is development funding, not a plant, site or license.
Announced or first reported · Agreement or program announced
Paraguay SMR and microreactor plans under the US-Paraguay strategic civil nuclear memorandum (August 2026) #
On 4 August 2026 Paraguay and the United States signed a non-binding Memorandum of Understanding on Strategic Civil Nuclear Cooperation. Paraguay's nuclear regulator head told ABC Color that microreactors could be operating around 2030 and SMRs in about ten years, but described the memorandum as a political step toward a binding Section 123 agreement, no project, site or vendor exists.
Announced or first reported · Agreement or program announced
TerraPower and SK Innovation term sheet to develop Korea's first commercial Natrium plant (2026) #
TerraPower and SK Innovation announced a term sheet in August 2026 to advance their intent to develop Korea's first commercial Natrium plant and expand internationally. The agreement also expands SK Innovation's participation in TerraPower's US demonstration and later commercial projects. No site, capacity, schedule or license application in Korea is named.
Announced or first reported · Agreement or program announced
TerraPower and Hyundai E&C framework agreement: EPC for up to eight Natrium reactors (2026) #
In August 2026 TerraPower signed a strategic framework agreement selecting Hyundai Engineering & Construction as its engineering, procurement and construction contractor for up to eight future Natrium reactors, with completion, price and performance guarantees. It follows a May 2026 TerraPower, HD Hyundai and HDEC memorandum. No specific plant, site or order for those units is named.
· Recorded development
Tarapur approved as site for BSMR-200 and SMR-55 lead units, DAE tells Parliament #
Written answers to Parliament posted in August and September 2026 state that the Atomic Energy Commission approved Tarapur as the site and gave in-principle approval for engineering and construction. Sanction and regulator consent are not reported.
Checking notes
Written answers posted in August and September 2026 state Atomic Energy Commission approval of Tarapur as the site and in-principle approval for engineering and construction; sanction and regulator consent are not reported.
· Recorded development
Radiant's Kaleidos reactor ships from El Segundo to INL #
Radiant's Kaleidos reactor shipped from El Segundo to INL.
Checking notes
Kaleidos reactor ships from El Segundo to INL.
Announced or first reported · Agreement or program announced
Holtec, Entergy and Hyundai E&C agreement to evaluate SMR-300 projects across Entergy's territory (2026) #
In August 2026 Holtec, Entergy and Hyundai E&C signed a non-binding memorandum of agreement to evaluate potential dual-unit SMR-300 projects for large-load customers in Entergy's service territory in Mississippi, Louisiana, Texas and Arkansas. It covers demand, candidate sites and commercial structures, no site or order is recorded.
Announced or first reported · Agreement or program announced
NuCube Energy and Alaska Fund NuAlaska initiative for NuSun-1 projects in Alaska #
NuCube Energy and Alaska Fund announced a memorandum of understanding in July 2026 creating NuAlaska, a joint initiative pairing NuCube's NuSun-1 reactor with Alaska Fund's financing to advance nuclear energy projects in Alaska. No site, unit count, order or license application is named.
Announced · Announcement
Holtec Oyster Creek SMR proposal documented #
Company proposes four SMR-300 units with expected combined output of 1,360 MWe, gross/net unspecified. Approval of the former station decommissioning plan is not an SMR construction permit.
· Application submitted
Application submitted: OTRERA ONE safety-options request #
ASNR states that Otrera filed a safety-options request on 30 July 2026 for OTRERA ONE, listed on the 14 October 2026 page as a 200 MWth sodium-cooled demonstrator/prototype. The page does not record an opinion or a creation authorization. This is not a sited project.
· Recorded development
Nuclearelectrica answers a government Control Body report on the Doicești SMR #
Nuclearelectrica responded to a summary of the Prime Minister's Control Body report on the SMR project, saying the schedule was always an estimate and citing IAEA site-review missions. The company's response to a summary of the report. The full report was published on 11 September 2026.
Checking notes
Nuclearelectrica published clarifications on issues raised in the summary of a report by the Romanian Prime Minister's Control Body about the SMR project, saying the original schedule was an estimate and citing IAEA site-review missions of 2022, 2024 and 2025.
Proposal published · Proposed
NRC proposes package-certification changes for microreactor transport #
The proposed rule would allow increased radiation-level limits for some Type B packages under stated conditions. It certifies no package and authorizes no reactor deployment.
Checking notes
Publication of the instrument described here. Later final disposition not established.
· Recorded development
DOE conditional HALEU commitment for the Buckley microreactor #
DOE made a conditional commitment on 23 July 2026 to provide high-assay low-enriched uranium to Radiant for its deployment of a microreactor to the Air Force's preferred location, Buckley Space Force Base; DOE will next begin the contracting process. This is a fuel allocation commitment, not delivery, a site decision or permission.
· Recorded development
Jimmy submits an updated Bazancourt creation-authorization file #
ASNR states that Jimmy filed an updated design and the remaining answers on 23 July 2026, and that MSNR referred that file to ASNR for review on 24 July 2026. The update is not a creation authorization.
· Selections announced
Selections announced: DOE HALEU Availability Program and HALEU allocation process #
Third round: conditional commitments to NASA and Radiant.
Announced or first reported · Agreement or program announced
X-energy participation in Project Prometheus #
X-energy announced Tier 1 participation in the INL-led Project Prometheus research initiative, contributing Xe-100/TRISO-X design data and $10 million in private capital. The company reports a $60 million award to the wider three-year initiative, not to X-energy alone. Work targets engineering, licensing and manufacturing workflows. Its FAQ rules out present Xe-100 control-room AI integration. Neither reactor permission nor achieved deployment acceleration is established.
Notice published · Published
NRC seeks comments on draft training-review guidance #
The notice describes draft NUREG-1220, Revision 2, including stationary microreactors and small modular LWRs. The underlying draft was not opened. This is not adopted guidance or a training-program approval.
Checking notes
Publication of the instrument described here. Later final disposition not established.
Announced · Announcement
Rolls-Royce SMR Tušimice candidate location proposal documented #
Named location under study in the ČEZ / Rolls-Royce SMR partnership. Site selection studies and a proposal do not establish construction or a committed unit count.
Announced · Announcement
Rolls-Royce SMR Dětmarovice candidate location proposal documented #
Named location under study in the ČEZ / Rolls-Royce SMR partnership. Site selection studies and a proposal do not establish construction or a committed unit count.
Announced · Announcement
Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1 #
Announced or first reported · Agreement or program announced
Czech Industry Ministry, ČEZ and Rolls-Royce SMR memorandum to prepare additional SMR sites #
On 21 July 2026 the Czech Ministry of Industry and Trade, ČEZ and Rolls-Royce SMR signed a memorandum opening the way to prepare further SMR sites, chiefly Dětmarovice and Tušimice, after the first unit planned at Temelín. Rolls-Royce SMR spoke of three Czech sites allowing up to six units. ČEZ also analyses other areas, including Prunéřov, Ledvice, Mělník and Dukovany, without proposals there.
· Amended
Amended: Pennsylvania Radiation Protection Act section 402.1: small modular reactor and microreactor fees #
The official compilation's compiler note says section 402.1 was added July 20, 2026, P.L. 464, No. 37. The official act page says the act was enacted from HB 2017 on that date and prints Effective 60 DAYS. No calendar effective date is printed, so none is stored, and the section's 30-day payment clock is not converted into a day.
· Environmental decision recorded
Environmental decision recorded: DOE Aurora-INL B5.26 environmental categorical exclusion #
DOE Idaho approved environmental determination DOE-ID-INL-26-018 on 20 July 2026 for the proposed Aurora-INL reactor construction, installation and operation scope under B5.26. The document describes anticipated activities and a planned construction period; it is an environmental determination, not evidence that reactor construction occurred, an approval of the preliminary safety analysis, or authority to load fuel or operate.
· Proposed
Proposed: Proposed modernization of reactor licensing, safety oversight and siting practices #
NRC proposal published 16 July 2026 under the Commission's revision of its rules ordered by Executive Order 14300; comments closed 31 August 2026. It is not in effect.
· Proposed
Proposed: Proposed modernization of NRC radiation-protection standards #
NRC proposed revisions to its radiation-protection standards on 15 July 2026, with comments due 31 August. The proposal includes rules used in reactor licensing and draft implementing guidance. No final rule or effective date is established by this notice, and it grants no reactor permission.
· Recorded development
Doicești FID conditions remain unresolved #
SNN reported unmet conditions and continuing commercial negotiations.
· Recorded development
Doicești: shareholders reject a strategy reassessment and note unmet investment-decision conditions #
Nuclearelectrica's shareholders acknowledged information on the work to fulfill the conditions attached to the February 2026 final investment decision and rejected initiating a reassessment of the 2022 SMR implementation strategy.
· Took effect
Took effect: Kentucky KRS 278.615: nuclear permit and license cost recovery #
The compiled statute says it was created by 2026 Ky. Acts ch. 56, section 2, effective 15 July 2026. It lets the commission consider cost recovery for specified NRC permit costs. It does not approve a plant. The session-law PDF prints the 8 April 2026 signature and does not print this effective line.
· Took effect
Took effect: Kentucky KRS 164.2805: Nuclear Reactor Site Readiness Pilot Program #
The compiled statute says it was created by 2026 Ky. Acts ch. 56, section 1, effective 15 July 2026. It authorizes a site-readiness grant process. The compiled page records no award. The session-law PDF prints the 8 April 2026 signature and does not print this effective line.
Announced or first reported · Agreement or program announced
FANCO–Hyundai E&C EAGL-1 cooperation framework #
Hyundai E&C reported an EAGL-1 framework signed on 13 July 2026 (published 14 July) covering early balance-of-plant design, Bridge Power support, construction-feasibility reviews and modularization, then a five-year master service agreement signed on 30 October 2026 for constructability reviews, design and engineering advice and construction feedback. Scope, duration and value are set by later task orders, a future EPC role is exploratory and initial Bridge Power gas generation is not nuclear capacity. No site, reactor order, operator or configuration is named.
· Published
Published: Estonia: Nuclear Energy and Nuclear Safety Act (Tuumaenergia ja -ohutuse seadus) #
RT I, 11.07.2026, 1.
Announced or first reported · Agreement or program announced
Holtec plan to use its retired nuclear plant sites (Pilgrim, Indian Point, Big Rock Point) for future SMR-300 units #
In its July 2026 Form S-1, Holtec Nuclear Corp. described an affiliate-owned SMR-300 deployment portfolio and identified its retired Pilgrim, Indian Point and Big Rock Point sites as potential locations for future SMR-300 units, alongside the existing Palisades and Oyster Creek projects. Beyond Palisades and Oyster Creek these are prospective sites only, with no license applications or construction decisions.
· Proposed
Proposed: Proposed revisions to NRC implementation of NEPA #
NRC proposed changes to its NEPA environmental-review procedures on 7 July 2026, with comments due 21 August. Proposed changes concern review scope, procedures, categorical exclusions and draft guidance. The notice establishes no final rule or effective date and grants no project exemption, construction permit or operating authority.
· First criticality
Aalo-X zero-power criticality #
Zero-power fueled criticality at INL. Not the RELLIS commercial proposal.
Announced · Announcement
Aalo announces Project Ascension #
Aalo names its proposed second reactor and future 10 MWe data-center demonstration. This is an announcement date, not a construction start or achieved generation.
· Electricity generation
Ward 250 reaches 100 kW thermal with electricity generation (DOE update) #
DOE's Reactor Pilot Program update of July 2026 lists 2 July 2026 as the day Ward 250 achieved full power of 100 kW thermal, with electricity generation. Valar's own statement dates electricity generation to 1 July 2026. The 250 kW thermal rating stored for this reactor comes from DOE's categorical exclusion; the update's full-power figure is 100 kW thermal.
Announced or first reported · Agreement or program announced
Thorizon-led Project Pronto under the Dutch MOOI Kernenergie scheme #
The Dutch government announced on 2 July 2026 that four projects would share EUR 12.6 million under MOOI Kernenergie, including Project Pronto, led by Thorizon. Thorizon's release reports a EUR 4 million grant to it, VDL Groep, NRG PALLAS, TU Delft and TNO for a full-scale non-nuclear prototype and corrosion tests in molten salt up to 650°C, supporting its PIONEER and Thorizon One plans. It does not name Pronto, and the match rests on Thorizon leading only that project. No reactor construction funding, order or permission is established.
· Awarded
Awarded: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) #
Announced 2 July 2026: four projects share EUR 12.6 million, using the whole available budget; RVO assessed five applications.
· Signed
Signed: Estonia: Nuclear Energy and Nuclear Safety Act (Tuumaenergia ja -ohutuse seadus) #
Proclaimed by the President of the Republic, resolution no. 772 of 2 July 2026.
· Electricity generation
Ward 250 first electricity #
Valar says Ward 250 generated its first electricity on 1 July 2026 and that the electricity directly powered an NVIDIA chip. DOE's Reactor Pilot Program update says full power of 100 kWt, with the electricity used to power an NVIDIA Spark, on 2 July 2026. Both dates are kept. Neither source states a kilowatt-electric rating or a grid connection.
Announced or first reported · Agreement or program announced
SGE plan for a 14-unit BWRX-300 fleet at three UK sites #
SGE's 1 July 2026 plan proposes 14 BWRX-300s at three unnamed UK sites under the Advanced Nuclear Framework. Earlier sources record expected site selection in H1 2027 and disputed Oldbury press reports, with GBE-N saying it held no record of SGE interest in the land. WNN reported on 22 October that SGE SMR UK and OPG subsidiary Origin Nuclear signed an LOI for a proposed UK operating company. It describes intended future fleet roles, not a named site's licensed operator appointment, reactor permission or site selection.
· Recorded development
Radiant receives first TRISO fuel tranche at INL's DOME facility #
Announced or first reported · Agreement or program announced
Dong Nai city plan seeking selection to pilot an SMR power plant by 2035 #
Dong Nai's People's Committee issued a plan implementing Vietnam's atomic energy strategy that aims for the city to be chosen by the central government to pilot an SMR power plant by 2035, and envisages a hybrid SMR-renewables system for data centers. It is an aspiration, no developer, design, site or central decision exists.
Plan dated · Announcement
Last Energy names Caldwell County, Texas, for its first commercial microreactor #
Last Energy's plan for NRC engagement says its first commercial PWR-20 unit is planned at a 44-acre Caldwell County site, its priority for NRC engagement. A company engagement plan, not an application or permit.
Checking notes
Last Energy's regulatory engagement plan, Revision 1.0, dated July 2026 and issued to the NRC on 30 July 2026 according to its record of change, says the company's first commercial PWR-20 unit is planned at a 44-acre site in Caldwell County, Texas, and calls the site its priority for NRC engagement. The plan schedules a limited work authorization application and a docket number for later in 2026; it is a company plan, not an application or permit.
· Recorded development
NRC draft safety evaluation sections completed for the Belews Creek ESP #
· Milestone
Milestone: DOE Reactor Pilot Program #
DOE reports four zero-power criticality demonstrations by July 2026.
Announced or first reported · Agreement or program announced
Bapco Energies study of a small modular nuclear plant for Bahrain #
Semafor reported in July 2026, citing MEED, that Bahrain is studying whether to build a small modular nuclear power plant, led by state-owned Bapco Energies through its venture capital arm. This follows a July 2025 US-Bahrain nuclear cooperation memorandum. No plant decision, design or site is recorded.
Announced or first reported · Agreement or program announced
GBE-N desktop study of land in Scotland technically suitable for new nuclear, including SMRs and microreactors #
GBE-N, advising DESNZ, published on 30 June 2026 a high-level desktop study identifying land areas in Scotland that may be technically suitable for future nuclear deployment, considering microreactors, SMRs/AMRs and GW-scale reactors. The report notes the Scottish Government's policy of not granting planning consent to new nuclear, it creates no project or site decision.
· First criticality
Unity criticality demonstration #
DOE fact sheet dates the INL demonstration 30 Jun 2026. Electrical output not stated.
Announced or first reported · Agreement or program announced
Rwanda Atomic Energy Board and Rosatom roadmap on small modular reactors (first Joint Coordinating Committee, 2026) #
At the first meeting of the Rwanda-Russia Joint Coordinating Committee on nuclear energy in Moscow, the Rwanda Atomic Energy Board and Rosatom signed a roadmap on small modular reactors, alongside work on a nuclear science center, personnel training and infrastructure. The roadmap names no design, site or plant and is not an order.
· Recorded development
Ward 250 passive-safety demonstration: shutdown with all active cooling off and simulated total loss of power #
Supplies the date the IAEA outlook omits for the loss-of-forced-cooling demonstration (company statement).
· Recorded development
Swedish Government decides to take a 60% stake in Videberg Kraft #
The Government decided that the state will own 60% of Videberg Kraft, with Vattenfall and Industrikraft at 20% each; formal transfer is expected in the second half of 2027 and the negotiated support terms go to the European Commission for state-aid review. Not an investment decision, permit or construction start.
· Regulatory step
NRC issues the final safety evaluation report for the Clinch River construction permit application #
The NRC's project page lists the final safety evaluation report (ML26168A505) as issued on 25 June 2026, within the accelerated schedule. A safety evaluation supports the permit decision; it is not itself the construction permit.
Proposal published · Proposed
NRC proposes materials-licensing changes for advanced reactor fuels #
The proposed rule includes changes to the Part 72 spent-fuel definition and damaged-fuel description. A proposed change, not an adopted rule, fuel approval or reactor authorization.
Checking notes
Publication of the instrument described here. Later final disposition not established.
· Recorded development
NRC formal review activities begin for the KRONOS construction permit application #
Announced · Recorded development
Williams Treaties First Nations announce C$700 million investment in Darlington new nuclear #
Seven First Nations will lend C$700 million to Darlington New Nuclear Project LP for construction of the first BWRX-300 unit; the loan converts to equity once all four units are built. Federal and Ontario programs guarantee the financing. The stake is in the four-unit new-build project, not the existing Darlington station, and no ownership percentage is published.
Checking notes
Seven Williams Treaties First Nations announced a C$700 million investment, structured as a loan to Darlington New Nuclear Project LP for construction of the first of four BWRX-300 units, converting to equity once all four are built. Federal and Ontario Indigenous loan-guarantee programs support about C$715 million in financing.
Announced or first reported · Agreement or program announced
Nuclear Energy Strategy for Canada (2026): SMR and microreactor objectives #
Natural Resources Canada published Canada's first national nuclear strategy on 22 June 2026, after announcing it in April. Its objectives include at least one nuclear deployment, including SMRs, operational or under construction outside Ontario by 2035, and a Canadian microreactor demonstrated by 2035 for later deployment to remote communities. These are policy targets, not approved projects.
· Failed
Failed: Arizona S.B. 1418, vetoed: corporation commission and small modular reactors #
The fact sheet prints Vetoed by the Governor 6/19/26. Senate Research prepared the sheet on 25 June 2026. The governor's 19 June 2026 action page lists SB 1418 under Vetoed.
· First criticality
Ward 250 zero-power criticality #
Zero-power fueled criticality at Utah San Rafael Energy Lab.
· Contract
Terrestrial Energy RELLIS ground lease #
Ground lease and research agreements for about 77 acres. Not a reactor license.
Announced · Announcement
Elementl announces Letart BWRX-300 proposal #
Named host and early works agreement; no construction permit inferred.
· Provision took effect
Provision took effect: Sweden: Act on Nuclear Activities (SFS 1984:3, lag om kärnteknisk verksamhet) #
Amendments by SFS 2026:587 (licensing split, advance rulings on design) in force 17 June 2026 per their transitional provisions.
· Took effect
Took effect: Sweden: Act on Government Approval of Nuclear Facilities (SFS 2026:585) #
Transitional provision 1; point 2 allows application to applications filed after 10 March 2026.
· Provision took effect
Provision took effect: Sweden: Act on Government Approval of Nuclear Facilities (SFS 2026:585) #
Companion Environmental Code amendments (SFS 2026:586) to chapter 17 ss. 1 and 6 a in force 17 June 2026.
Adopted · Passed
Estonia adopts a Nuclear Energy and Nuclear Safety Act, to take effect on 1 January 2027 #
The Riigikogu adopted the Act on 17 June 2026. It sets nuclear safety rules for each stage of an installation's life. The Ministry of Climate says it creates a nuclear regulator within the Consumer Protection and Technical Regulatory Authority. Not yet in force. The Act approves no site, design or project.
Checking notes
Vastu võetud 17.06.2026.
· Recorded development
NRC issues the KRONOS review schedule #
NRC milestone marked actual: review schedule established and schedule letter issued. The later 2027 dates on that schedule are targets.
· Regulatory step
Ministry requests more information on Stellaria's INB Alpha application #
Following ASNR's analysis, the ministry asked Stellaria on 16 June 2026 to complete its INB Alpha file. ASNR's technical review is suspended until that information arrives. A request for information, not a refusal or an authorization.
Checking notes
After ASNR's analysis, the ministry's nuclear-safety mission (MSNR) requested further information from Stellaria on the INB Alpha creation-authorization application on 16 June 2026; ASNR's technical review is suspended until it is provided.
· Published
Published: NRC final rule: Fee Schedules; Fee Recovery for Fiscal Year 2026 (with Executive Order 14300 fixed fee caps) #
NRC fee rule for fiscal year 2026, in force since 17 August 2026. It sets the full-cost review rate at $337 an hour and the reduced rate for advanced reactor applicants at $154, and adds fixed caps on review fees under Executive Order 14300 for applications that end in a final safety evaluation. It licenses no reactor and decides no applicant's eligibility.
· Passed
Passed: Puerto Rico House Bill 1092 (2026): nuclear energy and small modular reactors in the energy policy act #
The House passed the bill in final vote on 15 June 2026, 35 in favor and 11 against. It had its first reading in the Senate and was referred to the Senate Government Committee on 19 June 2026. House passage is not enactment.
· Comment period closed
Comment period closed: Proposed licensing requirements for microreactors and comparable reactors #
NRC proposal published 1 May 2026; the comment period closed on 15 June 2026. It is not in effect.
· Recorded development
Government receives Studsvik's state-support application covering Valdemarsvik and Nyköping #
Announced · Announcement
Oklo announces DOE approval of the Aurora-INL preliminary safety analysis #
Company statement of 11 June 2026. Oklo says DOE's Idaho Operations Office approved the preliminary documented safety analysis for the Aurora powerhouse at Idaho National Laboratory under the Reactor Pilot Program. The DOE approval document was not opened; an NRC audit plan confirms only that Oklo submitted the analysis to DOE. A preliminary safety analysis approval is not authority to load fuel or operate.
· Took effect
Took effect: New York PSC nuclear reliability backbone process #
The order prints Issued and Effective June 11, 2026. Staff's white paper is due within five months. That period is not stored as a calendar day.
Announced or first reported · Agreement or program announced
Natura and Quadrant prospective commercial-reactor HALEU framework #
Natura reported an agreement naming it as a prospective HALEU recipient from Quadrant for its commercial reactor systems. The companies intended to establish a long-term offtake framework. The release does not disclose a Natura allocation, delivery, firm long-term offtake order or MSR-1 fuel assignment. QNI's stated annual production capacity belongs to its planned facility, not to Natura.
· Recorded development
DOE approves the Unity critical experiment documented safety analysis #
DOE's Reactor Pilot Program update of July 2026 lists the Deployable Energy preliminary documented safety analysis as approved on 22 May 2026 and the documented safety analysis as approved on 11 June 2026, before criticality on 30 June 2026. The slides do not reproduce the approval documents. A safety-analysis approval for a zero-power test does not authorize a later power reactor.
· Recorded development
NRC preliminary feedback on its observation of Aurora-INL DOE submittals #
On 5 June 2026 the NRC sent Oklo preliminary feedback from observing DOE authorization submittals, including a preliminary documented safety analysis. The letter says DOE's own determination is independent and that a final audit report will follow. It does not approve the analysis and does not issue a license.
Notice published · Regulatory step
Regulator's Linglong One working group urges pre-fuel-load preparation #
The NNSA working group for the Changjiang demonstration reviewed safety issues found in review and commissioning and urged the operator to push ahead with production-readiness work before fuel loading. Regulatory oversight, not a fuel-load permit.
Checking notes
A notice published on 5 June 2026 by the NNSA's nuclear power safety supervision department reports a recent meeting of the special review and supervision working group for the Hainan Changjiang small modular reactor demonstration. The operating and design organizations reported construction progress and the handling of safety-significant issues found in review and site commissioning. The notice says the demonstration had entered a critical construction period and urged the operating and design organizations to resolve key technical issues and push ahead rigorously with production-readiness work before fuel loading. The meeting is regulatory oversight, not a fuel-load permit.
· Recorded development
Government receives Blykalla's state-support application for Norrsundet #
· First concrete
First concrete poured for Uzbekistan's first RITM-200N unit #
Uzbekistan's atomic energy agency says first concrete was poured into the first SMR unit's foundation on 4 June 2026, after the regulator decided to license its construction. This covers the first SMR unit only; the second unit has no reported construction license.
Checking notes
Uzatom reports that at a ceremony on 4 June 2026 in Farish district, first concrete was poured for the foundation of the first unit with a RITM-200N reactor: 133 cubic metres at the initial stage of more than 10,000. It says the pour gives the plant official under-construction status. The regulator decided the same day to issue the unit's construction license. World Nuclear News dates its report 5 June.
· Construction permission recorded
Construction permission recorded: License for construction of an NPP power unit with a RITM-200N reactor #
Council of the Committee decided 'today' (item dated 2026-06-04) to issue the license for construction of one power unit (singular 'энергоблока'); the Committee's notice states no license number or holder. Uzatom states that the license was issued to the state institution Directorate for the Construction of the Nuclear Power Plant; the license number is not published.
Announced or first reported · Agreement or program announced
DP World, CEA and TerraWater Institute SMR feasibility study for the Port of Constanța #
On 4 June 2026 DP World signed an agreement with France's CEA and TerraWater Institute for a feasibility study on whether SMRs could meet the Port of Constanța's long-term energy needs, modeling demand from 2030 to 2050. Any development would be subject to further technical assessment, regulatory review and stakeholder engagement.
· Took effect
Took effect: Croatia: Law on the Development of Nuclear Energy for Civil Purposes (NN 55/2026) #
Eighth day after publication (Article 15).
· First criticality
Antares Mark-0 zero-power criticality #
Zero-power fueled criticality at INL. Not grid connection.
· Recorded development
SSM opinion on the ReFirm Målma government-approval application #
SSM's 3 June 2026 opinion says the ReFirm Målma AB government-approval application is high-level and that some statements are deficient or incorrect. SSM says no Nuclear Activities Act license application has been filed, and that the government has to decide whether this application level is reasonable. The opinion is not a permit and not a refusal.
· Signed
Signed: Iowa House File 2757: nuclear generation tax treatment and workforce fund #
The governor's letter says House File 2757 is approved on 1 June 2026. No separate effective-date clause was stored.
Announced or first reported · Agreement or program announced
Province of Overijssel SMR siting study (Tractebel) #
A spatial study commissioned by the Province of Overijssel and carried out by Tractebel identified areas potentially suitable for SMRs, finding many possible locations for SMRs up to 100 MW and few for 100-500 MW units. The province stresses that no decision has been taken and no location designated.
· Recorded development
Pele core stacking complete (BWXT) #
Announced or first reported · Agreement or program announced
EDF, Nuward and Edison NUWARD SMR partnership for Italy (second-of-series plant targeted by 2035) #
EDF plans a first series of ten NUWARD SMRs in France, Italy, Poland, Belgium and Finland, with construction from 2030. In September 2026 EDF, Nuward and Edison presented the design with Italian industry, which had signed a declaration of interest in June 2026, and set an objective of a second plant in Italy operating by 2035. No Italian site or order is recorded.
Announced · Announcement
Last Energy states DOE approved a PWR-5 preliminary safety analysis #
Company statement of 28 May 2026. It says DOE approved a preliminary documented safety analysis for the RELLIS pilot, described as scaled for 5 MW electrical. The DOE letter was not opened, so this records the announcement, not a confirmed DOE decision or a completed construction milestone.
Announced · Announcement
Holtec Green River / Blue Castle, Utah proposal documented #
SMR-300 project partnership at Green River, Utah. Separate from Tata / BWXT Green River in Wyoming. No module count or construction start is established.
· Recorded development
Government assigns Gävleborg county administrative board to draft a facility plan for Norrsundet #
· Amended
Amended: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) #
Ceiling raised to EUR 12,600,000, retroactive to 5 January 2026.
· Published
Published: Croatia: Law on the Development of Nuclear Energy for Civil Purposes (NN 55/2026) #
Croatia enacted a civil nuclear-development framework law (NN 55/2026) that explicitly includes small modular reactors among technologies for a future nuclear plant, sets a program path toward at least 30% nuclear in annual electricity by 2040, and leaves site selection and later licensing steps to subsequent instruments. This is national program legislation, not a deployment project.
· Took effect
Took effect: Generic environmental impact statement rule for licensing new nuclear reactors #
Final NRC rule effective 26 May 2026 that lets environmental reviews of new reactor applications rely on generic findings. It is not an environmental decision on any project.
· Application submitted
Application submitted: Swedish Government approval application for a nuclear facility at Studsvik, Nyköping #
Studsvik AB applied on 25 May 2026 for the Government's approval of a nuclear facility for two to four light-water reactors of about 600-1,400 MW in total at Studsvik in Nyköping municipality; on 9 June 2026 the Government assigned the Södermanland county administrative board to draft a facility plan by 31 December 2026. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.
· Published
Published: Idaho PUC Order 37049: Kemmerer Unit 1 solicitation waiver #
The order is done on the 22nd day of May 2026, and the service header is 22 May 2026. The order does not state an effective date. It waives solicitation for the Kemmerer Unit 1 power-purchase agreement. It does not permit the reactor or approve rate recovery.
· Recorded development
DOE approves the Unity critical experiment preliminary documented safety analysis #
· Signed
Signed: Croatia: Law on the Development of Nuclear Energy for Civil Purposes (NN 55/2026) #
Presidential proclamation of the law.
· Amended
Amended: South Korea: Nuclear Safety Act (원자력안전법) #
Partial amendment, Act No. 21679 of 19 May 2026, shown as the current version on the national law portal.
Announced or first reported · Agreement or program announced
Holtec International and Rwanda Atomic Energy Board development agreement for SMR-300 units (up to about 5 GW) #
On 19 May 2026, at the Nuclear Energy Innovation Summit for Africa in Kigali, Holtec International and the Rwanda Atomic Energy Board signed a development agreement to work together to deploy SMR-300 units in Rwanda, with a potential total capacity of up to about 5 GW. No site, first unit, order or license application has been announced, the same occasion saw a separate US-Rwanda civil nuclear cooperation memorandum.
Announced or first reported · Agreement or program announced
Alva and Steady Energy one-year pre-study of nuclear district heating for Jyväskylä #
On 19 May 2026 Alva, Jyväskylä's municipal energy utility, and Steady Energy signed a letter of intent for a year-long pre-study of SMR district heating, covering regulation, locations, zoning, technology and costs. Alva states that it is not making an investment decision at this stage.
· Recorded development
NRC completes acceptance review of the KRONOS construction permit application #
NRC milestone marked actual: docketing decision letter issued and acceptance review complete. This accepts the application for review. It is not a construction permit.
· Environmental decision recorded
Environmental decision recorded: Long Mott environmental assessment, FONSI and review exemptions #
The NRC notice says the Long Mott construction-permit environmental assessment and finding of no significant impact were available on 18 May 2026 and that exemptions permitting this review in place of an environmental impact statement were issued the same day. The construction-permit application remains under review; this decision is not a construction permit or authority to operate.
· Application submitted
Application submitted: Swedish Government approval application for a nuclear facility at Norrsundet, Gävle #
Blykalla AB applied on 18 May 2026 for the Government's approval of a nuclear facility at Norrsundet in Gävle municipality; on 28 May 2026 the Government assigned the Gävleborg county administrative board to draft a facility plan by 31 December 2026. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.
· Took effect
Took effect: NRC final rule: Increased Flexibility in the Mandatory Hearing Process #
NRC rule in force since 15 May 2026 that makes the mandatory hearings held on reactor construction permit applications more flexible, in response to the ADVANCE Act and Executive Order 14300. It removes two environmental-finding provisions for presiding officers and clarifies that other references to hearings mean contested hearings. It licenses no reactor.
· Passed
Passed: Croatia: Law on the Development of Nuclear Energy for Civil Purposes (NN 55/2026) #
Croatia enacted a civil nuclear-development framework law (NN 55/2026) that explicitly includes small modular reactors among technologies for a future nuclear plant, sets a program path toward at least 30% nuclear in annual electricity by 2040, and leaves site selection and later licensing steps to subsequent instruments. This is national program legislation, not a deployment project.
· Selections announced
Selections announced: Gen III+ SMR selections of May 2026: early site permits and supply chain #
DOE selected eight companies on 14 May 2026 for more than $94 million in cost-shared funding, including two early site permit efforts whose sites the announcement does not name.
· Selections announced
Selections announced: DOE Generation III+ Small Modular Reactor program #
Eight further selections totalling more than $94 million.
· Issued
Issued: Sweden: Act on Government Approval of Nuclear Facilities (SFS 2026:585) #
Utfärdad 2026-05-13.
Announced or first reported · Agreement or program announced
FANCO–AtkinsRéalis EAGL-1 engineering alliance #
AtkinsRéalis announced a 20-year North American EPCM alliance for FANCO's EAGL-1 projects, with initial task orders covering design procedures, balance-of-plant conceptual design and nuclear steam supply system review. The framework supports US deployment aims, while its regional scope establishes no Canadian or Mexican deployment. It commits no reactor order, selected site, plant construction contract or permission.
· Recorded development
Studsvik completes its acquisition of Kärnfull Next #
Announced or first reported · Agreement or program announced
Nebraska Public Power District Gen III+ SMR early site permit program (DOE cost-shared) #
DOE awarded the Nebraska Public Power District about $27.9 million under its Gen III+ SMR program to obtain an NRC early site permit for a Nebraska location to support future Gen III+ SMR deployment. NPPD has narrowed 16 candidate communities to four finalists and formed a consortium with other public power utilities, no site, technology or application has been fixed, and NPPD says a larger reactor remains possible.
Notice published · Published
MARAD seeks information about a marine SMR concept #
The agency requested public information on a U.S.-built marine SMR concept and its deployment framework. A request for information, not a vessel award, license or deployment.
Checking notes
Publication of the instrument described here. Later final disposition not established.
· Recorded development
Government assigns Östergötland county administrative board to draft a facility plan for Målma #
Announced or first reported · Agreement or program announced
Terrestrial Energy and Riot Platforms memorandum on IMSR plants for data centers (up to 4 GW, 2026) #
On 6 May 2026 Terrestrial Energy and Riot Platforms announced a memorandum to pair future Riot data centers with multiple 390 MW IMSR plants totalling up to 4 GW, assessing sites including Riot's existing Texas and Kentucky facilities. It is a framework to evaluate sites, no site, order or license is recorded.
Announced or first reported · Agreement or program announced
Kenya first nuclear power plant program (NuPEA, SMR option under evaluation, Siaya County preferred area) #
Kenya's Nuclear Power and Energy Agency is preparing the country's first nuclear power plant in Siaya County, with KenGen designated owner-operator and a groundbreaking targeted for 2027. Nuclear Engineering International reports that NuPEA has shifted its focus toward multi-module SMRs and received proposals including a Rolls-Royce two-unit offer, but no technology, vendor or contract has been selected and reported capacities differ between sources.
· Proposed
Proposed: Proposed licensing requirements for microreactors and comparable reactors #
NRC proposal published 1 May 2026; the comment period closed on 15 June 2026. It is not in effect.
Announced · Recorded development
RoPower reports non-binding US EXIM and DFC financing interest for Doicești #
RoPower said EXIM was analyzing instruments of about USD 5.6 billion and DFC had issued a letter of intent for up to USD 2 billion. Both are indicative and conditional on due diligence and approvals. Letters of interest are not financing commitments.
Checking notes
RoPower Nuclear reported that US EXIM had expressed support in principle and was analyzing financing instruments of about USD 5.6 billion, and that DFC had issued a letter of intent for loan and equity financing of up to USD 2 billion, capped at 25% of investment cost. Both letters are indicative and non-binding.
· Recorded development
First RITM-200S reactor for the first PEB-106 floating unit manufactured #
Announced or first reported · Agreement or program announced
LG&E and KU (PPL) and X-energy collaboration to explore Xe-100 SMR deployment in Kentucky #
PPL's utilities LG&E and KU and X-energy announced in April 2026 that they are collaborating to explore deploying Xe-100 SMRs in Kentucky and have begun early project feasibility activities. This follows PPL's 2024 GAIN-funded feasibility work with X-energy, after an earlier study found the Ghent site suitable for an SMR plant. No site has been chosen and no order or license application is recorded.
· Recorded development
DOE approves the Aalo-X documented safety analysis #
DOE's Reactor Pilot Program update of July 2026 lists the Aalo preliminary documented safety analysis as approved on 3 March 2026 and the documented safety analysis as approved on 30 April 2026, before zero-power criticality on 4 July 2026. The slides do not reproduce the approval documents. A safety-analysis approval for a zero-power test does not authorize a later power reactor.
· Took effect
Took effect: NRC final rule: Categorical Exclusions From Environmental Review #
NRC rule in force since 29 April 2026 that revises the list of NRC actions excluded from environmental assessment because they normally have no significant environmental effect. The NRC says it changes no requirements for applicants or licensees and left broader exclusions for new reactors outside its scope. It approves no reactor or site.
· Took effect
Took effect: 10 CFR Part 53: risk-informed, technology-inclusive licensing framework #
The NRC's Part 53 licensing framework took effect on 29 April 2026. It sets how applications may be reviewed; it approves no design, site or reactor.
· Recorded development
NRC gives notice it will prepare an environmental impact statement for the Belews Creek early site permit #
Published 27 April 2026 at 91 FR 22549: the NRC will prepare an environmental impact statement for the early site permit application and opened a 30-day scoping period, with the U.S. Army Corps of Engineers as a cooperating agency.
· Published
Published: Generic environmental impact statement rule for licensing new nuclear reactors #
Final NRC rule effective 26 May 2026 that lets environmental reviews of new reactor applications rely on generic findings. It is not an environmental decision on any project.
· Recorded development
DOE approves the Ward 250 documented safety analysis #
DOE's Reactor Pilot Program update of July 2026 lists the Valar Atomics preliminary documented safety analysis as approved in February 2026 and the documented safety analysis as approved on 23 April 2026, before zero-power criticality on 18 June 2026. The slides do not reproduce the approval documents.
· Recorded development
Stellaria and CEA sign letter of intent on INB Alpha feasibility at Cadarache #
· Construction start
TerraPower announces the official start of construction at Kemmerer Unit 1 #
TerraPower announced on 23 April 2026 the official start of construction on Natrium Kemmerer Unit 1. The same release says TerraPower broke ground in June 2024 and began construction on non-nuclear support facilities. It does not say that safety-related or nuclear-island work began on 23 April 2026, and a senator quoted in it refers to construction on the energy island. This is a company announcement, not an NRC record of first safety-related concrete. An NRC inspection report dated 22 April 2026, the day before, on an inspection held on 23 to 26 March, says in passing that construction of the unit has not started. Stored electrical and thermal ratings are not changed.
· Environmental decision recorded
Environmental decision recorded: DOE categorical exclusion CX-271015 for the Ward250 research reactor #
Signed 22 April 2026 under NEPA identification DOE-ID-26-005. Determines that the 250 kWth Ward250 research reactor at USREL fits a categorical exclusion. It states no authorization number and no electrical output, and it does not confirm the company's later electricity claim.
Announced · Announcement
Radiant Kaleidos Buckley Space Force Base proposal documented #
Company reports Air Force / DIU selection for Buckley. Delivery by 2028 is a target. Separate from the INL demonstration and the unnamed fifteen-base Army fleet.
· Construction start
IAEA PRIS records construction start for Darlington SMR1 #
PRIS records physical construction start of Darlington SMR1 on 22 April 2026. This is distinct from the CNSC license to construct in April 2025 and from the pending operating-license application.
· Amended
Amended: Uzbekistan: Law No. ZRU-565 on the Use of Atomic Energy for Peaceful Purposes (2019) #
Law No. ZRU-1140; in force on official publication.
· Groundbreaking
Hermes 2 groundbreaking #
Groundbreaking reported for Hermes 2.
· Published
Published: NRC final rule: Increased Flexibility in the Mandatory Hearing Process #
NRC rule in force since 15 May 2026 that makes the mandatory hearings held on reactor construction permit applications more flexible, in response to the ADVANCE Act and Executive Order 14300. It removes two environmental-finding provisions for presiding officers and clarifies that other references to hearings mean contested hearings. It licenses no reactor.
· Environmental decision recorded
Environmental decision recorded: DOE Idaho categorical exclusion CX-271007 for the Unity zero-power test #
Approved 15 April 2026 under posting DOE-ID-INL-26-011. Covers a zero-power criticality test bounded at 0 MWth and 0 kWe. It does not authorize the future 1 MWe configuration and is not an operating license.
Announced or first reported · Agreement or program announced
Natura and HiFunda molten-salt chemistry sensor development #
Natura announced an agreement with HiFunda to develop an electrochemical molten-salt chemistry sensor. The release describes development work, not evidence that a complete nuclear-grade sensor had been qualified or installed in an operating reactor. HiFunda's reported prior component work does not establish completion of the whole instrument.
· Environmental decision recorded
Environmental decision recorded: DOE Idaho categorical exclusion CX-271002 for the Aalo-X critical assembly #
Approved 14 April 2026 under posting DOE-ID-INL-26-013. Covers installation and zero-power operation of the critical assembly at no more than 10 watts thermal. It is an environmental categorical exclusion, not a construction permit or operating license, and it does not authorize a later power reactor.
· Awarded
Awarded: United Kingdom: GBE-N selection of, and contract with, Rolls-Royce SMR #
Date GBE-N published the news that the contract had been signed; the selection-process page gives April 2026.
· Contract
Wylfa program design contract signed #
Contract initiates site-specific design and planning before a future investment decision.
· Recorded development
DOME test bed complete; Radiant begins its test campaign #
DOE reported on 8 April 2026 that construction of the DOME test bed was complete and that Radiant had started its scheduled year-long test campaign of the Kaleidos unit. Initial startup of the reactor was anticipated in the summer, which is a plan and not a recorded startup.
· Signed
Signed: New Jersey P.L. 2026, chapter 9: nuclear facility permit finding #
The official chapter page says Approved April 8, 2026.
· Took effect
Took effect: New Jersey P.L. 2026, chapter 9: nuclear facility permit finding #
Section 2 says the act takes effect immediately.
· Signed
Signed: Kentucky KRS 278.615: nuclear permit and license cost recovery #
The session-law PDF prints Signed by Governor April 8, 2026. It does not print the 15 July 2026 effective line. That date remains the compiled section.
· Signed
Signed: Kentucky KRS 164.2805: Nuclear Reactor Site Readiness Pilot Program #
The session-law PDF prints Signed by Governor April 8, 2026. It does not print the 15 July 2026 effective line. That date remains the compiled section.
· Signed
Signed: Kentucky KRS 164.2803: nuclear energy development grant cap #
The session-law PDF prints Signed by Governor April 8, 2026. It does not print an effective date for section 5. No award is named.
Announced or first reported · Agreement or program announced
ARC Clean Technology and IC Nuclear & Industry term sheet for ARC-100 deployment in Türkiye #
On 7 April 2026 ARC Clean Technology announced a term sheet with IC Nuclear & Industry, part of Türkiye's IC Holding, setting a commercial framework for deploying and developing the ARC-100 in Türkiye and the region. It covers joint technical, economic and regulatory feasibility studies, and the parties intend to negotiate definitive agreements on technology licensing, engineering and project implementation. No site, number of units, schedule or license application is named.
· Milestone
Milestone: United Kingdom: Great British Energy – Nuclear small modular reactor program and technology selection #
GBE-N and Rolls-Royce SMR entered into contract, concluding the technology selection process.
Announced or first reported · Agreement or program announced
US-funded phase-one FEED study for SMR pre-construction activities in Hungary #
The US Chargé d'Affaires in Budapest said Hungary was selected for a US-funded phase-one front-end engineering and design (FEED) study for SMR pre-construction activities, World Nuclear Association dates the US announcement to April 2026. No site, owner or design is named.
Announced or first reported · Agreement or program announced
Norwegian Nuclear Commission report (NOU 2026:4): prepare for possible future nuclear power but start no process now… #
The Norwegian Nuclear Commission, appointed in June 2024, submitted its report (NOU 2026:4) in April 2026 recommending that the government not start a nuclear power development process now but prepare for possible future use, including a national competence project. Ten notifications of proposed plants have been filed, apart from the Taftøy plan of several SMRs, which already has an assessment program, the government awaited the commission before acting on them. The report went to consultation until 8 October 2026.
Announced or first reported · Agreement or program announced
Indiana Office of Energy Development and Eli Lilly letter of intent on SMR and advanced nuclear projects #
Indiana Governor Mike Braun signed a nonbinding letter of intent under which the state's Office of Energy Development and Eli Lilly will collaborate to explore small modular reactor and other advanced nuclear projects for industrial, research and community power, including screening of the LEAP Research and Innovation District. It names no vendor, site or capacity and is not an order or permit.
Announced or first reported · Agreement or program announced
FPL plan to begin early site permitting for a potential SMR next to an existing nuclear plant (Florida) #
FPL's 2026-2035 Ten Year Site Plan says the utility plans to begin the initial stages of NRC early site permitting in 2026-2027 for a potential SMR at a site adjacent to one of its existing nuclear plants, taking a stepwise approach. No site, technology, application or in-service date within the plan period is stated.
· Recorded development
Basemat module lifted into the Darlington BWRX-300 reactor building shaft #
In April 2026 the basemat module, the roughly 953-tonne foundation of the reactor building, was lifted into the excavated reactor building shaft 35 metres below ground. A construction milestone reported by trade press, not a regulatory approval.
Checking notes
World Nuclear News reports that in April 2026 the basemat module, the foundation of the reactor building weighing nearly 953 tonnes, was lifted into the newly excavated reactor building shaft 35 metres below ground. The CNSC had removed the hold point for the reactor building foundation on 30 March 2026.
Announced or first reported · Agreement or program announced
DOE / NRIC Nuclear Energy Launch Pad (reactor and fuel-cycle developer selections) #
The Nuclear Energy Launch Pad, run by DOE's Office of Nuclear Energy and the National Reactor Innovation Center, emerged from the Reactor Pilot and Fuel Line Pilot programs and offers selected developers a prioritized path to DOE authorization, testing and deployment support. First selections in April 2026 named Deployable Energy, General Matter, NuCube Energy and Radiant, a second round in August 2026 selected 13 projects from 12 companies including Antares, Oklo, Valar Atomics, Forge Atomics and Scaled Atomics. Selections do not identify new plants or sites.
Announced or first reported · Agreement or program announced
Canada's National Defence and AECL joint feasibility program on Canadian-controlled microreactors for the North (2026) #
In April 2026 Canada's energy minister announced a joint feasibility program with the Department of National Defence and Atomic Energy of Canada Limited to assess Canadian-controlled microreactor technology for the North, with DND investing over CAD40 million that fiscal year. The June 2026 national strategy sets an objective to demonstrate a Canadian-controlled Generation IV microreactor by 2035 to support defense facilities. No design, vendor or site has been named.
· Recorded development
DOE approves the Antares Mark-0 documented safety analysis #
DOE's Reactor Pilot Program update of July 2026 lists the Antares preliminary documented safety analysis as approved in January 2026 and the documented safety analysis as approved in April 2026, before zero-power criticality on 4 June 2026. The update gives months, not days. The slides do not reproduce the approval documents. A safety-analysis approval for a zero-power test does not authorize a later power reactor.
· Application submitted
Application submitted: NRC construction permit application for the University of Illinois KRONOS MMR #
The university applied for a construction permit for one research reactor by letter dated 27 March 2026; the NRC records it as tendered on 31 March 2026, accepted it for docketing on 18 May 2026 as Docket No. 50-618 and published the hearing opportunity on 26 May 2026. The stated application power level is 45 MWth. No permit has been issued; target review dates in 2027 are not decisions.
· Design assessment: Review completed (not an approval)
Design assessment: Review completed (not an approval): Holtec SMR-300 UK Generic Design Assessment (two steps) #
Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in January 2023, according to the Environment Agency's Step 1 summary; it was renamed SMR-300 in January 2024. The UK regulators began a two-step Generic Design Assessment of Holtec's SMR-300 on 18 October 2023 at the government's request. Step 1 ran from October 2023 to August 2024 and Step 2 from August 2024 to March 2026. The Environment Agency records completing Step 2 on 31 March 2026, and ONR's page records the assessment as completed that month with no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
· Published
Published: NRC final rule: Categorical Exclusions From Environmental Review #
NRC rule in force since 29 April 2026 that revises the list of NRC actions excluded from environmental assessment because they normally have no significant environmental effect. The NRC says it changes no requirements for applicants or licensees and left broader exclusions for new reactors outside its scope. It approves no reactor or site.
· Construction permission recorded
Construction permission recorded: CNSC consent to remove Regulatory Hold Point 1 (reactor building foundation) #
Submitted date is OPG's request letter of 25 March 2026 cited as reference [1] in the CNSC letter.
· Published
Published: 10 CFR Part 53: risk-informed, technology-inclusive licensing framework #
The NRC's Part 53 licensing framework took effect on 29 April 2026. It sets how applications may be reviewed; it approves no design, site or reactor.
Filed · Regulatory step
Cascade licensing plan updated with a two-part permit application #
Energy Northwest New Nuclear updated its NRC engagement plan in March 2026. It plans to file its construction permit application in two parts. The filing dates are withheld and no application has been submitted.
Checking notes
Energy Northwest New Nuclear sent the NRC Revision 3 of its regulatory engagement plan, which plans a construction permit application in two parts, the first supporting early environmental review. The planned dates are withheld.
· Amended
Amended: Canada: Clean technology investment tax credit for small nuclear energy property (Income Tax Act s. 127.45) #
Royal Assent to S.C. 2026, c. 3; s. 52(1) repealed the small modular nuclear reactor definition and s. 52(3) replaced subparagraphs (d)(i) to (vii) of the clean technology property definition.
· Amended
Amended: Canada: Building Canada Act (S.C. 2025, c. 2, s. 4), national interest projects #
Last amendment shown in the consolidation; not reviewed separately.
· Recorded development
GBE-N and Anglesey council sign a Collaboration Agreement for Wylfa #
The agreement sets out how Great British Energy - Nuclear and Isle of Anglesey County Council will work together to support delivery of SMRs at Wylfa. A working agreement with the local authority, not planning consent or a site license.
Checking notes
Great British Energy - Nuclear and Isle of Anglesey County Council signed a Collaboration Agreement setting out how they will work together to support delivery of SMRs at Wylfa, under general principles covering matters including accountability, communication and sustainable development.
· Application submitted
Application submitted: OPG license to operate application #
20-year operating license application for one BWRX-300 and waste structure.
· Application submitted
Request to remove Darlington Regulatory Hold Point 1 #
The recorded application date for removal of Darlington Regulatory Hold Point 1 is 25 Mar 2026. The application itself is not an issued permission.
Later decision: 30 Mar 2026. Details are in Checking notes.
Checking notes
Submitted date is OPG's request letter of 25 March 2026 cited as reference [1] in the CNSC letter.
· Recorded development
Concrete works begin on foundation preparation for the small (RITM-200N) unit, same day as supplementary agreement #
Levelling/waterproofing/earthing works (~900 m3 of concrete); not first nuclear (safety-related) concrete.
· Site permission recorded
Site permission recorded: Permit to use the site for nuclear installations (Farish district NPP site) #
Regulator's own news item dated 4 June 2026 states the permit was issued on 23 March 'of the current year'. The notice reports permission to use the site designated for nuclear installations for NPP construction. It does not give a permit number.
· Application submitted
Application submitted: Swedish Government approval application for a nuclear facility at Målma, Valdemarsvik #
Refirm Målma AB applied on 23 March 2026 for the Government's approval of a nuclear facility at Målma in Valdemarsvik municipality, the first application under the new law; on 7 May 2026 the Government assigned the Östergötland county administrative board to draft a facility plan. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.
Announced or first reported · Agreement or program announced
US–Japan strategic investment in GE Vernova Hitachi BWRX-300 SMRs in Tennessee and Alabama (up to $40 billion) #
The US Department of Commerce announced in March 2026, under the US–Japan strategic investment initiative, a deal of up to $40 billion for GE Vernova Hitachi BWRX-300 SMRs totalling 3 GW in Tennessee and Alabama. No sites were identified, in August 2026 TVA said it was in discussions with GE Vernova Hitachi about placing multiple BWRX-300 units at its Bellefonte site but had made no decision. It is not an order, site selection or license application.
Announced or first reported · Agreement or program announced
X-energy and Talen Energy letter of intent to assess three or more four-unit Xe-100 plants (Pennsylvania and PJM) #
X-energy and independent power producer Talen Energy signed a letter of intent in March 2026 to assess deploying three or more four-unit Xe-100 SMR plants in Pennsylvania and across the PJM market, including possible conversion of fossil-fired sites. Planned work is early-stage (feasibility studies and site evaluations), no site, order or license application exists.
· Took effect
Took effect: TANEO grant rules (10 TAC chapter 331) #
TANEO's grant rules took effect on 19 March 2026 after a January proposal. They set how grants are applied for and decided; they award nothing themselves.
Announced · Announcement
Blykalla SEALER Norrsundet / Gävle proposal documented #
March 2026 planning release describes six units and about 300 MW; the same page describes a 55 MWe design. A later application may revise the configuration. Capacity stays unknown pending reconciliation; this is distinct from Untra.
Announced or first reported · Agreement or program announced
Vietnam atomic energy strategy (Decision 438/QD-TTg, 2026): at least one SMR project by 2035, 10-15 SMRs by 2050 #
On 16 March 2026 Vietnam approved its atomic energy strategy to 2035 with a vision to 2050, aiming to complete Ninh Thuan 1 and 2 and to deploy at least one SMR power plant project by 2035, and about 10-15 small modular reactors by 2050. The strategy names no SMR site, developer or design.
Notice published · Regulatory step
China's regulator names key Linglong One review issues #
An NNSA supervision activity named main-pump nozzle safety and once-through steam generator flow stability among key difficult issues in the Hainan small reactor's construction and commissioning. Regulatory oversight, not a license decision.
Checking notes
A notice published on 16 March 2026 by the Ministry of Ecology and Environment's nuclear power safety supervision department (NNSA) reports a recent supervision activity on the China-Russia cooperation projects and the Hainan small reactor, which studied key problems constraining the projects' entry into operation. For the Hainan small reactor it names main-pump nozzle safety and once-through steam generator flow stability among the key difficult issues in construction and commissioning. The activity is regulatory oversight, not a license decision.
· Published
Published: United Kingdom: Building our nuclear nation, government response to the Nuclear Regulatory Review 2025 #
UK government response, published 13 March 2026, accepting the Nuclear Regulatory Taskforce's 47 recommendations. It commits to give the Office for Nuclear Regulation a growth objective, merge it with the defense nuclear regulator, make it the lead regulator for projects involving several regulators and put the reforms, with any legislation, in place by the end of 2027. It approves no project.
· Published
Published: TANEO grant rules (10 TAC chapter 331) #
Adoption notice; section 331.32 adopted with changes.
· Recorded development
INL reports DOE approval of MARVEL's preliminary documented safety analysis #
INL's release of 11 March 2026 says DOE's Idaho Operations Office has approved MARVEL's preliminary documented safety analysis for a dry initial-criticality configuration. The date shown is the release date, a report date; the release gives no approval date, and the DOE approval document was not opened. The release does not report startup or criticality.
· Enacted
Enacted: South Korea: Special Act on the Promotion of and Support for Small Modular Reactor Development (소형모듈원자로 개발 촉진 및 지원에 관한 특별법) #
Enactment, Act No. 21422 of 10 March 2026 (promulgation date shown on the national law portal).
Announced or first reported · Agreement or program announced
El Salvador nuclear power program with early SMR evaluation (OIPEN, US DOE memorandum, 2026) #
El Salvador's long-term energy planning envisages nuclear power supplying about 15% of electricity by 2050, potentially through small modular reactors, and an IAEA INIR mission in 2026 noted the country's early evaluation of SMR technologies. The program, run by OIPEN, began with a 2023 memorandum with the Thorium Energy Alliance, in March 2026 El Salvador signed a memorandum with the US Department of Energy's Office of Nuclear Energy. No design, vendor or site has been selected.
· Construction permission recorded
Construction permission recorded: TerraPower Natrium construction permit #
The NRC issued construction permit CPAR-1 on 9 March 2026 to US SFR Owner, LLC (TerraPower) for Kemmerer Power Station Unit 1, after the Commission's 4 March 2026 decision on the uncontested hearing. The permit authorizes construction only; an operating license is a separate NRC decision.
· Took effect
Took effect: Uzbekistan: Requirements for the site and territory of a nuclear power plant (Committee resolution No. 39, 2026) #
Uzbekistan's nuclear safety committee set binding site requirements for nuclear power plants in force from 7 March 2026: a plant may not be sited where there are active faults, high groundwater, seismicity above 8 points (MSK-64), sulfate or salt karst, or a nature-protection ban. The rules name no site and are not a site permit.
Announced or first reported · Agreement or program announced
KAERI and Korea Chemical Industry Association memorandum on HTGRs for petrochemicals (2026) #
In March 2026 KAERI and the Korea Chemical Industry Association agreed to cooperate on studying high-temperature gas-cooled reactors as a carbon-free heat source for the petrochemical industry. The memorandum covers technology cooperation and commercialisation opportunities only. No design, site or plant is named.
· Recorded development
NRC mandatory hearing on Kemmerer Unit 1 construction permit #
Announced or first reported · Agreement or program announced
Holtec SMR-300 early regulatory dialogue with Sweden (ENSREG SMR dashboard) #
The ENSREG SMR Task Force dashboard dated 3 March 2026 lists Holtec's SMR-300 in early dialogue with the Swedish regulator, with electricity production as the target market. No Swedish host, utility or site is named.
Announced or first reported · Agreement or program announced
Copenhagen Atomics thorium molten-salt reactor early regulatory dialogue with Sweden (ENSREG SMR dashboard) #
The ENSREG SMR Task Force dashboard of 3 March 2026 lists Copenhagen Atomics' 100 MWth thorium molten-salt reactor, aimed at industrial customers such as aluminium, ammonia or hydrogen plants, in early dialogue with the Swedish regulator. No host or site is named.
· Recorded development
DOE approves the Aalo-X preliminary documented safety analysis #
Announced or first reported · Agreement or program announced
Singapore EMA and KHNP memorandum on joint SMR studies (2026) #
On 1 March 2026 Singapore's Energy Market Authority and KHNP signed a memorandum on civil nuclear cooperation focused on joint studies of SMRs for potential use in Singapore, plus training and information sharing. It is a study framework, Singapore has not decided to deploy nuclear energy.
Announced or first reported · Agreement or program announced
Greece's Inter-Ministerial Committee to examine small modular reactors (2026) #
Greek Prime Minister Kyriakos Mitsotakis announced in March 2026 that Greece would examine the potential role of SMRs, and by August 2026 the Council of Ministers had set up an Inter-Ministerial Committee to do so. He said its brief is scientific investigation and a defined framework, not the construction of nuclear plants. No site, design or decision to build exists.
· Recorded development
BARC Visakhapatnam hydrogen reactor: siting consent and environmental terms of reference reported #
DAE's written answers state siting consent received and environmental-clearance terms of reference issued; the consent's date and issuing body are not stated.
Announced · Announcement
Yakutia: Units 1 and 2 siting-material hearings reported #
Atomnaya energiya reports that public hearings on siting-license supporting materials for Units 1 and 2 took place on 26 February 2026. The event date here is the report publication. A hearing is not a siting or construction license. The linked operator original was inaccessible on this review.
Announced or first reported · Agreement or program announced
NANO Nuclear Energy and EHC Investment memorandum on KRONOS MMR deployment in the UAE #
On 24 February 2026 NANO Nuclear Energy signed a memorandum with Abu Dhabi holding company EHC Investment to explore a joint venture for deploying micro modular reactors, notably KRONOS MMR, in the UAE and the wider Gulf. A formal joint venture is anticipated only after securing a first commercial project or order.
Announced or first reported · Agreement or program announced
Colombia Ministry of Mines and Energy and IAEA memorandum covering nuclear planning and small modular reactors… #
On 24 February 2026 in Cartagena, Colombia's Ministry of Mines and Energy and the IAEA signed a non-binding memorandum of understanding establishing technical cooperation on energy planning, nuclear infrastructure development and small modular reactors, to evaluate nuclear power as an option. It creates no financial obligations and names no project.
· Signed
Signed: Illinois Executive Order 2026-01: nuclear notice of inquiry #
The order is dated 18 February 2026 and requests a notice of inquiry within 60 days. That period is not stored as a calendar day.
· Issued
Issued: Uzbekistan: Requirements for the site and territory of a nuclear power plant (Committee resolution No. 39, 2026) #
Resolution No. 39; registered by the Ministry of Justice on 6 March 2026 (No. 3785).
Announced or first reported · Agreement or program announced
Meralco PowerGen SMR feasibility study funded by USTDA (Meralco NEST program) #
In February 2026 USTDA funded Meralco PowerGen to evaluate US SMR designs, identify preferred technology and sites, and develop an implementation roadmap for the Philippines' first SMR plant, under Meralco's Nuclear Energy Strategic Transition (NEST) program. Meralco and MGEN chose Sargent & Lundy with AMH Philippines in September 2026 to run the study, due by late 2027. No design, site or decision to build exists, three possible proof-of-concept sites were reported in 2024.
· Recorded development
Operation Windlord: Ward 250 modules airlifted by C-17 to Hill AFB, then trucked to Emery County #
· Regulatory step
NRC finds Part 1 of the Pioneer phased CP application (with LWA request) acceptable for docketing #
· Final investment decision
Doicești conditional shareholder investment decision #
Shareholder approval was subject to conditions; not a construction start.
· Milestone
Milestone: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) #
Application window closed.
Announced · Announcement
Taftøy Aure / Heim SMR proposal documented #
Government approved the impact assessment program in February 2026. This is not a construction permit or final policy decision. Technology and unit configuration remain unselected.
Announced · Announcement
Radiant announces DOE approval of the Kaleidos authorization request (DARK) #
Company statement of 9 February 2026. Radiant says DOE granted approval of its DOE Authorization Request for Kaleidos (DARK), designed to meet the intent of a preliminary documented safety analysis, and calls it the second of three safety document submittals in DOE's authorization pathway. Radiant says it is now preparing the final documented safety analysis submittal and readiness review, leading to authorization and startup at INL that summer. This is Radiant's account; the DOE approval document was not opened. No startup or criticality is recorded.
· Recorded development
Federal Register notice: NRC has accepted and docketed the Belews Creek early site permit application #
Published 9 February 2026 at 91 FR 5787: NRC staff accepted and docketed Duke Energy Carolinas' early site permit application under Docket No. 52-055. Hearing requests were due by 10 April 2026. A later NRC notice dates the acceptance letter 8 February 2026. Acceptance for docketing starts the detailed review. It is not a permit.
Announced or first reported · Agreement or program announced
UK Advanced Nuclear Framework and pipeline for private advanced, small and micro modular reactor projects (2026) #
The UK Department for Energy Security and Net Zero published the Advanced Nuclear Framework on 4 February 2026 to support private advanced, small and micro modular reactor projects, opening a pipeline that developers could apply to join from March 2026. Successful projects receive in-principle government endorsement after assessment by government and GBE-N and are expected to be privately financed. Endorsement is not a planning consent, license or funding award.
Announced · Announcement
Tarapur SMR-55 lead proposal documented #
DAE's SMR-55 lead proposal at Tarapur is separate in capacity and stage from the BSMR-200 proposal and the operating conventional units.
Announced · Announcement
Tarapur BSMR-200 lead proposal documented #
DAE names Tarapur for a 220 MWe BSMR-200 lead unit. Product name does not imply 200 MWe. This is separate from existing Tarapur BWR and PHWR plants.
Announced · Announcement
BARC Visakhapatnam HTGCR hydrogen demonstration proposal documented #
DAE names BARC Vizag for an up-to-5 MWth hydrogen reactor. Thermal demonstration capacity is not electrical output or commercial operation.
Announced or first reported · Agreement or program announced
Natura Resources and NGL Water Solutions Permian agreement on MSR-100 power and produced-water treatment (Texas) #
Natura Resources signed an agreement with NGL Water Solutions Permian, a subsidiary of NGL Energy Partners, to pursue opportunities to combine Natura's 100-megawatt molten salt reactor with thermal desalination for power production and oil and gas produced-water treatment in the Permian Basin. It is an agreement to seek and evaluate opportunities, not an order, site selection or permit.
· Recorded development
Daegu Gunwi: first-unit bid lapses after KHNP's coastal-site requirement #
Daegu said its plan to host the first SMR unit fell through because KHNP's site call required coastal sites; it will pursue a later unit.
Announced or first reported · Agreement or program announced
Wisconsin PSC and UW-Madison nuclear power siting study (2025 Wisconsin Act 12) #
Under 2025 Wisconsin Act 12, the Public Service Commission of Wisconsin and UW-Madison's nuclear engineering department are carrying out a state nuclear power siting study, announced in February 2026 and due by the start of 2027. Its scope covers traditional nuclear, small modular reactors and advanced technologies including fusion, it identifies siting opportunities but proposes no plant.
· Recorded development
DOE approves the Ward 250 preliminary documented safety analysis #
Announced or first reported · Agreement or program announced
SGE, Altra and GE Vernova Hitachi memorandum to assess BWRX-300 deployment in Lithuania #
SGE, Lithuania's Altra and GE Vernova Hitachi signed a memorandum (reported 27 February 2026) setting a framework for a technical and economic assessment of possible BWRX-300 deployment in Lithuania. It is an assessment agreement, with no site or order.
Announced or first reported · Agreement or program announced
Korea's NSSC SMR regulatory roadmap and pre-review system (companies signal intent, 2026) #
South Korea's nuclear regulator announced an SMR regulatory roadmap in February 2026 and a pre-review system starting in November 2026 that examines parts of a design before formal licensing. In July 2026 it said about three domestic and foreign companies had signalled intent to apply, reportedly including TerraPower and Saltfoss Energy. No application, project or site exists yet.
Announced or first reported · Agreement or program announced
France's third Multiannual Energy Programme (PPE3): first small reactor targeted around the early 2030s (2026) #
France's government published its third Multiannual Energy Programme (PPE3) for 2026-2035 in February 2026. Alongside six EPR2 reactors and reactor life extensions, it backs small modular reactors with the objective of a first reactor at the start of the 2030s. The PPE is a policy trajectory, not legislation, and names no SMR design or site.
· Introduced
Introduced: Puerto Rico House Bill 1092 (2026): nuclear energy and small modular reactors in the energy policy act #
Filed on 29 January 2026. It was first read and referred to the House Government Committee on 2 February 2026, then on 5 February 2026 to the House Economic Development Committee, which reported it with amendments in June 2026. The filed text is not the text the House passed.
· Environmental decision recorded
Environmental decision recorded: DOE Idaho categorical exclusion CX-035340 for the Antares Mark-0 experiment #
Approved 26 January 2026 under posting DOE-ID-INL-25-037. Covers the zero-power Mark-0 heat-pipe experiment in MFC-793. No measurable thermal output is claimed. This is not an operating license, and it does not approve the later Mark-1 reactor.
· Recorded development
ANSN meets IEN and Terminus on licensing the critical unit #
ANSN reports meeting IEN/CNEN and the designer Terminus on 21 January 2026 on the next licensing steps. Its preliminary evaluation of the site report found points to improve. It states no permission.
· Signed
Signed: New Jersey Executive Order No. 2: Nuclear Power Task Force #
The order says it is given the 20th day of January, Two Thousand and Twenty-Six, and that it takes effect immediately.
· Took effect
Took effect: China: Atomic Energy Law of the People's Republic of China (2025) #
Article 62.
Announced or first reported · Agreement or program announced
Brazil federal technical group on land-based small and micro modular reactors (CDPNB Resolution 43, January 2026) #
Resolution CDPNB 43, dated 6 January 2026 and published on 7 January, established a technical group coordinated by Brazil's Ministry of Mines and Energy to assess infrastructure and challenges for land-based small and micro modular reactors. Its technical document is due within 180 days of publication of the member-designation act, extendable once by up to 90 days. An MME notice republished by IPEN in April 2026 reported the group's installation, but its weekday/date conflict leaves the meeting day unresolved. This is a study, not a decision to build.
· Opened
Opened: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) #
Application window 05-01-2026 t/m 12-02-2026.
· Signed
Signed: Iowa Executive Order 17: Nuclear Energy Task Force #
Signature block: the fifth day of January 2026. The order says it applies prospectively as of its effective date and does not say that day is the signature day.
· Proposed
Proposed: TANEO grant rules (10 TAC chapter 331) #
TANEO's grant rules took effect on 19 March 2026 after a January proposal. They set how grants are applied for and decided; they award nothing themselves.
· Provision took effect
Provision took effect: South Korea: Act on Physical Protection and Radiological Emergency (원자력시설 등의 방호 및 방사능 방재 대책법), emergency planning zones #
Current version, Act No. 20720 of 21 January 2025, in force 1 January 2026.
· Recorded development
SINAP small modular thorium molten-salt research reactor: siting-stage assessment resubmitted #
January 2026 resubmission of the siting-stage environmental impact report (30 MWt, 10 MWe), posted by the ecology ministry on 12 March 2026.
Announced or first reported · Agreement or program announced
NextEra Energy evaluation of 6 GW of SMR capacity at its nuclear sites and new sites (2026) #
NextEra Energy's chief executive told investors in January 2026 that the company is evaluating SMR vendors and sees 6 GW of SMR co-location opportunities at its nuclear sites, mainly to serve data centers, while also developing greenfield sites. Any new build would depend on commercial terms and risk-sharing. No vendor, site or project has been selected.
Announced or first reported · Agreement or program announced
NANO Nuclear Energy and DS Danseok memorandum on introducing micro modular reactors in South Korea (2026) #
DS Danseok, a South Korean resource-recycling energy company, announced in January 2026 a memorandum with NANO Nuclear Energy on introducing micro modular reactors in Korea, covering technology review, regulatory response, supply chain and business models for industrial sites, with a possible phased introduction. The specific NANO design is not named. No site or order exists.
Announced or first reported · Agreement or program announced
NANO Nuclear Energy and Ameresco memorandum on deploying NANO microreactors at US federal and commercial sites (2026) #
Ameresco signed a memorandum with NANO Nuclear Energy, reported in January 2026, to explore deploying NANO's microreactors - including KRONOS MMR, ZEUS and LOKI MMR - at US federal and commercial sites, with Ameresco expected to lead EPC under later site-specific agreements. No site, order or license application is named.
Announced or first reported · Agreement or program announced
Danish government analysis of serially produced SMRs and the 1985 nuclear ban #
In January 2026 Denmark's climate ministry set the terms for a three-track analysis of the possible role of serially produced SMRs in the Danish energy system, regulatory and authority requirements, and business potential, following a 2025 parliamentary decision. The 1985 ban on nuclear power remains in force, there is no project or site.
· Recorded development
DOE approves the Antares Mark-0 preliminary documented safety analysis #
· Construction start
Last Energy states it began PWR-5 construction at RELLIS #
· Application submitted
Application submitted: Pioneer Units 1 and 2 phased construction permit application (with limited work authorization request) #
Holtec filed Part 1 of a phased construction permit application for two SMR-300 units (Pioneer 1 and 2) at the Palisades Energy Center on 31 December 2025, including a limited work authorization request. The NRC accepted it for docketing in February 2026 and began weekly notices of receipt on 1 October 2026. Its fourth notice, published 22 October, again records receipt and availability; it does not grant an LWA or construction permit. Part 2 (a complete preliminary safety analysis report, with an updated Quality Assurance Topical Report and exemption requests) was filed on 30 September 2026, according to the NRC's notice of receipt dated 5 November and published 10 November 2026 (91 FR 72577; ADAMS package ML26273A416), which began a second series of four weekly notices. The notice says the NRC staff was then undertaking its acceptance review of Part 2; no acceptance or docketing of Part 2 is recorded. The application remains recorded as under review; this receipt notice is not a new permission decision.
· Application submitted
Application submitted: Belews Creek early site permit application #
Duke Energy Carolinas applied on 30 December 2025 for an early site permit for the Belews Creek site in Stokes and Forsyth counties, North Carolina. The NRC accepted and docketed the application in February 2026 under Docket No. 52-055, and it is under review. If issued, an early site permit approves a site independent of a specific plant design. It is not a construction permit or a combined license, and no reactor design is selected. The NRC gave notice on 27 April 2026 that it will prepare an environmental impact statement, and its project page marks the uncontested hearing of 17 September 2026 as held. On 29 September 2026, NRC letter ML26259A008 set a $2,178,000 cap on NRC review fees. That cap is not a project cost or a permit. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The letter accelerates the 8 February 2026 schedule. NRC targets, not completed: advanced final safety evaluation report without open items December 2026 (from March 2027), draft environmental impact statement December 2026 (from February 2027), final safety evaluation February 2027 (from May 2027), and final environmental impact statement March 2027 (from May 2027). The decision date is listed as to be determined. Duke Energy Carolinas' Revision 2 cover letter (ML26274A437), dated 1 October 2026, states that Duke is not requesting a limited work authorization. The NRC project page lists the Revision 2 package as ML26274A436.
· Recorded development
Swedish Government announces receipt of Videberg Kraft's state-support application #
On 23 December 2025 the Government announced that it had received the first application for state support for new nuclear, from Videberg Kraft, for reactors of about 1,500 MW in total on the Värö peninsula at Ringhals. An application is not an award.
· Recorded development
MSNR asks ASNR to review the Stellaria INB Alpha application #
ASNR states that MSNR referred the INB Alpha creation-authorization application, filed on 19 December 2025, to it for review on 22 December 2025. As of the page fetched 5 October 2026, technical review is suspended pending further information. The page does not date that suspension. No creation authorization has been granted.
Conclusion issued · Regulatory step
Ministry sets the scope of the Tušimice SMR environmental assessment #
ČEZ must justify the site against regional alternatives and cover the listed surveys in its environmental-impact documentation. A scoping step in the environmental assessment, not a permit or nuclear license.
Checking notes
The Ministry of the Environment's screening conclusion of 22 December 2025 sets what ČEZ's environmental-impact documentation for Tušimice must cover, including a justification of the site against alternatives in the region. A full assessment is mandatory for nuclear plants under Czech law; the conclusion is not a permit.
Announced or first reported · Agreement or program announced
Blue Bird Energy and SGE letter of intent for a joint venture to build up to six BWRX-300s in Bulgaria #
On 22 December 2025 Bulgarian company Blue Bird Energy and SGE announced a letter of intent to form a joint venture aimed at building a fleet of up to six BWRX-300 SMRs in Bulgaria, for industry, data centers and district heating. The joint venture would still have to select sites.
· Published
Published: India: Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Act, 2025 (No. 39 of 2025) #
Gazette of India, Extraordinary, Part II Section 1, No. 63.
· Enacted
Enacted: India: Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Act, 2025 (No. 39 of 2025) #
Presidential assent on 20 December 2025 (Bill No. 196-F of 2025).
· Application submitted
Application submitted: Stellaria INB Alpha creation-authorization application #
ASNR states that Stellaria filed a creation-authorization application on 19 December 2025 for INB Alpha, including the ALVIN research reactor at CEA Cadarache. MSNR referred it to ASNR on 22 December 2025. Following ASNR analysis, MSNR requested further information on 16 June 2026. The page updated 14 October says technical review is suspended pending that information; it does not separately date the suspension. No creation authorization is recorded.
Announced or first reported · Agreement or program announced
Ontario Power Generation and New York Power Authority memorandum on advanced nuclear, including SMRs (2025) #
On 19 December 2025 NYPA and OPG signed a memorandum establishing a framework for collaboration on advanced nuclear technologies, including large reactors and SMRs, covering information sharing, financing and economics, and workforce development. Governor Hochul and Premier Ford separately signed a declaration of intent on cooperation. The memorandum selects no technology, site or project.
· Application submitted
Application submitted: newcleo LFR-AS-30 safety-options request #
ASNR states that newcleo filed a safety-options request on 19 December 2025 for LFR-AS-30. The page does not record an opinion or a creation authorization.
· Effective date recorded
Effective date recorded: United Kingdom: National Policy Statement for nuclear energy generation (EN-7) #
England and Wales planning policy for nuclear fission power projects, in force since 18 December 2025. Together with EN-1 it guides the Energy Secretary's decisions on development consent, and it opens siting to a wider range of locations than the eight sites named in the older EN-6. It grants no consent and approves no site.
· Amended
Amended: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) #
Regulation of 15 December 2025 renumbering the theme as innovation theme 5.
Announced or first reported · Agreement or program announced
China's HTGR Modern Industrial Chain Alliance led by CNNC's Chinergy (2025) #
CNNC subsidiary Chinergy launched the High-Temperature Gas-Cooled Reactor Modern Industrial Chain Alliance in Beijing on 11 December 2025, bringing together more than 60 organizations. It covers research and design, fuel and equipment manufacturing, construction, operation and overseas markets, aiming to extend HTGR use to heating and hydrogen. It is an industrial alliance, not a deployment project.
Announced or first reported · Agreement or program announced
Natura acquisition of Shepherd Power and commercialization agreement with NOV #
On 10 December 2025 Natura reported acquiring Shepherd Power from NOV and signing a commercialization agreement with NOV. The intended market includes data centers and industrial applications. NOV becoming an investor is prospective. Neither delivered funds nor a named customer, reactor site or reactor order is established.
· Recorded development
CNEN ceremony marks formal start of UCRI site licensing #
Announced or first reported · Agreement or program announced
Algeria and IAEA joint statement prioritising SMRs for electricity and desalination (December 2025) #
On 8 December 2025 the IAEA and Algeria signed a joint statement under which the IAEA will support Algeria in exploring nuclear energy options, including small modular reactors for electricity and seawater desalination, and offered an expert mission on SMR feasibility. In September 2026 Algeria's energy minister and the IAEA Director General reviewed progress under the agreement. No site, design or project has been named.
Announced or first reported · Agreement or program announced
Steady Energy and Korea District Heating Corp. cooperation on heat-only SMRs #
Steady Energy and Korea District Heating Corp. announced an agreement in December 2025 to foster cooperation on heat-only small modular reactors. The release does not state the agreement's terms and names no Korean site, unit count, order or license application.
· Recorded development
Army reports the first TRISO fuel delivery to INL that week #
The Army's article dated 3 December 2025 says Idaho National Laboratory received the first TRISO fuel delivery for Project Pele that week. The article does not give the delivery day. It is not a safety-analysis approval, not authorization to load fuel, and not authorization to operate.
· Recorded development
Welsh Government announces intention to dissolve Cwmni Egino #
The Welsh Government's written statement of 3 December 2025 says the Welsh Ministers, as sole shareholder, intend at the end of the current agreement on 31 March 2026 to pass a special resolution directing the directors to dissolve Cwmni Egino, the company set up in 2021 to deliver a site development plan for Trawsfynydd. It notes that in May 2024 the UK Government did not include Trawsfynydd among the initial sites considered in its SMR competition, and that Cwmni Egino's work will be archived for possible future use. The statement records an intention. The Companies House register read on 9 October 2026 still lists the company as active with no dissolution filing, so the dissolution is not recorded as completed.
· Application submitted
Application submitted: Reported IEN request to construct the UCRI critical unit #
CNEN reports an IEN letter to ANSN dated 2 December 2025 seeking construction permission and use of Argonauta facilities for the critical experiment. This is a reported submission; the letter, acceptance and a permission decision are not recorded.
Announced · Recorded development
DOE selects TVA for $400 million in cost-shared funding for Clinch River BWRX-300 #
DOE named TVA one of two first-mover teams for Gen III+ small modular reactors, with $400 million in federal cost-shared funding for its Clinch River BWRX-300. A funding selection is not a final investment decision, construction start or NRC permission.
Checking notes
DOE announced on 2 December 2025 that it selected TVA for $400,000,000 of up to $800 million in federal cost-shared funding for early Gen III+ SMR deployments, to advance a GE Vernova Hitachi BWRX-300 at the Clinch River Nuclear site. A funding selection is not a construction decision or a permit.
· Recorded development
Huakun One: siting-stage environmental assessment accepted #
The ecology ministry accepted the siting-stage environmental impact report for the floating platform at the Taipingling site.
Announced · Recorded development
DOE selects Holtec for $400 million in cost-shared funding for two SMR-300s at Palisades #
DOE named Holtec Government Services one of two first-mover teams for Gen III+ small modular reactors, with $400 million in federal cost-shared funding for two SMR-300 units at Palisades. A funding selection is not a final investment decision, construction start or NRC permission.
Checking notes
DOE announced on 2 December 2025 that it selected Holtec Government Services, LLC for $400,000,000 of up to $800 million in federal cost-shared funding for early Gen III+ SMR deployments, to deploy two SMR-300 reactors at the Palisades site in Covert, Michigan. A funding selection is not a construction decision or a permit.
· Selections announced
Selections announced: Gen III+ SMR selection: TVA (Clinch River BWRX-300) #
DOE selected TVA on 2 December 2025 for up to $400 million in cost-shared funding for its first BWRX-300 at Clinch River.
· Selections announced
Selections announced: Gen III+ SMR selection: Holtec (Palisades SMR-300) #
DOE selected Holtec on 2 December 2025 for up to $400 million in cost-shared funding for two SMR-300 units at Palisades.
· Selections announced
Selections announced: DOE Generation III+ Small Modular Reactor program #
Two first-mover selections of up to $400 million each.
Announced or first reported · Agreement or program announced
Great Plains New Nuclear Consortium study of 1,000-2,000 MW of new nuclear, including SMRs, in Nebraska (2025) #
Four public-power utilities - Nebraska Public Power District, Omaha Public Power District, Lincoln Electric System and Oklahoma's Grand River Dam Authority - formed the Great Plains New Nuclear Consortium by memorandum on 1 December 2025. It will study the feasibility, sites and technologies for 1,000-2,000 MW of new nuclear capacity, including SMRs, in Nebraska. No construction or investment decision has been made.
Announced or first reported · Agreement or program announced
Rosatom and India's Ministry of Ports, Shipping and Waterways working group on floating nuclear power plants (2025) #
Rosatom's director general said in December 2025, as reported by Tass and WNN, that Rosatom and India's Ministry of Ports, Shipping and Waterways had set up a working group to examine floating nuclear power plants in India. At the same summit President Putin said SMRs and floating plants could be relevant to cooperation. No design, site or agreement to build is recorded.
Reported · Contract
Natura signs an Other Transaction Agreement with DOE for MSR-1 #
ANS reported that Natura executed an Other Transaction Agreement with DOE for its molten salt research reactor at Abilene Christian University, moving the project onto DOE's authorization pathway. The agreement is not DOE authorization to construct or operate.
Checking notes
ANS reported on 19 December 2025 that Natura had executed an Other Transaction Agreement with DOE for the Molten Salt Research Reactor at Abilene Christian University, under which the project would proceed through DOE authorization. The execution day and terms are not published. The agreement is not an authorization to construct or operate.
Announced or first reported · Agreement or program announced
MVM and Holtec memorandum to explore SMR-300 deployment in Hungary #
In December 2025 Holtec announced a memorandum with Hungarian state energy group MVM to explore deploying SMR-300 units in Hungary, building on the November 2025 US-Hungary nuclear energy MoU. No site, order or license is recorded.
· Design assessment: Review completed (not an approval)
Design assessment: Review completed (not an approval): BWRX-300 UK Generic Design Assessment (two steps) #
The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
· Groundbreaking
Groundbreaking for the Gravity pilot at Great Plains Industrial Park, Parsons #
Groundbreaking is not first nuclear concrete; check whether the record already holds it.
· Milestone
Milestone: United Kingdom: Building our nuclear nation, government response to the Nuclear Regulatory Review 2025 #
Nuclear Regulatory Taskforce final report published.
· Recorded development
Project Nova: Valar zero-power test core operated by Los Alamos at NCERC (Nevada) #
A separate zero-power test core proving Ward 250 physics, not the Ward 250 reactor itself.
· Published
Published: Virginia SCC final order: Appalachian Power Joshua Falls development costs #
The caption prints AT RICHMOND, NOVEMBER 12, 2025. The order states no later effective date.
· Published
Published: United Kingdom: National Policy Statement for nuclear energy generation (EN-7) #
England and Wales planning policy for nuclear fission power projects, in force since 18 December 2025. Together with EN-1 it guides the Energy Secretary's decisions on development consent, and it opens siting to a wider range of locations than the eight sites named in the older EN-6. It grants no consent and approves no site.
Announced or first reported · Agreement or program announced
US-Hungary nuclear energy memorandum covering SMRs (November 2025) #
On 7 November 2025 the US and Hungarian governments signed a nuclear energy memorandum that, per the US State Department, signals intent to negotiate cooperation including SMRs, it said Hungary signalled support for up to ten SMRs worth up to USD 20 billion. It is a statement of intent, not an order.
Announced or first reported · Agreement or program announced
Terrestrial Energy and Springfields IMSR fuel-pilot manufacturing contract #
On 5 November 2025 Terrestrial reported a manufacturing and supply contract with Springfields Fuels Limited, a Westinghouse subsidiary, for an IMSR fuel pilot plant at Springfields in Preston. It expands an August 2023 planning/design contract. Design and construction were contracted. A 2026 construction start was a target. This establishes neither completed construction, enrichment services, delivered fuel nor a reactor deployment.
· Recorded development
Pele TRISO core (40,000 fuel compacts) delivered to INL TREAT facility (day per INL) #
Refines the existing month-precision fuel-delivery event (2025-11). ANS relays INL; the Army article of 3 Dec 2025 ('this week') is an announcement date, not the delivery day.
Announced or first reported · Agreement or program announced
Natura and 3M lithium-7 development and qualification agreement #
Natura and 3M signed a cooperative work agreement on 4 November 2025. 3M agreed to begin developing and qualifying lithium-7 for molten-salt reactor technology. No supply quantity, delivered material, reactor deployment or completed qualification is established. This is distinct from the later DOE FLiBe allocation.
Announced · Announcement
First American Nuclear and Indiana announce an EAGL-1 energy park plan #
FANCO and the State of Indiana announced plans for FANCO's headquarters, manufacturing facilities and one energy park in Indiana. No county or site is named. Not a construction permit and not a module count. ANS reported the announcement on 10 November 2025.
· Recorded development
SINAP announces first thorium-to-uranium fuel conversion #
Announced or first reported · Agreement or program announced
Türkiye national target of 5,000 MWe of SMR capacity by 2050 #
In November 2025 Türkiye's energy minister set a target of 5,000 MWe of SMR capacity by 2050, in addition to 12 large reactors. It is a national target, no SMR site, vendor or project has been chosen.
Announced or first reported · Agreement or program announced
Terra Innovatum and Uvation letter of intent for a SOLO microreactor pilot for data centers (2025) #
Terra Innovatum signed a letter of intent with US technology company Uvation in November 2025 for a 1 MWe SOLO pilot program, with a strategic option to scale to 100 MWe for Uvation's AI and data-center infrastructure. Uvation called the pilot a first step that could extend across multiple sites. No site, order or license application is named.
Announced or first reported · Agreement or program announced
Stellaria and Equinix pre-order agreement for power from Stellarium reactors (2025) #
French molten-salt reactor developer Stellaria signed a pre-order agreement in November 2025 under which data-center operator Equinix secured the first power-capacity reservation on the Stellarium, which Stellaria plans to deploy from 2035. Stellaria's release heads it as a pre-order of up to 500 MWe. No site or number of units is stated. It is a capacity reservation, not a construction order or permit.
Announced or first reported · Agreement or program announced
SINAP thorium molten-salt reactor program: 100 MWt prototype targeted by 2035 #
After the Wuwei experimental thorium molten-salt reactor achieved thorium-to-uranium conversion, SINAP said in November 2025 that it aims to complete construction and demonstration of a 100 MWt prototype by 2035 and work with SPIC and others on an industrial supply chain. No site, approval or construction is recorded for the prototype.
· Recorded development
Advanced nuclear fuel delivered to INL for Project Pele #
DOE stated on 23 May 2026 that advanced nuclear fuel for Project Pele was delivered to Idaho National Laboratory in November 2025. The Army's article of 3 December 2025 says the first TRISO fuel delivery arrived at INL that week. The month is not settled between those official statements, and neither statement gives a calendar day. Delivery of fuel is not fuel loading, startup or operation.
Announced or first reported · Agreement or program announced
Hexana and Atoomcoöperatie memorandum on Hexana SMR deployment in the Netherlands (2025) #
In November 2025 French SMR developer Hexana and the Dutch citizen energy cooperative Atoomcoöperatie signed a memorandum to explore developing Hexana's sodium-cooled SMR platform in the Netherlands, with the cooperative coordinating stakeholder engagement. No site or project is named.
Announced or first reported · Agreement or program announced
Finnish government-commissioned AFRY study on promoting nuclear energy, including SMR electricity and heat options… #
Finland's Ministry of Economic Affairs and Employment commissioned AFRY in November 2025 to study options, costs and market effects of promoting nuclear energy, covering large reactors, SMR electricity and heat solutions, and life extensions. The report, submitted in March 2026, found heat-producing SMRs may be better placed for market-based implementation than new large plants. It is a study, not a program decision.
Announced or first reported · Agreement or program announced
Aecon and Norsk Kjernekraft strategic cooperation on BWRX-300 SMRs in Norway (2025) #
Aecon, a contractor on Canada's first BWRX-300 at Darlington, and Norwegian developer Norsk Kjernekraft signed a strategic cooperation agreement in November 2025 focused on the GE Vernova Hitachi BWRX-300. It aims at a roadmap for feasibility studies, licensing, stakeholder management and site identification. It does not assign the design to any of Norsk Kjernekraft's specific project sites.
· Published
Published: Argentina: Strategic Guidelines on Innovation, Science and Technology 2025-2027 (Resolución 282/2025) #
Boletín Oficial No. 35782, page 81.
· Issued
Issued: Argentina: Strategic Guidelines on Innovation, Science and Technology 2025-2027 (Resolución 282/2025) #
Sanción 30-10-2025.
· Passed
Passed: Michigan 2025 House Bill 4128: proposed credit for small modular reactor and uprate electricity #
The House passed substitute H-3 on 28 October 2025 and gave it immediate effect, yeas 78, nays 26. The Senate referred the bill to the Committee on Energy and Environment on 30 October 2025. House passage is not enactment.
Announced or first reported · Agreement or program announced
Nova Scotia and Ontario memorandum of understanding on small modular reactors (2025) #
Nova Scotia and Ontario signed a memorandum effective 23 October 2025 under which Nova Scotia will draw on Ontario's experience to explore SMRs as a clean-energy option. The provinces will share knowledge on SMR technology, regulation, supply chain, economics, waste and engagement, and advocate for federal support. Nova Scotia said SMRs would not be established in the province soon, no site or project is named.
Announced · Announcement
Kiewit, Black & Veatch and Aecon venture chosen to negotiate Cascade design-build #
Energy Northwest is negotiating with Cascade Nuclear Partners to plan, design and build the first four Xe-100 modules. The development phase is meant to set scope, schedule and cost. Negotiations are not a signed construction contract.
Checking notes
Energy Northwest said it is in negotiations with Cascade Nuclear Partners, an equal joint venture of Kiewit, Black & Veatch and Aecon, to plan, design and build the first four Xe-100 modules under a progressive design-build model.
Announced · Announcement
Last Energy and the Texas A&M System announce the PWR-5 pilot at RELLIS #
Last Energy and the Texas A&M University System announced the PWR-5 pilot at Texas A&M-RELLIS; Last Energy said it had a site lease, a full core load of fuel and an agreement with DOE. The announcement is not DOE authorization.
Checking notes
On 15 October 2025 Last Energy and the Texas A&M University System announced the PWR-5 pilot at Texas A&M-RELLIS. Last Energy said it had secured a lease at the campus, procured a full core load of fuel, signed an Other Transaction Agreement with DOE and begun formal licensing submissions. Announcement only; not an authorization.
Announced or first reported · Agreement or program announced
U.S. Army Janus Program for commercial microreactors on Army installations #
The Janus Program is the Army's next-generation nuclear power program to build commercial microreactors on installations through Defense Innovation Unit milestone-based contracting. The Army shortlisted nine installations in November 2025 and in August 2026 named the first five, each paired with a vendor, Fort Wainwright, Holston Army Ammunition Plant, Joint Base Lewis-McChord and Redstone Arsenal were shortlisted but not selected.
· Recorded development
ANSN pre-licensing harmonisation meeting at AMAZUL #
Announced or first reported · Agreement or program announced
Blykalla–evroc–Studsvik nuclear-powered data-center feasibility memorandum #
In October 2025 Blykalla, evroc and Studsvik signed a memorandum to assess commercial and technical co-location of data centers and SEALER reactors at Studsvik’s existing nuclear site in Nyköping. Work includes municipal and landowner engagement and considering a future PPA structure. The release planned a steering committee and later partnership negotiations. Their completion is not established. Studsvik’s existing site license does not authorize a new Blykalla reactor. No unit count or capacity is committed.
· Provision took effect
Provision took effect: ADVANCE Act of 2024 #
The reduced hourly rate first applied from this date at $148 an hour (against $318 full cost) under the FY2025 fee rule. The FY2026 fee rule set it at $154 against $337 from 17 August 2026.
Announced or first reported · Agreement or program announced
Ukraine's draft SMR implementation roadmap and draft law on small modular reactors (2025) #
In October 2025 Ukraine's Ministry of Energy convened a working group on a draft action plan (roadmap) for introducing SMRs, and a draft law on SMR implementation was presented to parliament's energy committee. The bill would let private owners of SMRs choose their operators and drop the requirement to submit three alternative sites. Registered as bill No. 14164 on 29 October 2025, it was recommended for adoption at first reading by the lead committee on 22 April 2026, and parliament's bill card showed it awaiting that reading in October 2026. No site or design is named.
Announced or first reported · Agreement or program announced
Terra Innovatum and Ameresco memorandum on siting and deploying SOLO micro-modular reactors (2025) #
Terra Innovatum announced in October 2025 a memorandum with US energy-solutions company Ameresco setting a framework for siting, development, construction, integration, operation and decommissioning planning of its SOLO micro-modular reactor, with Ameresco helping to identify and secure sites. No site, order or license application is named.
Announced or first reported · Agreement or program announced
South Africa IRP 2025 new-nuclear plan and Necsa SMR partner selection #
South Africa's Integrated Resource Plan 2025, approved in October 2025, calls for 5,200 MWe of new nuclear capacity by 2039. In line with Decision 4 of IRP 2025, Necsa launched an expression of interest on 31 March 2026 to find partners to develop, demonstrate and deploy SMRs, and in June 2026 said it hoped to select a development partner within a year. No SMR technology, partner or site has been selected, the earlier 2,500 MWe procurement was paused in 2024.
· Recorded development
Linglong One completes cold functional testing #
Cold functional testing of the Linglong One unit was completed, the first of the two key system tests before grid connection. Hot testing, fuel loading, criticality and grid connection were still ahead.
Checking notes
China News Service reported on 1 October 2026 that cold functional testing of the Linglong One unit was completed in October 2025. The National Energy Administration's China Nuclear Power Development Report 2026 (July 2026) also records cold functional tests completed in 2025. Cold testing precedes hot functional testing, fuel loading, criticality and grid connection, none of which this entry records. China News Service describes cold and hot functional testing as the two key checks a unit passes before grid connection, with fuel loading the next step after hot testing.
Announced or first reported · Agreement or program announced
Diamante Energia evaluation of an SMR at the Jorge Lacerda coal complex (ANSN pre-licensing consultation, IAEA/ABDAN… #
Diamante Energia is evaluating a small modular reactor at its Jorge Lacerda coal-fired complex in Capivari de Baixo, Santa Catarina: the regulator ANSN visited in October 2025 and, on 26 May 2026, began a formal consultation requested by Diamante on the requirements for a preliminary site license, and in September 2026 Diamante signed a letter of intent with the IAEA and ABDAN to assess the conversion of one unit. No reactor design or investment decision has been made, Rosatom says it has offered a RITM-family plant.
Announced · Recorded development
Canada Growth Fund and Building Ontario Fund commit C$3 billion in equity to Darlington new nuclear #
The two funds committed up to C$2 billion and C$1 billion for minority stakes of 15% and 7.5% in the four-unit project. The first tranche funds this first unit; OPG remains majority owner and operator. The capital is committed subject to conditions; it is not a record of funds drawn.
Checking notes
Canada Growth Fund committed up to C$2 billion and Building Ontario Fund C$1 billion for minority stakes of 15% and 7.5% in the four-unit Darlington New Nuclear Project; the first tranche funds this first unit, and OPG remains majority owner and operator.
Announced or first reported · Agreement or program announced
Armenia's plan for an SMR as its next nuclear unit (US FIRST pre-feasibility study, US-Armenia nuclear agreement) #
Armenia's prime minister said in October 2025 that the next reactor would be an SMR. In February 2026 Armenia and the US completed negotiations on a civil nuclear cooperation agreement, which US Vice President Vance said means US SMR technology coming to Armenia, and in May 2026 a US-funded FIRST pre-feasibility study short-listed four US SMR technologies to replace the Armenian NPP unit. No vendor has been selected.
Reported approval month · Recorded development
Antares reports Mark-0 safety-design agreement approval in October 2025 #
A contemporaneous October 2025 announcement reports DOE approval for Antares' first reactor, and the October 2026 retrospective explicitly identifies Mark-0 and its approval month. Company reports only, with approval month established but no approval day or operating authority inferred.
Checking notes
Antares' announcement dated 29 October 2025 says DOE approved the safety-design agreement for its first reactor. Its 23 October 2026 retrospective explicitly identifies Mark-0 and places approval in October 2025. The approval month is recorded at month precision because neither statement establishes an approval day, and the company-reported framework is not itself operating authorization.
Announced or first reported · Agreement or program announced
ABS, Core Power and Athlos Energy assessment of floating nuclear power plants for Greece (Deon Policy Institute… #
As part of a Joint Development Program, the American Bureau of Shipping, CORE POWER UK and Greek company Athlos Energy held a workshop in Athens on 30-31 October 2025 on deploying floating nuclear power plants in Greece. The resulting Deon Policy Institute report, published in May 2026, found no fundamental barriers but open policy, regulatory, financial and social-acceptance issues. No plant, site or design is selected.
· Recorded development
JAEA files an amendment to the HTTR hydrogen-coupling application #
Announced or first reported · Agreement or program announced
Nucleon Energy and ARC Clean Technology NuARC partnership to deploy ARC-100 SMRs, starting in Alberta #
Calgary-based Nucleon Energy and ARC Clean Technology formed a partnership entity, NuARC, in September 2025 to develop and deploy generation facilities using ARC's ARC-100 sodium-cooled SMR, with an initial focus on Alberta. No site, unit count, order or license application is named.
Announced or first reported · Agreement or program announced
TerraPower, Evergy and Kansas Department of Commerce memorandum to explore siting a Natrium plant in Kansas #
TerraPower, Evergy and the Kansas Department of Commerce signed a memorandum of understanding in September 2025 to explore siting a Natrium reactor and energy storage system in Evergy's Kansas service territory. Greenwood County invited community support for a bid and said TerraPower was expected to narrow the field to two or three communities, no site has been selected and no license application filed.
· Signed
Signed: Idaho Executive Order 2025-06: Advanced Nuclear Energy Task Force #
The order's witness clause is 22 September 2025 at the Capitol in Boise. The order creates an advisory task force. It does not license a reactor. The press sentence locating the signing at Idaho National Laboratory is a separate sentence on the same page.
Groundbreaking · Groundbreaking
Valar breaks ground on Ward 250 at the Utah San Rafael Energy Lab #
Valar dates the start of Ward 250 site work in Emery County, Utah, to 17 September 2025. The date is the developer's; no state or DOE construction record was opened.
Checking notes
Valar dates the Ward 250 groundbreaking at the Utah San Rafael Energy Lab to 17 September 2025, the dateline of ETV News's report. DOE's environmental determination says construction stayed within the existing site with minimal excavation. A groundbreaking is site work, not fuel loading or operation.
· Took effect
Took effect: NRC direct final rule: Revising the Duration of Design Certifications #
Effective date confirmed in the Federal Register on 26 August 2025 (90 FR 41503).
Announced · Announcement
Last Energy London Gateway PWR-20 proposal documented #
Port power proposal under an MOU, targeting 2030. This announcement does not establish financing, permission to construct or physical construction.
· Issued
Issued: Indonesia: Government Regulation No. 40 of 2025 on National Energy Policy (Peraturan Pemerintah Nomor 40 Tahun 2025 tentang Kebijakan Energi Nasional) #
Ditetapkan di Jakarta, pada tanggal 15 September 2025.
· Took effect
Took effect: Indonesia: Government Regulation No. 40 of 2025 on National Energy Policy (Peraturan Pemerintah Nomor 40 Tahun 2025 tentang Kebijakan Energi Nasional) #
Article 93: in force on promulgation; promulgated 15 September 2025.
· Signed
Signed: Arizona Executive Order 2025-13: energy task force #
The governor's order page prints Executive Order 2025-13 and September 15, 2025. The 1 March 2026 report dates are directions. Delivery was not opened.
· Passed
Passed: China: Atomic Energy Law of the People's Republic of China (2025) #
Adopted by the NPC Standing Committee.
Announced or first reported · Agreement or program announced
Kairos Power and BWXT commercial TRISO fuel development collaboration #
On 3 September 2025 Kairos Power and BWXT announced cooperation to explore commercial TRISO manufacture, possible fuel supply for Hermes 2 and subsequent Kairos reactors, and a possible jointly developed fuel-fabrication facility. Existing US laboratories and BWXT production capabilities are inputs to the study, not a selected new factory. No firm fuel order, funded new facility, delivered fuel or reactor permission is established. The US scope follows the named Hermes 2 target, not every potential customer.
Announced or first reported · Agreement or program announced
NANO Nuclear AFWERX research contract to explore a KRONOS MMR at Joint Base Anacostia-Bolling #
AFWERX awarded NANO Nuclear a Direct-to-Phase II Small Business Innovation Research contract of about $1.25 million in September 2025 to explore the feasibility of deploying its KRONOS MMR at Joint Base Anacostia-Bolling, examining energy demand, siting options and regulatory pathways. It is a research contract only, there is no deployment decision or license application.
· Took effect
Took effect: Texas HB 14 (2025): Texas Advanced Nuclear Energy Office and development fund #
Texas law signed on 20 June 2025 and effective 1 September 2025. It creates a state nuclear office and fund; it does not license or approve any reactor, which remains the NRC's role.
· Opened
Opened: Texas Advanced Nuclear Development Fund #
Fund created when HB 14 took effect.
Announced or first reported · Agreement or program announced
X-energy Canada study of repurposing an Alberta thermal power site with Xe-100 reactors (2025) #
A study by X-energy Canada, funded by Emissions Reduction Alberta and carried out with TransAlta, Hatch, PCL and Kinectrics, reported in September 2025 that repurposing an existing thermal generation site in Alberta with Xe-100 reactors is feasible. The site is not named. It is a completed feasibility study, not a project, site selection or license application.
Announced or first reported · Agreement or program announced
TerraPower and KBR studies of potential UK sites for Natrium reactors (2025) #
In September 2025 TerraPower and KBR announced that they would jointly conduct studies and evaluate potential UK sites for TerraPower's Natrium reactor. The UK government's February 2026 Advanced Nuclear Framework announcement described the work as continuing. No site has been named, Natrium's UK Generic Design Assessment is a separate, design-level process.
Announced or first reported · Agreement or program announced
Iran (AEOI) and Rosatom memorandum on building small nuclear power plants in Iran #
In September 2025 Russia and Iran signed a memorandum on cooperation in building small nuclear power plants in Iran, following a meeting of Rosatom's head and Iranian Vice President Eslami. Rosatom said it envisages specific implementation steps. A report published on 5 October 2026 quotes the deputy chair of Russia's Security Council as saying another nuclear plant and small nuclear plants remain on the agenda. That political statement names no site, design or contract and does not establish a new project or program instrument.
Announced · Contract
Antares executes its DOE agreement to take a reactor critical by July 2026 #
Antares said it executed an agreement with DOE to take an advanced reactor critical by 4 July 2026; DOE's Mark-0 determination refers to an Other Transaction Agreement between the two. The agreement's terms are not published, and it is not an authorization to operate.
Checking notes
Antares said on 22 September 2025 that it had executed its agreement with DOE that week to take an advanced reactor critical by 4 July 2026. DOE's Mark-0 determination refers to an Other Transaction Agreement between Antares and DOE. The terms are not published. The agreement is not an authorization to operate.
· Took effect
Took effect: Missouri section 393.1400: new nuclear units excluded from qualifying-plant rate treatment #
The revisor page prints Effective - 28 Aug 2025. The three histories named on that line were not opened.
Announced · Recorded development
DOE commits HALEU to Abilene Christian University and Natura for MSR-1 #
DOE made a conditional commitment of HALEU to Abilene Christian University and Natura Resources for their molten salt research reactor in Texas. A conditional commitment is not a delivery or fuel loading.
Checking notes
On 26 August 2025 DOE made a conditional HALEU commitment to Abilene Christian University and Natura Resources for a new molten salt research reactor in Texas, which DOE described as under construction. A conditional commitment is not fuel delivery or fuel loading.
· Selections announced
Selections announced: DOE HALEU Availability Program and HALEU allocation process #
Second round: conditional commitments to three companies.
Announced · Recorded development
DOE commits HALEU to Antares for the reactor due to reach criticality by July 2026 #
DOE made a conditional commitment of HALEU to Antares Nuclear for the microreactor that was to reach criticality by 4 July 2026; DOE's environmental determination ties that fuel to Mark-0. A conditional commitment is not a delivery date or fuel loading.
Checking notes
On 26 August 2025 DOE made a conditional commitment of HALEU to Antares Nuclear for the microreactor design that was to reach criticality by 4 July 2026 under the Reactor Pilot Program. DOE's environmental determination for Mark-0 says Antares plans to use HALEU TRISO fuel in Mark-0 under a HALEU agreement with DOE. A conditional commitment is not a fuel delivery.
Announced or first reported · Agreement or program announced
Utah Office of Energy Development, TerraPower and Flagship Companies memorandum to explore siting a Natrium plant in… #
The Utah Office of Energy Development, TerraPower and land developer Flagship Companies signed a non-binding memorandum in August 2025, under Governor Cox's Operation Gigawatt, to identify and assess sites for a potential Natrium reactor and storage plant in Utah, aiming for preliminary site recommendations by the end of 2025. No site, order or license application is recorded.
· Took effect
Took effect: Ohio power-siting definition of a major utility facility #
The official section page prints Effective August 14, 2025. That date is not the effective date of section 4906.04.
· Selections announced
Selections announced: DOE Reactor Pilot Program #
Initial selections: ten companies, Oklo with two projects.
· Took effect
Took effect: Colorado Chapter 45 of 2025: nuclear energy in the clean-energy definitions #
The bill page opened 5 October 2026 states Effective Date 08/06/2025. The June and July 2025 digest calculated the same default day before the petition deadline and is not the finding that no petition was filed.
· Took effect
Took effect: Sweden: Act on State Support for Investment in New Nuclear Power (SFS 2025:587) #
Commencement clause of SFS 2025:587.
Announced or first reported · Agreement or program announced
SGE and Slovenské elektrárne MoU to explore BWRX-300 opportunities in Slovakia, Czech Republic and the UK #
SGE and Slovenské elektrárne signed a memorandum to explore cooperation on BWRX-300 projects. The original names opportunities in Slovakia, the Czech Republic and the United Kingdom through local partnerships, special-purpose vehicles and other agreed business models, plus links to digital infrastructure. This is program scope, with no committed plant, site, order or permission established. World Nuclear Association dates the memorandum to August 2025.
· Recorded development
Last Energy selected for DOE's Reactor Pilot Program #
Reported · Groundbreaking
Aalo breaks ground for Aalo-X next to INL's Materials and Fuels Complex #
World Nuclear News reported in late August 2025 that Aalo had broken ground at a site next to Idaho National Laboratory's Materials and Fuels Complex to start building Aalo-X. Aalo's own timing for the Critical Test Reactor building does not match this date, and no groundbreaking day is published.
Checking notes
World Nuclear News reported on 29 August 2025 that Aalo had broken ground at a site next to Idaho National Laboratory's Materials and Fuels Complex to start building Aalo-X. No groundbreaking day is given. Aalo later said its Critical Test Reactor went from groundbreaking to criticality in less than eight months, which does not fit an August 2025 start for that building.
· Site permission recorded
Site permission recorded: BAPETEN Kelasa site-evaluation approval #
Decision 00003.556.1.300725 authorizes PT Thorcon Power Indonesia to conduct site evaluation under its PET and SMET. It is not a construction license.
· Regulatory step
CNSC requests action from OPG after worker injuries at the Darlington new-build site #
The CNSC asked OPG for information and corrective action after three serious contract-worker injuries on the construction site since April 2025. It later found OPG's response sufficient and closed the request. An enforcement request on conventional safety, not a license decision.
Checking notes
The CNSC issued a request under subsection 12(2) of the General Nuclear Safety and Control Regulations after three serious contract-worker injuries on the Darlington New Nuclear Project construction site since April 2025. The CNSC later recorded OPG's response as sufficient and closed the request.
Announced or first reported · Agreement or program announced
Ocean-Power and Copenhagen Atomics MoU to study thorium molten-salt reactors in Norway #
Ocean-Power AS and Copenhagen Atomics signed a memorandum of understanding, announced in July 2025, to jointly study producing electricity and heat in Norway with thorium-based molten-salt reactors. The study is to cover technical and regulatory conditions, power and heat demand, site selection and a conceptual plant design. No site, unit count, order or license application is named.
· Regulatory step
NRC completes PSAR acceptance review (application docketed) #
· Amended
Amended: Internal Revenue Code sections 45Y and 48E: clean electricity production and investment credits, as amended by Public Law 119-21 #
Pub. L. 119-21 secs. 70512-70513, approved 4 July 2025.
· Took effect
Took effect: 2025 Wisconsin Act 12: nuclear power siting study #
Current s. 991.11 says an act that does not expressly prescribe its time takes effect the day after publication. This act prescribes no other effective time. The day after 3 July 2025 is 4 July 2025. The bracketed report date is a separate insert.
· Published
Published: 2025 Wisconsin Act 12: nuclear power siting study #
The official act states its date of publication as 3 July 2025.
· Published
Published: NRC direct final rule: Revising the Duration of Design Certifications #
NRC rule in force since 15 September 2025 that makes US design certifications valid for 40 years instead of 15, both for the five certifications then in effect, including NuScale's, and for future ones. Issue dates are unchanged. It certifies no design and licenses no reactor.
· Enacted
Enacted: 2025 Wisconsin Act 12: nuclear power siting study #
The official act states its date of enactment as 2 July 2025. It is 2025 Senate Bill 125. Enactment orders a study. It does not approve a reactor.
· Recorded development
DOE conditionally selects Radiant for the first DOME tests #
On 1 July 2025 DOE made conditional selections of Radiant and Westinghouse to perform the first tests in the DOME test bed at Idaho National Laboratory, and said both were working through DOE's multi-phase authorization process. A conditional selection is not an authorization to start up a reactor.
· Took effect
Took effect: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) #
Artikel III.
· Took effect
Took effect: Indiana SEA 424 (2025): SMR development cost recovery #
The enrolled act states an effective date of 1 July 2025. That date is separate from the 10 April 2025 signature recorded by Bill Watch.
· Took effect
Took effect: Indiana SEA 423 (2025): SMR pilot program and partnerships #
The enrolled act states that the new chapter is effective 1 July 2025. That date is separate from the 1 May 2025 signature recorded by Bill Watch.
· Amended
Amended: Indiana Code 8-1-8.5-12.1: small modular nuclear reactor certificates #
SEA 424's amendment of this section took effect. The definition moved from subsection (a) to (b). Signature of SEA 424 is a separate date on that act's record.
· Recorded development
BWXT core assembly production began #
Announced or first reported · Agreement or program announced
Ignalina NPP and newcleo memorandum to study LFR deployment feasibility in Lithuania #
In July 2025 the state-owned Ignalina Nuclear Power Plant and newcleo signed a memorandum of understanding to study the feasibility of deploying newcleo's lead-cooled LFR-AS-200 technology in Lithuania, in the presence of the energy minister. No site or plant has been named.
Announced or first reported · Agreement or program announced
Hunatom and Synthos Green Energy letter of intent on up to 10 BWRX-300 SMRs in Hungary #
In July 2025 Hungarian nuclear development firm Hunatom and Synthos Green Energy signed a letter of intent establishing a pre-framework for joint project development for up to ten BWRX-300 SMRs, in the presence of Hungary's foreign minister. It names no site and is not an order.
Announced or first reported · Agreement or program announced
Fortum and GE Vernova Hitachi early works agreement for BWRX-300 SMRs in Finland and Sweden (2025) #
In mid-2025 Fortum and GE Vernova Hitachi agreed to carry out pre-licensing and site-adaptation engineering aimed at deploying BWRX-300 SMRs in Finland and Sweden in the 2030s. In August 2026 Fortum's project company NuCore Energi applied for Swedish state aid for a 1,200 to 3,400 MW new nuclear project in Oskarshamn municipality. Its options include SMRs and large reactors, and no technology has been selected.
Executive summary dated · Design assessment: Review completed (not an approval)
CNSC lists Phase 2 of its ARC-100 vendor design review as completed #
CNSC lists Phase 2 of its pre-licensing vendor design review of the ARC-100 as completed, with an executive summary dated July 2025. A vendor design review does not certify a design or issue a license.
Checking notes
CNSC lists Phase 1 (executive summary dated October 2019) and Phase 2 (executive summary dated July 2025) of its pre-licensing vendor design review of ARC Clean Technology's ARC-100 among completed reviews. CNSC entered into the Phase 2 agreement with ARC on 9 March 2022; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barriers to licensing at that time and listed further design work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. NB Power's Point Lepreau site application is a separate process.
· Issued
Issued: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) #
Regeling van 30 juni 2025.
· Enacted
Enacted: Canada: Building Canada Act (S.C. 2025, c. 2, s. 4), national interest projects #
Assented to and in force on assent.
· Signed
Signed: Louisiana Executive Order JML 25-074: environmental permitting review #
Witnessed at Baton Rouge on the 24th day of June 2025. Effective upon signature. The 31 December 2025 report deadline is not a finding that the report was delivered.
· Took effect
Took effect: Rhode Island authorization to participate in nuclear-power procurement #
The history line prints effective June 23, 2025 for both 2025 public laws cited on the page.
· Signed
Signed: Texas HB 14 (2025): Texas Advanced Nuclear Energy Office and development fund #
Texas law signed on 20 June 2025 and effective 1 September 2025. It creates a state nuclear office and fund; it does not license or approve any reactor, which remains the NRC's role.
Announced or first reported · Agreement or program announced
DOE Reactor Pilot Program (DOE-authorized advanced test reactors) #
DOE announced the Reactor Pilot Program on 18 June 2025 to test advanced reactors under DOE authorization, aiming for at least three to reach criticality by 4 July 2026, and selected 11 projects from ten companies on 12 August 2025. DOE reports criticality for Antares's Mark-0 (4 June 2026), Valar's Ward 250 (18 June), Aalo-X (4 July) and Oklo's Groves isotope test reactor, reported on 6 August as critical the night before. DOE also counted Deployable Energy's Unity, critical on 30 June under the Nuclear Energy Launch Pad (which DOE calls the program's next evolution), toward the goal.
· Opened
Opened: DOE Reactor Pilot Program #
Request for applications issued.
· Selections announced
Selections announced: United Kingdom: Great British Energy – Nuclear small modular reactor program and technology selection #
Rolls-Royce SMR selected as preferred bidder.
· Selections announced
Selections announced: United Kingdom: GBE-N selection of, and contract with, Rolls-Royce SMR #
GBE-N chose Rolls-Royce SMR as preferred bidder on 10 June 2025 and announced a signed contract on 13 April 2026. The contract starts design, regulatory engagement and planning for a three-unit project of at least 1.4 GWe ahead of a future investment decision. It is not a license, consent or investment decision.
· Signed
Signed: Oklahoma 2025 chapter 491: nuclear energy feasibility study #
The page prints approval on the 9th day of June, 2025. Senate passage is printed as 22 May 2025 and House passage as 27 May 2025. The emergency clause makes the act effective on passage and approval.
· Provision took effect
Provision took effect: Japan: Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors (Act No. 166 of 1957) #
Revision from Act No. 44 of 2023 enforced; Article 43-3-32 replaced by the long-term facility management plan system.
· Published
Published: Sweden: Act on State Support for Investment in New Nuclear Power (SFS 2025:587) #
Sweden's 2025 Act lets the Government grant state loans for building new nuclear power reactors and two-way contracts for difference for their operation, mainly for reactors totalling at least 300 MW of installed electrical capacity at one site, to a dedicated project company that has already applied for its nuclear and environmental licenses. In force 1 August 2025; it awards support to no one by itself.
Announced or first reported · Agreement or program announced
Constellation evaluation of an advanced reactor or SMR at the Clinton Clean Energy Center (Illinois) #
Announcing its 20-year power deal with Meta for the Clinton plant in June 2025, Constellation said it is evaluating whether to extend Clinton's existing early site permit or seek a new construction permit to pursue an advanced nuclear reactor or SMR at the site. No filing, technology choice or order is recorded.
Announced or first reported · Agreement or program announced
Norsk Kjernekraft and Hexana memorandum on advanced reactor deployment in Norway (2025) #
In June 2025 Norwegian developer Norsk Kjernekraft signed a memorandum with France's Hexana to explore joint deployment of Hexana's sodium-cooled SMR with heat storage in Norway, aimed at industrial decarbonisation. No site or project is named.
Announced or first reported · Agreement or program announced
New York Power Authority program for at least 1 GW of new nuclear in upstate New York (large reactors and/or SMRs) #
Following Governor Hochul's June 2025 directive, the New York Power Authority is developing at least 1 GW of new nuclear capacity in upstate New York, its May 2026 request for qualifications admits large reactors such as the AP1000 and/or SMRs such as the BWRX-300. Eight upstate communities and 23 developers responded to earlier requests for information. No technology, developer or host community has been selected.
Announced or first reported · Agreement or program announced
KHNP and EGAT memorandum on SMR cooperation in Thailand (2025) #
In June 2025 KHNP and EGAT signed a memorandum to exchange SMR technical information, jointly review options for introducing an SMR in Thailand and cooperate on staff training. It does not select a design or site.
· Published
Published: Indiana tax guidance on the SMR manufacturing expense credit #
The bulletin states June 2025, with no publication day. Its "Upon Publication" effective label refers to the bulletin, not a separately verified commencement date of the statute.
Announced or first reported · Agreement or program announced
Hunatom and Rolls-Royce SMR memorandum on potential use of Rolls-Royce SMRs in Hungary #
Hunatom and Rolls-Royce SMR signed a memorandum on the potential use of Rolls-Royce SMR technology in Hungary, Hunatom stresses it is not yet a binding commitment. World Nuclear Association dates it to June 2025. It follows a January 2025 UK-Hungary strategic cooperation focused on SMRs.
· Published
Published: Executive Order 14302: nuclear industrial base #
Directive to federal agencies, signed 23 May 2025. It appropriates no money and makes no project award.
· Published
Published: Executive Order 14301: reactor testing at the Department of Energy #
Directive to DOE, signed 23 May 2025, that led to the DOE Reactor Pilot Program.
· Published
Published: Executive Order 14300: reform of the Nuclear Regulatory Commission #
Directive to the NRC, signed 23 May 2025, with an 18-month target (late November 2026) for final revised rules. It grants no license itself.
· Published
Published: Executive Order 14299: advanced reactors for national security #
Directive to federal agencies, signed 23 May 2025. It sets agency goals; it does not license or approve any particular reactor.
· Design assessment recorded
Design assessment recorded: NRC standard design approval for the NuScale US460 #
The NRC issued a standard design approval to NuScale Power for the US460 small modular reactor design on 29 May 2025, completing its staff technical review. NuScale submitted the application in stages: the first part by letter dated 23 November 2022 and the remaining portions in stages between 29 November and 31 December 2022. The NRC notified NuScale by letter dated 31 July 2023 that the application was acceptable for docketing. The approval lets an applicant reference the design in a construction permit, operating license, combined license or manufacturing license application. It is a design approval only: it grants no permission for any site, construction or operation.
· Issued
Issued: Sweden: Act on State Support for Investment in New Nuclear Power (SFS 2025:587) #
Utfärdad den 28 maj 2025 (Prop. 2024/25:150, bet. 2024/25:NU20, rskr. 2024/25:217).
· Signed
Signed: Executive Order 14302: nuclear industrial base #
Directive to federal agencies, signed 23 May 2025. It appropriates no money and makes no project award.
· Signed
Signed: Executive Order 14301: reactor testing at the Department of Energy #
Directive to DOE, signed 23 May 2025, that led to the DOE Reactor Pilot Program.
· Signed
Signed: Executive Order 14300: reform of the Nuclear Regulatory Commission #
Directive to the NRC, signed 23 May 2025, with an 18-month target (late November 2026) for final revised rules. It grants no license itself.
· Signed
Signed: Executive Order 14299: advanced reactors for national security #
Directive to federal agencies, signed 23 May 2025. It sets agency goals; it does not license or approve any particular reactor.
· Regulatory step
TVA submits construction permit application Part Two (PSAR) #
Announced or first reported · Agreement or program announced
Nucleon and ARC memorandum to explore ARC-100 deployment in Alberta and Texas #
ARC Clean Technology Inc. and Nucleon Energy announced a memorandum to explore ARC-100 deployment at combined-heat-and-power and electricity-only sites under development by Nucleon in Alberta and Texas. The framework covers siting evaluation and progressing toward licensing. It names no site, committed unit count, order or filed application. The partnership it pointed toward was announced in September 2025 as NuARC, a separate record whose initial focus is Alberta.
· Took effect
Took effect: South Carolina section 58-33-196: advanced nuclear study costs #
The official compilation's history line says 2025 Act No. 41 (H.3309), Section 11, effective 12 May 2025. The enrolled act was not opened as a separate document.
· Signed
Signed: South Carolina Act 41 of 2025: Governor's Nuclear Advisory Council #
The bill page records Governor's Action: May 12, 2025, Signed. The act text prints Approved the 12th day of May, 2025.
· Took effect
Took effect: South Carolina Act 41 of 2025: Governor's Nuclear Advisory Council #
Section 46 says this act takes effect upon approval by the Governor. No separate council effective date is printed.
· Regulatory step
NRC dockets Long Mott construction permit application #
Announced · Final investment decision
Ontario announces final investment decision for the first Darlington BWRX-300 #
The Province of Ontario announced its final investment decision on 8 May 2025, giving OPG the go-ahead to build the first BWRX-300 small modular reactor at Darlington. An investment decision is not a construction start.
Checking notes
The Province of Ontario announced its final investment decision on 8 May 2025, giving OPG the go-ahead to build the first BWRX-300 at Darlington.
· Other regulatory action recorded
NRC allows early energy-island work at Kemmerer before a construction permit #
The NRC exempted specified non-safety-related energy-island work, such as piles and foundations, from the rule against construction before a permit. It did not authorize nuclear construction; the construction permit came separately in March 2026.
Federal Register notice: 15 May 2025.
Checking notes
The Federal Register notice (90 FR 20692, 15 May 2025) states that the NRC issued an exemption on 7 May 2025, in response to TerraPower's 28 February 2025 request for US SFR Owner, LLC, modifying the definition of construction for Kemmerer Unit 1. It allows specified work for non-safety-related structures, systems and components on the energy island, such as pile driving and foundations, before a construction permit and without a limited work authorization. It is not a construction permit or operating authority.
Notification received · Regulatory step
ČEZ files environmental assessment notification for Tušimice SMRs #
The notification covers one to six light-water SMRs of up to 1,500 MWe net at the Tušimice coal-plant site; the supplier is not chosen. An environmental assessment step, not a nuclear license application or permit.
Checking notes
The Ministry of the Environment received ČEZ's environmental-assessment notification for a new SMR nuclear source at Tušimice on 6 May 2025 and opened screening the next day. The notification covers one to six light-water SMRs of up to 1,500 MWe net and does not choose a supplier.
Announced or first reported · Agreement or program announced
Latvia Ministry of Climate and Energy informative report on nuclear energy and SMRs #
On 6 May 2025 Latvia's Ministry of Climate and Energy presented the government with an informative report on nuclear energy focused on SMRs, saying Latvia is at an early planning stage and should start with research and capacity building. A 300 MW SMR appears only as a cost example, there is no project or site.
· Construction start
Hermes nuclear safety-related construction begins #
Kairos's 8 May 2025 release says safety-related construction started on 1 May 2025, focused on the building foundation. Its letter to the NRC dated 1 May 2025, required by permit condition 3.D, says excavation for the first drilled pier of the safety-related foundation began that day. Company statements; the first safety-related concrete is a separate event.
· Signed
Signed: Indiana SEA 423 (2025): SMR pilot program and partnerships #
Governor's Bill Watch records the signature.
· First concrete
First nuclear safety-related concrete at Hermes #
Release dated 8 May 2025 reports the pour as completed; exact pour day not stated.
Announced or first reported · Agreement or program announced
Brazil Ministry of Mines and Energy and Rosatom (Tenex) cooperation on uranium and small modular reactors (2025) #
During a May 2025 mission to Russia, Brazil's Ministry of Mines and Energy signed an agreement with Rosatom subsidiary Tenex to map Brazil's uranium potential and the development of small nuclear plants, and the minister said Brazil would form a partnership with Rosatom on small modular reactors. No design, site, order or follow-on agreement has been verified.
· Application submitted
Application for the Clinch River Unit 1 construction permit #
The NRC milestone table records the environmental report (part one) as submitted on 28 Apr 2025 and the preliminary safety analysis report (part two) on 20 May 2025. The application itself is not an issued permission.
Later decision: 28 Sep 2026. Details are in Checking notes.
Checking notes
The Federal Register published this notice on 5 October 2026 at 91 FR 63311. It states that construction permit CPAR-2 was issued to TVA on 28 September 2026 for Clinch River Nuclear Unit 1, is immediately effective, and authorizes construction of a power reactor facility in Roane County, Tennessee. The notice says the conditions in early site permit ESP-006 had been met except those listed in the construction permit. The permit sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, expires on that latest date and does not restate an output rating. TVA announced the permit on 29 September 2026. The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Announced or first reported · Agreement or program announced
Nigeria national nuclear power program evaluating SMRs and large reactors (NAEC, Geregu and Itu candidate sites) #
Nigeria's September 2025 national report to the Convention on Nuclear Safety says the country is evaluating both large reactors and small modular reactors, participates in the US FIRST SMR program, and has Geregu (Kogi State) and Itu (Akwa Ibom) as top candidate sites for nuclear power plants. No SMR technology, vendor or site assignment has been decided.
Announced or first reported · Agreement or program announced
EnergySolutions, Intermountain Power Agency and Utah initiative to explore advanced nuclear, including SMRs, at the… #
EnergySolutions announced in April 2025 an initiative with the Intermountain Power Agency and the State of Utah to explore developing advanced nuclear generation, including potential advanced SMRs, at the Intermountain Power Project site near Delta, Utah. It names no technology, site plan, order or license application.
· Amended
Amended: Russia: Federal Law No. 170-FZ 'On the Use of Atomic Energy' (1995) #
Federal Law No. 98-FZ, the last amendment in the consolidated text read.
· Signed
Signed: Arizona Chapter 56 of 2025: nuclear emergency management fund appropriation #
The chapter prints APPROVED BY THE GOVERNOR APRIL 18, 2025. The same page prints FILED IN THE OFFICE OF THE SECRETARY OF STATE APRIL 21, 2025. The emergency clause says the act is operative immediately as provided by law and does not print a separate calendar operative day.
· Passed
Passed: Tennessee Public Chapter 530: nuclear supply-chain carry-forward #
The act prints PASSED: April 16, 2025, with the House and Senate speakers named. Passage is not the approval day.
· Enacted
Enacted: Arkansas Act 707 of 2025: nuclear generation feasibility study #
The enrolled act prints APPROVED: 4/16/25.
· Took effect
Took effect: Arkansas Act 707 of 2025: nuclear generation feasibility study #
Emergency clause: the act is effective on the date of the Governor's approval. Section 1(a) starts the consultant engagement only within 60 days after the effective date on which the act is funded. The opened act does not show that funding, so the study duty is not recorded as started.
· Signed
Signed: Indiana SEA 424 (2025): SMR development cost recovery #
Governor's Bill Watch records the signature. The enrolled PDF's signature line is blank.
· Issued
Issued: Indiana Executive Order 25-48: Nuclear Indiana Coalition #
Issue date as reported; no signature date was read. The Office of Energy Development's December 2025 annual report says Executive Order 25-48 was issued on 10 April 2025. The order copy opened does not print a legible date, and no separate effective date was read.
· Construction permission recorded
Construction permission recorded: OPG license to construct BWRX-300 #
CNSC issued license to construct PRCL 32.00/2035 for one BWRX-300 on 4 April 2025, valid to 31 March 2035, with regulatory hold points. OPG's application was received on 31 October 2022.
· Recorded development
CNSC grants Darlington construction license #
License to construct one BWRX-300 issued.
· Milestone
Milestone: DOE HALEU Availability Program and HALEU allocation process #
First HALEU amounts announced for five companies.
· Application submitted
Application for the Long Mott construction permit #
Long Mott Energy's construction permit application for four Xe-100 modules at Dow's Seadrift site is dated 31 Mar 2025 and was accepted and docketed by the NRC. The application itself is not an issued permission.
Later decision: 9 Nov 2026. Details are in Checking notes.
Checking notes
Long Mott Energy's construction permit application, dated 31 March 2025, was accepted and docketed by the NRC. NRC news release 26-083 of 9 November 2026 states that the NRC has issued the construction permit for the four-reactor Xe-100 Long Mott Generating Station in Calhoun County, Texas, that staff completed the safety evaluation in October, and that the permit authorizes building the facility but not operation; a separate operating license is required before fuel loading. The release gives no permit number; the permit itself is Construction Permit No. CPAR-3 (ADAMS ML26301A133), issued 9 November 2026, and the Federal Register notice of issuance (91 FR 72925, 12 November 2026) says it is immediately effective and authorizes construction of a power reactor facility in Calhoun County, Texas. The permit sets the earliest construction completion date as 1 July 2033 and the latest as 31 December 2033 and expires on that date. Its conditions include that Long Mott Energy notify the NRC when the site grading design and the passive engineered flooding protection design that may impact site grading are available for NRC staff examination, and that it perform geologic mapping of each foundation excavation for safety-related structures, evaluate it against the site characterization and notify the NRC when it is available for examination; the permit also incorporates an environmental protection plan. It says a license authorizing operation will not be issued unless the applicant submits the complete final safety analysis report, the Commission makes the stated findings on final design and environmental requirements, and the applicant submits proof of financial protection and executes an indemnity agreement. The NRC's project page, updated 12 November 2026, lists the hearing as held on 22 September 2026 and the construction permit decision as 8 November 2026; the permit and the Federal Register notice date issuance to 9 November 2026, and the one-day difference is unexplained in the sources read. Earlier steps: the uncontested (mandatory) hearing was held on 22 September 2026 in Port Lavaca; the Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review supports issuance; NRC issued an environmental assessment and finding of no significant impact plus related exemptions on 18 May 2026. In the contested proceeding, both admitted contentions were dismissed as moot in 2026 and on 7 August 2026 the Commission dismissed the applicant's appeal as moot; on 6 November 2026 the Commission denied the intervenor's separate petition for review (CLI-26-15). The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
· Signed
Signed: Colorado Chapter 45 of 2025: nuclear energy in the clean-energy definitions #
The session law prints Approved: March 31, 2025.
· Recorded development
NPG describes 12 modules and says no contract is signed #
Ghana News Agency: no formal contract had been signed. NPG described 12 modules of 77 MW, totaling 924 MW, and said the location was still being determined.
· Regulatory step
JAEA applies to the NRA to connect a hydrogen production plant to HTTR #
· Signed
Signed: Kentucky Chapter 51 of 2025: nuclear energy development grant appropriation #
The act prints Signed by Governor March 24, 2025. The emergency clause says the act takes effect upon passage and approval by the Governor or upon its otherwise becoming a law.
· Amended
Amended: DOE Generation III+ Small Modular Reactor program #
DOE program with two first-mover selections on 2 December 2025 (TVA and Holtec, up to $400 million each) and eight further selections on 14 May 2026 (more than $94 million for early site permits and supply chains). DOE's program page says applications closed on 23 April 2025.
· Enacted
Enacted: Arkansas Act 373 of 2025: advanced-energy strategic investment rider #
The enrolled act prints APPROVED: 3/20/25.
· Took effect
Took effect: Arkansas Act 373 of 2025: advanced-energy strategic investment rider #
Emergency clause: the enrolled act is effective on the date of the Governor's approval. The current code page returned a server error (HTTP 500) and an empty file, so this status is the enrolled act, not a confirmation that the compiled section still reads this way.
Announced or first reported · Agreement or program announced
Brazilian Microreactor (MNB) technology-development program #
Diamante, Terminus and INB describe a Brazilian microreactor technology-development program involving IEN, IPEN and other research partners. Diamante's project page describes 5 MWe in a 40-foot container. IEN's November 2025 account describes about 5 MWth. These specifications remain unreconciled, and the program's relationship to the HARPIA design is unresolved. This program record does not establish an operating commercial reactor or an authorized deployment.
· Recorded development
Finep approves funding for the Brazilian microreactor project #
Announced or first reported · Agreement or program announced
Opmeer municipality SMR feasibility program (Allseas explored as initiator) #
Opmeer municipality, on its council's instruction, is investigating whether an SMR could be built locally, a feasibility study reported in September 2025 and a follow-up explored an intention agreement with Allseas. On 23 September 2026 the executive chose a broader regional approach. No developer agreement, site decision or permit is recorded.
· Recorded development
First Linglong One reactor operators licensed #
The first 34 people received operator licenses for the Linglong One demonstration unit, as reported from the site by China News Service. Operator licenses are a staffing step, not an operating license for the unit.
Checking notes
China News Service reported on 1 October 2026, from a site visit, that in March 2025 the first 34 people received reactor operator licenses for the Linglong One demonstration unit. Operator licensing is a staffing step; it is not fuel loading, criticality or an operating license for the unit.
· Application submitted
Request for an energy-island construction exemption at Kemmerer Unit 1 #
The recorded request date for the Kemmerer Unit 1 energy-island exemption is 28 Feb 2025. TerraPower filed it for US SFR Owner. The request itself is not an issued permission.
Later decision: 7 May 2025.
Checking notes
The Federal Register notice (90 FR 20692, 15 May 2025) states that the NRC issued an exemption on 7 May 2025, in response to TerraPower's 28 February 2025 request for US SFR Owner, LLC, modifying the definition of construction for Kemmerer Unit 1. It allows specified work for non-safety-related structures, systems and components on the energy island, such as pile driving and foundations, before a construction permit and without a limited work authorization. It is not a construction permit or operating authority.
Announced · Announcement
Last Energy Haskell County PWR-20 campus proposal documented #
Last Energy announced thirty proposed PWR-20 units at one controlled Haskell County campus. The announcement did not specify the electrical gross/net basis; the later NRC pre-application page calls 20 MWe per unit gross. This is one proposed site, not thirty deployment sites, and no early site permit is recorded.
· Introduced
Introduced: Michigan 2025 House Bill 4128: proposed credit for small modular reactor and uprate electricity #
The status page says Representative Greg VanWoerkom introduced the bill on 25 February 2025. The introduced text is not the House-passed substitute.
Announced or first reported · Agreement or program announced
Kärnfull Next Re:Firm South program: candidate SMR sites in Karlshamn, Motala and Västervik #
Kärnfull Next (acquired by Studsvik in March 2026) runs a south-Swedish SMR siting program, Re:Firm South. Beyond its published Valdemarsvik and Nyköping records, it signed landowner agreements for pre-studies at Elleholm and Guö-Köpegårda (Karlshamn) and Stora Askö (Västervik), and a conceptual-study agreement with Motala municipality. Motala says no decision to build has been taken.
Announced or first reported · Agreement or program announced
Ecuador nuclear power plan: first-stage 300 MW modular reactor (Ministry of Energy) #
In February 2025 Ecuador's electricity vice-minister said the government's roadmap would first provide 300 MW of nuclear power through a modular reactor, later followed by a 1 GW plant, with a tender to select a builder planned for 2026. In December 2025 the ministry created a nuclear program implementing organization and set a horizon of about ten years for the first reactor (RNE1). No design, vendor, site or tender award has been announced.
· Recorded development
Kärnfull Next secures permanent land rights for an SMR park at Målma #
Announced · Announcement
Last Energy Llynfi PWR-20 proposal documented #
Four PWR-20 units proposed at the former Llynfi coal station. ONR's 2 February 2026 licensing page, read 5 October 2026, still describes pre-application engagement, not a filed site-license application and not an issued license. The 2027 first-power date is a target.
· Regulatory step
Ministry requests more information on Jimmy's Bazancourt reactor application #
Following ASNR's analysis, the ministry asked Jimmy Energy on 13 February 2025 to complete its creation-authorization file for the Fermi reactor at Bazancourt. A request for information, not a refusal or an authorization.
Checking notes
After ASNR's analysis of the file, the ministry's nuclear-safety mission (MSNR) sent Jimmy Energy requests for further information on the Bazancourt Fermi creation-authorization application on 13 February 2025.
Announced or first reported · Agreement or program announced
TerraPower–nVision Natrium development framework #
TerraPower and nVision Energy announced an agreement to develop a repeatable model for Natrium reactor and energy-storage projects across the United States, combining reactor technology with nVision's project-development and financing work. The announcement commits no units, customer purchase, selected site or license application.
Announced · Announcement
Texas A&M offers RELLIS land to four reactor companies #
Chancellor announced agreements to pursue Kairos, Natura, Terrestrial, and Aalo projects at RELLIS.
Announced or first reported · Agreement or program announced
Singapore government study of nuclear energy and SMRs (no deployment decision, IAEA INIR planned) #
Singapore is studying whether nuclear energy, including SMRs, could suit it in the longer term, EMA commissioned Mott MacDonald to assess the safety and technical feasibility of advanced nuclear technologies. In August 2026 the ministry said no deployment decision has been made, buffer-zone and siting parameters are premature, and an IAEA infrastructure review is planned for the next year.
· Recorded development
Initial Safety Assessment Report (ISAR) review begins #
Announced or first reported · Agreement or program announced
Croatia's Working Group for Nuclear Energy: siting studies and SMR-versus-large comparison #
In February 2025 Croatia's Ministry of the Economy set up a Working Group for Nuclear Energy to prepare studies on potential locations, compare the financial and economic aspects of SMRs with large plants, and draft a legislative framework including an independent regulator. No site or technology decision is recorded.
Announced · Contract
GE Hitachi awards BWXT the reactor pressure vessel contract for the first Darlington BWRX-300 #
GE Hitachi Nuclear Energy awarded BWX Technologies a contract to manufacture the reactor pressure vessel for the first BWRX-300 at the Darlington New Nuclear Project site. A component supply contract under the reactor vendor; it does not make BWXT a construction contractor.
Checking notes
GE Hitachi Nuclear Energy awarded BWX Technologies a contract to manufacture the reactor pressure vessel for the first BWRX-300 at the Darlington New Nuclear Project site.
Announced or first reported · Agreement or program announced
TerraPower–Sabey Data Centers exploratory Natrium memorandum #
TerraPower and Sabey Data Centers announced an MOU to explore Natrium power for Sabey's current and future data-center operations. They identified the Rocky Mountain region and Texas as areas to explore and planned to consider several project structures. The MOU names no selected site, reactor count, purchase commitment or permit application.
Announced · Announcement
AEP Rockport BWRX-300 proposal documented #
Indiana site named for a potential BWRX-300 deployment in an application for federal support. Funding and development remain conditional; no construction start is established.
Announced · Announcement
AEP Joshua Falls SMR proposal documented #
Virginia locality identified for potential advanced nuclear development. Reactor technology remains under assessment; grant and site planning activity are not permission to construct.
Announced · Recorded development
Last Energy accepts a 22 MW grid connection offer for its first Llynfi unit #
Last Energy said it accepted an offer from National Grid Electricity Distribution for 22 MW of export and 3 MW of import capacity for its first unit in South Wales. An accepted connection offer is not a grid connection or a planning or site-license decision.
Checking notes
Last Energy announced on 16 January 2025 that it had accepted a connection offer from National Grid Electricity Distribution for 22 MW of export capacity and 3 MW of import capacity for its first unit in South Wales. An accepted offer is not a physical grid connection.
Announced · Regulatory step
Wyoming siting permit approved for the non-NRC parts of Kemmerer Unit 1 #
TerraPower said Wyoming's Industrial Siting Council approved its permit for construction and operational activities outside NRC jurisdiction. A state siting permit does not cover the nuclear island, which needed the NRC construction permit.
Checking notes
TerraPower announced on 14 January 2025 that the Wyoming Industrial Siting Council had approved its state permit for Kemmerer Unit 1, covering construction and operational activities outside NRC jurisdiction. The Council's order itself is not recorded here.
· Milestone
Milestone: France: Basic nuclear installation (INB) regime, Code de l'environnement, livre V, titre IX #
The ASNR, created by the law of 21 May 2024 from the ASN and IRSN, started on 1 January 2025.
Announced or first reported · Agreement or program announced
ULC-Energy and Chiltern Vital Group letter of intent on SMR-powered clean-energy clusters at UK business parks #
In January 2025 ULC-Energy and Chiltern Vital Group signed a letter of intent to collaborate on clean-energy solutions for CVG business parks, initially the Berkeley Science and Technology Park and the Yorkshire Energy Park. CVG says it intends to encourage the roll-out of Rolls-Royce SMRs at a Berkeley campus. No plant, unit count or license application is recorded.
Announced or first reported · Agreement or program announced
Texas Tech, Abilene Christian University, Natura Resources and Texas Produced Water Consortium molten-salt-reactor… #
Texas Tech, ACU, Natura and the Texas Produced Water Consortium announced a research memorandum in January 2025, backed by a state appropriation to Texas Tech and subaward to ACU. An earlier Natura release of 24 July 2024 described collaboration to examine reactor deployment for produced-water treatment. It was not the later memorandum or a deployment decision. The existing ACU MSR-1 is a separate project.
· Signed
Signed: Tennessee Public Chapter 530: nuclear supply-chain carry-forward #
The approval line prints APPROVED, the year 2025, and Governor Bill Lee. The day and month are not legible in the opened extract.
· Construction start
Oklo-reported Aurora-INL construction start #
Company statement. DOE CX-035336 (Dec 2025) covered non-nuclear site/support construction with no reactor components; do not read as nuclear construction.
Reported · Recorded development
NuScale says FEED Phase 2 work for RoPower finished in late 2025 #
NuScale said its work supporting Fluor's FEED Phase 2 services for RoPower was completed in late 2025. A company statement in a financial release. It does not establish acceptance of the FEED results or that investment-decision conditions were met.
Checking notes
NuScale's third-quarter 2026 results say its work associated with Fluor's front-end engineering and design Phase 2 services for the RoPower project was completed in late 2025, with no comparable activity in 2026. The source gives no completion day.
· Enacted
Enacted: North Dakota 2025 House Bill 1025: advanced nuclear study and appropriation #
The enrolled print is the 2025 regular session. The signature lines are blank. The overview prints Signed on 04/18 and Filed with Secretary of State 04/16, so no day is stored.
· Recorded development
Natura (MSR-1) selected for DOE's Reactor Pilot Program #
· Enacted
Enacted: Montana legislative conditions for uranium conversion and enrichment #
History: enacted as section 1, Chapter 503, Laws of 2025. The compilation prints no calendar day.
· Enacted
Enacted: Louisiana Act 462 of 2025: green energy includes nuclear reactors #
The enrolled header prints 2025 Regular Session and ACT No. 462. The APPROVED line does not print a day, so no signature day is stored.
· Enacted
Enacted: Louisiana Act 111 of 2025: small modular reactor environmental permitting #
The PDF is the 2025 regular session enrolled Act No. 111. The APPROVED line is blank, so no day is stored.
· Issued
Issued: Russia: General Scheme for the placement of electric power facilities to 2042 (Government Order No. 4153-r, 2024) #
Russia's General Scheme for the placement of power facilities to 2042, approved by Government Order No. 4153-r of 30 December 2024, lists planned nuclear plants including small plants at Norilsk, Ust-Kuyga (Yakutia) and in Chukotka, the Baimsky floating power units and the BREST-OD-300 unit at Seversk. Several small-plant entries depend on consumer agreements. It is a planning document, not a construction decision or license.
Announced · Recorded development
Fuel plant for BREST-OD-300 enters pilot operation #
Rosatom said the on-site nitride-fuel module began pilot operation, making mock-up assemblies with depleted uranium. Uranium-plutonium fuel production awaited regulator approval; no first-core fuel is recorded as made.
Checking notes
Rosatom announced on 25 December 2024 that the on-site module for fabricating and refabricating BREST-OD-300 nitride fuel had entered pilot-industrial operation and had made mock-up fuel cassettes with depleted-uranium nitride pellets under a Rostekhnadzor license of 29 March 2024. Production of uranium-plutonium nitride fuel awaited regulatory approval to handle plutonium. The date is the release date.
· Amended
Amended: Uzbekistan: Presidential Resolution PP-188 on the Atomic Energy Agency and its development fund (2024) #
Decree UP-224 reworded the fund's dividend source.
Announced · Recorded development
EXIM letter of interest for $103.7 million toward a Last Energy microreactor in South Wales #
Last Energy said EXIM issued a non-binding letter of interest to carry out due diligence on $103.7 million of financing for its first planned microreactor in South Wales. A letter of interest is not a financing commitment.
Checking notes
Last Energy announced on 13 December 2024 that the Export-Import Bank of the United States had issued a non-binding letter of interest. The letter confirms EXIM's willingness to carry out due diligence on $103.7 million of financing for a Last Energy microreactor planned in South Wales. It is not a loan commitment.
Announced or first reported · Agreement or program announced
BWXT Canada and Westinghouse AP300/AP1000 component-manufacturing memorandum #
BWXT Canada and Westinghouse signed a memorandum on 12 December 2024 covering potential AP300 and AP1000 component manufacture in Canada and globally. Prospective work includes vessels, steam generators and heat exchangers. Definitive manufacturing agreements remain necessary. No component order, selected reactor site or construction is established. AP1000 is large-reactor context.
Announced or first reported · Agreement or program announced
NANO Nuclear and DOE Idaho Operations Office memorandum to evaluate siting ZEUS and ODIN prototypes at INL #
NANO Nuclear and the DOE Idaho Operations Office signed a five-year memorandum of understanding in December 2024 to evaluate the feasibility of siting, building, operating and decommissioning NANO's ZEUS and ODIN experimental microreactors at Idaho National Laboratory. It is an evaluation framework, not a siting decision or license.
Announced or first reported · Agreement or program announced
USTDA grant to Bulgarian Energy Holding for SMR design-option and site evaluation #
In December 2024 USTDA signed a grant with state-owned Bulgarian Energy Holding for a technical analysis of US SMR design options, an examination of potential plant sites and an implementation and financing roadmap. No site or vendor has been chosen.
Announced or first reported · Agreement or program announced
Terrestrial Energy and EnergySolutions memorandum to site IMSR plants at EnergySolutions-owned sites #
Terrestrial Energy and EnergySolutions signed a memorandum of understanding in December 2024 to collaborate on siting and deploying Integral Molten Salt Reactor plants at EnergySolutions-owned sites, such as the former Kewaunee plant in Wisconsin, and to select the most suitable site. No IMSR site has been selected, EnergySolutions' later Kewaunee licensing notice with WEC Energy Group names no technology.
Announced or first reported · Agreement or program announced
Rosatom small nuclear power plant program (62 small reactors by 2039, four more floating plants) #
Rosatom's corporate newspaper reported in December 2024 that Rosatom plans to build 62 small-NPP reactors by 2039, about 18 of them for floating plants, and in August 2026 a Rosatom director said four more floating plants are planned. These are unsited program statements, sited projects are recorded separately.
· Recorded development
Regional councils report the Energy Ministry's interim reply holding the Vardø assessment program #
On 22 November 2024 the Øst-Finnmark and Vest-Finnmark regional councils reported that the Energy Ministry's interim reply of 1 October had put the Vardø assessment program on hold pending the Aure and Heim hearing, and backed the municipality's objection. The event date is the councils' letter date; the ministry's reply was not opened. Subsequent status is not established by these documents; this report grants no project permission.
· Construction permission recorded
Construction permission recorded: Kairos Hermes 2 construction permit #
The NRC issued construction permits CPTR-7 and CPTR-8 for the two-unit Hermes 2 test reactor facility on 21 November 2024. Operation needs separate operating licenses.
Announced or first reported · Agreement or program announced
ENEC and ADNOC agreement to assess SMRs and advanced reactors for ADNOC operations #
In November 2024 ENEC and ADNOC signed a strategic collaboration agreement to evaluate deploying advanced nuclear technology such as SMRs for ADNOC's operations, including a technical and economic assessment of best-fit reactor technologies and studies on using excess Barakah heat. No plant or site is named.
· Application submitted
Application submitted: Calogena CAL30 safety-options requests #
ASNR records a CAL30 safety-options request on 31 October 2024 and further requests through 28 August 2026. Its 19 May 2026 opinion concerns shutdown-system diversification: principles are broadly satisfactory, with stronger electrical diversification, detailed design and qualification evidence, and a simple, robust alternative shutdown means required for possible common-mode rod blockage. These are requirements for a possible future creation-authorization application, not whole-design approval or a Cadarache site permission. The opinion dates the amended letter 19 June 2025, while the earlier listing records 20 June 2025.
· Proposed
Proposed: 10 CFR Part 53: risk-informed, technology-inclusive licensing framework #
The NRC's Part 53 licensing framework took effect on 29 April 2026. It sets how applications may be reviewed; it approves no design, site or reactor.
· Opened
Opened: DOE Generation III+ Small Modular Reactor program #
DOE program with two first-mover selections on 2 December 2025 (TVA and Holtec, up to $400 million each) and eight further selections on 14 May 2026 (more than $94 million for early site permits and supply chains). DOE's program page says applications closed on 23 April 2025.
Announced · Announcement
Amazon to fund Cascade feasibility work, with rights to first-phase power #
Amazon agreed to fund the initial feasibility phase of Energy Northwest's Xe-100 project. Amazon has the right to buy electricity from the first four modules, about 320 MW. It is not a power purchase agreement, investment decision or construction start.
Checking notes
Energy Northwest and Amazon announced an agreement under which Amazon funds the initial feasibility phase of the Xe-100 project near Columbia Generating Station and has the right to purchase electricity from the first four modules (320 MW).
Announced or first reported · Agreement or program announced
Nuclear Fuel Services selection for DOE HALEU deconversion IDIQ #
On 8 October 2024 BWXT reported that Nuclear Fuel Services was selected for DOE HALEU deconversion services under an indefinite-delivery, indefinite-quantity contract. The $2 million minimum ordering guarantee is not a funded task order or proof of cash received. Future orders are competed among awardees. Deconversion is not enrichment or an operating fuel plant.
Announced or first reported · Agreement or program announced
Last Energy PWR-20 licensing engagement with Romania's regulator CNCAN #
In October 2024 Last Energy said CNCAN confirmed it had completed the pre-authorization phase and could enter the authorization phase for its PWR-20. The ENSREG dashboard of March 2026 lists Last Energy's Quantum (60 MWth) in preparatory review in Romania, while the European SMR Industrial Alliance suspended the Quantum project working group in November 2025 pending clarification. No site is named in these sources.
· Proposed
Proposed: Generic environmental impact statement rule for licensing new nuclear reactors #
Proposed rule 89 FR 80797.
· Recorded development
First thorium addition to TMSR-LF1 #
Announced or first reported · Agreement or program announced
KISR preliminary assessment of SMRs for non-electric applications in Kuwait #
KISR researchers presented at the IAEA SMR conference in October 2024 a preliminary assessment of SMRs for non-electric uses in Kuwait, concluding that pressurised-water SMRs suit desalination. Kuwait has no nuclear power infrastructure, this is research, not a government decision or project.
Announced or first reported · Agreement or program announced
Jamaica nuclear energy assessment focused on SMRs (Nuclear Energy Working Committee, CNL/AECL memorandum) #
Jamaica's government is assessing nuclear power through a reconstituted Nuclear Energy Working Committee, building on an October 2024 memorandum with Canadian Nuclear Laboratories and Atomic Energy of Canada Limited that covers SMRs. In June 2026 the science minister said the program's documents converge on SMRs under a build-own-operate-transfer model, but that Jamaica is not about to build a plant, next steps are public consultation, a nuclear cooperation agreement with Canada, IAEA notification and a regulatory framework.
Announced or first reported · Agreement or program announced
Energoatom and the exclusion-zone agency: SMR siting in the Chornobyl exclusion zone (Kopachi, Leliv) #
Since October 2024 Energoatom, Chornobyl NPP and Ukraine's exclusion-zone agency have reviewed areas in the Chornobyl exclusion zone for future SMRs, in May 2025 the agency said it was ready to allocate land and expected an agreement. Its 2025 report says potential sites were proposed near the abandoned villages of Kopachi and Leliv. No design, signed allocation or plant is recorded.
· Design assessment recorded
Design assessment recorded: Korean standard design approval for SMART100 #
The NSSC's 201st meeting approved SMART100's standard design on 26 September 2024. Printed minutes pp.121–123 distinguish standard-design approval from construction permission, direct administrative follow-up on power-system review during later licensing and continued verification improvements, and remove disputed wording asserting that a single off-site power circuit presents no safety impediment. The application date is recorded in the technical agenda. This does not authorize any project, construction or operation, does not approve SMART-C, and is not a Saudi or Canadian license. No separate issued certificate number was opened.
· Construction permission recorded
Construction permission recorded: ACU Molten Salt Research Reactor construction permit #
The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center on its Abilene campus. ACU's application is dated 12 August 2022; the NRC notified ACU by letter dated 18 November 2022 that it was acceptable for docketing. Operation needs a separate operating license.
· Amended
Amended: United Kingdom: Nuclear Installations Act 1965 (c. 57), nuclear site licensing #
Subsections 1(2A)-(2B) (fusion exclusion) and 1(12) (territorial sea) inserted by the Energy Act 2023.
· Recorded development
Haiyang integrated small reactor: regulator siting review opinion issued #
NNSA issued site-selection review opinion No. 2414; a siting opinion, not a construction license.
· Site permission recorded
Site permission recorded: NNSA site-selection review opinion No. 2414, Haiyang integrated small reactor demonstration #
The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2414号) on 10 September 2024 for one 200 MWt integrated natural-circulation small PWR and auxiliary facilities at the southwest corner of the Haiyang nuclear plant site. The opinion agrees that design work may proceed on the stated site parameters.
· Milestone
Milestone: United Kingdom: Great British Energy – Nuclear small modular reactor program and technology selection #
Initial tender phase concluded with four companies down-selected.
Reported · Groundbreaking
Department of Defense breaks ground for Project Pele at Idaho National Laboratory #
DOE reported in September 2024 that the Department of Defense had broken ground on the Project Pele microreactor project at Idaho National Laboratory. Groundbreaking is site work; the reactor is still being built in Lynchburg and has not been fueled.
Checking notes
DOE's article dated 24 September 2024 says the Department of Defense broke ground on the Project Pele microreactor project at Idaho National Laboratory. The article does not state the groundbreaking day. Groundbreaking is site work, not reactor installation or fuel loading.
Announced · Announcement
DOE reports the Ghana VOYGR-12 agreement #
Department of Energy article: one agreement to deploy a single VOYGR-12 plant. Not a construction start and not a signed engineering contract.
Announced or first reported · Agreement or program announced
EGAT and CNNC Overseas memorandum on SMR knowledge exchange (2024) #
On 14 August 2024 EGAT and CNNC Overseas signed a memorandum to exchange knowledge and technology on nuclear plants and study the possibility of using SMRs in Thailand, with CNOS supporting EGAT's SMR preparation. It selects no design or site.
· Issued
Issued: Rwanda: RURA Regulation No 013/2024 governing licensing of nuclear installations #
Regulation dated 30 July 2024; signed at Kigali on 9 August 2024 and in force on signature.
Announced or first reported · Agreement or program announced
NANO Nuclear Energy and Rwanda Atomic Energy Board memorandum on SMRs and microreactors (ZEUS, ODIN) #
NANO Nuclear Energy signed a memorandum of understanding with the Rwanda Atomic Energy Board establishing a framework to facilitate the introduction of small modular reactors and microreactors such as NANO's ZEUS and ODIN designs in Rwanda, plus training and education support. It is a framework memorandum, not an order, no site or schedule is committed in the WNN report.
Began · Regulatory step
NRC pre-application engagement begins for Cascade #
The NRC began pre-application activities with Energy Northwest New Nuclear in August 2024 for a future construction permit application. Pre-application engagement is not an application, review or permit.
Checking notes
The NRC lists pre-application activities with Energy Northwest New Nuclear for a future construction permit application from August 2024. No application has been filed.
· Design assessment: Review completed (not an approval)
Design assessment: Review completed (not an approval): Rolls-Royce SMR UK Generic Design Assessment, Step 2 #
The UK regulators completed Step 2 of their three-step Generic Design Assessment of the Rolls-Royce SMR on 30 July 2024 and issued Step 2 statements. Step 2 began on 3 April 2023, after Step 1 from April 2022 to April 2023. Step 3, the detailed assessment, began in July 2024 and is recorded separately as under way. Completing Step 2 is not a Design Acceptance Confirmation or permission for any site.
· Signed
Signed: Michigan 2024 Public Act 121: targeted energy investment #
The act prints Approved by the Governor on 24 July 2024, filed the same day. The first-page item-veto list does not include section 811.
· Took effect
Took effect: Michigan 2024 Public Act 121: targeted energy investment #
The act prints EFFECTIVE DATE: July 24, 2024.
· Enacted
Enacted: ADVANCE Act of 2024 #
Federal law enacted on 9 July 2024. The NRC applies its reduced advanced-reactor review rate from 1 October 2025. The Act does not license, fund or approve any particular reactor.
· Amended
Amended: Kansas property-tax exemption for certain new electric generation, including nuclear #
The history line prints L. 2024, ch. 81, § 2; July 1, without repeating the year. The effective day is stored as 1 July 2024 from that session-law line.
Signed · Contract
RoPower signs FEED Phase 2 engineering contract with Fluor for Doicești #
Nuclearelectrica and RoPower Nuclear signed the front-end engineering and design Phase 2 contract with Fluor, leading to an updated cost estimate, schedule and safety analyses. An engineering contract, not a construction contract.
Checking notes
Nuclearelectrica and RoPower Nuclear signed the front-end engineering and design Phase 2 contract with Fluor for the Doicești SMR project, covering design and engineering services, an updated cost estimate and schedule, and safety analyses needed for an investment decision.
· Groundbreaking
Kairos breaks ground at the Hermes site #
· Took effect
Took effect: EU: Net-Zero Industry Act (Regulation (EU) 2024/1735) #
Art. 49: in force the day after publication and applies from 29 June 2024.
· Published
Published: EU: Net-Zero Industry Act (Regulation (EU) 2024/1735) #
OJ L series 2024/1735, 28.6.2024.
· Enacted
Enacted: Canada: Clean technology investment tax credit for small nuclear energy property (Income Tax Act s. 127.45) #
Royal Assent to S.C. 2024, c. 15; s. 36 added s. 127.45.
· Signed
Signed: EU: Net-Zero Industry Act (Regulation (EU) 2024/1735) #
Done at Brussels, 13 June 2024.
Reported month · Recorded development
TMSR-LF1 first reaches full power #
A national newspaper reported that the 2 MW thermal experimental molten-salt reactor first ran at full power in June 2024. Thermal operation of a test reactor, not electricity generation.
Checking notes
Economic Daily reported that the 2 MW thorium molten-salt experimental reactor first reached full-power operation in June 2024. The report gives the month, not the day.
Announced or first reported · Agreement or program announced
Steady Energy LDR-50 district-heating market entry in Sweden (with Kärnfull Next partnership) #
In June 2024 Kärnfull Next and Steady Energy formed a strategic partnership to introduce SMRs for district heating in Sweden, and in March 2026 Steady Energy said it was establishing a Swedish presence with a country manager. No Swedish customer, site or order is recorded.
Announced or first reported · Agreement or program announced
Rosatom and Guinea memorandum to study floating nuclear power plants with RITM-200 reactors #
Rosatom signed a memorandum of understanding with Guinea at the St Petersburg International Economic Forum in June 2024 to explore the possible deployment of floating power plants equipped with RITM-200 reactors. It is an exploratory memorandum, no site, number of units or contract was reported.
Announced or first reported · Agreement or program announced
Energoatom and EDF cooperation agreement covering study of NUWARD SMR technology #
In June 2024 Energoatom and EDF signed a cooperation agreement covering study of EDF's EPR and NUWARD SMR technologies and operating-experience exchange. It is a study agreement, no NUWARD site or order is recorded.
· Took effect
Took effect: Uzbekistan: Presidential Resolution PP-188 on the Atomic Energy Agency and its development fund (2024) #
Uzbekistan's 2024 presidential resolution PP-188 organizes the Atomic Energy Agency, including a directorate for building the nuclear power plant, and creates a Fund for Development of the Atomic Energy Use Sphere financed partly by 4% of Navoiyuran dividends that may be spent on tasks for building atomic energy facilities. It names no project and records no disbursement.
· Signed
Signed: Uzbekistan: Presidential Resolution PP-188 on the Atomic Energy Agency and its development fund (2024) #
Uzbekistan's 2024 presidential resolution PP-188 organizes the Atomic Energy Agency, including a directorate for building the nuclear power plant, and creates a Fund for Development of the Atomic Energy Use Sphere financed partly by 4% of Navoiyuran dividends that may be spent on tasks for building atomic energy facilities. It names no project and records no disbursement.
Announced · Announcement
Yakutia: environmental-expert conclusion on Unit 1 license materials reported #
Atom Media reported Rosprirodnadzor approval of a positive environmental-expert conclusion on Unit 1 construction-license supporting materials, including environmental impact assessment. The date is the announcement, not an established decision date. No nuclear construction permit or physical reactor-construction start is inferred.
Announced or first reported · Agreement or program announced
Oklo and Wyoming Hyperscale non-binding letter of intent for 100 MW of Aurora power to a data-center campus #
Oklo and Wyoming Hyperscale signed a non-binding letter of intent in May 2024 outlining their intent to enter a 20-year power purchase agreement for Oklo to supply 100 megawatts from Aurora powerhouses to a Wyoming Hyperscale data-center campus. It is not a binding contract and names no powerhouse site.
· Regulatory step
NRC dockets Kemmerer Unit 1 construction permit application #
Announced or first reported · Agreement or program announced
Idaho Strategic Resources and Radiant memorandum on Kaleidos microreactors at a mine site (2024) #
In May 2024 Idaho Strategic Resources signed a non-binding memorandum with Radiant to join the Kaleidos Frontier Pilot Program, creating a pathway to operate one or more of the first five Kaleidos microreactors at a viable Idaho Strategic site. The two companies agreed to study licensing and operations, no site is named.
Announced or first reported · Agreement or program announced
GPSC and Seaborg (now Saltfoss) memorandum on a CMSR Power Barge study in Thailand (2024) #
In April 2024 Thailand's GPSC and Denmark's Seaborg (now Saltfoss Energy) signed a memorandum to assess how a CMSR Power Barge could be used in Thailand and to scope an initial project, in a study expected to take about four years. A 200-800 MWe barge would be considered only after the studies.
· Environmental decision recorded
Environmental decision recorded: MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit) #
The Ministry of Ecology and Environment approved the siting-stage environmental impact report for Xuwei Phase I on 17 April 2024 (环审〔2024〕43号). The approval describes Phase I as two Hualong One pressurized-water units and one HTR-PM600S high-temperature gas-cooled reactor unit with supporting facilities at Xizoushan, Xuwei New Area, Lianyungang. It is an environmental decision for the siting stage covering the whole Phase I project, of which Unit 3 is the HTGR; it is not a construction license. The Hualong One units are outside SMRMap's scope.
· Signed
Signed: Virginia § 56-585.1:15: Phase I small modular nuclear facility development-cost recovery #
Chapter 836 states that it was approved on 17 April 2024. It lets a Phase I utility seek recovery of small modular nuclear facility development costs, capped at $25 million a year and $125 million overall excluding the site. It does not approve a reactor.
· Signed
Signed: Virginia § 56-585.1:14: Phase II small modular reactor development-cost recovery #
Chapter 789 states that it was approved on 17 April 2024. It lets a Phase II utility ask the State Corporation Commission to recover small modular reactor development costs. It does not approve a reactor.
· Recorded development
Preliminary site survey report finds the site suitable #
· Application submitted
Application for the Natrium construction permit #
The recorded application date for the Natrium construction permit is 28 Mar 2024. The application itself is not an issued permission.
Later decision: 9 Mar 2026. Details are in Checking notes.
Checking notes
The NRC issued construction permit CPAR-1 on 9 March 2026 to US SFR Owner, LLC (TerraPower) for Kemmerer Power Station Unit 1, after the Commission's 4 March 2026 decision on the uncontested hearing. The permit authorizes construction only; an operating license is a separate NRC decision.
· Recorded development
IAEA expert mission on CDE safety analysis and design safety features #
· Completed
Completed: France: France 2030 call for projects « Réacteurs nucléaires innovants » (first call) #
Last three laureates announced, closing the examination of applications to the first call.
· Recorded development
NRC issues environmental assessment and FONSI for the ACU construction permit #
Announced or first reported · Agreement or program announced
Sri Lanka nuclear power program roadmap and siting (SMR capability considered) #
Sri Lanka's Cabinet committed in March 2024 to a nuclear power planning program, and the Atomic Energy Board's roadmap aims for a bid invitation by 2027 and plant operation by 2034. The roadmap took account of the ability to build SMRs, and six candidate sites from three regions have been identified for evaluation. No technology, vendor or site has been selected.
Announced or first reported · Agreement or program announced
Serbia's goal of 1,200 MW from small modular reactors (four SMRs) #
In March 2024 President Vučić said Serbia was seeking international support to reach 1,200 MW of capacity from small modular reactors. In December 2024 the National Assembly ended the 35-year prohibition on building nuclear plants. No site, vendor or project is recorded.
Announced or first reported · Agreement or program announced
Prodigy Clean Energy and Des Nëdhé Group memorandum on transportable microreactor plants for remote Canada #
Prodigy Clean Energy and the Indigenous economic development corporation Des Nëdhé Group signed a memorandum of understanding to explore using Prodigy's transportable microreactor plants to power remote mines and communities in Canada and to pursue Indigenous ownership and workforce roles. It names no site, order or license application, Prodigy's separate Belledune commercial pilot is recorded as its own project.
Announced or first reported · Agreement or program announced
Iraq's consideration of SMRs and small-reactor cooperation talks with Russia #
During an IAEA visit in March 2024 Iraq said it was looking at options such as SMRs for energy security and desalination. World Nuclear Association reports that in 2025 the head of Iraq's atomic energy commission announced cooperation being developed with Russia on small reactors for electricity, though no agreements had been signed.
· Recorded development
HTTR full-power thermal safety demonstration #
JAEA's August 2026 symposium slides show an achieved March 2024 safety demonstration at 100% reactor power (30 MW thermal). This is thermal testing, not electricity generation, commercial service or a hydrogen-coupling permission. The source gives the month, so no exact day is assigned.
· Took effect
Took effect: Michigan 2023 Public Act 235: nuclear generation in the clean-energy standard #
The act page prints EFFECTIVE DATE: February 27, 2024.
Announced · Announcement
Community Nuclear Power North Teesside AP300 proposal documented #
Private proposal for four AP300 units in North Teesside. A 2027 site-license date and operation in the 2030s are targets, not completed authorizations.
· Took effect
Took effect: Missouri PSC order on Wolf Creek decommissioning costs #
The order says it shall be effective on February 3, 2024.
· Contract
Oklo SODI land option for two Ohio powerhouses #
Option and right of first refusal for two powerhouses at the former Portsmouth site. Later company materials describe a larger phased campus on this same effort.
Announced or first reported · Agreement or program announced
Slovenia SMR option studies: US Project Phoenix pre-feasibility support and GEN energija SMR assessment #
In February 2024 Slovenia was selected for US Project Phoenix support to complete a pre-feasibility study for potential future SMR deployment. In November 2024 GEN energija said it would intensify study of SMRs alongside the large JEK2 project. At a May 2026 event the Šoštanj thermal plant site was mentioned as a potential SMR location, no decision has been taken.
Announced or first reported · Agreement or program announced
Capital Power and Ontario Power Generation assessment of grid-scale SMRs for Alberta #
Capital Power and Ontario Power Generation agreed in January 2024 to jointly assess developing and deploying grid-scale small modular reactors in Alberta, including ownership and operating structures. Capital Power's 2025 annual information form says the first funded pre-feasibility phase is complete and the partners extended their collaboration for two more years, no site, reactor design or order is recorded.
· Issued
Issued: Missouri PSC order on Wolf Creek decommissioning costs #
Issue date printed on the order: January 4, 2024.
Reported October 2024 · Recorded development
US EXIM approves a USD 98 million loan for Doicești pre-project services #
The US Export-Import Bank's board approved a final commitment for a USD 98 million loan for pre-project services for the Doicești NuScale SMR. Pre-project financing, not construction financing.
Checking notes
The US Export-Import Bank's board approved a final commitment for a USD 98 million loan under its Engineering Multiplier Program for pre-project services for the first NuScale SMR in Romania; World Nuclear News reported it on 2 October 2024.
· Application submitted
Application submitted: Jimmy Bazancourt creation-authorization application #
ASNR records Jimmy's 2024 creation-authorization application for an industrial-heat reactor at a Cristal Union factory in Bazancourt. Published filing dates differ across the project sources, so the stored submission date remains at year precision. MSNR requested further information on 13 February 2025. Jimmy submitted an updated design and the remaining answers on 23 July 2026, and MSNR referred that updated file to ASNR for review on 24 July 2026. These sources do not record an issued creation authorization.
· Took effect
Took effect: Emergency preparedness rule for small modular reactors and other new technologies #
Final NRC rule in effect since 18 December 2023 offering SMRs and other new technologies an alternative emergency preparedness framework. It approves no emergency plan for any site.
· Construction permission recorded
Construction permission recorded: Kairos Hermes 1 construction permit #
The NRC issued construction permit CPTR-6 for the Hermes non-power test reactor on 14 December 2023. A 13 May 2026 order extended the latest construction completion date from 31 December 2026 to 30 April 2029. Operation needs a separate operating license.
· Provision took effect
Provision took effect: Ukraine: Regulation on the State Nuclear Regulatory Inspectorate (Cabinet of Ministers Resolution No. 363 of 20 August 2014, Положення про Державну інспекцію ядерного регулювання України) #
Subpoints 1 and 3 of point 1 of the 2023 changes (radiation protection expert competence, training and knowledge checks) took effect on 11 December 2023 (Resolution No. 268, point 2).
Announced · Announcement
OSGE Ostrołęka BWRX-300 proposal documented #
One of six locations named in OSGE decisions in principle. Further regulatory applications are required; this is not a construction license. The 24-unit fleet total does not establish a site module count.
Announced · Announcement
OSGE Kraków / Nowa Huta BWRX-300 proposal documented #
One of six locations named in OSGE decisions in principle. Further regulatory applications are required; this is not a construction license. The 24-unit fleet total does not establish a site module count.
Announced · Announcement
OSGE Dąbrowa Górnicza BWRX-300 proposal documented #
One of six locations named in OSGE decisions in principle. Further regulatory applications are required; this is not a construction license. The 24-unit fleet total does not establish a site module count.
· Commercial operation
HTR-PM commercial operation #
Commercial operation reported for HTR-PM.
Announced or first reported · Agreement or program announced
JAEC and KHNP memorandum for a feasibility study of an i-SMR in Jordan #
The 5 December 2023 JAEC–KHNP memorandum was reported as covering a comprehensive technical and economic feasibility study for KHNP's i-SMR in Jordan. In a release datelined 9 April 2025, KHNP described a joint pre-feasibility study as under way under that agreement. The terminology differs, and the update establishes neither study completion nor current activity. No site or order is recorded.
Announced or first reported · Agreement or program announced
ENEC ADVANCE program for advanced reactors and its COP28 SMR memoranda #
Around COP28 in December 2023 ENEC launched a program to evaluate advanced reactors, later named ADVANCE, and signed memoranda with MoltexFLEX, X-energy and USNC, after earlier MoUs with GE Hitachi (BWRX-300), TerraPower (Natrium) and Westinghouse. These are evaluation agreements, no plant, site or order is recorded.
Executive summary dated · Design assessment: Review completed (not an approval)
CNSC lists a completed vendor design review of the Xe-100 #
CNSC lists combined Phases 1 and 2 of its pre-licensing vendor design review of the Xe-100 as completed, with an executive summary dated December 2023. A vendor design review does not certify a design or issue a license.
Checking notes
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of X-energy's Xe-100 among its completed reviews, with an executive summary dated December 2023. CNSC entered into the agreement with X-energy to conduct the review on 20 July 2020; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
· Signed
Signed: Michigan 2023 Public Act 235: nuclear generation in the clean-energy standard #
Approved by the Governor on 28 November 2023 and filed with the Secretary of State on 29 November 2023.
Announced or first reported · Agreement or program announced
Saskatchewan Research Council microreactor demonstration program (installation paused) #
In November 2023 the Government of Saskatchewan announced $80 million for the Saskatchewan Research Council to pursue licensing and demonstration of a first Westinghouse eVinci microreactor, with the location to be determined during regulatory processes. In April 2026 SRC told the Legislative Assembly's Economy Committee that Westinghouse had canceled the eVinci project and that SRC had put the reactor installation on pause while it continues to follow other microreactor technologies. No site, license application or construction was recorded.
· Published
Published: Emergency preparedness rule for small modular reactors and other new technologies #
Final NRC rule in effect since 18 December 2023 offering SMRs and other new technologies an alternative emergency preparedness framework. It approves no emergency plan for any site.
· Cancellation
UAMPS CFPP canceled #
UAMPS and NuScale announced mutual termination on 8 November 2023. NRC recorded a 10 November 2023 withdrawal letter and suspended its review on 13 November 2023.
Announced or first reported · Agreement or program announced
Meralco and Ultra Safe Nuclear micro-modular reactor pre-feasibility study (2023, ended) #
In November 2023 Meralco signed a cooperation agreement with Ultra Safe Nuclear Corporation for a four-month pre-feasibility study of deploying one or more Micro-Modular Reactor systems in the Philippines. The World Nuclear Association reports that the cooperation ended after USNC's October 2024 bankruptcy filing. No project followed.
Announced or first reported · Agreement or program announced
KHNP, ARC Clean Technology and NB Power collaboration on global ARC-100 fleet deployment (2023-2024) #
After a November 2023 memorandum, KHNP, ARC Clean Technology and NB Power signed a collaboration agreement in May 2024 aimed at teaming agreements for global ARC-100 fleet deployment, starting with the demonstration unit planned at Point Lepreau, New Brunswick. It sets deliverables for discussions on participation and possible investment, it is not an order.
Announced or first reported · Agreement or program announced
DL E&C and Saline Water Conversion Corporation memorandum on SMRs for desalination #
On 22 October 2023 South Korea's DL E&C and Saudi Arabia's Saline Water Conversion Corporation signed a memorandum, reported by the Korea Economic Daily, to explore using SMRs in desalination plants and to research SMR-based hydrogen and ammonia production. No design, plant or site is named.
· First criticality
TMSR-LF1 first criticality #
TMSR-LF1 first criticality, dated 11 October 2023 by World Nuclear News and the IAEA Research Reactor Database. Operating license 2307 sets the first approach to criticality as a hold point to be released by the Ministry of Ecology and Environment's Northwest Nuclear and Radiation Safety Supervision Station; no release document was opened.
· Enacted
Enacted: North Carolina G.S. 62-133.8: clean energy portfolio standard #
Session Law 2023-138 became law notwithstanding the Governor's objections at 1:29 p.m. on 10 October 2023. The current compilation also cites 2025-25, s. 29(5), which was not opened, so this is not a single effective date for every sentence of the current section.
Announced or first reported · Agreement or program announced
Southern Infrastructure and Kaizen ANZ letter of intent for a 40 MW thorium STGR20 reactor in the Philippines (2023) #
On 9 October 2023 in Adelaide, the Philippine Trade Secretary witnessed a letter of intent by Australia's Southern Infrastructure, with Kaizen ANZ, to develop an initial 40 MW thorium-fueled STGR20 gas-cooled reactor in the Philippines. The developer describes STGR20 as a scalable SMR. No host, site or license application is recorded.
Announced · Announcement
NuScale announces the Standard Power Pennsylvania facility #
Announcement of one Pennsylvania facility. The 24-module and 1,848 MWe figures are combined with Ohio and are not stored on this record.
Announced · Announcement
NuScale announces the Standard Power Ohio facility #
Announcement of one Ohio facility. The 24-module and 1,848 MWe figures are combined with Pennsylvania and are not stored on this record.
· Took effect
Took effect: Ohio Revised Code Chapter 4164: Nuclear Development Authority #
The official chapter page marks each displayed section effective 3 October 2023 and names House Bill 33 of the 135th General Assembly. The enrolled bill was opened on 4 October 2026 and lists these sections. An approval line was not isolated, so this effective date is unchanged.
Announced or first reported · Agreement or program announced
Rosatom early study of an additional modernised floating power unit for Pevek (Chukotka request) #
In October 2023 Rosatom told Kommersant it was studying, at the Chukotka administration's request, the supply of an additional modernised floating power unit to Pevek, and that the work was at a very early stage. No decision has been recorded, the four 106 MW units cited by officials in 2026 are the existing Baimsky project.
Announced or first reported · Agreement or program announced
BWXT and Wyoming Energy Authority contract to assess BANR microreactor deployment in Wyoming #
BWXT announced a two-phase Wyoming Energy Authority microreactor viability contract in September 2023. Its 17 June 2024 phase-two award covers conceptual design, regulatory planning, a fleet model and supply-chain demonstrations. Approximately $20 million is the total cost-share program value, not phase-two cash received. This is a study contract, not a selected site, reactor order or license.
· Regulatory step
NRC dockets Hermes 2 construction permit application #
Announced or first reported · Agreement or program announced
KAERI and AECL memorandum seeking a SMART demonstration at an AECL-owned site in Canada #
KAERI and Atomic Energy of Canada Limited signed a memorandum of understanding in September 2023 on civilian nuclear R&D, KAERI said the partnership seeks a demonstration of its SMART reactor at an AECL-owned, CNL-managed site, building on Hyundai Engineering and KAERI's effort to bring SMART to Canada. No site, agreement to build or license application has been published.
Announced or first reported · Agreement or program announced
US Project Phoenix coal-to-SMR feasibility study for Slovakia (four sites found suitable) #
Slovakia was selected in September 2023 for US Project Phoenix support for a coal-to-SMR feasibility study, carried out by Sargent & Lundy with the Ministry of Economy and Slovenské elektrárne. The study, reported in January 2026, found Bohunice, Mochovce, Vojany and the US Steel Košice site all meet baseline SMR criteria. It selects no technology and creates no project.
Announced or first reported · Agreement or program announced
Pertamina NRE and Seaborg (now Saltfoss) memorandum on a CMSR Power Barge in Indonesia (2023) #
In September 2023 Pertamina NRE signed a memorandum with Denmark's Seaborg (now Saltfoss Energy) to assess deployment of the CMSR Power Barge in Indonesia and scope an initial project. A barge of 200-800 MWe would be considered only after the studies. No site, order or license followed in the sources read.
Announced or first reported · Agreement or program announced
Nuclep and Rosatom Energy Projects memorandum on large and smaller nuclear projects, including SMR manufacturing (2023) #
At the IAEA General Conference in Vienna in September 2023, Brazilian state equipment maker Nuclep and Rosatom Energy Projects signed a memorandum of understanding for the Russian side to develop large and smaller nuclear projects with Nuclep, Nuclep's commercial director said it could let Nuclep lead SMR production in Brazil. It is a memorandum only, with no design, site or order.
Announced or first reported · Agreement or program announced
Energoatom and Westinghouse memorandum on AP300 SMR deployment in Ukraine #
In September 2023 Energoatom and Westinghouse signed a memorandum on developing and deploying AP300 SMRs in Ukraine, alongside a separate AP1000 agreement. No AP300 site or order is recorded.
· Recorded development
RAEB and Dual Fluid sign the CDE cooperation agreement #
· Amended
Amended: Romania: Law 111/1996 on the safe conduct, regulation, licensing and control of nuclear activities #
Consolidation records Law 234/2023 changes, including art. 8(8^1), as applying from 19 August 2023.
Announced or first reported · Agreement or program announced
Rosatom list of prospective Arctic sites for SHELF-M microreactor plants (Yakutia, Krasnoyarsk, Chukotka) #
In August 2023 Rosatom named five prospective sites for SHELF-M small nuclear plants: the Sovinoe deposit (Chukotka), the Agylki deposit and Batagay (Yakutia), and Baikit and Bolshevik Island (Krasnoyarsk). Krasnoyarsk officials said they intended to sign an agreement for a first plant at Baikit by 2035. Only Sovinoe has advanced to a project record.
Announced or first reported · Agreement or program announced
JAVYS and Westinghouse memoranda on AP300 SMR (and AP1000) deployment in Slovakia #
On 17 July 2023 JAVYS and Westinghouse announced non-exclusive memoranda on potential AP1000 and AP300 deployment, providing a framework for technical and development plans. The announcements establish no AP300 site or order. The AP1000 part is outside SMR scope, and generic AP300 timelines are not Slovak deployment milestones.
· Application submitted
Application for the Hermes 2 construction permits #
The recorded application date for the Hermes 2 construction permits is 14 Jul 2023. The application itself is not an issued permission.
Later decision: 21 Nov 2024. Details are in Checking notes.
Checking notes
The NRC issued construction permits CPTR-7 and CPTR-8 for the two-unit Hermes 2 test reactor facility on 21 November 2024. Operation needs separate operating licenses.
· Opened
Opened: United Kingdom: Great British Energy – Nuclear small modular reactor program and technology selection #
Contract notice and selection questionnaire.
Announced or first reported · Agreement or program announced
Norsk Kjernekraft and Seaborg (now Saltfoss) letter of intent on CMSR deployment in Norway (2023) #
In July 2023 Norsk Kjernekraft and Seaborg (now Saltfoss Energy) signed a letter of intent to investigate deploying Seaborg's compact molten salt reactor in Norway, as a longer-term option after conventional SMRs. No site or project is named.
Announced or first reported · Agreement or program announced
Japan's HTGR demonstration reactor program (METI/ANRE, MHI core company, site not selected) #
Japan's government plans a high-temperature gas-cooled demonstration reactor for hydrogen production, targeted to operate in the 2030s, METI's ANRE selected MHI in July 2023 as core company for its design and construction. The conceptual specification is about 200 MWt. Site selection and the implementing body have not been decided, although Ibaraki Prefecture has asked to host it.
· Application submitted
Application submitted: NB Power license to prepare site application #
Site preparation license application for ARC-100.
· Milestone
Milestone: France: France 2030 call for projects « Réacteurs nucléaires innovants » (first call) #
First call closed.
· Published
Published: France: Loi n° 2023-491 du 22 juin 2023 (accélération des procédures nucléaires près des sites existants) #
Journal officiel n° 144 du 23 juin 2023.
· Enacted
Enacted: France: Loi n° 2023-491 du 22 juin 2023 (accélération des procédures nucléaires près des sites existants) #
Loi n° 2023-491 du 22 juin 2023, after Constitutional Council decision 2023-851 DC of 21 June 2023.
· Operating authority recorded
Operating authority recorded: TMSR-LF1 operating license 2307 #
NNSA issued operating license 国核安证字第2307号 to SINAP on 7 June 2023, expiring 6 June 2033. The instrument includes separate commissioning hold points; it does not prove their release.
· Amended
Amended: Japan: Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors (Act No. 166 of 1957) #
Act No. 44 of 2023 (GX decarbonized power supply act) promulgated.
Announced or first reported · Agreement or program announced
Gazprom study of four floating nuclear power units for the Tambey field cluster (Yamal) #
Kommersant reported in June and October 2023 that Gazprom was studying four floating nuclear power units, about 400 MW in total, to supply the Tambey cluster of fields on Yamal. It is an option under study, no decision, order or berth has been recorded.
· Regulatory step
Rostekhnadzor issues Rosenergoatom a siting license for the Yakutia land-based SMR (Ust-Yansky ulus) (reported) #
Rosatom corporate newspaper report; license instrument not opened. URL slug says 'construction' but text says siting (razmeshchenie). Station-level siting license; Feb 2026 hearings covered unit-level siting-license materials for Units 1 and 2.
Announced or first reported · Agreement or program announced
Energoatom and Holtec cooperation agreement for up to 20 SMR-160 plants in Ukraine #
On 21 April 2023 Energoatom and Holtec signed a cooperation agreement envisaging an SMR-160 pilot and an execution plan for up to 20 more SMR-160 plants in Ukraine, focusing on former coal sites, plus local manufacturing. A December 2024 Energoatom statement describes plans for an SMR-300 component plant. No license or construction is recorded.
· Milestone
Milestone: Canada: Enabling Small Modular Reactors Program (Natural Resources Canada) #
Application period closed.
· Amended
Amended: Indiana Code 8-1-8.5-12.1: small modular nuclear reactor certificates #
Caucus release: SEA 176 signed; it reports the capacity limit raised from 350 MW to 470 MW. Not the code text.
Executive summary dated · Design assessment: Review completed (not an approval)
CNSC lists Phase 2 of its IMSR400 vendor design review as completed #
CNSC lists Phase 2 of its pre-licensing vendor design review of the IMSR400 as completed, with an executive summary dated April 2023. A vendor design review does not certify a design or issue a license.
Checking notes
CNSC lists Phase 1 (executive summary dated November 2017) and Phase 2 (executive summary dated April 2023) of its pre-licensing vendor design review of Terrestrial Energy's IMSR400 among completed reviews. CNSC entered into the Phase 2 agreement with Terrestrial Energy on 9 May 2018; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barrier to licensing within the reviewed topics and required further design and safety work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
Announced or first reported · Agreement or program announced
ARC and Invest Alberta commercialization memorandum #
ARC Clean Technology Canada and Invest Alberta announced a memorandum to support commercialization of the ARC-100 in Alberta, including operations expansion and supply-chain development toward a possible fleet. This is a commercialization objective, with no site, unit count, reactor order or license identified in the announcement.
Announced or first reported · Agreement or program announced
Energoatom and Rolls-Royce SMR memorandum on SMR deployment for Ukraine's recovery #
On 20 March 2023 Energoatom and Rolls-Royce SMR signed a memorandum to explore deploying Rolls-Royce SMRs in Ukraine as it rebuilds. No site or order is recorded.
· Amended
Amended: Ukraine: Regulation on the State Nuclear Regulatory Inspectorate (Cabinet of Ministers Resolution No. 363 of 20 August 2014, Положення про Державну інспекцію ядерного регулювання України) #
Resolution No. 268 of 10 March 2023 amends points 4 and 5. It is in force on publication, and the publication date is not shown on the page.
Announced or first reported · Agreement or program announced
Last Energy power purchase agreement for ten 20 MWe plants in the Katowice Special Economic Zone #
Last Energy agreed with the Katowice Special Economic Zone to develop ten of its 20 MWe micro nuclear plants, selling power under PPAs to zone investors, World Nuclear News reported the deal in March 2023. No specific plant site, decision in principle or license application is recorded.
Executive summary dated · Design assessment: Review completed (not an approval)
CNSC lists a completed vendor design review of the BWRX-300 #
CNSC lists combined Phases 1 and 2 of its pre-licensing vendor design review of the BWRX-300 as completed, with an executive summary dated March 2023. A vendor design review does not certify a design or issue a license.
Checking notes
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
Announced · Announcement
ČEZ names Tušimice a preferred SMR site #
ČEZ tentatively chose the site after a preliminary assessment and began exploration for faults, groundwater and bedrock. Site suitability was not yet established; no vendor, unit count or application.
Checking notes
ČEZ said on 27 February 2023 that, after a preliminary assessment, it had tentatively identified Tušimice and Dětmarovice as preferred sites for further small modular reactors after Temelín, and that exploration of the power-plant sites for active faults, hydrogeology and bedrock had begun in the first half of February. It said suitability would be clear only after further exploration.
Announced · Announcement
ČEZ names Dětmarovice a preferred SMR site #
ČEZ tentatively chose the site after a preliminary assessment and began exploration for faults, groundwater and bedrock. Site suitability was not yet established; no vendor, unit count or application.
Checking notes
ČEZ said on 27 February 2023 that, after a preliminary assessment, it had tentatively identified Dětmarovice and Tušimice as preferred sites for further small modular reactors after Temelín, and that exploration of the power-plant sites for active faults, hydrogeology and bedrock had begun in the first half of February. It said suitability would be clear only after further exploration.
· Took effect
Took effect: South Korea: Innovative SMR (i-SMR) Technology Development Programme (혁신형 소형모듈원자로 기술개발사업) #
Joint operation and management directive in force (MSIT Directive No. 227, MOTIE Directive No. 246).
· Design assessment recorded
Design assessment recorded: NRC design certification of the NuScale US600 #
The NRC lists the NuScale US600 among its issued design certifications. NuScale filed the application by letter dated 31 December 2016; the NRC lists it as tendered in December 2016, with the submission completed in January 2017. The certification rule, Appendix G to 10 CFR Part 52, was published on 19 January 2023 (88 FR 3306) and may be referenced for 40 years from 21 February 2023. The US600 is NuScale's earlier configuration of up to twelve modules of 50 MWe and 160 MWt each, which also received a standard design approval on 11 September 2020; the later US460 holds its own 2025 standard design approval. A design certification approves a design independent of any site and is not permission to build or operate.
· Took effect
Took effect: EU: Commission Delegated Regulation (EU) 2022/1214 adding nuclear energy activities to the EU taxonomy #
Art. 3: applies from 1 January 2023.
Announced or first reported · Agreement or program announced
Respect Energy and EDF agreement to develop NUWARD SMR projects in Poland #
In January 2023 Polish energy trader Respect Energy and EDF agreed to cooperate on NUWARD SMR projects in Poland and to start evaluating greenfield sites. EDF later redesigned NUWARD (2024-25). No decision in principle, site or order is recorded.
· Application submitted
Holtec submits its design to the UK government for Generic Design Assessment #
Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in Jan 2023, according to the Environment Agency. The regulators began the assessment on 18 Oct 2023. Entering design assessment is not an issued permission, nor an application for a site, construction or operating permission.
Step 2 completed 31 Mar 2026. Details are in Checking notes.
Checking notes
Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in January 2023, according to the Environment Agency's Step 1 summary; it was renamed SMR-300 in January 2024. The UK regulators began a two-step Generic Design Assessment of Holtec's SMR-300 on 18 October 2023 at the government's request. Step 1 ran from October 2023 to August 2024 and Step 2 from August 2024 to March 2026. The Environment Agency records completing Step 2 on 31 March 2026, and ONR's page records the assessment as completed that month with no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
· Opened
Opened: Japan: Long-Term Decarbonization Power Source Auction (capacity market, from FY2023) #
OCCTO states the auction was opened as part of the capacity market from FY2023.
· Regulatory step
Federal minister declines to designate the Point Lepreau SMR for a federal impact assessment #
After a public request, the federal environment minister determined that NB Power's SMR demonstration project at Point Lepreau does not warrant designation under the Impact Assessment Act. This is not a project approval; CNSC licensing and the provincial assessment still apply.
Checking notes
After a public designation request, the federal Minister of Environment and Climate Change determined that NB Power's SMR demonstration project at Point Lepreau does not warrant designation under the Impact Assessment Act.
· Regulatory step
Federal Register notice: NRC accepts and dockets the ACU construction permit application #
· Application submitted
OPG applies for the Darlington BWRX-300 construction license #
The recorded application date for the Darlington BWRX-300 construction license is 31 Oct 2022. The application itself is not an issued permission.
Later decision: 4 Apr 2025. Details are in Checking notes.
Checking notes
CNSC issued license to construct PRCL 32.00/2035 for one BWRX-300 on 4 April 2025, valid to 31 March 2035, with regulatory hold points. OPG's application was received on 31 October 2022.
Announced or first reported · Agreement or program announced
PacifiCorp and TerraPower joint study of up to five additional Natrium reactors by 2035 #
TerraPower and PacifiCorp announced in October 2022 a joint feasibility study of up to five additional Natrium reactor and storage systems by 2035. TerraPower’s 31 March 2023 release says PacifiCorp’s resource plan forecast two additional Utah systems before final site selection. PacifiCorp’s 2025 IRP preferred portfolio includes the Natrium demonstration and does not select additional nuclear units. These are successive planning positions, not two committed Utah projects, site permissions or evidence that the wider study was canceled.
· Took effect
Took effect: Michigan 2022 Public Act 218: nuclear feasibility study #
Approved by the Governor, filed with the Secretary of State, and effective on 14 October 2022.
· Took effect
Took effect: Alaska Chapter 4, SLA 2022: microreactor siting #
The same bill history says the effective date of the law is 8/22/22. The enrolled PDF that was opened contains no effective-date section.
· Enacted
Enacted: Internal Revenue Code sections 45Y and 48E: clean electricity production and investment credits, as amended by Public Law 119-21 #
Sections added by Pub. L. 117-169, approved 16 August 2022.
· Regulatory step
ACU submits construction permit application for the Molten Salt Research Reactor #
Application dated · Application submitted
ACU applies for its molten salt research reactor construction permit #
Abilene Christian University's construction permit application is dated 12 Aug 2022. The NRC notified ACU by letter dated 18 Nov 2022 that it was acceptable for docketing. The date is the application's own date, not an NRC receipt date. The application itself is not an issued permission.
Later decision: 16 Sep 2024. Details are in Checking notes.
Checking notes
The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center on its Abilene campus. ACU's application is dated 12 August 2022; the NRC notified ACU by letter dated 18 November 2022 that it was acceptable for docketing. Operation needs a separate operating license.
· Recorded development
Ministry of Ecology and Environment approves TMSR-LF1 commissioning plan #
The Ministry of Ecology and Environment told SINAP on 2 August 2022 that its commissioning plan, version V1.3, was approved, as World Nuclear News reported. That approved the plan; it was not an operating license.
Announced or first reported · Agreement or program announced
ULC-Energy exclusive agreement with Rolls-Royce SMR for deployment in the Netherlands #
In August 2022 Rolls-Royce SMR signed an exclusive agreement with ULC-Energy to collaborate on deploying Rolls-Royce SMR plants in the Netherlands, with ULC-Energy selecting it as its technology. The Dutch regulator ANVS lists ULC-Energy (Rolls-Royce SMR, 1,500 MWth / 500 MWe) among four parties in orientation talks. No site or license application is recorded.
Reported · Construction start
Keel laid for first Baimsky floating unit barge #
A keel-laying ceremony at a Chinese shipyard started construction of the barge for the first of four floating power units. This starts hull construction only; reactor installation, licensing for operation and towing to Chukotka remain ahead.
Checking notes
World Nuclear News reported on 31 August 2022, relaying Rosatom and Atomenergomash, that a keel-laying ceremony had been held at a Chinese shipyard for the barge of the first of four floating power units, which will later be fitted with two RITM-200S reactors. The ceremony day is not given.
· Published
Published: EU: Commission Delegated Regulation (EU) 2022/1214 adding nuclear energy activities to the EU taxonomy #
OJ L 188, 15.7.2022.
Announced or first reported · Agreement or program announced
OPG and X-energy framework agreement to deploy Xe-100 SMRs at industrial sites in Canada #
Ontario Power Generation and X-energy signed a framework agreement in July 2022 to pursue opportunities to deploy Xe-100 SMRs at industrial sites in Ontario and to identify further end users and sites across Canada, for applications such as oil sands and mining. No site, order or license application is recorded.
· Amended
Amended: Washington RCW 80.50: energy facility site certification #
The official note on the RCW 80.50.010 page says 2022 chapter 183 takes effect 30 June 2022. Later amendatory citations on section 80.50.060 were not opened, so this is not a calendar effective date for the current text of every opened section.
Announced or first reported · Agreement or program announced
Maryland Energy Administration grant study of repurposing a Maryland coal plant with X-energy's Xe-100 #
The Maryland Energy Administration awarded grants in June 2022 to X-energy and Frostburg State University to evaluate repurposing a specific Maryland coal-fired plant with X-energy's Xe-100 SMR, with findings due later that year. The coal plant was not named and no proposal, order or license application followed in the sources read.
· Milestone
Milestone: South Korea: Innovative SMR (i-SMR) Technology Development Programme (혁신형 소형모듈원자로 기술개발사업) #
MSIT and MOTIE announced that the program passed the preliminary feasibility study.
Company timeline · Contract
BWXT awarded the contract to build and deliver the Pele prototype #
BWXT says the Department of Defense's Strategic Capabilities Office awarded it the contract to build and deliver the Pele prototype in June 2022. The contract value and exact date are not stated.
Checking notes
BWXT's program timeline says the Strategic Capabilities Office awarded it the contract to build and deliver the Pele prototype in June 2022. Company account; the contract value and day are not given.
Announced or first reported · Agreement or program announced
PECC2, Seaborg (now Saltfoss) and Siemens Energy joint study on floating CMSR power plants in Vietnam (2022) #
A 2022 joint study by Vietnamese consultancy PECC2, Seaborg (now Saltfoss Energy) and Siemens Energy examined floating CMSR power plants for electricity, hydrogen and ammonia in Vietnam. Its preliminary report set out milestones toward a first modular floating plant, starting with a national modular nuclear power program and environmental assessment. No government decision or project followed in the sources read.
Announced or first reported · Agreement or program announced
Enea and Last Energy letter of intent to cooperate on SMRs in Poland #
In June 2022 state-owned utility Enea signed a letter of intent with Last Energy to cooperate on the development, construction and distribution of SMRs, possibly through a Polish joint company. Further steps depended on confirming viability and obtaining certificates, no site or plant is recorded.
· Signed
Signed: Alaska Chapter 4, SLA 2022: microreactor siting #
The official bill history says signed into law 5/24, Chapter 4 SLA 22. The journal row that carries that sentence is dated 5 October 2022. The enrolled PDF's chapter-number field is blank, so the chapter number is taken from this history line.
· Took effect
Took effect: West Virginia Enrolled Senate Bill 4 (2022): repeal of the nuclear-construction article #
The enrolled act says it is in effect 90 days from passage. Ninety days after 31 January 2022 is 1 May 2022. Current code pages display both repealed sections.
· Environmental decision recorded
Environmental decision recorded: Project Pele record of decision (prototype mobile microreactor environmental impact statement) #
Signed 5 April 2022 and published 15 April 2022 at 87 FR 22521. The Strategic Capabilities Office decided to implement the proposed action of its final environmental impact statement: fabricate the prototype mobile microreactor and its fuel at existing off-site commercial facilities and demonstrate it at the Idaho National Laboratory Site. This is a National Environmental Policy Act decision. This record addresses the environmental decision; it does not establish the status of any separate DOE safety authorization. No such authorization document was opened.
Announced or first reported · Agreement or program announced
UK Advanced Modular Reactor RD&D program HTGR demonstrator (Hartlepool proposed as host by EDF) #
The UK government's Advanced Modular Reactor research, development and demonstration program is working towards a high temperature gas reactor demonstrator. In Phase A (2022-2023) EDF proposed its Hartlepool Heat Hub as host site and found Hartlepool could be an appropriate HTGR site, while a NNL, JAEA and Jacobs team adapting Japan's HTGR design won a Phase B bid. Construction depends on a later government decision. A JAEA presentation of August 2026 still shows Hartlepool as a candidate site.
· Signed
Signed: Wyoming 2022 Chapter 103: advanced nuclear reactor requirements #
The digest says the governor signed House Enrolled Act No. 0059 on 21 March 2022 and the act was assigned Chapter 103 the same day. The enrolled PDF leaves its approval-date lines blank; the digest supplies the day.
· Took effect
Took effect: Wyoming 2022 Chapter 103: advanced nuclear reactor requirements #
The enrolled act says it is effective immediately upon completion of all acts necessary for a bill to become law under Article 4, Section 8 of the Wyoming Constitution. The digest records the signature and chapter number on 21 March 2022. The constitution section itself was not opened.
· Passed
Passed: Wyoming 2022 Chapter 103: advanced nuclear reactor requirements #
The digest records House concurrence on 11 March 2022, assignment of House Enrolled Act No. 0059 that day, and the signatures of the Speaker and the President of the Senate that day. Passage is not the governor's signature.
· Issued
Issued: EU: Commission Delegated Regulation (EU) 2022/1214 adding nuclear energy activities to the EU taxonomy #
Commission Delegated Regulation of 9 March 2022.
Announced or first reported · Agreement or program announced
Philippine national nuclear energy program (first plant targeted for 2032, SMRs among options) #
The Philippines aims to have its first nuclear plant operating by 2032 and is considering either reviving Bataan or building a small modular reactor. In 2026 the government finalised a whole-of-government licensing flowchart and consulted on draft rules for competitive tendering of nuclear capacity. The program is technology-neutral and has not selected any SMR plant or site.
· Opened
Opened: France: France 2030 call for projects « Réacteurs nucléaires innovants » (first call) #
DGE gives 2 March 2022 as the launch; the Government communiqué dated 9 March 2022 says the first call is open that day.
Announced or first reported · Agreement or program announced
Copper Valley Electric Association and Ultra Safe Nuclear Corporation Micro Modular Reactor feasibility study (Alaska) #
Copper Valley Electric Association and Ultra Safe Nuclear Corporation agreed in 2022 to study the feasibility of building a first commercial Micro Modular Reactor installation in Alaska, projected at 10 MWe, for the cooperative that serves the Valdez-Glennallen region. The study was to determine location, cost and social acceptance, no site, license application or later decision appears in the sources read.
· Passed
Passed: West Virginia Enrolled Senate Bill 4 (2022): repeal of the nuclear-construction article #
The enrolled act says it passed on 31 January 2022. It repeals the two sections of the nuclear-construction article. Repeal is not approval of a reactor.
· Other regulatory action: Denied
Other regulatory action: Denied: Oklo Aurora custom combined license application (2020), denied without prejudice #
Oklo Power applied on 11 March 2020 for a custom combined license, which covers construction and operation, for one Aurora microreactor at Idaho National Laboratory. The NRC denied it without prejudice by letter of 6 January 2022 because requested information was not provided, and said Oklo may resubmit. This is an earlier application than the current Aurora powerhouse, which is following DOE authorization under the Reactor Pilot Program. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only (project 99902095) and no docketed application.
· Took effect
Took effect: Rhode Island Energy Facility Siting Board rules #
The Department of State rules page prints Regulation Status Active and Effective 01/04/2022.
· Provision took effect
Provision took effect: Brazil: Law 14.222/2021 creating the National Nuclear Safety Authority (ANSN) #
Art. 41, I: changes to the licensing, control and inspection fee (TLC).
· Amended
Amended: Wyoming advanced nuclear reactor requirements #
The compilation marks subsection (a) and definition subparts (A) through (C) repealed by Laws 2022, chapter 103, section 2. It does not print the day. The day is on the separate 2022 session-law record.
· Grid connection
HTR-PM grid connection #
· Regulatory step
NRC dockets Hermes construction permit application #
Announced or first reported · Agreement or program announced
Nuclear Alternative Project study of SMR and microreactor site suitability in Puerto Rico (DOE-funded) #
DOE's Office of Nuclear Energy published an abstract in November 2021 for a Nuclear Alternative Project award to evaluate the general site suitability for small modular reactors and microreactors in Puerto Rico. The non-profit says it is studying the feasibility of advanced reactors for the island, no site, project or license application exists.
· Environmental decision recorded
Environmental decision recorded: DOE finding of no significant impact for MARVEL (DOE/EA-2146) #
Issued at Idaho Falls on 12 November 2021 for environmental assessment DOE/EA-2146. DOE found that designing and demonstrating MARVEL in the north high bay of the Transient Reactor Test facility would not significantly affect the human environment, so no environmental impact statement is required. It is an environmental finding. It is not approval of a safety analysis and not authority to load fuel or operate. The 2021 text describes about 20 kW electric; DOE's current project page gives 85 kW thermal and about 10 kW electric.
· Published
Published: Brazil: Law 14.222/2021 creating the National Nuclear Safety Authority (ANSN) #
Diário Oficial da União, p. 2.
· Took effect
Took effect: Brazil: Law 14.222/2021 creating the National Nuclear Safety Authority (ANSN) #
Art. 41: in force on publication; most provisions take effect when the decree approving ANSN's regimental structure enters into force.
· Signed
Signed: Brazil: Law 14.222/2021 creating the National Nuclear Safety Authority (ANSN) #
Brazil's Law 14.222/2021 split the National Nuclear Safety Authority (ANSN) from CNEN and gives it competence to issue licenses and authorizations for site selection, construction, commissioning, operation and decommissioning of nuclear installations. Most provisions take effect with the decree approving ANSN's structure. It licenses no reactor itself.
· Site permission recorded
Site permission recorded: Renewal of Darlington New Nuclear Project site preparation license (PRSL 18.00/2031) #
Record of Decision DEC 21-H4; application received 29 June 2020.
Announced or first reported · Agreement or program announced
Bulgarian Energy Holding and Fluor memorandum on NuScale SMRs to replace coal units #
In October 2021 Bulgarian Energy Holding signed a memorandum with Fluor covering, among other things, evaluation of replacing coal boilers with NuScale SMRs, BEH described it more generally as information exchange and preliminary assistance. No site or order is recorded.
· Application submitted
Application for the Hermes 1 construction permit #
The recorded application date for the Hermes 1 construction permit is 29 Sep 2021. The application itself is not an issued permission.
Later decision: 14 Dec 2023. Details are in Checking notes.
Checking notes
The NRC issued construction permit CPTR-6 for the Hermes non-power test reactor on 14 December 2023. A 13 May 2026 order extended the latest construction completion date from 31 December 2026 to 30 April 2029. Operation needs a separate operating license.
· Recorded development
HTTR reaches 100% power and 850°C after restart #
JAEA reports that HTTR reached 100% reactor power and an 850°C coolant temperature on 19 September 2021, and that the periodic licensee inspection confirming performance at full power was completed on 22 September 2021, completing the reactor's new-regulatory-standard compliance. Thermal test operation; no electricity. The safety-demonstration test operation planned from about January 2022 is a plan in this notice, not an achieved event.
· First criticality
HTR-PM first criticality (IAEA PRIS unit date) #
PRIS lists the twin-module plant as one unit; this is the unit-level first-criticality date.
Announced or first reported · Agreement or program announced
Unimot and Getka agreement with NuScale to explore coal-repurposing SMRs in Poland #
In September 2021 Polish fuels and power trader Unimot and US firm Getka signed an agreement with NuScale to explore deploying NuScale Power Modules as a coal-repurposing solution at Polish coal plants. No site, decision in principle or order is recorded.
Announced or first reported · Agreement or program announced
Energoatom and NuScale memorandum to explore NuScale SMRs replacing fossil plants in Ukraine #
In September 2021 Energoatom and NuScale signed a memorandum to explore deploying NuScale SMRs to replace fossil-fuel plants, with NuScale supporting a feasibility study including proposed sites. No site or order is recorded.
· Operating authority recorded
Operating authority recorded: NNSA operating license for the Shidaowan HTR-PM demonstration #
NNSA issued operating license 国核安证字第2119号 on 20 August 2021 for the high-temperature gas-cooled demonstration (CN-44) at Ningjin Town, Rongcheng, Shandong. The holder and operating organization is Huaneng Shandong Shidao Bay Nuclear Power Company, Ltd. Validity runs through 19 August 2061. First fuel loading is the start of operation. Condition 23 sets control points at 15 percent and 65 percent of plant rated electrical power and states no megawatt number. The legal representative named on the license is not stored.
Reported · Regulatory step
Rusatom Overseas reports a Rostekhnadzor construction-activity license #
A 2021 media report cited the developer as saying the regulator licensed it to construct nuclear installations for the Yakutia plant. No number or scope is given; it is not the unit construction license, which later reports still place ahead.
Checking notes
Snob reported on 6 August 2021, citing Rusatom Overseas's press service, that Rostekhnadzor had issued the company a license for construction of nuclear installations at the planned Yakutia plant after an inspection. The date is the report date. The report gives no license number or scope. Later reporting shows the unit siting and construction licenses still ahead, so this is not recorded as construction permission.
· Recorded development
HTTR resumes operation after new-regulatory-standard review #
HTTR resumed operation on 30 July 2021 after the new-regulatory-standard installation-change permit and compliance work; JAEA's Oarai notice of that day records the restart.
· Construction start
Linglong-1 construction start (IAEA PRIS) #
· Took effect
Took effect: Vermont Act 52 of 2021: radiological emergency response plan fund #
Section 18 says sections 12 through 17, including the fund amendment in section 16, take effect on July 1, 2021.
· Construction permission recorded
Construction permission recorded: NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One) #
NNSA issued construction license 国核安证字第2117号 on 1 July 2021, valid to 30 June 2031, after reviewing the construction application and inspecting readiness for the first nuclear-island concrete. The license names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations. IAEA PRIS reports a different construction-license date, 15 July 2019; the license document carries 1 July 2021, so the PRIS date is kept visible as a conflicting statement and is not treated as the license date. This is a construction license, not an operating license.
· Construction start
BREST-OD-300 construction start (IAEA PRIS) #
· Signed
Signed: Vermont Act 52 of 2021: radiological emergency response plan fund #
The enrolled PDF prints Date Governor signed bill: June 3, 2021.
Executive summary dated · Design assessment: Review completed (not an approval)
CNSC lists Phase 1 of its SSR-W vendor design review as completed #
CNSC lists Phase 1 of its pre-licensing vendor design review of Moltex's SSR-W300 as completed, with an executive summary dated May 2021. A vendor design review does not certify a design or issue a license.
Checking notes
CNSC lists Phase 1 of its pre-licensing vendor design review of Moltex Energy's SSR-W300 among completed reviews, with an executive summary dated May 2021. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
Announced or first reported · Agreement or program announced
NuScale and Kozloduy NPP - New Build memorandum to evaluate NuScale SMRs at the Kozloduy site #
On 17 February 2021 NuScale and Kozloduy NPP - New Build signed a memorandum to evaluate the suitability of NuScale's SMR for the Kozloduy site, with studies and a timeline for a feasibility assessment. It is an evaluation agreement, not a plant proposal, no later step was found.
· Regulatory step
Rostekhnadzor construction license for BREST-OD-300 issued to Siberian Chemical Combine #
Date from IAEA PRIS constructionLicenseDate; WNN (11 Feb 2021) says the license was signed 'yesterday'. Official Rostekhnadzor instrument not opened, so recorded as an event, not a regulatory action.
· Signed
Signed: Idaho Executive Order 2021-02: Leadership in Nuclear Energy Commission #
The witness clause is 26 January 2021 at the Capitol in Boise. The order continues an advisory commission. It does not license a reactor.
· Published
Published: Rwanda: Presidential Order N° 127/01 establishing the Rwanda Atomic Energy Board (2020) #
Official Gazette n° Special; in force on publication (Article 31).
· Signed
Signed: Rwanda: Presidential Order N° 127/01 establishing the Rwanda Atomic Energy Board (2020) #
Rwanda's Presidential Order of 3 December 2020 established the Rwanda Atomic Energy Board to promote peaceful use of atomic energy, advise the Government and promote and support the construction of nuclear energy installations for electricity. It is an institutional measure; it names no project and grants no license.
· Amended
Amended: Indonesia: Law No. 10 of 1997 on Nuclear Energy (Undang-Undang Nomor 10 Tahun 1997 tentang Ketenaganukliran) #
Article 43 of Law No. 11 of 2020 on Job Creation, signed and promulgated 2 November 2020, in force on promulgation (Article 186).
· Awarded
Awarded: DOE Advanced Reactor Demonstration Program (demonstration awards) #
First awards: TerraPower and X-energy.
· Awarded
Awarded: ARDP demonstration award: X-energy (Xe-100) #
DOE awarded X-energy $80 million in initial ARDP funding on 13 October 2020 for the Xe-100 demonstration.
· Awarded
Awarded: ARDP demonstration award: TerraPower (Natrium) #
DOE awarded TerraPower $80 million in initial ARDP funding on 13 October 2020 for the Natrium demonstration.
· Design assessment recorded
Design assessment recorded: NRC standard design approval for the NuScale US600 #
The NRC records that NuScale requested a standard design approval for the US600 on 13 July 2020 and that it was approved on 11 September 2020 (ML20247J564). The design was later certified by rule in January 2023. A standard design approval approves a design independent of any site; it is not permission to build or operate.
Executive summary dated · Design assessment: Review completed (not an approval)
CNSC lists Phase 1 of its SMR-160 vendor design review as completed #
CNSC lists Phase 1 of its pre-licensing vendor design review of Holtec's SMR-160 as completed, with an executive summary dated August 2020. A vendor design review does not certify a design or issue a license.
Checking notes
CNSC lists Phase 1 of its pre-licensing vendor design review of the SMR-160 by SMR, LLC (Holtec International) among completed reviews, with an executive summary dated August 2020. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
· Application submitted
NuScale requests a standard design approval for the US600 #
The NRC records that NuScale requested a standard design approval for the US600 on 13 Jul 2020. The application itself is not an issued permission. A standard design approval is not permission to build or operate.
Later decision: 11 Sep 2020. Details are in Checking notes.
Checking notes
The NRC records that NuScale requested a standard design approval for the US600 on 13 July 2020 and that it was approved on 11 September 2020 (ML20247J564). The design was later certified by rule in January 2023. A standard design approval approves a design independent of any site; it is not permission to build or operate.
· Took effect
Took effect: North Carolina G.S. 166A-29: fixed nuclear facility emergency-planning fee #
Session Law 2020-83 was approved at 5:37 p.m. on 1 July 2020. Section 11.1(b) says that section becomes effective 1 July 2020 and applies to fees assessed on or after that date. The current compilation's history ends with that section.
· Application submitted
Application to renew the Darlington site preparation license #
The recorded application date for renewal of the Darlington site preparation license is 29 Jun 2020. The application itself is not an issued permission.
Later decision: 12 Oct 2021. Details are in Checking notes.
Checking notes
Record of Decision DEC 21-H4; application received 29 June 2020.
· Other regulatory action recorded
Other regulatory action recorded: NRA decision to grant the HTTR installation-change permit #
On 3 June 2020 the Nuclear Regulation Authority decided that the application to change the HTTR installation at Oarai meets the permit criteria and that the installation-change permit shall be granted under article 26(1) of the Reactor Regulation Act. The application was received on 26 November 2014. The draft letter has a blank number and a blank date, so no permit number is stored. This decision is not an operating license and is distinct from the July 2021 restart.
· Commercial operation
Akademik Lomonosov commercial operation (both units) #
The project field commercial_operation already holds this date; the record has no event row for it.
· Application submitted
Application for the Aurora combined license #
The recorded application date for the Aurora combined license is 11 Mar 2020. The application itself is not an issued permission.
Later denial decision: 6 Jan 2022. Details are in Checking notes.
Checking notes
Oklo Power applied on 11 March 2020 for a custom combined license, which covers construction and operation, for one Aurora microreactor at Idaho National Laboratory. The NRC denied it without prejudice by letter of 6 January 2022 because requested information was not provided, and said Oklo may resubmit. This is an earlier application than the current Aurora powerhouse, which is following DOE authorization under the Reactor Pilot Program. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only (project 99902095) and no docketed application.
· Application submitted
Application for SMART100 standard-design approval #
The recorded application date for SMART100 standard-design approval is 30 Dec 2019. The application itself is not an issued permission.
Later decision: 26 Sep 2024. Details are in Checking notes.
Checking notes
The NSSC's 201st meeting approved SMART100's standard design on 26 September 2024. Printed minutes pp.121–123 distinguish standard-design approval from construction permission, direct administrative follow-up on power-system review during later licensing and continued verification improvements, and remove disputed wording asserting that a single off-site power circuit presents no safety impediment. The application date is recorded in the technical agenda. This does not authorize any project, construction or operation, does not approve SMART-C, and is not a Saudi or Canadian license. No separate issued certificate number was opened.
· Site permission recorded
Site permission recorded: Clinch River Nuclear Site early site permit ESP-006 #
NRC: application for two or more SMR modules (up to 800 MWe, 2420 MWt) submitted 12 May 2016, docketed 30 Dec 2016; Commission decision 17 Dec 2019.
· Grid connection
Akademik Lomonosov grid connection (both units) #
· Took effect
Took effect: Russia: Federal norms and rules NP-032-19 'Nuclear power plant site. Safety requirements' (Rostekhnadzor Order No. 287, 2019) #
Entry-into-force date as given by the regulator's technical support catalog.
· Took effect
Took effect: China: Safety licensing procedure for nuclear power plants, research reactors and fuel cycle facilities (MEE Order No. 8, 2019) #
China's 2019 safety licensing procedure rule sets how operators apply to the National Nuclear Safety Administration for a site selection review opinion and for construction, operation and decommissioning licenses. It allows a combined siting and construction application for some research reactors and for factory-built floating or mobile nuclear power units on an already approved site. It is a procedure rule, not a project permission.
· Took effect
Took effect: Uzbekistan: Law No. ZRU-565 on the Use of Atomic Energy for Peaceful Purposes (2019) #
Uzbekistan's 2019 Law on the Use of Atomic Energy for Peaceful Purposes requires licenses from the Committee for Industrial, Radiation and Nuclear Safety for building and operating nuclear installations, reserves the construction decision to the President and the site choice to the Cabinet of Ministers, and requires a regulator permit to use the site. It was last amended in April 2026. It is a framework statute, not a project permission.
· Signed
Signed: Uzbekistan: Law No. ZRU-565 on the Use of Atomic Energy for Peaceful Purposes (2019) #
Uzbekistan's 2019 Law on the Use of Atomic Energy for Peaceful Purposes requires licenses from the Committee for Industrial, Radiation and Nuclear Safety for building and operating nuclear installations, reserves the construction decision to the President and the site choice to the Cabinet of Ministers, and requires a regulator permit to use the site. It was last amended in April 2026. It is a framework statute, not a project permission.
· Took effect
Took effect: Canada: Physical Activities Regulations, Schedule item 27 – new fission or fusion reactors (SOR/2019-285) #
Editorial note in the consolidated text: in force 28 August 2019 (SI/2019-86).
· Issued
Issued: China: Safety licensing procedure for nuclear power plants, research reactors and fuel cycle facilities (MEE Order No. 8, 2019) #
Adopted by the ministry meeting on 11 July 2019 and promulgated on 26 August 2019.
· Issued
Issued: Canada: Physical Activities Regulations, Schedule item 27 – new fission or fusion reactors (SOR/2019-285) #
Order in Council P.C. 2019-1182; registered as SOR/2019-285 on 8 August 2019.
· Issued
Issued: Russia: Federal norms and rules NP-032-19 'Nuclear power plant site. Safety requirements' (Rostekhnadzor Order No. 287, 2019) #
Rostekhnadzor Order No. 287; registered by the Ministry of Justice on 2 December 2019 (No. 56661).
· Regulatory step
NucNet reports receipt of Akademik Lomonosov operating license #
NucNet reported on 27 June 2019 that Rosenergoatom had received a ten-year Rostekhnadzor license to operate the Akademik Lomonosov floating plant, valid until 2029, as announced by Rosatom. The event date is the report date; the issue date, instrument and license number are unknown and the license document has not been reviewed.
Executive summary dated · Design assessment: Review completed (not an approval)
CNSC lists Phase 1 of its USNC MMR vendor design review as completed #
CNSC lists Phase 1 of its pre-licensing vendor design review of the MMR by USNC-Power Ltd. as completed, with an executive summary dated February 2019. A vendor design review does not certify a design or issue a license.
Checking notes
CNSC lists Phase 1 of its pre-licensing vendor design review of the MMR by USNC-Power Ltd. (Ultra Safe Nuclear Corporation) among completed reviews, with an executive summary dated February 2019. No later phase is listed. CNSC's Chalk River project page names Ultra Safe Nuclear Corporation as the parent of Global First Power, whose proposed micro modular reactor this profile records. CNSC staff paused the Chalk River environmental assessment and licence-to-prepare-site application review as of August 2024. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
· First criticality
Akademik Lomonosov Unit 2 first criticality #
Unit-level event (unit-lomonosov-2).
· First criticality
Akademik Lomonosov Unit 1 first criticality #
Unit-level event (unit-lomonosov-1).
· Construction start
TMSR-LF1 construction begins #
· Took effect
Took effect: Indonesia: BAPETEN Regulation No. 4 of 2018 on Safety Provisions for Site Evaluation of Nuclear Installations #
Article 57: in force on promulgation; promulgated 8 August 2018.
Announced or first reported · Agreement or program announced
Philippine DOE and KHNP SMART pre-feasibility study at CEZA, Santa Ana, Cagayan (2018-2019) #
Under a July 2018 memorandum on nuclear infrastructure cooperation, the Philippine Department of Energy and KHNP carried out a pre-feasibility study of building a SMART reactor in the Cagayan Economic Zone Authority at Santa Ana, Cagayan. The final study was handed over in December 2019. It was an evaluation, no project decision followed in the sources read.
· Issued
Issued: Indonesia: BAPETEN Regulation No. 4 of 2018 on Safety Provisions for Site Evaluation of Nuclear Installations #
Ditetapkan di Jakarta pada tanggal 23 Juli 2018.
· Issued
Issued: Netherlands: Environmental Quality Decree (Besluit kwaliteit leefomgeving), nuclear power plant locations #
Besluit van 3 juli 2018. Article 13.1 leaves entry into force to royal decree.
Announced or first reported · Agreement or program announced
Jordan Atomic Energy Commission SMR program (vendor studies, floating plant at Aqaba considered) #
After canceling its two-unit large plant in 2018, JAEC pursued SMR cooperation with Rolls-Royce, X-energy, Rosatom, CNNC and others. Its chairman said in April 2023 that small reactors were chosen for desalination and power, with a floating plant at Aqaba under consideration. JAEC's own undated project page describes a 100–300 MWe small-reactor class for electricity or seawater desalination, alongside technology evaluation, infrastructure work and vendor agreements. It names no selected site, vendor or unit count.
· Published
Published: Rwanda: Law N° 59/2017 governing radiation protection #
Official Gazette n° Special; in force on publication (Article 37).
· Signed
Signed: Rwanda: Law N° 59/2017 governing radiation protection #
Rwanda's 2018 radiation protection law gives the utilities regulator (RURA) independent authority to regulate and authorize ionising-radiation activities. It contains no reactor-specific licensing sequence; RURA's 2024 nuclear installation licensing regulation is made under it. A comprehensive nuclear law was still being drafted in March 2026.
· Provision took effect
Provision took effect: Nebraska section 71-3505: nuclear-plant emergency-response and surveillance fee #
The subsection says the inflation-adjustment recommendation commences on this date. It is not the section's enactment date, and no adjusted dollar amount is stored.
· Took effect
Took effect: China: Nuclear Safety Law of the People's Republic of China (2017) #
Article 94.
Announced or first reported · Agreement or program announced
CGN and Tsinghua NHR200-II nuclear district-heating demonstration: NEA-approved preliminary work (2018) #
In January 2018 China's National Energy Administration agreed that CGN and Tsinghua University should carry out preliminary work, including planning and site selection, for China's first nuclear district-heating demonstration using the NHR200-II low-temperature heating reactor in North China. No site was named. By 2025 INET described promoting the 'Huapeng One' industrial-coupling demonstration with CGN.
Announced or first reported · Agreement or program announced
Philippine DOE and Rosatom cooperation on small modular reactor feasibility (2017 memorandum, 2019 agreement) #
In November 2017 the Philippine Department of Energy and Rosatom signed a memorandum of cooperation under which Russia would help with feasibility studies on onshore or offshore small modular reactors, among other nuclear infrastructure work. In October 2019 the DOE signed a further agreement with Rosatom to assess a small nuclear plant, floating or on land. No site or project is recorded.
Announced or first reported · Agreement or program announced
JAEC and X-energy memorandum to assess Xe-100 deployment in Jordan #
In November 2017 JAEC signed a memorandum with X-energy to assess the potential deployment of the Xe-100 high-temperature gas-cooled reactor in Jordan, for electricity, desalination and industrial uses. No site, order or later step is recorded.
· Passed
Passed: China: Nuclear Safety Law of the People's Republic of China (2017) #
Adopted by the NPC Standing Committee.
· Took effect
Took effect: Norway: Regulations on impact assessments (FOR-2017-06-21-854), Annex I item 2 b on nuclear reactors #
Section 38: in force 1 July 2017.
· Issued
Issued: Norway: Regulations on impact assessments (FOR-2017-06-21-854), Annex I item 2 b on nuclear reactors #
Fastsatt ved kgl.res. 21. juni 2017.
· Took effect
Took effect: Czechia: SÚJB Decree No. 378/2016 Coll. on siting of a nuclear installation #
s. 21.
· Took effect
Took effect: Czechia: Atomic Act (Act No. 263/2016 Coll., atomový zákon) #
Effect clause: in force on 1 January 2017.
· Issued
Issued: Czechia: SÚJB Decree No. 378/2016 Coll. on siting of a nuclear installation #
Decree No. 378/2016 Coll. of 7th November 2016.
· Issued
Issued: Czechia: Atomic Act (Act No. 263/2016 Coll., atomový zákon) #
Act No. 263/2016 of Coll. of 14th July 2016.
· Published
Published: EU: Treaty establishing the European Atomic Energy Community (Euratom Treaty), consolidated version 2016 #
Consolidated version published in OJ C 203 of 7 June 2016.
· Application submitted
Application for the Clinch River early site permit #
The recorded application date for the Clinch River early site permit is 12 May 2016. The application itself is not an issued permission.
Later decision: 19 Dec 2019. Details are in Checking notes.
Checking notes
NRC: application for two or more SMR modules (up to 800 MWe, 2420 MWt) submitted 12 May 2016, docketed 30 Dec 2016; Commission decision 17 Dec 2019.
· Took effect
Took effect: 2015 Wisconsin Act 344: repeal of the nuclear-construction conditions #
The act page quotes s. 991.11, and the current section says an act that does not prescribe its own time takes effect the day after publication. This act prescribes no other time. The day after 2 April 2016 is 3 April 2016.
· Published
Published: 2015 Wisconsin Act 344: repeal of the nuclear-construction conditions #
The official act states its date of publication as 2 April 2016.
· Enacted
Enacted: 2015 Wisconsin Act 344: repeal of the nuclear-construction conditions #
The official act states its date of enactment as 1 April 2016. It is 2015 Assembly Bill 384. Enactment is not a Public Service Commission certificate.
Announced or first reported · Agreement or program announced
Guizhou provincial plan for a CGN small-reactor nuclear demonstration (4 x 100 MW, 13th Five-Year Plan draft) #
Guizhou's draft 13th Five-Year energy plan (reported April 2016) listed a nuclear small-reactor demonstration in which CGN proposed four 100 MW small reactors, with site selection in Xingyi, Zhenning, Yuping and other places. In 2013 a provincial site-survey report and a small-reactor site resource analysis had passed expert review. This is a provincial planning target, not a selected site, approval or construction.
Announced or first reported · Agreement or program announced
K.A.CARE and CNEC memorandum and feasibility study for a high-temperature gas-cooled reactor in Saudi Arabia #
On 19 January 2016 K.A.CARE and CNEC signed a memorandum on building a high-temperature gas-cooled reactor in Saudi Arabia, without size or timeline. A joint working group began a feasibility study in May 2017, aiming to finish that year. No later step is recorded.
Announced or first reported · Agreement or program announced
CNNC ACP100S floating nuclear power plant demonstration program (2016 plan inclusion) #
In January 2016 China's NDRC agreed to include CNNC's ACP100S floating nuclear power plant, the marine version of the ACP100, in the 13th Five-Year energy innovation plan. CNNC's Nuclear Power Institute said it planned to start building a demonstration reactor at the end of 2016 and operate it in 2019. These were planned dates, no host site, construction or license is recorded in the sources read.
Announced or first reported · Agreement or program announced
K.A.CARE and KAERI cooperation on SMART/SMART100 SMRs for Saudi Arabia #
K.A.CARE and KAERI agreed in March 2015 to assess building at least two SMART reactors in Saudi Arabia and carried out pre-project engineering, in 2019 the two countries agreed to cooperate on commercialising SMART, including a reactor in Saudi Arabia. KAERI, KHNP and K.A.CARE jointly obtained Korean standard design approval for SMART100 in September 2024. No Saudi site or construction commitment is recorded.
· Application submitted
Application for the HTTR installation-change permit #
The recorded application date for the HTTR installation-change permit is 26 Nov 2014. The application itself is not an issued permission.
Later decision: 3 Jun 2020. Details are in Checking notes.
Checking notes
On 3 June 2020 the Nuclear Regulation Authority decided that the application to change the HTTR installation at Oarai meets the permit criteria and that the installation-change permit shall be granted under article 26(1) of the Reactor Regulation Act. The application was received on 26 November 2014. The draft letter has a blank number and a blank date, so no permit number is stored. This decision is not an operating license and is distinct from the July 2021 restart.
· Issued
Issued: Ukraine: Regulation on the State Nuclear Regulatory Inspectorate (Cabinet of Ministers Resolution No. 363 of 20 August 2014, Положення про Державну інспекцію ядерного регулювання України) #
ПОСТАНОВА від 20 серпня 2014 р. № 363.
· Operating authority recorded
HTR-10 operating license valid through June 2024; operation listed, not confirmed #
NNSA's notice of 15 July 2014 issued the reactor's operating license, valid through 30 June 2024. Operation after that date required a new application twelve months before expiry. No successor license was opened and no dated recent power run was found, so operation is listed rather than confirmed. The stage is unchanged, and the reactor is not recorded as stopped.
Checking notes
NNSA notice 国核安发〔2014〕158号, dated 15 July 2014, issued operating license 国核安证字1405号 to Tsinghua University's Institute of Nuclear and New Energy Technology for the 10 MW high-temperature gas-cooled experimental reactor. The license is valid through 30 June 2024. Continued operation after that date requires a new application twelve months before expiry. No successor instrument was opened. The extracted license pages do not print a separate issue date; the decision-letter date is used. Personal names on the license are not stored.
· Amended
Amended: EU: Council Directive 2009/71/Euratom on the nuclear safety of nuclear installations, as amended by Directive 2014/87/Euratom #
Amended by Council Directive 2014/87/Euratom of 8 July 2014 (OJ L 219, 25.7.2014, p. 42).
· Amended
Amended: South Korea: Act on Physical Protection and Radiological Emergency (원자력시설 등의 방호 및 방사능 방재 대책법), emergency planning zones #
Article 20-2 on radiological emergency planning zones added.
· Provision took effect
Provision took effect: United Kingdom: Nuclear Installations Act 1965 (c. 57), nuclear site licensing #
Section 1 substituted by the Energy Act 2013, s. 156(1) and Sch. 12 para. 17 (S.I. 2014/251, art. 4).
· Provision took effect
Provision took effect: United Kingdom: Energy Act 2013 (c. 32), Part 3, Office for Nuclear Regulation #
Section 67 (the ONR's purposes) in force under S.I. 2014/251, art. 4.
· Provision took effect
Provision took effect: United Kingdom: Energy Act 2013 (c. 32), Part 3, Office for Nuclear Regulation #
Section 77 (the ONR) in force under S.I. 2014/251, art. 3(b).
· Issued
Issued: Indonesia: Government Regulation No. 2 of 2014 on Licensing of Nuclear Installations and Use of Nuclear Material (Peraturan Pemerintah Nomor 2 Tahun 2014) #
Ditetapkan di Jakarta pada tanggal 16 Januari 2014.
· Took effect
Took effect: Indonesia: Government Regulation No. 2 of 2014 on Licensing of Nuclear Installations and Use of Nuclear Material (Peraturan Pemerintah Nomor 2 Tahun 2014) #
Article 134: in force on promulgation; promulgated 16 January 2014.
· Took effect
Took effect: Japan: NRA rule on standards for the location, structure and equipment of commercial power reactors (NRA Rule No. 5 of 2013) #
Supplementary provision 1.
· Issued
Issued: Japan: NRA rule on standards for the location, structure and equipment of commercial power reactors (NRA Rule No. 5 of 2013) #
Promulgation date.
· Construction start
HTR-PM construction start (IAEA PRIS) #
· Design assessment recorded
Design assessment recorded: Korean standard design approval for SMART #
KAERI's release says the Nuclear Safety and Security Commission issued a standard design approval for the original SMART (100 MWe, 330 MWth) on 4 July 2012 under Article 12 of the Nuclear Safety Act, after KAERI and KEPCO applied on 30 December 2010. The approval document itself was not opened. SMART100 holds a separate 2024 approval. A standard design approval is not a construction or operating permission.
· Site permission: Superseded
Site permission: Superseded: Original Darlington New Nuclear Project site preparation license (PRSL 18.00/2022) #
CNSC's project timeline records that Ontario Power Generation applied for a license to prepare site in September 2006, for the original Darlington New Nuclear Project. The 2021 renewal decision says the license was issued in 2012. The project timeline says the Joint Review Panel, as a panel of the Commission, issued a 10-year site preparation license in 2012. The license document itself was not opened, so the stored decision date stays at year precision.
· Published
Published: South Africa: Regulations on Licensing of Sites for New Nuclear Installations (GN R. 927 of 11 November 2011) #
Government Notice No. R. 927, Government Gazette No. 34735.
· Enacted
Enacted: South Korea: Nuclear Safety Act (원자력안전법) #
Enacted as Act No. 10911 (신규제정 2011. 7. 25).
· Milestone
Milestone: EU: Council Directive 2009/71/Euratom on the nuclear safety of nuclear installations, as amended by Directive 2014/87/Euratom #
Art. 10(1): transposition deadline for the original Directive.
· Took effect
Took effect: Poland: Act on preparing and carrying out investments in nuclear power facilities and accompanying investments (2011 special act) #
Art. 63.
· Issued
Issued: Poland: Act on preparing and carrying out investments in nuclear power facilities and accompanying investments (2011 special act) #
Ustawa z dnia 29 czerwca 2011 r.
· Application submitted
KAERI and KEPCO apply for a standard design approval of SMART #
KAERI's release says KAERI and KEPCO applied for a standard design approval of the original SMART on 30 Dec 2010. This is the applicants' own account; the approval document itself was not opened. The application itself is not an issued permission.
Later decision: 4 Jul 2012. Details are in Checking notes.
Checking notes
KAERI's release says the Nuclear Safety and Security Commission issued a standard design approval for the original SMART (100 MWe, 330 MWth) on 4 July 2012 under Article 12 of the Nuclear Safety Act, after KAERI and KEPCO applied on 30 December 2010. The approval document itself was not opened. SMART100 holds a separate 2024 approval. A standard design approval is not a construction or operating permission.
· Published
Published: Romania: CNCAN nuclear safety norms on the siting of nuclear power plants (NSN-01) #
Monitorul Oficial, Partea I nr. 836.
· Issued
Issued: Romania: CNCAN nuclear safety norms on the siting of nuclear power plants (NSN-01) #
Norm dated 23 November 2010.
Announced or first reported · Agreement or program announced
SRNS and GE Hitachi agreement to explore a PRISM prototype at the Savannah River Site (2010) #
In October 2010 Savannah River Nuclear Solutions, DOE's management contractor at the Savannah River Site, signed an agreement with GE Hitachi to explore deploying a prototype of GEH's PRISM reactor as part of a proposed demonstration of small modular reactor technologies at the site. It was exploratory only, with no deployment commitment, license application or construction.
· Took effect
Took effect: Northern Mariana Islands 2 CMC § 1326: small modular reactor exemption from the nuclear-free zone law #
The Law Revision Commission's comment says Public Law 17-10 took effect on 28 July 2010; the section's source line gives the same date. The public law itself was not opened.
· Recorded development
HTTR 50-day continuous operation at 950°C #
· Took effect
Took effect: EU: Council Directive 2009/71/Euratom on the nuclear safety of nuclear installations, as amended by Directive 2014/87/Euratom #
Art. 11: twentieth day after publication in OJ L 172 of 2 July 2009.
· Published
Published: EU: Council Directive 2009/71/Euratom on the nuclear safety of nuclear installations, as amended by Directive 2014/87/Euratom #
OJ L 172, 2.7.2009, p. 18.
· Issued
Issued: EU: Council Directive 2009/71/Euratom on the nuclear safety of nuclear installations, as amended by Directive 2014/87/Euratom #
Council Directive 2009/71/Euratom of 25 June 2009.
· Amended
Amended: Kansas nuclear generation facility siting permit #
Both sections' history lines end with L. 2007, ch. 113 and then July 1, without repeating the year. The effective day is stored as 1 July 2007 from that session-law line. Earlier amendment years are not this record's effective date.
· Took effect
Took effect: South Carolina Base Load Review Act #
The compilation's history line for section 58-33-210 says 2007 Act No. 16, Section 2, effective upon approval, and that it became law without the governor's signature on 3 May 2007. Act No. 16 was not opened as a separate document.
· Construction start
Akademik Lomonosov construction start (both units, IAEA PRIS) #
Announced or first reported · Agreement or program announced
Feasibility study for a four-unit VK-300 nuclear cogeneration plant in the Arkhangelsk region #
A paper at an April 2007 IAEA conference (proceedings 2009) reports a feasibility study for a four-unit VK-300 nuclear cogeneration plant in the Arkhangelsk region with 1000 MW electric and 1600 Gcal/h heat capacity, reviewed and approved by a Rosatom scientific and technical board. No later project step is recorded.
· Application submitted
OPG applies for the original Darlington site preparation license #
CNSC's project timeline records that Ontario Power Generation applied for a license to prepare site in Sep 2006, for the original Darlington New Nuclear Project. The application itself is not an issued permission.
Later decision: license issued in 2012. The same timeline records OPG submitting its environmental impact statement and license documentation in Sep 2009. Details are in Checking notes.
Checking notes
CNSC's project timeline records that Ontario Power Generation applied for a license to prepare site in September 2006, for the original Darlington New Nuclear Project. The 2021 renewal decision says the license was issued in 2012. The project timeline says the Joint Review Panel, as a panel of the Commission, issued a 10-year site preparation license in 2012. The license document itself was not opened, so the stored decision date stays at year precision.
· Published
Published: Romania: Law 111/1996 on the safe conduct, regulation, licensing and control of nuclear activities #
Republication in Monitorul Oficial, Partea I nr. 552.
· Enacted
Enacted: France: Basic nuclear installation (INB) regime, Code de l'environnement, livre V, titre IX #
Law 2006-686 of 13 June 2006 on transparency and security in nuclear matters renovated the INB regime, later codified in the Environment Code.
· Enacted
Enacted: Florida Statutes § 366.93: nuclear and gasification plant cost recovery #
The official history line begins with section 44 of chapter 2006-230 and also cites chapters 2007-5, 2007-117, 2008-227 and 2013-184. Those acts were not opened. The year is the first chapter number on that line, not a calendar effective date for the current text.
· Electricity generation
HTR-10 combined heat-and-power trial operation #
NNSA's 2014 attachment records combined heat-and-power operation from October 2004 to April 2005 and from November 2005 to April 2006, during trial operation that began in December 2003. This is test operation; no grid connection, measured electrical output or commercial service is stated, and it is not evidence of current operation.
· Took effect
Took effect: New Mexico location approval for a large capacity plant #
The part prints EFFECTIVE DATE: May 1, 2004, unless a later date is cited at the end of a section. Section 17.9.592.8's history line is 5/1/2004.
· Published
Published: Minnesota Rules chapter 7855: certificate applications for nuclear fuel and waste facilities #
The revisor prints Published Electronically: November 14, 2003. That line is not stored as an adoption date.
· Enacted
Enacted: South Korea: Act on Physical Protection and Radiological Emergency (원자력시설 등의 방호 및 방사능 방재 대책법), emergency planning zones #
Enacted as Act No. 6873 (신규제정 2003. 5. 15).
· Recorded development
Yantai nuclear seawater desalination project: state approval of the project proposal #
INET's NHR200 page states that the Shandong nuclear seawater desalination project received state approval of its project proposal in March 2003. The 2019 INPRO slides name that project at Yantai.
· Recorded development
HTR-10 reaches full power (10 MW thermal) #
HTR-10 reached full power of 10 MW on 26 January 2003. The same NNSA attachment states overall parameters of 10 MW thermal and 2 MW electric, so the 10 MW full-power figure is the thermal power. It does not state a measured electrical output or a grid connection.
· Amended
Amended: Minnesota Statutes § 216B.243, subdivision 3b: nuclear certificate of need #
The current code's history line says 2003 c. 11, art. 1, s. 4 amended subdivision 3b. The 2003 session law was not opened, so the day of that amendment is not recorded. The current text includes the spent-fuel storage sentence, which was not in the 1994 subdivision.
· Took effect
Took effect: Poland: Atomic Law (Ustawa z dnia 29 listopada 2000 r. – Prawo atomowe) #
Art. 139, with exceptions for chapter 13 and art. 136 (14 days after publication) and arts. 21 ust. 2 and 27 ust. 2 (24 months after publication).
· Amended
Amended: New Hampshire RSA 162-F:1: decommissioning funding responsibility #
The source line prints 2001, 193:3, eff. Sept. 3, 2001. That is the latest cited amendment, not a finding about the 1971, 1981, or 1991 acts.
· Recorded development
Shenyang nuclear heating project: state approval of the project proposal #
INET states the 2 x 200 MW project proposal received state approval in April 2001.
· Recorded development
HTTR reaches full-power operation #
· First criticality
HTR-10 initial criticality #
· Issued
Issued: Poland: Atomic Law (Ustawa z dnia 29 listopada 2000 r. – Prawo atomowe) #
Ustawa z dnia 29 listopada 2000 r.
· Fuel load
HTR-10 first fuel loading begins #
· Took effect
Took effect: Canada: Nuclear Safety and Control Act (S.C. 1997, c. 9) #
Editorial note in the consolidated text: Act in force 31 May 2000 (SI/2000-42).
· Issued
Issued: Canada: Class I Nuclear Facilities Regulations (SOR/2000-204) #
Made by the CNSC and approved by P.C. 2000-784; registered 31 May 2000.
· Took effect
Took effect: Canada: Class I Nuclear Facilities Regulations (SOR/2000-204) #
Section 15: in force on the day approved by the Governor in Council (P.C. 2000-784 dated 31 May 2000).
· Recorded development
HTR-10 system commissioning begins #
· Operating authority recorded
Operating authority recorded: NNSA first fuel loading license for HTR-10 #
Reported in NNSA's own 2014 letter attachment; the 2000 license instrument itself was not opened, so no license number.
· Published
Published: South Africa: National Nuclear Regulator Act, 1999 (Act No. 47 of 1999) #
Government Gazette No. 20760, Office of the Presidency Notice No. 1537: the President has assented to the Act.
· Enacted
Enacted: South Africa: Nuclear Energy Act, 1999 (Act No. 46 of 1999) #
The Act's title gives the year 1999; the copy read shows no assent or commencement date.
· Amended
Amended: Maine Title 35-A, § 4302: nuclear construction referendum #
The official history line says PL 1999, c. 398, §A95 amended the section. The day and the changed words were not opened in the 1999 act.
· First criticality
HTTR first criticality #
· Published
Published: Argentina: Law 24.804, National Nuclear Activity Law (Ley Nacional de la Actividad Nuclear) #
Boletín Oficial No. 28634, page 1.
· Took effect
Took effect: Argentina: Law 24.804, National Nuclear Activity Law (Ley Nacional de la Actividad Nuclear) #
Article 41: in force from publication in the Boletín Oficial, 25 April 1997.
· Signed
Signed: Argentina: Law 24.804, National Nuclear Activity Law (Ley Nacional de la Actividad Nuclear) #
Promulgated partially by Decree 358/97 of 23 April 1997, which observed Article 40 (domestic nuclear fuel requirement) and the words 'under the Presidency of the Nation' in Article 2.
· Signed
Signed: Indonesia: Law No. 10 of 1997 on Nuclear Energy (Undang-Undang Nomor 10 Tahun 1997 tentang Ketenaganukliran) #
Disahkan di Jakarta pada tanggal 10 April 1997.
· Took effect
Took effect: Indonesia: Law No. 10 of 1997 on Nuclear Energy (Undang-Undang Nomor 10 Tahun 1997 tentang Ketenaganukliran) #
Article 48: in force on promulgation; promulgated 10 April 1997.
· Passed
Passed: Argentina: Law 24.804, National Nuclear Activity Law (Ley Nacional de la Actividad Nuclear) #
Sanción 02-04-1997.
· Enacted
Enacted: Canada: Nuclear Safety and Control Act (S.C. 1997, c. 9) #
Royal Assent to S.C. 1997, c. 9.
· Took effect
Took effect: Romania: Law 111/1996 on the safe conduct, regulation, licensing and control of nuclear activities #
Consolidated text header: in force from 28 December 1996.
· Enacted
Enacted: Romania: Law 111/1996 on the safe conduct, regulation, licensing and control of nuclear activities #
Law dated 10 October 1996.
· Signed
Signed: Russia: Federal Law No. 170-FZ 'On the Use of Atomic Energy' (1995) #
Russia's Federal Law on the Use of Atomic Energy (No. 170-FZ of 1995, consolidated to April 2025) requires licenses from the independent state safety regulation bodies for siting, construction, operation and decommissioning of nuclear installations. The law does not itself name the regulator. It is a framework statute, not a project permission.
· Passed
Passed: Russia: Federal Law No. 170-FZ 'On the Use of Atomic Energy' (1995) #
Adopted by the State Duma.
· Construction start
HTR-10 construction begins #
· Amended
Amended: California Public Resources Code § 25524.2: waste-disposal condition #
The official code says this section was amended by 1994 chapter 1145, section 17, effective 1 January 1995. It conditions state land use and certification on a high-level-waste finding. It does not approve a plant.
· Amended
Amended: California Public Resources Code § 25524.1: reprocessing condition #
The official code says this section was amended by 1994 chapter 1145, section 16, effective 1 January 1995. The original enactment date is not on this page. The condition is a state land-use and certification limit, not an NRC decision and not an SMR-only rule.
· Took effect
Took effect: Minnesota Statutes § 216B.243, subdivision 3b: nuclear certificate of need #
Article 2 says it is effective the day following final enactment. The same chapter records the 10 May 1994 signature, so that following day is 11 May 1994.
· Signed
Signed: Minnesota Statutes § 216B.243, subdivision 3b: nuclear certificate of need #
Chapter 641 records that the governor signed it on 10 May 1994. Article 2 added the certificate-of-need bar for a new nuclear-powered electric generating plant.
· Recorded development
Daqing siting report, EIA and feasibility study approved #
· Construction start
HTTR construction begins #
JAEA's history says construction of the 30 MW thermal test reactor began in 1991. The source gives the year only.
Checking notes
JAEA's history states that construction of HTTR began in 1991, after the November 1990 installation permit; installation work was largely finished in 1996.
· Recorded development
Decision to build an NHR-200 demonstration heating plant at Daqing #
· Regulatory step
HTTR installation permit granted #
JAEA's history says the HTTR installation permit was granted in November 1990. Reported by the operator; the permit document and its number were not reviewed.
Checking notes
JAEA's history states that the HTTR installation permit was obtained in November 1990. The permit document itself was not opened, so no number or day is recorded.
· Regulatory step
HTTR installation-permit application filed #
JAEA's history says the application for the HTTR installation permit was submitted to the government in February 1989. An application is not a permit.
Checking notes
JAEA's history states that the HTTR installation-permit application was submitted to the state in February 1989.
· Enacted
Enacted: Nevada prohibition on storing high-level radioactive waste #
The source note prints Added to NRS by 1989, 2113. No calendar day is printed.
· Took effect
Took effect: Finland: Nuclear Energy Act (ydinenergialaki 990/1987) #
Finlex voimaantulo 1.3.1988.
· Enacted
Enacted: Brazil: Federal Constitution art. 225 § 6, location of nuclear power plants defined by federal law #
The compilation identifies the text as the 1988 Federal Constitution (CF/1988); the promulgation day is not stated on the page read.
· Issued
Issued: Finland: Nuclear Energy Act (ydinenergialaki 990/1987) #
Finlex antopäivä 11.12.1987.
· Enacted
Enacted: Maine Title 35-A, § 4302: nuclear construction referendum #
The official history line says PL 1987, c. 141, §A6 enacted this section. The day is not on the page. The requirement is a statewide voter question before construction, not an approval of a plant.
· Enacted
Enacted: Rhode Island energy facility siting license #
The license section history prints P.L. 1986, ch. 531, § 1. It does not print a day.
· Took effect
Took effect: Sweden: Act on Nuclear Activities (SFS 1984:3, lag om kärnteknisk verksamhet) #
Transitional provision 1984:3 point 1.
· Issued
Issued: Sweden: Act on Nuclear Activities (SFS 1984:3, lag om kärnteknisk verksamhet) #
Utfärdad 1984-01-12.
· Amended
Amended: South Dakota energy facility construction permit #
The source line prints SL 1977, ch 390, § 4 and SL 1983, ch 349. It does not print a day. The 1 July 1979 date is the construction threshold in the section, not a stored effective date.
· Enacted
Enacted: Idaho Code § 39-3027: voter submission before a law prohibiting nuclear generation #
The official history line says the section was added in 1982 by Initiative Measure 3. The day is not on the page. The section limits a prohibition; it does not approve a plant.
· Took effect
Took effect: Ohio certificate required before major-utility construction #
The official section page prints Effective November 15, 1981. The fifty-megawatt definition's 14 August 2025 date is stored on the section 4906.01 record.
· Enacted
Enacted: Oregon conditions for a nuclear-fueled thermal power plant #
The 2025 edition cites 1981 chapter 1 for these sections. It does not print a calendar day. Later amendment years printed on the storage section are not stored as this record's effective date.
· Enacted
Enacted: Hawaii Constitution article XI, section 8: nuclear fission plants #
The compilation prints Add Const Con 1978 and election Nov 7, 1978. It does not print a separate effective date.
· Took effect
Took effect: Norway: Act on Atomic Energy Activities (LOV-1972-05-12-28, atomenergiloven) #
Note 1 to s. 58: in force from 1 July 1973 under royal resolution of 25 May 1973; ss. 40-41 from 4 December 1974.
· Issued
Issued: Norway: Act on Atomic Energy Activities (LOV-1972-05-12-28, atomenergiloven) #
Lovdata identifier LOV-1972-05-12-28 (Act of 12 May 1972 no. 28).
· Enacted
Enacted: Idaho Code § 39-3020: Western Interstate Nuclear Compact #
The official history line says the section was added in 1969 by chapter 34, section 1, page 61. The day is not on the page. That year is not the compact's initial effective date.
· Issued
Issued: Netherlands: Nuclear Energy Act (Kernenergiewet) #
Wet van 21 februari 1963. Article 89 leaves the in-force dates of most provisions to royal decree.
· Enacted
Enacted: Japan: Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors (Act No. 166 of 1957) #
Promulgation date of Act No. 166 of 1957.
Upcoming targets
Earliest first. Planned, target and estimated dates are not achievements or commitments. Show the 4 met and historical targets, listed separately.
Target · Planned step
Unity reactor-physics testing incl. passive shutdown and decay-heat tests (planned) #
Target · Construction start
CDE construction start (company target stated in February 2026, not reconfirmed by the May edition) #
Earlier 2026 company construction-start target from the February 2026 paper, not an achieved milestone. The May edition instead describes core completion two years after financing and then two years of testing; that relative sequence does not reconfirm this calendar-year target. No comparable structured revision is inferred.
Target · First criticality
Last Energy targets a 2026 criticality demonstration for its RELLIS pilot #
Last Energy said it expected to demonstrate criticality of the PWR-5 pilot in 2026, after DOE's readiness review and startup authorization. A target only; DOE has not published a startup authorization.
Checking notes
Last Energy said in December 2025 that it was preparing for an anticipated 2026 criticality demonstration at RELLIS. In October 2026 it said it was moving into DOE's readiness review, the final step before DOE can issue startup authorization. A company target, not an achieved milestone.
Target · Planned step
Reported target: Linglong One fuel loading and grid connection within 2026 #
China News Service reported from the Changjiang site on 1 October 2026 that the unit was aiming for fuel loading and grid-connected generation within the year; NucNet relayed this as targets before the end of 2026. These are reported targets, not achieved milestones. No fuel-loading approval is shown in the sources reviewed. This entry does not cover commercial operation.
Target · Planned step
MARVEL assembly expected to finish #
DOE's project page, read on 5 October 2026, says assembly is expected to finish in 2026. It does not give a day or a quarter. This is a target, not an achieved milestone, and not a safety approval.
Target · Milestone
Milestone: Executive Order 14300: reform of the Nuclear Regulatory Commission #
Section 5: final rules and guidance to conclude the NRC's revision within 18 months of the order, signed 23 May 2025. The order gives the period, not a calendar date; November 2026 is the month it ends. A target, not a result.
Planned · Provision effective date recorded
Provision effective date recorded: South Korea: Nuclear Safety Act (원자력안전법) #
The government's legislative entry for the enforcement rule gives 20 November as the start date for the pre-review amendment; the Commission's May press release said November.
Target · Planned step
NRC target: advanced final safety evaluation report without open items for the Belews Creek ESP #
NRC target: advanced final safety evaluation report without open items for the Belews Creek ESP in December 2026, accelerated from March 2027 by the 29 September 2026 schedule letter.
Revised target. Earlier target: Mar 2027, stated 8 Feb 2026. Moved earlier.
Target · Planned step
NRC target: draft environmental impact statement for the Belews Creek ESP #
NRC target: draft environmental impact statement for the Belews Creek ESP in December 2026, accelerated from February 2027 by the 29 September 2026 schedule letter.
Revised target. Earlier target: Feb 2027, stated 8 Feb 2026. Moved earlier.
Target · Planned step
Norrsundet facility plan proposal due to the Government #
Target · Planned step
Applicant-requested date for LWA and 10 CFR 50.10(d) exemption issuance #
Applicant's requested review schedule, not an NRC commitment.
Target · Planned step
Målma facility plan proposal due to the Government #
Target · Planned step
Target: interim report on RoPower Nuclear's measures #
The shareholder note for the 29 October 2026 meeting calls for a phased schedule at RoPower Nuclear with an interim report on the steps taken by 31 December 2026; shareholders adopted the note's Section 4 measures on 29 October 2026. A deadline from Nuclearelectrica's note, not a result; whether the report has been made is not recorded.
Target · Planned step
Ascension on-site data-center supply target #
The company targets 2027 pilot electricity supply. This is not achieved generation or a stated commercial-operation date.
Target · Planned step
Aalo-X full-power test (30 MWth, ~10 MWe) planned #
Full-power test is beyond the zero-power critical assembly covered by CX-271002.
Target · Electricity generation
Antares target: Mark-1 electricity production at INL in 2027 #
Antares's 17 February 2026 roadmap says it intends to produce electricity with its full-scale Mark-1 reactor within 2027, in the INL test facility it established for the Mark-0 pilot.
Target · Planned step
Concreting of the BREST-OD-300 reactor vessel to finish (company target) #
Source says 'winter 2027' (season precision not supported by schema).
Target · Planned step
First Baimsky floating unit: reported power-service target (August 2022) #
At the August 2022 keel-laying, WNN reported that the first unit would supply power at Cape Nagloynyn by 2027. An Interfax report of 13 August 2026 states, in its own background note, that the first unit is expected to be put into service in 2028.
Target · Regulatory step
Blue Energy target: submit the remaining construction permit application (Part 2) in 2027 #
Target · Planned step
Deep Fission Parsons DOE pilot targeted #
Undated company project page read 13 October 2026 targets the DOE pilot phase in 2027 and still lists DOE authorization as a next step. A data well and non-nuclear canister are not a fueled reactor.
Target · Planned step
Unity full-power DOME test targeted #
INL’s 30 September 2026 release targets 2027 for Unity testing at DOME. Conditional schedule, not an achieved test.
Target · First criticality
MARVEL dry initial criticality anticipated #
DOE's project page, read on 5 October 2026, says dry initial criticality is anticipated in 2027; it gives a year, not a day. INL's release dated 6 October 2026 says criticality is anticipated to occur in December, with initial startup tests this winter; it prints no year beside December, and SMRMap reads it as the coming December only from that context. The two official targets therefore appear to differ. Neither is an achieved criticality or operating authority.
Target · Planned step
Formal Pele system testing (BWXT plan, as early as) #
Target · Planned step
Temelín SMR EIA process expected to be completed #
Target · Construction start
NANO expectation: initial construction activities at U. of I. in the second half of 2027 #
Planned · Effective date recorded
Effective date recorded: Finland: Nuclear Energy Act (ydinenergialaki 775/2026) #
Section 473: in force 1 January 2027.
Planned · Provision effective date recorded
Provision effective date recorded: South Korea: Nuclear Safety Act (원자력안전법) #
NSSC: periodic inspection exemption and fine provisions apply from 1 January 2027.
Target · Planned step
NRC target for Pioneer advanced safety evaluation report #
The NRC milestone table targets an advanced safety evaluation report without open items for 31 January 2027. This is a target, not an issued report, authorization or permit.
Target · Planned step
NRC target: final safety evaluation for the Belews Creek ESP #
NRC target: final safety evaluation for the Belews Creek ESP in February 2027, accelerated from May 2027 by the 29 September 2026 schedule letter.
Revised target. Earlier target: May 2027, stated 8 Feb 2026. Moved earlier.
Target · Planned step
NRC target for a draft KRONOS safety evaluation #
NRC schedule target for a draft safety evaluation. Not a completed decision.
Target · Planned step
NRC target for a draft KRONOS environmental assessment #
NRC schedule target for a draft environmental assessment. Not a completed decision.
Target · Planned step
NRC target: final environmental impact statement for the Belews Creek ESP #
NRC target: final environmental impact statement for the Belews Creek ESP in March 2027, accelerated from May 2027 by the 29 September 2026 schedule letter.
Revised target. Earlier target: May 2027, stated 8 Feb 2026. Moved earlier.
Target · Planned step
NRC target for Pioneer final safety evaluation report #
The NRC milestone table targets the final safety evaluation report for 31 March 2027. This is a target, not an issued report, authorization or permit.
Target · Planned step
NRC target for Pioneer final environmental impact statement #
The NRC milestone table targets the final environmental impact statement for 31 March 2027. This is a target, not an issued statement, authorization or permit.
Target · Planned step
Untra facility plan proposal due to the Government #
Target · Planned step
NRC target for a final KRONOS environmental assessment #
NRC schedule target for a final environmental assessment. Not a completed decision.
Target · Planned step
NRC target for a final KRONOS safety evaluation #
NRC schedule target for a final safety evaluation. Not a completed decision.
Target · Milestone
Milestone: United Kingdom: Building our nuclear nation, government response to the Nuclear Regulatory Review 2025 #
Government commitment to implement the recommendations, including legislation, before the end of 2027, subject to parliamentary timings.
Target · Planned step
First Baimsky floating unit: reported power-service target #
First of four Baimsky floating power units commissioned (target). 'введут первый блок' = put into service; exact milestone type (commissioning vs commercial operation) not specified.
Target · Planned step
BALDER: first tests no earlier than 2028 #
PSI’s Q3 2026 planning statement (re-read 10 November 2026) gives an earliest boundary for first tests, not a commitment to tests during 2028. The application and permissions remain pending.
Target · Planned step
CDE testing phase (company target stated in February 2026, not reconfirmed by the May edition) #
Earlier 2028 company testing target from the February 2026 paper, not an achieved milestone. The May edition instead describes core completion two years after financing and then two years of testing; that relative sequence does not reconfirm this calendar-year target. No comparable structured revision is inferred.
Target · Planned step
Kairos expects Hermes test reactor construction to be complete in 2028 #
Kairos told the NRC in March 2026 that it expects to finish building the Hermes test reactor in 2028; the NRC later extended the permit’s latest completion date to April 2029. A construction target; no fuel-loading or operation date is stated and no operating license is recorded.
Checking notes
In its March 2026 request to extend construction permit CPTR-6, Kairos said it now expects to complete construction of the Hermes test reactor facility in 2028; the NRC extended the latest completion date to 30 April 2029. The 2028 date is a company target.
Target · Electricity generation
MARVEL full-power operation and electricity generation anticipated #
DOE's project page says the transition to full-power operation is anticipated in 2028, with electricity generation first. The page gives a year, not a day. This is a target. It is not commercial operation and not authority to operate.
Target · Commercial operation
Aurora-INL commercial deployment target #
Aurora-INL commercial deployment target of 2028 on Oklo's undated Idaho page, read on 7 October and 11 November 2026. Oklo's report on Form 10-Q signed 6 November 2026 gives a target of 2028-2029 for deploying its first powerhouse at INL, where its report signed 7 August 2026 gave 2028. Company targets, not an achieved milestone.
Target · Electricity generation
Pele first electricity at INL (BWXT plan, as soon as) #
Target · Construction start
Start of full-scope nuclear construction (applicant expectation) #
Conditional on Part 2 submittal and NRC construction-permit issuance.
Estimate · Planned step
MARVEL process-heat stage likely #
DOE's project page says a second stage, likely in 2029, would supply process heat after electricity. The page says likely. This is not an achieved milestone and not authority to operate.
Target · First criticality
First criticality of first RITM-200N unit (expected late 2029) #
Source says 'late 2029'.
Target · Planned step
U. of I. expectation: system on-line in 2029–2030 #
Target · Grid connection
OPG target: connect Darlington BWRX-300 Unit 1 to the grid by the end of 2030 #
In October 2025 OPG said it expects to complete construction of SMR 1 by the end of the decade and connect it to the grid by the end of 2030, as reported by WNN.
Revised target. Earlier target: 2029, stated 30 Nov 2023. Moved later.
Target · Planned step
Elementl target for starting construction of the first Letart unit #
Elementl expects construction of the first unit to begin in 2030, subject to a final investment decision and NRC and Ohio Power Siting Board approvals, with the first unit's completion anticipated in 2034. A company target, not a commitment, a permission or a construction start.
Target · Planned step
HTTR hydrogen production (JAEA target) #
Target · Planned step
Kairos target: Hermes 2 to begin operations in 2030 #
Kairos Power said on 18 August 2025 that it would raise Hermes 2 output from 28 MW to 50 MW generated by a single reactor, scheduled to begin operations in 2030. This is a company target for a configuration the NRC permits do not reflect. It is not an achieved milestone, and no operating license is recorded.
Target · Planned step
TerraPower targets 2030 construction completion for Kemmerer Unit 1 #
TerraPower said in September 2026 that its schedule calls for construction completion in 2030 and commercial operation by 2031. A target only; no operating license application or operating license is recorded. POWER reported in April 2026 that US SFR Owner told the NRC it expects to complete construction by February 2031.
Checking notes
A TerraPower spokesperson, quoted in September 2026, said the project timeline calls for construction completion in 2030 and commercial operation by 2031. These are company targets, not achieved milestones. POWER's 23 April 2026 timeline says US SFR Owner told the NRC it expects to complete construction by February 2031. The two statements are not reconciled here.
Target · Commercial operation
StarCore targets first commercial power #
Current undated investor page identifies Whiteshell first facility and targets first commercial power 2030. Company schedule only; no plant rating, module count or permission is inferred. The undated Pinawa page separately targets operations by end 2028; the company schedules are unreconciled.
Target · First criticality
Alvin: company target for first criticality #
Stellaria’s 23 April 2026 program description targets Alvin criticality in 2030. This is a company target, not a regulatory decision or achieved operation.
Revised target. Earlier target: 2029, stated 12 Mar 2025. Moved later.
Target · Planned step
ALFRED: RATEN roadmap target for siting permit #
RATEN's 2026 workshop roadmap targets siting permit in 2031. This is a planning target, not an achieved milestone or granted permission.
Target · Commercial operation
Fourth Baimsky floating power unit commissioned (target) #
Target · Planned step
Construction of both Pioneer units completed (applicant expectation) #
Target · Planned step
Kemmerer Unit 1: reported online target at the end of 2031 #
Utah Division of Public Utilities testimony dated 23 January 2026 projects the plant online at the end of 2031; this is the witness's projection, not an achieved milestone or a TerraPower commitment. POWER's 23 April 2026 retrospective timeline attributes a 2028 commercial-operation target to November 2021 and reports an interim 2030 completion target in 2023. These are selected historical statements, not consecutive revisions. The testimony does not define online as commercial operation, so no same-milestone change is calculated.
Target · Planned step
Xuwei Phase I, all three units, expected to be fully completed in 2031 #
A press report says the whole of Phase I, including the Unit 3 high-temperature reactor, is expected to be fully completed and in use in 2031. This target covers the whole phase; it is not a Unit 3 commercial-operation date.
Checking notes
China Energy News reported on 3 August 2026 that the whole of Xuwei Phase I, two Hualong One units and the Unit 3 high-temperature gas-cooled reactor, is expected to be fully completed and in use in 2031. This target covers the whole phase; it is not a Unit 3 commercial-operation date.
Target · Planned step
Yakutia: reported operation target #
The 27 February 2026 report gives 2031 as the planned operation year. This reported target is not an operating license or achieved operation. Rosatom in May 2024 described first-unit launch in 2027 and commissioning in 2028. The February 2026 report concerns a two-unit facility. These are separate dated statements; a directly comparable revision of the same unit and milestone is not established.
Target · Planned step
ALFRED: RATEN roadmap target for construction permit #
RATEN's 2026 workshop roadmap targets construction permit in 2032. This is a planning target, not an achieved milestone or granted permission.
Target · Commercial operation
Blue Energy target: five BWRX-300 units on line in 2032 #
Target · Planned step
INB Alpha: company target to convert the facility to MegAlvin #
Target · Milestone
Milestone: India: Nuclear Energy Mission for small modular reactors (Union Budget 2025-26 announcement) #
Government aim stated by PIB: at least five indigenously designed SMRs operational by 2033.
Target · Planned step
Fermi Energia application: first reactor could start operating in 2035 at the earliest #
Estonia's government said on 22 May 2025 that the first of the two planned reactors could, according to Fermi Energia's application, start operating in 2035 at the earliest, assuming smooth processes. Fermi's planning page says the first reactor would produce electricity in the second half of 2035. This is an applicant's earliest case, not a commitment or an achieved milestone, and no site is final.
Target · Planned step
ALFRED: RATEN roadmap target for commissioning permit #
RATEN's 2026 workshop roadmap targets commissioning permit in 2036. This is a planning target, not an achieved milestone or granted permission.
Target · Commercial operation
Duke conditional plan: first SMR on line at Belews Creek in 2036 #
Target · Planned step
ALFRED: RATEN roadmap target for operation #
RATEN's 2026 workshop roadmap targets operation in 2037. This is a planning target, not an achieved milestone or granted permission.
Targets whose recorded period has passed
No development meeting these is recorded. A passed target period alone does not mean the step failed or was canceled.
Target · Planned step · Date passed; not recorded as met
NRC target for Pioneer draft environmental impact statement #
The NRC milestone table targeted a draft environmental impact statement for 31 October 2026. The NRC's project page, updated 30 October 2026, lists that milestone's date as TBD and shows no draft as issued. This is a target, not an achieved review or permission.
Target · Planned step · Date passed; not recorded as met
Radiant target: 150-hour continuous full-power run at DOME #
Targets met
Each is linked to the recorded development of the same project and step that met it.
Target · First concrete · Met on
Xuwei Unit 3 (HTGR) first concrete expected #
Target · Planned step · Met on
NRC target: final safety evaluation for the Clinch River construction permit #
On 18 June 2026 (ML26160A308) the NRC staff moved its planned issue of the Clinch River final safety evaluation to 30 June 2026, ahead of the November 2026 schedule, citing review efficiencies.
Revised target. Earlier target: Nov 2026, stated 25 Jul 2025. Moved earlier.
Target · Planned step · Met on
NRC target for the Long Mott final safety evaluation #
NRC schedule target for issuing its final safety evaluation of the construction-permit application. NRC news release 26-083 of 9 November 2026 says staff completed the safety evaluation in October, one month ahead of schedule, and the permit has been issued. The NRC's project page, re-read on 10 November, still showed the November target. The evaluation was completed; the target date itself is kept as the schedule that was stated.
Targets on earlier-plan and canceled records
Targets kept from earlier plans or canceled projects. They are history, not live plans.
Target · Construction start · Date passed; not recorded as met
Daqing NHR-200 construction start (historical target, not met) #
Targets without a usable date
Planned, target or estimated entries without a usable date. They are not achievements.
Target · Planned step
OSGE states first Włocławek BWRX-300 unit is to be commissioned in the mid-2030s #
OSGE's release of 22 October 2026 on the umbrella agreement among Orlen, SGE and OSGE says the first BWRX-300 unit at Włocławek is to be commissioned in the mid-2030s. Its 29 June 2026 release had assumed 2032, and a 29 September 2026 release said the first BWRX-300 in Poland may start in 2032 without naming a site. These are company statements, not permit dates.
Last editorial review (selected sources): 18 Oct 2026
Finishing pass of 18 October 2026: the 90 pending monitoring leads were opened and classified; all 42 published projects at licensing, construction, commissioning or operating stage were re-read against their regulator, government and developer sources (stage, permission, operator, capacity basis, fuel, named customers, funders and contractors, next milestone); national policy instruments were reviewed for the ten countries outside the US hosting those projects; and named leads (Amazon/Cascade, Bechtel/Natrium, NuCore Oskarshamn, Steady Energy, Philippines agreements) were adjudicated. Other projects' sources were not rechecked. This is a review date, not an event date or a claim that every source is current. Daily source checks raise leads for review; verified changes are published separately.