Policy and licensing

Unlike Agreements, which follows agreements, plans and studies by who takes part, this page records laws, rules, funding programs and awards as measures (status, scope and dated steps), together with every recorded permit and application.

Explore nuclear-policy measures and the recorded applications and decisions for tracked projects and designs.

192 policy records · 76 regulatory records. A record is not necessarily an approval.

Selected source-linked records, not a complete policy inventory. A law, funding selection or design assessment does not approve a reactor.

Recent changes

The 30 latest policy and regulatory steps recorded as having happened, newest first, including international actions. A date given only as a month or year means the day is not recorded.

Coming up

Effective dates already set for the future, planned dates and targets that had not passed when this page was published, soonest first. A planned date or a target is not an achievement or a commitment.

All US policy steps → · All project, policy and regulatory updates →

Policy records

192 records listed

Grouped by jurisdiction: the United States (federal) and other countries first, then the European Union, then US states and territories. Within each, the measure with the newest recorded step comes first.

MeasureJurisdictionCategoryStatusLatest step
United States (federal) · 36 records
Proposed regulatory enhancements for reactor licensing, decommissioning and operational oversightUnited States (federal)Bills, proposed rules and consultationsProposed ruleProposed — not in effectComment period closed
NRC consultation: draft non-light-water reactor materials guidanceUnited States (federal)Bills, proposed rules and consultationsConsultationProposed — not in effectComment period closed
NRC final rule: Streamlining Contested Adjudications in Licensing ProceedingsUnited States (federal)Laws, rules and executive directivesFinal ruleAdopted, not yet in effectPublished
NRC direct final rule: NRC Modernization: Rulemaking Procedure, Federal Advisory Committee Act Alignment, Access, and SecurityUnited States (federal)Laws, rules and executive directivesFinal ruleIn effectTook effect
NRC reviews of reactor designs previously authorized by DOE or the Department of WarUnited States (federal)Laws, rules and executive directivesFinal ruleAdopted, not yet in effectPublished
NRC final rule: Fee Schedules; Fee Recovery for Fiscal Year 2026 (with Executive Order 14300 fixed fee caps)United States (federal)Laws, rules and executive directivesFinal ruleIn effectProvision took effect
NRC consultation: draft training-review guidanceUnited States (federal)Bills, proposed rules and consultationsConsultationProposed — not in effectComment period closed
Army adoption of DOE advanced-reactor categorical exclusionUnited States (federal)Regulatory guidance and inspector policiesRegulatory guidancePublished guidance — not a law or project permissionPublished
Proposed modernization of reactor licensing, safety oversight and siting practicesUnited States (federal)Bills, proposed rules and consultationsProposed ruleProposed — not in effectComment period closed
NRC proposal: package certification and microreactor transportUnited States (federal)Bills, proposed rules and consultationsProposed ruleProposed — not in effectProposed
DOE HALEU Availability Program and HALEU allocation processUnited States (federal)Funding and support programsFunding programIn effectNo award recordedSelections announced
Proposed modernization of NRC radiation-protection standardsUnited States (federal)Bills, proposed rules and consultationsProposed ruleProposed — not in effectProposed
Proposed revisions to NRC implementation of NEPAUnited States (federal)Bills, proposed rules and consultationsProposed ruleProposed — not in effectProposed
DOE Reactor Pilot ProgramUnited States (federal)Funding and support programsAuthorization programIn effectNo award recordedMilestone
NRC proposal: modernizing materials licensingUnited States (federal)Bills, proposed rules and consultationsProposed ruleProposed — not in effectProposed
Proposed licensing requirements for microreactors and comparable reactorsUnited States (federal)Bills, proposed rules and consultationsProposed ruleProposed — not in effectComment period closed
Generic environmental impact statement rule for licensing new nuclear reactorsUnited States (federal)Laws, rules and executive directivesFinal ruleIn effectTook effect
NRC final rule: Increased Flexibility in the Mandatory Hearing ProcessUnited States (federal)Laws, rules and executive directivesFinal ruleIn effectTook effect
DOE Generation III+ Small Modular Reactor programUnited States (federal)Funding and support programsFunding programIn effectSelections announced
Gen III+ SMR selections of May 2026: early site permits and supply chainUnited States (federal)Awards and selectionsAwardSelected — award terms not recorded as finalSelections announced
MARAD consultation: a marine SMR conceptUnited States (federal)Bills, proposed rules and consultationsConsultationProposed — not in effectPublished
10 CFR Part 53: risk-informed, technology-inclusive licensing frameworkUnited States (federal)Laws, rules and executive directivesFinal ruleIn effectTook effect
NRC final rule: Categorical Exclusions From Environmental ReviewUnited States (federal)Laws, rules and executive directivesFinal ruleIn effectTook effect
Gen III+ SMR selection: Holtec (Palisades SMR-300)United States (federal)Awards and selectionsAwardSelected — award terms not recorded as finalSelections announced
Gen III+ SMR selection: TVA (Clinch River BWRX-300)United States (federal)Awards and selectionsAwardSelected — award terms not recorded as finalSelections announced
ADVANCE Act of 2024United States (federal)Laws, rules and executive directivesStatuteIn effectProvision took effect
NRC direct final rule: Revising the Duration of Design CertificationsUnited States (federal)Laws, rules and executive directivesFinal ruleIn effectTook effect
Internal Revenue Code sections 45Y and 48E: clean electricity production and investment credits, as amended by Public Law 119-21United States (federal)Laws, rules and executive directivesStatuteIn effectAmended
Executive Order 14299: advanced reactors for national securityUnited States (federal)Laws, rules and executive directivesExecutive orderIn effectPublished
Executive Order 14300: reform of the Nuclear Regulatory CommissionUnited States (federal)Laws, rules and executive directivesExecutive orderIn effectPublished
Executive Order 14301: reactor testing at the Department of EnergyUnited States (federal)Laws, rules and executive directivesExecutive orderIn effectPublished
Executive Order 14302: nuclear industrial baseUnited States (federal)Laws, rules and executive directivesExecutive orderIn effectPublished
Emergency preparedness rule for small modular reactors and other new technologiesUnited States (federal)Laws, rules and executive directivesFinal ruleIn effectTook effect
ARDP demonstration award: TerraPower (Natrium)United States (federal)Awards and selectionsAwardAwardedAwarded
ARDP demonstration award: X-energy (Xe-100)United States (federal)Awards and selectionsAwardAwardedAwarded
DOE Advanced Reactor Demonstration Program (demonstration awards)United States (federal)Funding and support programsFunding programIn effectAwarded
Argentina · 2 records
Argentina: Strategic Guidelines on Innovation, Science and Technology 2025-2027 (Resolución 282/2025)ArgentinaRegulatory guidance and inspector policiesRegulatory guidancePublished guidance — not a law or project permissionPublished
Argentina: Law 24.804, National Nuclear Activity Law (Ley Nacional de la Actividad Nuclear)ArgentinaLaws, rules and executive directivesStatuteIn effectPublished
Brazil · 2 records
Brazil: Law 14.222/2021 creating the National Nuclear Safety Authority (ANSN)BrazilLaws, rules and executive directivesStatuteIn effectProvision took effect
Brazil: Federal Constitution art. 225 § 6, location of nuclear power plants defined by federal lawBrazilLaws, rules and executive directivesStatuteIn effectEnacted
Canada · 6 records
Canada: Building Canada Act (S.C. 2025, c. 2, s. 4), national interest projectsCanadaLaws, rules and executive directivesStatuteIn effectAmended
Canada: Clean technology investment tax credit for small nuclear energy property (Income Tax Act s. 127.45)CanadaLaws, rules and executive directivesStatuteIn effectAmended
Canada: Enabling Small Modular Reactors Program (Natural Resources Canada)CanadaFunding and support programsFunding programIn effectNo award recordedMilestone
Canada: Physical Activities Regulations, Schedule item 27 – new fission or fusion reactors (SOR/2019-285)CanadaLaws, rules and executive directivesFinal ruleIn effectTook effect
Canada: Class I Nuclear Facilities Regulations (SOR/2000-204)CanadaLaws, rules and executive directivesFinal ruleIn effectIssued
Canada: Nuclear Safety and Control Act (S.C. 1997, c. 9)CanadaLaws, rules and executive directivesStatuteIn effectTook effect
China · 3 records
China: Atomic Energy Law of the People's Republic of China (2025)ChinaLaws, rules and executive directivesStatuteIn effectTook effect
China: Safety licensing procedure for nuclear power plants, research reactors and fuel cycle facilities (MEE Order No. 8, 2019)ChinaLaws, rules and executive directivesFinal ruleIn effectTook effect
China: Nuclear Safety Law of the People's Republic of China (2017)ChinaLaws, rules and executive directivesStatuteIn effectTook effect
Croatia · 1 record
Croatia: Law on the Development of Nuclear Energy for Civil Purposes (NN 55/2026)CroatiaLaws, rules and executive directivesStatuteIn effectTook effect
Czechia · 2 records
Czechia: Atomic Act (Act No. 263/2016 Coll., atomový zákon)CzechiaLaws, rules and executive directivesStatuteIn effectTook effect
Czechia: SÚJB Decree No. 378/2016 Coll. on siting of a nuclear installationCzechiaLaws, rules and executive directivesFinal ruleIn effectTook effect
Estonia · 1 record
Estonia: Nuclear Energy and Nuclear Safety Act (Tuumaenergia ja -ohutuse seadus)EstoniaLaws, rules and executive directivesStatuteAdopted, not yet in effectPublished
Finland · 2 records
Finland: Nuclear Energy Act (ydinenergialaki 775/2026)FinlandLaws, rules and executive directivesStatuteAdopted, not yet in effectPublished
Finland: Nuclear Energy Act (ydinenergialaki 990/1987)FinlandLaws, rules and executive directivesStatuteIn effectTook effect
France · 3 records
France: Basic nuclear installation (INB) regime, Code de l'environnement, livre V, titre IXFranceLaws, rules and executive directivesStatuteIn effectMilestone
France: France 2030 call for projects « Réacteurs nucléaires innovants » (first call)FranceFunding and support programsFunding programCompletedNo award recordedCompleted
France: Loi n° 2023-491 du 22 juin 2023 (accélération des procédures nucléaires près des sites existants)FranceLaws, rules and executive directivesStatuteIn effectPublished
India · 4 records
India: Draft SHANTI Regulations, 2026 (Atomic Energy Regulatory Board consultation)IndiaBills, proposed rules and consultationsConsultationProposed — not in effectComment period closed
India: Draft SHANTI Rules, 2026 (Department of Atomic Energy consultation)IndiaBills, proposed rules and consultationsConsultationProposed — not in effectComment period closed
India: Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Act, 2025 (No. 39 of 2025)IndiaLaws, rules and executive directivesStatuteAdopted, not yet in effectPublished
India: Nuclear Energy Mission for small modular reactors (Union Budget 2025-26 announcement)IndiaFunding and support programsFunding programIn effectNo award recordedNo dated step recorded
Indonesia · 4 records
Indonesia: Government Regulation No. 40 of 2025 on National Energy Policy (Peraturan Pemerintah Nomor 40 Tahun 2025 tentang Kebijakan Energi Nasional)IndonesiaLaws, rules and executive directivesFinal ruleIn effectIssued
Indonesia: Law No. 10 of 1997 on Nuclear Energy (Undang-Undang Nomor 10 Tahun 1997 tentang Ketenaganukliran)IndonesiaLaws, rules and executive directivesStatuteIn effectAmended
Indonesia: BAPETEN Regulation No. 4 of 2018 on Safety Provisions for Site Evaluation of Nuclear InstallationsIndonesiaLaws, rules and executive directivesFinal ruleIn effectTook effect
Indonesia: Government Regulation No. 2 of 2014 on Licensing of Nuclear Installations and Use of Nuclear Material (Peraturan Pemerintah Nomor 2 Tahun 2014)IndonesiaLaws, rules and executive directivesFinal ruleIn effectIssued
Japan · 3 records
Japan: NRA rule on standards for the location, structure and equipment of commercial power reactors (NRA Rule No. 5 of 2013)JapanLaws, rules and executive directivesFinal ruleIn effectAmended
Japan: Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors (Act No. 166 of 1957)JapanLaws, rules and executive directivesStatuteIn effectProvision took effect
Japan: Long-Term Decarbonization Power Source Auction (capacity market, from FY2023)JapanFunding and support programsFunding programIn effectNo award recordedOpened
Netherlands · 3 records
Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie)NetherlandsFunding and support programsFunding programIn effectNo award recordedAwarded
Netherlands: Environmental Quality Decree (Besluit kwaliteit leefomgeving), nuclear power plant locationsNetherlandsLaws, rules and executive directivesFinal ruleIn effectIssued
Netherlands: Nuclear Energy Act (Kernenergiewet)NetherlandsLaws, rules and executive directivesStatuteIn effectIssued
Norway · 2 records
Norway: Regulations on impact assessments (FOR-2017-06-21-854), Annex I item 2 b on nuclear reactorsNorwayLaws, rules and executive directivesFinal ruleIn effectTook effect
Norway: Act on Atomic Energy Activities (LOV-1972-05-12-28, atomenergiloven)NorwayLaws, rules and executive directivesStatuteIn effectTook effect
Poland · 3 records
Poland: Polish Nuclear Power Programme, 2026 update (Council of Ministers Resolution No. 198 of 29 September 2026)PolandLaws, rules and executive directivesExecutive orderIn effectTook effect
Poland: Act on preparing and carrying out investments in nuclear power facilities and accompanying investments (2011 special act)PolandLaws, rules and executive directivesStatuteIn effectProvision took effect
Poland: Atomic Law (Ustawa z dnia 29 listopada 2000 r. – Prawo atomowe)PolandLaws, rules and executive directivesStatuteIn effectProvision took effect
Romania · 2 records
Romania: Law 111/1996 on the safe conduct, regulation, licensing and control of nuclear activitiesRomaniaLaws, rules and executive directivesStatuteIn effectAmended
Romania: CNCAN nuclear safety norms on the siting of nuclear power plants (NSN-01)RomaniaLaws, rules and executive directivesFinal ruleIn effectPublished
Russia · 3 records
Russia: Federal Law No. 170-FZ 'On the Use of Atomic Energy' (1995)RussiaLaws, rules and executive directivesStatuteIn effectAmended
Russia: General Scheme for the placement of electric power facilities to 2042 (Government Order No. 4153-r, 2024)RussiaLaws, rules and executive directivesExecutive orderIn effectIssued
Russia: Federal norms and rules NP-032-19 'Nuclear power plant site. Safety requirements' (Rostekhnadzor Order No. 287, 2019)RussiaLaws, rules and executive directivesFinal ruleIn effectTook effect
Rwanda · 3 records
Rwanda: RURA Regulation No 013/2024 governing licensing of nuclear installationsRwandaLaws, rules and executive directivesFinal ruleIn effectIssued
Rwanda: Presidential Order N° 127/01 establishing the Rwanda Atomic Energy Board (2020)RwandaLaws, rules and executive directivesExecutive orderIn effectPublished
Rwanda: Law N° 59/2017 governing radiation protectionRwandaLaws, rules and executive directivesStatuteIn effectPublished
South Africa · 3 records
South Africa: Regulations on Licensing of Sites for New Nuclear Installations (GN R. 927 of 11 November 2011)South AfricaLaws, rules and executive directivesFinal ruleIn effectPublished
South Africa: National Nuclear Regulator Act, 1999 (Act No. 47 of 1999)South AfricaLaws, rules and executive directivesStatuteIn effectPublished
South Africa: Nuclear Energy Act, 1999 (Act No. 46 of 1999)South AfricaLaws, rules and executive directivesStatuteIn effectEnacted
South Korea · 4 records
South Korea: Special Act on the Promotion of and Support for Small Modular Reactor Development (소형모듈원자로 개발 촉진 및 지원에 관한 특별법)South KoreaLaws, rules and executive directivesStatuteIn effectTook effect
South Korea: Nuclear Safety Act (원자력안전법)South KoreaLaws, rules and executive directivesStatuteIn effectAmended
South Korea: Act on Physical Protection and Radiological Emergency (원자력시설 등의 방호 및 방사능 방재 대책법), emergency planning zonesSouth KoreaLaws, rules and executive directivesStatuteIn effectProvision took effect
South Korea: Innovative SMR (i-SMR) Technology Development Programme (혁신형 소형모듈원자로 기술개발사업)South KoreaFunding and support programsFunding programIn effectNo award recordedTook effect
Sweden · 3 records
Sweden: Act on Government Approval of Nuclear Facilities (SFS 2026:585)SwedenLaws, rules and executive directivesStatuteIn effectTook effect
Sweden: Act on Nuclear Activities (SFS 1984:3, lag om kärnteknisk verksamhet)SwedenLaws, rules and executive directivesStatuteIn effectProvision took effect
Sweden: Act on State Support for Investment in New Nuclear Power (SFS 2025:587)SwedenLaws, rules and executive directivesStatuteIn effectTook effect
Ukraine · 1 record
Ukraine: Regulation on the State Nuclear Regulatory Inspectorate (Cabinet of Ministers Resolution No. 363 of 20 August 2014, Положення про Державну інспекцію ядерного регулювання України)UkraineLaws, rules and executive directivesFinal ruleIn effectProvision took effect
United Kingdom · 7 records
ONR policy on using relevant good practiceUnited KingdomRegulatory guidance and inspector policiesRegulatory guidancePublished guidance — not a law or project permissionPublished
United Kingdom: GBE-N selection of, and contract with, Rolls-Royce SMRUnited KingdomAwards and selectionsAwardAwardedAwarded
United Kingdom: Great British Energy – Nuclear small modular reactor program and technology selectionUnited KingdomFunding and support programsFunding programIn effectMilestone
United Kingdom: Building our nuclear nation, government response to the Nuclear Regulatory Review 2025United KingdomRegulatory guidance and inspector policiesRegulatory guidancePublished guidance — not a law or project permissionPublished
United Kingdom: National Policy Statement for nuclear energy generation (EN-7)United KingdomRegulatory guidance and inspector policiesRegulatory guidancePublished guidance — not a law or project permissionEffective date recorded
United Kingdom: Nuclear Installations Act 1965 (c. 57), nuclear site licensingUnited KingdomLaws, rules and executive directivesStatuteIn effectAmended
United Kingdom: Energy Act 2013 (c. 32), Part 3, Office for Nuclear RegulationUnited KingdomLaws, rules and executive directivesStatuteIn effectProvision took effect
Uzbekistan · 3 records
Uzbekistan: Law No. ZRU-565 on the Use of Atomic Energy for Peaceful Purposes (2019)UzbekistanLaws, rules and executive directivesStatuteIn effectAmended
Uzbekistan: Requirements for the site and territory of a nuclear power plant (Committee resolution No. 39, 2026)UzbekistanLaws, rules and executive directivesFinal ruleIn effectTook effect
Uzbekistan: Presidential Resolution PP-188 on the Atomic Energy Agency and its development fund (2024)UzbekistanLaws, rules and executive directivesExecutive orderIn effectAmended
European Union (EU and Euratom) · 4 records
EU: Net-Zero Industry Act (Regulation (EU) 2024/1735)European Union (EU and Euratom)Laws, rules and executive directivesStatuteIn effectTook effect
EU: Commission Delegated Regulation (EU) 2022/1214 adding nuclear energy activities to the EU taxonomyEuropean Union (EU and Euratom)Laws, rules and executive directivesFinal ruleIn effectTook effect
EU: Treaty establishing the European Atomic Energy Community (Euratom Treaty), consolidated version 2016European Union (EU and Euratom)Laws, rules and executive directivesStatuteIn effectPublished
EU: Council Directive 2009/71/Euratom on the nuclear safety of nuclear installations, as amended by Directive 2014/87/EuratomEuropean Union (EU and Euratom)Laws, rules and executive directivesStatuteIn effectAmended
Alaska · 1 record
Alaska Chapter 4, SLA 2022: microreactor sitingAlaskaLaws, rules and executive directivesStatuteIn effectTook effect
Arizona · 3 records
Arizona S.B. 1418, vetoed: corporation commission and small modular reactorsArizonaBills, proposed rules and consultationsBillFailedFailed
Arizona Executive Order 2025-13: energy task forceArizonaLaws, rules and executive directivesExecutive orderIn effectSigned
Arizona Chapter 56 of 2025: nuclear emergency management fund appropriationArizonaLaws, rules and executive directivesStatuteIn effectSigned
Arkansas · 2 records
Arkansas Act 707 of 2025: nuclear generation feasibility studyArkansasLaws, rules and executive directivesStatuteIn effectEnacted
Arkansas Act 373 of 2025: advanced-energy strategic investment riderArkansasLaws, rules and executive directivesStatuteIn effectEnacted
California · 2 records
California Public Resources Code § 25524.1: reprocessing conditionCaliforniaLaws, rules and executive directivesStatuteIn effectAmended
California Public Resources Code § 25524.2: waste-disposal conditionCaliforniaLaws, rules and executive directivesStatuteIn effectAmended
Colorado · 1 record
Colorado Chapter 45 of 2025: nuclear energy in the clean-energy definitionsColoradoLaws, rules and executive directivesStatuteIn effectTook effect
Florida · 1 record
Florida Statutes § 366.93: nuclear and gasification plant cost recoveryFloridaLaws, rules and executive directivesStatuteIn effectEnacted
Hawaii · 1 record
Hawaii Constitution article XI, section 8: nuclear fission plantsHawaiiLaws, rules and executive directivesStatuteIn effectEnacted
Idaho · 5 records
Idaho PUC Order 37049: Kemmerer Unit 1 solicitation waiverIdahoLaws, rules and executive directivesCommission orderIn effectPublished
Idaho Executive Order 2025-06: Advanced Nuclear Energy Task ForceIdahoLaws, rules and executive directivesExecutive orderIn effectSigned
Idaho Executive Order 2021-02: Leadership in Nuclear Energy CommissionIdahoLaws, rules and executive directivesExecutive orderIn effectSigned
Idaho Code § 39-3027: voter submission before a law prohibiting nuclear generationIdahoLaws, rules and executive directivesStatuteIn effectEnacted
Idaho Code § 39-3020: Western Interstate Nuclear CompactIdahoLaws, rules and executive directivesStatuteIn effectEnacted
Illinois · 1 record
Illinois Executive Order 2026-01: nuclear notice of inquiryIllinoisLaws, rules and executive directivesExecutive orderIn effectSigned
Indiana · 5 records
Indiana Code 8-1-8.5-12.1: small modular nuclear reactor certificatesIndianaLaws, rules and executive directivesStatuteIn effectAmended
Indiana SEA 423 (2025): SMR pilot program and partnershipsIndianaLaws, rules and executive directivesStatuteIn effectTook effect
Indiana SEA 424 (2025): SMR development cost recoveryIndianaLaws, rules and executive directivesStatuteIn effectTook effect
Indiana tax guidance on the SMR manufacturing expense creditIndianaRegulatory guidance and inspector policiesRegulatory guidancePublished guidance — not a law or project permissionPublished
Indiana Executive Order 25-48: Nuclear Indiana CoalitionIndianaLaws, rules and executive directivesExecutive orderIn effectIssued
Iowa · 2 records
Iowa House File 2757: nuclear generation tax treatment and workforce fundIowaLaws, rules and executive directivesStatuteIn effectSigned
Iowa Executive Order 17: Nuclear Energy Task ForceIowaLaws, rules and executive directivesExecutive orderIn effectSigned
Kansas · 2 records
Kansas property-tax exemption for certain new electric generation, including nuclearKansasLaws, rules and executive directivesStatuteIn effectAmended
Kansas nuclear generation facility siting permitKansasLaws, rules and executive directivesStatuteIn effectAmended
Kentucky · 4 records
Kentucky KRS 164.2805: Nuclear Reactor Site Readiness Pilot ProgramKentuckyFunding and support programsAuthorization programIn effectNo award recordedTook effect
Kentucky KRS 278.615: nuclear permit and license cost recoveryKentuckyLaws, rules and executive directivesStatuteIn effectTook effect
Kentucky KRS 164.2803: nuclear energy development grant capKentuckyLaws, rules and executive directivesStatuteIn effectSigned
Kentucky Chapter 51 of 2025: nuclear energy development grant appropriationKentuckyLaws, rules and executive directivesStatuteIn effectSigned
Louisiana · 3 records
Louisiana Executive Order JML 25-074: environmental permitting reviewLouisianaLaws, rules and executive directivesExecutive orderIn effectSigned
Louisiana Act 111 of 2025: small modular reactor environmental permittingLouisianaLaws, rules and executive directivesStatuteIn effectEnacted
Louisiana Act 462 of 2025: green energy includes nuclear reactorsLouisianaLaws, rules and executive directivesStatuteIn effectEnacted
Maine · 1 record
Maine Title 35-A, § 4302: nuclear construction referendumMaineLaws, rules and executive directivesStatuteIn effectAmended
Michigan · 4 records
Michigan 2025 House Bill 4128: proposed credit for small modular reactor and uprate electricityMichiganBills, proposed rules and consultationsBillProposed — not in effectPassed
Michigan 2024 Public Act 121: targeted energy investmentMichiganLaws, rules and executive directivesStatuteIn effectSigned
Michigan 2023 Public Act 235: nuclear generation in the clean-energy standardMichiganLaws, rules and executive directivesStatuteIn effectTook effect
Michigan 2022 Public Act 218: nuclear feasibility studyMichiganLaws, rules and executive directivesStatuteIn effectTook effect
Minnesota · 2 records
Minnesota Rules chapter 7855: certificate applications for nuclear fuel and waste facilitiesMinnesotaLaws, rules and executive directivesFinal ruleIn effectPublished
Minnesota Statutes § 216B.243, subdivision 3b: nuclear certificate of needMinnesotaLaws, rules and executive directivesStatuteIn effectAmended
Missouri · 2 records
Missouri section 393.1400: new nuclear units excluded from qualifying-plant rate treatmentMissouriLaws, rules and executive directivesStatuteIn effectTook effect
Missouri PSC order on Wolf Creek decommissioning costsMissouriLaws, rules and executive directivesCommission orderIn effectTook effect
Montana · 1 record
Montana legislative conditions for uranium conversion and enrichmentMontanaLaws, rules and executive directivesStatuteIn effectEnacted
Nebraska · 1 record
Nebraska section 71-3505: nuclear-plant emergency-response and surveillance feeNebraskaLaws, rules and executive directivesStatuteIn effectProvision took effect
Nevada · 1 record
Nevada prohibition on storing high-level radioactive wasteNevadaLaws, rules and executive directivesStatuteIn effectEnacted
New Hampshire · 1 record
New Hampshire RSA 162-F:1: decommissioning funding responsibilityNew HampshireLaws, rules and executive directivesStatuteIn effectAmended
New Jersey · 2 records
New Jersey P.L. 2026, chapter 9: nuclear facility permit findingNew JerseyLaws, rules and executive directivesStatuteIn effectSigned
New Jersey Executive Order No. 2: Nuclear Power Task ForceNew JerseyLaws, rules and executive directivesExecutive orderIn effectSigned
New Mexico · 1 record
New Mexico location approval for a large capacity plantNew MexicoLaws, rules and executive directivesFinal ruleIn effectTook effect
New York · 1 record
New York PSC nuclear reliability backbone processNew YorkLaws, rules and executive directivesCommission orderIn effectTook effect
North Carolina · 2 records
North Carolina G.S. 62-133.8: clean energy portfolio standardNorth CarolinaLaws, rules and executive directivesStatuteIn effectEnacted
North Carolina G.S. 166A-29: fixed nuclear facility emergency-planning feeNorth CarolinaLaws, rules and executive directivesStatuteIn effectTook effect
North Dakota · 1 record
North Dakota 2025 House Bill 1025: advanced nuclear study and appropriationNorth DakotaLaws, rules and executive directivesStatuteIn effectEnacted
Ohio · 3 records
Ohio power-siting definition of a major utility facilityOhioLaws, rules and executive directivesStatuteIn effectTook effect
Ohio Revised Code Chapter 4164: Nuclear Development AuthorityOhioLaws, rules and executive directivesStatuteIn effectTook effect
Ohio certificate required before major-utility constructionOhioLaws, rules and executive directivesStatuteIn effectTook effect
Oklahoma · 1 record
Oklahoma 2025 chapter 491: nuclear energy feasibility studyOklahomaLaws, rules and executive directivesStatuteIn effectSigned
Oregon · 1 record
Oregon conditions for a nuclear-fueled thermal power plantOregonLaws, rules and executive directivesStatuteIn effectEnacted
Pennsylvania · 1 record
Pennsylvania Radiation Protection Act section 402.1: small modular reactor and microreactor feesPennsylvaniaLaws, rules and executive directivesStatuteIn effectAmended
Rhode Island · 3 records
Rhode Island authorization to participate in nuclear-power procurementRhode IslandLaws, rules and executive directivesStatuteIn effectTook effect
Rhode Island Energy Facility Siting Board rulesRhode IslandLaws, rules and executive directivesFinal ruleIn effectTook effect
Rhode Island energy facility siting licenseRhode IslandLaws, rules and executive directivesStatuteIn effectEnacted
South Carolina · 3 records
South Carolina Act 41 of 2025: Governor's Nuclear Advisory CouncilSouth CarolinaLaws, rules and executive directivesStatuteIn effectSigned
South Carolina section 58-33-196: advanced nuclear study costsSouth CarolinaLaws, rules and executive directivesStatuteIn effectTook effect
South Carolina Base Load Review ActSouth CarolinaLaws, rules and executive directivesStatuteIn effectTook effect
South Dakota · 1 record
South Dakota energy facility construction permitSouth DakotaLaws, rules and executive directivesStatuteIn effectAmended
Tennessee · 1 record
Tennessee Public Chapter 530: nuclear supply-chain carry-forwardTennesseeLaws, rules and executive directivesStatuteIn effectPassed
Texas · 3 records
TANEO grant rules (10 TAC chapter 331)TexasLaws, rules and executive directivesFinal ruleIn effectTook effect
Texas Advanced Nuclear Development FundTexasFunding and support programsFunding programIn effectNo award recordedOpened
Texas HB 14 (2025): Texas Advanced Nuclear Energy Office and development fundTexasLaws, rules and executive directivesStatuteIn effectTook effect
Vermont · 1 record
Vermont Act 52 of 2021: radiological emergency response plan fundVermontLaws, rules and executive directivesStatuteIn effectTook effect
Virginia · 3 records
Virginia SCC final order: Appalachian Power Joshua Falls development costsVirginiaLaws, rules and executive directivesCommission orderIn effectPublished
Virginia § 56-585.1:14: Phase II small modular reactor development-cost recoveryVirginiaLaws, rules and executive directivesStatuteIn effectSigned
Virginia § 56-585.1:15: Phase I small modular nuclear facility development-cost recoveryVirginiaLaws, rules and executive directivesStatuteIn effectSigned
Washington · 1 record
Washington RCW 80.50: energy facility site certificationWashingtonLaws, rules and executive directivesStatuteIn effectAmended
West Virginia · 1 record
West Virginia Enrolled Senate Bill 4 (2022): repeal of the nuclear-construction articleWest VirginiaLaws, rules and executive directivesStatuteIn effectTook effect
Wisconsin · 2 records
2025 Wisconsin Act 12: nuclear power siting studyWisconsinLaws, rules and executive directivesStatuteIn effectTook effect
2015 Wisconsin Act 344: repeal of the nuclear-construction conditionsWisconsinLaws, rules and executive directivesStatuteIn effectTook effect
Wyoming · 2 records
Wyoming 2022 Chapter 103: advanced nuclear reactor requirementsWyomingLaws, rules and executive directivesStatuteIn effectSigned
Wyoming advanced nuclear reactor requirementsWyomingLaws, rules and executive directivesStatuteIn effectAmended
Northern Mariana Islands · 1 record
Northern Mariana Islands 2 CMC § 1326: small modular reactor exemption from the nuclear-free zone lawNorthern Mariana IslandsLaws, rules and executive directivesStatuteIn effectTook effect
Puerto Rico · 1 record
Puerto Rico House Bill 1092 (2026): nuclear energy and small modular reactors in the energy policy actPuerto RicoBills, proposed rules and consultationsBillProposed — not in effectPassed
Jurisdictions and coverage limits

Selected federal, state, territory, and national measures whose official text was opened. This is not a complete list of laws, rules, programs or guidance for any jurisdiction. A jurisdiction without a page here is not a finding that it has no policy, and these pages do not rate or prefer any jurisdiction. Nothing here implies that a project is eligible for, or approved under, any measure.

Jurisdictions with published instruments

  • United States (federal) — 36 records
    Laws, rules and executive directives: 16 · Bills, proposed rules and consultations: 10 · Funding and support programs: 4 · Awards and selections: 5 · Regulatory guidance and inspector policies: 1
  • Argentina — 2 records
    Laws, rules and executive directives: 1 · Regulatory guidance and inspector policies: 1
  • Brazil — 2 records
    Laws, rules and executive directives: 2
  • Canada — 6 records
    Laws, rules and executive directives: 5 · Funding and support programs: 1
  • China — 3 records
    Laws, rules and executive directives: 3
  • Croatia — 1 record
    Laws, rules and executive directives: 1
  • Czechia — 2 records
    Laws, rules and executive directives: 2
  • Estonia — 1 record
    Laws, rules and executive directives: 1
  • Finland — 2 records
    Laws, rules and executive directives: 2
  • France — 3 records
    Laws, rules and executive directives: 2 · Funding and support programs: 1
  • India — 4 records
    Laws, rules and executive directives: 1 · Bills, proposed rules and consultations: 2 · Funding and support programs: 1
  • Indonesia — 4 records
    Laws, rules and executive directives: 4
  • Japan — 3 records
    Laws, rules and executive directives: 2 · Funding and support programs: 1
  • Netherlands — 3 records
    Laws, rules and executive directives: 2 · Funding and support programs: 1
  • Norway — 2 records
    Laws, rules and executive directives: 2
  • Poland — 3 records
    Laws, rules and executive directives: 3
  • Romania — 2 records
    Laws, rules and executive directives: 2
  • Russia — 3 records
    Laws, rules and executive directives: 3
  • Rwanda — 3 records
    Laws, rules and executive directives: 3
  • South Africa — 3 records
    Laws, rules and executive directives: 3
  • South Korea — 4 records
    Laws, rules and executive directives: 3 · Funding and support programs: 1
  • Sweden — 3 records
    Laws, rules and executive directives: 3
  • Ukraine — 1 record
    Laws, rules and executive directives: 1
  • United Kingdom — 7 records
    Laws, rules and executive directives: 2 · Funding and support programs: 1 · Awards and selections: 1 · Regulatory guidance and inspector policies: 3
  • Uzbekistan — 3 records
    Laws, rules and executive directives: 3
  • European Union (EU and Euratom) — 4 records
    Laws, rules and executive directives: 4
  • Alaska — 1 record
    Laws, rules and executive directives: 1
  • Arizona — 3 records
    Laws, rules and executive directives: 2 · Bills, proposed rules and consultations: 1
  • Arkansas — 2 records
    Laws, rules and executive directives: 2
  • California — 2 records
    Laws, rules and executive directives: 2
  • Colorado — 1 record
    Laws, rules and executive directives: 1
  • Florida — 1 record
    Laws, rules and executive directives: 1
  • Hawaii — 1 record
    Laws, rules and executive directives: 1
  • Idaho — 5 records
    Laws, rules and executive directives: 5
  • Illinois — 1 record
    Laws, rules and executive directives: 1
  • Indiana — 5 records
    Laws, rules and executive directives: 4 · Regulatory guidance and inspector policies: 1
  • Iowa — 2 records
    Laws, rules and executive directives: 2
  • Kansas — 2 records
    Laws, rules and executive directives: 2
  • Kentucky — 4 records
    Laws, rules and executive directives: 3 · Funding and support programs: 1
  • Louisiana — 3 records
    Laws, rules and executive directives: 3
  • Maine — 1 record
    Laws, rules and executive directives: 1
  • Michigan — 4 records
    Laws, rules and executive directives: 3 · Bills, proposed rules and consultations: 1
  • Minnesota — 2 records
    Laws, rules and executive directives: 2
  • Missouri — 2 records
    Laws, rules and executive directives: 2
  • Montana — 1 record
    Laws, rules and executive directives: 1
  • Nebraska — 1 record
    Laws, rules and executive directives: 1
  • Nevada — 1 record
    Laws, rules and executive directives: 1
  • New Hampshire — 1 record
    Laws, rules and executive directives: 1
  • New Jersey — 2 records
    Laws, rules and executive directives: 2
  • New Mexico — 1 record
    Laws, rules and executive directives: 1
  • New York — 1 record
    Laws, rules and executive directives: 1
  • North Carolina — 2 records
    Laws, rules and executive directives: 2
  • North Dakota — 1 record
    Laws, rules and executive directives: 1
  • Ohio — 3 records
    Laws, rules and executive directives: 3
  • Oklahoma — 1 record
    Laws, rules and executive directives: 1
  • Oregon — 1 record
    Laws, rules and executive directives: 1
  • Pennsylvania — 1 record
    Laws, rules and executive directives: 1
  • Rhode Island — 3 records
    Laws, rules and executive directives: 3
  • South Carolina — 3 records
    Laws, rules and executive directives: 3
  • South Dakota — 1 record
    Laws, rules and executive directives: 1
  • Tennessee — 1 record
    Laws, rules and executive directives: 1
  • Texas — 3 records
    Laws, rules and executive directives: 2 · Funding and support programs: 1
  • Vermont — 1 record
    Laws, rules and executive directives: 1
  • Virginia — 3 records
    Laws, rules and executive directives: 3
  • Washington — 1 record
    Laws, rules and executive directives: 1
  • West Virginia — 1 record
    Laws, rules and executive directives: 1
  • Wisconsin — 2 records
    Laws, rules and executive directives: 2
  • Wyoming — 2 records
    Laws, rules and executive directives: 2
  • Northern Mariana Islands — 1 record
    Laws, rules and executive directives: 1
  • Puerto Rico — 1 record
    Bills, proposed rules and consultations: 1

Federal measures are stored once and apply across the United States; state pages link to them instead of repeating them. A jurisdiction without a page is still accounted for in the research coverage table.

Applications and decisions

Filter by country, action type and status. A pending application is not a permit, a construction permit is not operating authority, and an environmental decision is not a reactor license.

76 regulatory records listed

Record and targetCountryAction typeStatusAuthority
Long Mott construction permit
Document and scope

Long Mott Energy's construction permit application, dated 31 March 2025, was accepted and docketed by the NRC. NRC news release 26-083 of 9 November 2026 states that the NRC has issued the construction permit for the four-reactor Xe-100 Long Mott Generating Station in Calhoun County, Texas, that staff completed the safety evaluation in October, and that the permit authorizes building the facility but not operation; a separate operating license is required before fuel loading. The release gives no permit number; the permit itself is Construction Permit No. CPAR-3 (ADAMS ML26301A133), issued 9 November 2026, and the Federal Register notice of issuance (91 FR 72925, 12 November 2026) says it is immediately effective and authorizes construction of a power reactor facility in Calhoun County, Texas. The permit sets the earliest construction completion date as 1 July 2033 and the latest as 31 December 2033 and expires on that date. Its conditions include that Long Mott Energy notify the NRC when the site grading design and the passive engineered flooding protection design that may impact site grading are available for NRC staff examination, and that it perform geologic mapping of each foundation excavation for safety-related structures, evaluate it against the site characterization and notify the NRC when it is available for examination; the permit also incorporates an environmental protection plan. It says a license authorizing operation will not be issued unless the applicant submits the complete final safety analysis report, the Commission makes the stated findings on final design and environmental requirements, and the applicant submits proof of financial protection and executes an indemnity agreement. The NRC's project page, updated 12 November 2026, lists the hearing as held on 22 September 2026 and the construction permit decision as 8 November 2026; the permit and the Federal Register notice date issuance to 9 November 2026, and the one-day difference is unexplained in the sources read. Earlier steps: the uncontested (mandatory) hearing was held on 22 September 2026 in Port Lavaca; the Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review supports issuance; NRC issued an environmental assessment and finding of no significant impact plus related exemptions on 18 May 2026. In the contested proceeding, both admitted contentions were dismissed as moot in 2026 and on 7 August 2026 the Commission dismissed the applicant's appeal as moot; on 6 November 2026 the Commission denied the intervenor's separate petition for review (CLI-26-15). The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.

Sources: Federal Register 90 FR 24428 (10 Jun 2025): Long Mott Generating Station construction permit application; Federal Register 91 FR 53900 (20 Aug 2026): Long Mott Generating Station notice of hearing; NRC / ANS Dow Long Mott Xe-100 EA-FONSI; NRC Federal Register notice: Long Mott environmental assessment, FONSI and exemptions; NRC: Long Mott Generating Station Xe-100 application page; NRC Commission order CLI-26-10, Long Mott Energy, LLC (Docket 50-614-CP); NRC meeting notice: mandatory hearing on the Long Mott construction permit application; NRC Advisory Committee on Reactor Safeguards: report on the safety aspects of the Long Mott construction permit application (16 Oct 2026); Federal Register 2026-18898 (15 Sep 2026): 739th meeting of the Advisory Committee on Reactor Safeguards; X-energy: NRC completes safety review of the Xe-100 for Long Mott (final safety evaluation report), 30 Oct 2026; NRC news release 26-083: first construction permit in nearly 60 years for a high-temperature gas-cooled reactor (Long Mott); X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site; Federal Register 91 FR 72925 (12 Nov 2026): Long Mott Generating Station construction permit CPAR-3, notice of issuance; NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133); NRC Commission order CLI-26-15, Long Mott Energy, LLC (Docket 50-614-CP)

United StatesConstruction application / decisionIssued / approvedNRC
NNSA construction license 国核安证字第2621号 for Xuwei Phase I Unit 3 (HTGR)
Document and scope

China's nuclear regulator reported on 26 June 2025 that it had started the construction-license review for Unit 3 of the Xuwei nuclear heating and power plant, covering the preliminary safety analysis report and the construction-stage environmental impact report, with CNNC Sueneng Nuclear Power presenting the high-temperature gas-cooled reactor. That notice gives no filing day and no license decision. The 9 October 2026 pre-construction inspection report found that preparations met the conditions for issuing a construction license and set seven corrective requirements; it does not itself issue the license. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction license 国核安证字第2621号 for Unit 3 to CNNC Sueneng, valid to 1 November 2036, and says the company may begin pouring the first concrete for the nuclear-island foundation. The license requires an operating-license application before first fuel loading. It is not an operating license. No construction start is recorded; a permit is not a physical construction start.

Sources: NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3

ChinaConstruction application / decisionIssued / approvedNNSA
NNSA site-selection review opinion No. 2620, Huakun One science and technology demonstration project
Document and scope

The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2620号) on 2 November 2026 to CGN Ocean Energy for the Huakun One floating reactor platform and maintenance base at the Taipingling nuclear base in Huidong county. The review found no disqualifying site factor affecting safety that engineering measures could not resolve, and the opinion agrees that design work may proceed on the stated site parameters. It is not a construction license: before holding one the company may not pour seismic Category I foundation concrete or build other safety-important structures.

Sources: NNSA: site-selection review opinion No. 2620 for the Huakun One science and technology demonstration project (2 November 2026)

ChinaSite application / decisionIssued / approvedNNSA
Last Energy Caldwell site phased construction permit application, Part 1 (with limited work authorization request)
Document and scope

Last Energy filed Part 1 of a two-part phased construction permit application on 20 October 2026 for a PWR-20 facility at the Caldwell Site in Caldwell County, Texas. Part 1 includes a limited work authorization request under 10 CFR 50.10(d) covering early foundation work, with financial information, a preliminary safety analysis report for the LWA scope, an environmental report and a site redress plan. The NRC published a notice of receipt on 5 November 2026 (91 FR 69895). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction.

Sources: Federal Register 91 FR 69895 (5 Nov 2026): Last Energy phased construction permit application with limited work authorization request, Caldwell site (notice of receipt)

United StatesConstruction application / decisionApplication receivedNRC
DOE PWR-5 Phase 1 environmental categorical exclusion
Document and scope

DOE approved NEPA determination DOE-ID-26-008 on 30 September 2026 for proposed PWR-5 Phase 1 initial criticality and low-power testing at RELLIS. The Phase 1 research configuration is bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export. The 19.5 MWth PWR-5 design point applies to later phases. This environmental decision is not DOE startup authorization, proof of achieved criticality, or authorization for later phases.

Sources: DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008

United StatesEnvironmental decisionIssued / approvedU.S. Department of Energy, Office of Nuclear Energy
HEXANA first safety-options request
Document and scope

ASNR reports that Hexana requested an opinion on a first safety option for its small modular reactor on 30 September 2026. The page places this in pre-instruction safety-options exchanges. This is a design assessment request, not a Gard Rhodanien site application, construction permission or issued opinion.

Sources: ASNR, PRM projects and technical exchanges (14 October 2026 update)

FranceDesign assessmentApplication receivedASNR
Clinch River Unit 1 construction permit
Document and scope

The Federal Register published this notice on 5 October 2026 at 91 FR 63311. It states that construction permit CPAR-2 was issued to TVA on 28 September 2026 for Clinch River Nuclear Unit 1, is immediately effective, and authorizes construction of a power reactor facility in Roane County, Tennessee. The notice says the conditions in early site permit ESP-006 had been met except those listed in the construction permit. The permit sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, expires on that latest date and does not restate an output rating. TVA announced the permit on 29 September 2026. The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.

Sources: Federal Register 91 FR 63311 (5 Oct 2026): Clinch River Nuclear Unit 1 construction permit and record of decision; TVA construction permit announcement; NRC: TVA Clinch River construction permit application; NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056)

United StatesConstruction application / decisionIssued / approvedNRC
Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application, Part 1 (with limited work authorization request)
Document and scope

Blue Energy filed Part 1 of a phased construction permit application on 15 September 2026 for one BWRX-300 unit, Blue Energy Center–Port of Victoria Nuclear Unit 1, in Victoria, Texas. Part 1 includes a limited work authorization request, two related exemption requests and an environmental report. The NRC published a notice of receipt on 8 October 2026 (91 FR 64409). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction. The applicant intends to file the full construction permit application within 18 months of Part 1.

Sources: Federal Register 91 FR 64409 (8 Oct 2026): Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application with limited work authorization request (notice of receipt); Blue Energy letter submitting Construction Permit Application Part 1 (ADAMS ML26258A339); Federal Register 91 FR 64409 (8 Oct 2026), govinfo copy: Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application, notice of receipt

United StatesConstruction application / decisionApplication receivedNRC
NNSA approval of the Xuwei HTGR safety design criteria
Document and scope

NNSA instrument 国核安发〔2026〕161号, signed 31 August 2026, approves B-version safety design criteria for the Xuwei HTGR. Its later 29 September announcement describes a small nuclear power reactor with multiple modules and one turbine. The criteria guide safety review and are not a construction license.

Sources: NNSA: safety design criteria for the Xuwei high-temperature gas-cooled reactor; NNSA: Xuwei HTGR safety design criteria approval, instrument 161

ChinaOther regulatory actionIssued / approvedNNSA
NRC exemption for specified Pioneer support-of-excavation walls before LWA
Document and scope

The NRC issued a narrow exemption on 28 August 2026 allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization. The notice does not issue or commit to an LWA or construction permit. The exemption does not show that physical work began or authorize all construction.

Sources: NRC exemption for specified Pioneer support-of-excavation walls

United StatesOther regulatory actionIssued / approvedNRC
NRC environmental assessment and FONSI for Pioneer excavation-wall exemption
Document and scope

The NRC made an environmental assessment and finding of no significant impact available on 24 August 2026; its later exemption notice describes the finding as issued on 25 August. It addresses environmental effects of the requested support-of-excavation-wall exemption; it is not the 28 August exemption and does not issue an LWA or construction permit.

Sources: NRC environmental assessment and FONSI for Pioneer excavation-wall exemption; NRC exemption for specified Pioneer support-of-excavation walls

United StatesEnvironmental decisionIssued / approvedNRC
Swedish Government approval application for a nuclear facility at Untra, Tierp
Document and scope

Blykalla AB applied on 25 August 2026 (recorded as received on 26 August) for the Government's approval of eight lead-cooled small modular reactors of about 440 MW in total at Untra in Tierp municipality; on 28 August 2026 the Government assigned the Uppsala county administrative board to draft a facility plan by 30 April 2027. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.

Sources: Government of Sweden: Government review of new nuclear (status of applications); Government of Sweden: facility-plan assignment for the Untra application

SwedenSite application / decisionUnder reviewGovernment of Sweden
OTRERA ONE safety-options request
Document and scope

ASNR states that Otrera filed a safety-options request on 30 July 2026 for OTRERA ONE, listed on the 14 October 2026 page as a 200 MWth sodium-cooled demonstrator/prototype. The page does not record an opinion or a creation authorization. This is not a sited project.

Sources: ASNR, PRM projects and their fuel-fabrication plants

FranceDesign assessmentApplication receivedASNR
DOE Aurora-INL B5.26 environmental categorical exclusion
Document and scope

DOE Idaho approved environmental determination DOE-ID-INL-26-018 on 20 July 2026 for the proposed Aurora-INL reactor construction, installation and operation scope under B5.26. The document describes anticipated activities and a planned construction period; it is an environmental determination, not evidence that reactor construction occurred, an approval of the preliminary safety analysis, or authority to load fuel or operate.

Sources: DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018

United StatesEnvironmental decisionIssued / approvedU.S. Department of Energy, Idaho Operations Office
License for construction of an NPP power unit with a RITM-200N reactor
Document and scope

Council of the Committee decided 'today' (item dated 2026-06-04) to issue the license for construction of one power unit (singular 'энергоблока'); the Committee's notice states no license number or holder. Uzatom states that the license was issued to the state institution Directorate for the Construction of the Nuclear Power Plant; the license number is not published.

Sources: Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026; Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026)

UzbekistanConstruction application / decisionIssued / approvedCommittee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of the Republic of Uzbekistan
Swedish Government approval application for a nuclear facility at Studsvik, Nyköping
Document and scope

Studsvik AB applied on 25 May 2026 for the Government's approval of a nuclear facility for two to four light-water reactors of about 600-1,400 MW in total at Studsvik in Nyköping municipality; on 9 June 2026 the Government assigned the Södermanland county administrative board to draft a facility plan by 31 December 2026. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.

Sources: Government of Sweden: Government review of new nuclear (status of applications); Government of Sweden: facility-plan assignment for the Studsvik application

SwedenSite application / decisionUnder reviewGovernment of Sweden
Long Mott environmental assessment, FONSI and review exemptions
Document and scope

The NRC notice says the Long Mott construction-permit environmental assessment and finding of no significant impact were available on 18 May 2026 and that exemptions permitting this review in place of an environmental impact statement were issued the same day. The construction-permit application remains under review; this decision is not a construction permit or authority to operate.

Sources: NRC Federal Register notice: Long Mott environmental assessment, FONSI and exemptions

United StatesEnvironmental decisionIssued / approvedU.S. Nuclear Regulatory Commission
Swedish Government approval application for a nuclear facility at Norrsundet, Gävle
Document and scope

Blykalla AB applied on 18 May 2026 for the Government's approval of a nuclear facility at Norrsundet in Gävle municipality; on 28 May 2026 the Government assigned the Gävleborg county administrative board to draft a facility plan by 31 December 2026. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.

Sources: Government of Sweden: Government review of new nuclear (status of applications); Government of Sweden: facility-plan assignment for the Norrsundet application

SwedenSite application / decisionUnder reviewGovernment of Sweden
DOE categorical exclusion CX-271015 for the Ward250 research reactor
Document and scope

Signed 22 April 2026 under NEPA identification DOE-ID-26-005. Determines that the 250 kWth Ward250 research reactor at USREL fits a categorical exclusion. It states no authorization number and no electrical output, and it does not confirm the company's later electricity claim.

Sources: DOE categorical exclusion CX-271015 PDF: Ward250 research reactor

United StatesEnvironmental decisionIssued / approvedU.S. Department of Energy, Office of Nuclear Energy
DOE Idaho categorical exclusion CX-271007 for the Unity zero-power test
Document and scope

Approved 15 April 2026 under posting DOE-ID-INL-26-011. Covers a zero-power criticality test bounded at 0 MWth and 0 kWe. It does not authorize the future 1 MWe configuration and is not an operating license.

Sources: DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality

United StatesEnvironmental decisionIssued / approvedU.S. Department of Energy, Idaho Operations Office
DOE Idaho categorical exclusion CX-271002 for the Aalo-X critical assembly
Document and scope

Approved 14 April 2026 under posting DOE-ID-INL-26-013. Covers installation and zero-power operation of the critical assembly at no more than 10 watts thermal. It is an environmental categorical exclusion, not a construction permit or operating license, and it does not authorize a later power reactor.

Sources: DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly

United StatesEnvironmental decisionIssued / approvedU.S. Department of Energy, Idaho Operations Office
NRC construction permit application for the University of Illinois KRONOS MMR
Document and scope

The university applied for a construction permit for one research reactor by letter dated 27 March 2026; the NRC records it as tendered on 31 March 2026, accepted it for docketing on 18 May 2026 as Docket No. 50-618 and published the hearing opportunity on 26 May 2026. The stated application power level is 45 MWth. No permit has been issued; target review dates in 2027 are not decisions.

Sources: NRC: University of Illinois Urbana-Champaign KRONOS MMR construction permit application; Federal Register 91 FR 21321 (21 Apr 2026): University of Illinois construction permit application received; Federal Register 91 FR 30730 (26 May 2026): University of Illinois construction permit application docketed

United StatesConstruction application / decisionUnder reviewNRC
Holtec SMR-300 UK Generic Design Assessment (two steps)
Document and scope

Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in January 2023, according to the Environment Agency's Step 1 summary; it was renamed SMR-300 in January 2024. The UK regulators began a two-step Generic Design Assessment of Holtec's SMR-300 on 18 October 2023 at the government's request. Step 1 ran from October 2023 to August 2024 and Step 2 from August 2024 to March 2026. The Environment Agency records completing Step 2 on 31 March 2026, and ONR's page records the assessment as completed that month with no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.

Sources: Environment Agency: assessing new nuclear reactor designs; ONR, Holtec SMR-300 Generic Design Assessment; Environment Agency: GDA Step 1 of the Holtec SMR, statement of findings public summary

United KingdomDesign assessmentReview completed (not an approval)Step 2 completed 31 March 2026. No Step 3 or design acceptance recorded.ONR/EA (UK)
CNSC consent to remove Regulatory Hold Point 1 (reactor building foundation)CanadaConstruction application / decisionIssued / approvedCNSC
OPG license to operate application
Document and scope

20-year operating license application for one BWRX-300 and waste structure.

Sources: CNSC Darlington New Nuclear Project

CanadaOperating application / decisionUnder reviewCNSC
Swedish Government approval application for a nuclear facility at Målma, Valdemarsvik
Document and scope

Refirm Målma AB applied on 23 March 2026 for the Government's approval of a nuclear facility at Målma in Valdemarsvik municipality, the first application under the new law; on 7 May 2026 the Government assigned the Östergötland county administrative board to draft a facility plan. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.

Sources: Government of Sweden: Government review of new nuclear (status of applications); Government of Sweden: facility-plan assignment for the Valdemarsvik application

SwedenSite application / decisionUnder reviewGovernment of Sweden
Permit to use the site for nuclear installations (Farish district NPP site)
Document and scope

Regulator's own news item dated 4 June 2026 states the permit was issued on 23 March 'of the current year'. The notice reports permission to use the site designated for nuclear installations for NPP construction. It does not give a permit number.

Sources: Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026

UzbekistanSite application / decisionIssued / approvedCommittee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of the Republic of Uzbekistan
TerraPower Natrium construction permit
Document and scope

The NRC issued construction permit CPAR-1 on 9 March 2026 to US SFR Owner, LLC (TerraPower) for Kemmerer Power Station Unit 1, after the Commission's 4 March 2026 decision on the uncontested hearing. The permit authorizes construction only; an operating license is a separate NRC decision.

Sources: Federal Register 91 FR 12628 (16 Mar 2026): Kemmerer Power Station Unit 1 construction permit and record of decision; NRC TerraPower Natrium / Kemmerer; U.S. NRC: Natrium Kemmerer Unit 1

United StatesConstruction application / decisionIssued / approvedNRC
DOE Idaho categorical exclusion CX-035340 for the Antares Mark-0 experiment
Document and scope

Approved 26 January 2026 under posting DOE-ID-INL-25-037. Covers the zero-power Mark-0 heat-pipe experiment in MFC-793. No measurable thermal output is claimed. This is not an operating license, and it does not approve the later Mark-1 reactor.

Sources: DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0

United StatesEnvironmental decisionIssued / approvedU.S. Department of Energy, Idaho Operations Office
Pioneer Units 1 and 2 phased construction permit application (with limited work authorization request)
Document and scope

Holtec filed Part 1 of a phased construction permit application for two SMR-300 units (Pioneer 1 and 2) at the Palisades Energy Center on 31 December 2025, including a limited work authorization request. The NRC accepted it for docketing in February 2026 and began weekly notices of receipt on 1 October 2026. Its fourth notice, published 22 October, again records receipt and availability; it does not grant an LWA or construction permit. Part 2 (a complete preliminary safety analysis report, with an updated Quality Assurance Topical Report and exemption requests) was filed on 30 September 2026, according to the NRC's notice of receipt dated 5 November and published 10 November 2026 (91 FR 72577; ADAMS package ML26273A416), which began a second series of four weekly notices. The notice says the NRC staff was then undertaking its acceptance review of Part 2; no acceptance or docketing of Part 2 is recorded. The application remains recorded as under review; this receipt notice is not a new permission decision.

Sources: Federal Register 91 FR 62565 (1 Oct 2026): Pioneer Units 1 and 2 phased construction permit application with limited work authorization request; NRC news 26-008 Holtec Pioneer LWA; Holtec: Major regulatory developments in the Palisades Pioneer Unit 1 & 2 program (30 September 2026); NRC fourth weekly notice of receipt and availability: Pioneer Units 1 and 2 phased construction permit application; Federal Register 91 FR 72577 (10 Nov 2026): Pioneer Units 1 and 2, receipt of construction permit application (Part 2), first of four weekly notices; NRC Pioneer Units 1 and 2 LWA page

United StatesConstruction application / decisionUnder reviewNRC
Belews Creek early site permit application
Document and scope

Duke Energy Carolinas applied on 30 December 2025 for an early site permit for the Belews Creek site in Stokes and Forsyth counties, North Carolina. The NRC accepted and docketed the application in February 2026 under Docket No. 52-055, and it is under review. If issued, an early site permit approves a site independent of a specific plant design. It is not a construction permit or a combined license, and no reactor design is selected. The NRC gave notice on 27 April 2026 that it will prepare an environmental impact statement, and its project page marks the uncontested hearing of 17 September 2026 as held. On 29 September 2026, NRC letter ML26259A008 set a $2,178,000 cap on NRC review fees. That cap is not a project cost or a permit. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The letter accelerates the 8 February 2026 schedule. NRC targets, not completed: advanced final safety evaluation report without open items December 2026 (from March 2027), draft environmental impact statement December 2026 (from February 2027), final safety evaluation February 2027 (from May 2027), and final environmental impact statement March 2027 (from May 2027). The decision date is listed as to be determined. Duke Energy Carolinas' Revision 2 cover letter (ML26274A437), dated 1 October 2026, states that Duke is not requesting a limited work authorization. The NRC project page lists the Revision 2 package as ML26274A436.

Sources: Federal Register 91 FR 5787 (9 Feb 2026): Belews Creek early site permit application, acceptance for docketing and opportunity to request a hearing; Federal Register 91 FR 542 (7 Jan 2026): Belews Creek early site permit application, notice of receipt; Federal Register 91 FR 22549 (27 Apr 2026): Belews Creek early site permit, notice of intent to prepare an environmental impact statement; Federal Register 91 FR 50896 (6 Aug 2026): Belews Creek early site permit application, notice of uncontested hearing; NRC: Duke Energy's Belews Creek early site permit application; NRC letter: fixed fee cap and revised schedule for the Belews Creek early site permit review (ADAMS ML26259A008); Duke Energy Carolinas letter RA-26-0157: Revision 2 of the Belews Creek early site permit application (ADAMS ML26274A437)

United StatesSite application / decisionUnder reviewNRC
Stellaria INB Alpha creation-authorization application
Document and scope

ASNR states that Stellaria filed a creation-authorization application on 19 December 2025 for INB Alpha, including the ALVIN research reactor at CEA Cadarache. MSNR referred it to ASNR on 22 December 2025. Following ASNR analysis, MSNR requested further information on 16 June 2026. The page updated 14 October says technical review is suspended pending that information; it does not separately date the suspension. No creation authorization is recorded.

Sources: ASNR, PRM projects and their fuel-fabrication plants; ASNR, PRM projects and technical exchanges (14 October 2026 update)

FranceConstruction application / decisionUnder reviewASNR says technical review is suspended pending further information requested on 16 June 2026.ASNR
newcleo LFR-AS-30 safety-options request
Document and scope

ASNR states that newcleo filed a safety-options request on 19 December 2025 for LFR-AS-30. The page does not record an opinion or a creation authorization.

Sources: ASNR, PRM projects and their fuel-fabrication plants

FranceDesign assessmentApplication receivedASNR
Reported IEN request to construct the UCRI critical unit
Document and scope

CNEN reports an IEN letter to ANSN dated 2 December 2025 seeking construction permission and use of Argonauta facilities for the critical experiment. This is a reported submission; the letter, acceptance and a permission decision are not recorded.

Sources: CNEN: reported licensing request for the UCRI critical unit

BrazilConstruction application / decisionApplication receivedANSN
BWRX-300 UK Generic Design Assessment (two steps)
Document and scope

The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.

Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs

United KingdomDesign assessmentReview completed (not an approval)Step 2 statement issued December 2025. No Step 3 or design acceptance recorded.ONR/EA (UK)
BAPETEN Kelasa site-evaluation approval
Document and scope

Decision 00003.556.1.300725 authorizes PT Thorcon Power Indonesia to conduct site evaluation under its PET and SMET. It is not a construction license.

Sources: BAPETEN site-evaluation approval, Thorcon 500, Kelasa; BAPETEN safety-evaluation report index, Thorcon 500

IndonesiaSite application / decisionIssued / approvedBAPETEN
CNSC vendor design review, Phase 2 (ARC-100)
Document and scope

CNSC lists Phase 1 (executive summary dated October 2019) and Phase 2 (executive summary dated July 2025) of its pre-licensing vendor design review of ARC Clean Technology's ARC-100 among completed reviews. CNSC entered into the Phase 2 agreement with ARC on 9 March 2022; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barriers to licensing at that time and listed further design work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. NB Power's Point Lepreau site application is a separate process.

Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: ARC-100 Phase 2 vendor design review executive summary

CanadaDesign assessmentReview completed (not an approval)Phase 2. Phase 1 summary dated October 2019.CNSC
NRC standard design approval for the NuScale US460
Document and scope

The NRC issued a standard design approval to NuScale Power for the US460 small modular reactor design on 29 May 2025, completing its staff technical review. NuScale submitted the application in stages: the first part by letter dated 23 November 2022 and the remaining portions in stages between 29 November and 31 December 2022. The NRC notified NuScale by letter dated 31 July 2023 that the application was acceptable for docketing. The approval lets an applicant reference the design in a construction permit, operating license, combined license or manufacturing license application. It is a design approval only: it grants no permission for any site, construction or operation.

Sources: Federal Register 90 FR 23716 (4 Jun 2025): NuScale US460 standard design approval; Federal Register FR Doc. 2023-05457 (17 Mar 2023): NuScale US460 standard design approval application received; Federal Register FR Doc. 2023-16679 (4 Aug 2023): NuScale US460 standard design approval application accepted for docketing

United StatesDesign assessmentIssued / approvedNRC
Kemmerer Unit 1 exemption for energy-island work before a construction permit
Document and scope

The Federal Register notice (90 FR 20692, 15 May 2025) states that the NRC issued an exemption on 7 May 2025, in response to TerraPower's 28 February 2025 request for US SFR Owner, LLC, modifying the definition of construction for Kemmerer Unit 1. It allows specified work for non-safety-related structures, systems and components on the energy island, such as pile driving and foundations, before a construction permit and without a limited work authorization. It is not a construction permit or operating authority.

Sources: Federal Register 90 FR 20692 (15 May 2025): US SFR Owner, LLC; Kemmerer Power Station, Unit 1; Exemption

United StatesOther regulatory actionIssued / approvedNRC
OPG license to construct BWRX-300
Document and scope

CNSC issued license to construct PRCL 32.00/2035 for one BWRX-300 on 4 April 2025, valid to 31 March 2035, with regulatory hold points. OPG's application was received on 31 October 2022.

Sources: CNSC Darlington New Nuclear Project; CNSC Record of Proceedings, Including Reasons for Decision: OPG application for a licence to construct one BWRX-300 (CMD 24-H3)

CanadaConstruction application / decisionIssued / approvedCNSC
Kairos Hermes 2 construction permit
Document and scope

The NRC issued construction permits CPTR-7 and CPTR-8 for the two-unit Hermes 2 test reactor facility on 21 November 2024. Operation needs separate operating licenses.

Sources: Federal Register 89 FR 94767 (29 Nov 2024): Hermes 2 test reactor facility construction permits; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 2 construction permit

United StatesConstruction application / decisionIssued / approvedNRC
Calogena CAL30 safety-options requests
Document and scope

ASNR records a CAL30 safety-options request on 31 October 2024 and further requests through 28 August 2026. Its 19 May 2026 opinion concerns shutdown-system diversification: principles are broadly satisfactory, with stronger electrical diversification, detailed design and qualification evidence, and a simple, robust alternative shutdown means required for possible common-mode rod blockage. These are requirements for a possible future creation-authorization application, not whole-design approval or a Cadarache site permission. The opinion dates the amended letter 19 June 2025, while the earlier listing records 20 June 2025.

Sources: ASNR, PRM projects and their fuel-fabrication plants; ASNR, PRM projects and technical exchanges (14 October 2026 update); ASNR opinion 2026-AV-027: CAL30 shutdown-system safety options

FranceDesign assessmentUnder reviewASNR
Korean standard design approval for SMART100
Document and scope

The NSSC's 201st meeting approved SMART100's standard design on 26 September 2024. Printed minutes pp.121–123 distinguish standard-design approval from construction permission, direct administrative follow-up on power-system review during later licensing and continued verification improvements, and remove disputed wording asserting that a single off-site power circuit presents no safety impediment. The application date is recorded in the technical agenda. This does not authorize any project, construction or operation, does not approve SMART-C, and is not a Saudi or Canadian license. No separate issued certificate number was opened.

Sources: NSSC: SMART100 approval agenda and technical review (26 September 2024, Korean); NSSC: 201st meeting minutes, SMART100 decision (26 September 2024, Korean); KAERI: SMART100 standard design approval and SMART upgrade (27 September 2024)

South KoreaDesign assessmentIssued / approvedNSSC (Republic of Korea)
ACU Molten Salt Research Reactor construction permit
Document and scope

The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center on its Abilene campus. ACU's application is dated 12 August 2022; the NRC notified ACU by letter dated 18 November 2022 that it was acceptable for docketing. Operation needs a separate operating license.

Sources: Federal Register 89 FR 77197 (20 Sep 2024): ACU Molten Salt Research Reactor construction permit; Federal Register 89 FR 18678 (14 Mar 2024): ACU Molten Salt Research Reactor environmental assessment; Federal Register 87 FR 73051 (28 Nov 2022): ACU construction permit application accepted for docketing

United StatesConstruction application / decisionIssued / approvedNRC
NNSA site-selection review opinion No. 2414, Haiyang integrated small reactor demonstration
Document and scope

The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2414号) on 10 September 2024 for one 200 MWt integrated natural-circulation small PWR and auxiliary facilities at the southwest corner of the Haiyang nuclear plant site. The opinion agrees that design work may proceed on the stated site parameters.

Sources: NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024)

ChinaSite application / decisionIssued / approvedNNSA
Rolls-Royce SMR UK Generic Design Assessment, Step 2
Document and scope

The UK regulators completed Step 2 of their three-step Generic Design Assessment of the Rolls-Royce SMR on 30 July 2024 and issued Step 2 statements. Step 2 began on 3 April 2023, after Step 1 from April 2022 to April 2023. Step 3, the detailed assessment, began in July 2024 and is recorded separately as under way. Completing Step 2 is not a Design Acceptance Confirmation or permission for any site.

Sources: Environment Agency: assessing new nuclear reactor designs; ONR Generic Design Assessment: Rolls-Royce SMR; Environment Agency and Natural Resources Wales: GDA Step 2 of the Rolls-Royce SMR

United KingdomDesign assessmentReview completed (not an approval)Step 2 completed 30 July 2024. Step 3 is listed separately as under way.ONR/EA (UK)
MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit)
Document and scope

The Ministry of Ecology and Environment approved the siting-stage environmental impact report for Xuwei Phase I on 17 April 2024 (环审〔2024〕43号). The approval describes Phase I as two Hualong One pressurized-water units and one HTR-PM600S high-temperature gas-cooled reactor unit with supporting facilities at Xizoushan, Xuwei New Area, Lianyungang. It is an environmental decision for the siting stage covering the whole Phase I project, of which Unit 3 is the HTGR; it is not a construction license. The Hualong One units are outside SMRMap's scope.

Sources: MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号

ChinaEnvironmental decisionIssued / approvedMEE
Jimmy Bazancourt creation-authorization application
Document and scope

ASNR records Jimmy's 2024 creation-authorization application for an industrial-heat reactor at a Cristal Union factory in Bazancourt. Published filing dates differ across the project sources, so the stored submission date remains at year precision. MSNR requested further information on 13 February 2025. Jimmy submitted an updated design and the remaining answers on 23 July 2026, and MSNR referred that updated file to ASNR for review on 24 July 2026. These sources do not record an issued creation authorization.

Sources: ASNR, PRM projects and their fuel-fabrication plants; ASN 2024 annual report: Bazancourt Fermi application and reactor rating

FranceConstruction application / decisionUnder reviewASNR
Kairos Hermes 1 construction permit
Document and scope

The NRC issued construction permit CPTR-6 for the Hermes non-power test reactor on 14 December 2023. A 13 May 2026 order extended the latest construction completion date from 31 December 2026 to 30 April 2029. Operation needs a separate operating license.

Sources: Federal Register 88 FR 88137 (20 Dec 2023): Hermes test reactor construction permit; Federal Register 91 FR 28629 (18 May 2026): Hermes test reactor construction completion date extension; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 1 construction permit

United StatesConstruction application / decisionIssued / approvedNRC
CNSC vendor design review, Phases 1 and 2 (Xe-100)
Document and scope

CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of X-energy's Xe-100 among its completed reviews, with an executive summary dated December 2023. CNSC entered into the agreement with X-energy to conduct the review on 20 July 2020; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.

Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: X-energy Xe-100 vendor design review executive summary

CanadaDesign assessmentReview completed (not an approval)Combined Phases 1 and 2.CNSC
NB Power license to prepare site application
Document and scope

Site preparation license application for ARC-100.

Sources: CNSC NB Power ARC-100 Project

CanadaSite application / decisionUnder reviewCNSC
TMSR-LF1 operating license 2307
Document and scope

NNSA issued operating license 国核安证字第2307号 to SINAP on 7 June 2023, expiring 6 June 2033. The instrument includes separate commissioning hold points; it does not prove their release.

Sources: NNSA: TMSR-LF1 operating licence 2307

ChinaOperating application / decisionIssued / approvedNNSA
CNSC vendor design review, Phase 2 (IMSR400)
Document and scope

CNSC lists Phase 1 (executive summary dated November 2017) and Phase 2 (executive summary dated April 2023) of its pre-licensing vendor design review of Terrestrial Energy's IMSR400 among completed reviews. CNSC entered into the Phase 2 agreement with Terrestrial Energy on 9 May 2018; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barrier to licensing within the reviewed topics and required further design and safety work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.

Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: IMSR400 Phase 2 pre-licensing vendor design review summary

CanadaDesign assessmentReview completed (not an approval)Phase 2. Phase 1 summary dated November 2017.CNSC
CNSC vendor design review, Phases 1 and 2 (BWRX-300)
Document and scope

CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.

Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary

CanadaDesign assessmentReview completed (not an approval)Combined Phases 1 and 2.CNSC
NRC design certification of the NuScale US600
Document and scope

The NRC lists the NuScale US600 among its issued design certifications. NuScale filed the application by letter dated 31 December 2016; the NRC lists it as tendered in December 2016, with the submission completed in January 2017. The certification rule, Appendix G to 10 CFR Part 52, was published on 19 January 2023 (88 FR 3306) and may be referenced for 40 years from 21 February 2023. The US600 is NuScale's earlier configuration of up to twelve modules of 50 MWe and 160 MWt each, which also received a standard design approval on 11 September 2020; the later US460 holds its own 2025 standard design approval. A design certification approves a design independent of any site and is not permission to build or operate.

Sources: eCFR: Appendix G to 10 CFR Part 52, Design Certification Rule for NuScale; NRC: Design Certification - NuScale US600 (past licensing activities); NRC: Design Certification Applications for New Reactors; Federal Register FR Doc. 2017-06309 (30 Mar 2017): NuScale design certification application accepted for docketing

United StatesDesign assessmentIssued / approvedCertification rule published 19 January 2023, effective 21 February 2023.NRC
Project Pele record of decision (prototype mobile microreactor environmental impact statement)
Document and scope

Signed 5 April 2022 and published 15 April 2022 at 87 FR 22521. The Strategic Capabilities Office decided to implement the proposed action of its final environmental impact statement: fabricate the prototype mobile microreactor and its fuel at existing off-site commercial facilities and demonstrate it at the Idaho National Laboratory Site. This is a National Environmental Policy Act decision. This record addresses the environmental decision; it does not establish the status of any separate DOE safety authorization. No such authorization document was opened.

Sources: Federal Register 87 FR 22521 (15 Apr 2022): Record of Decision, Construction and Demonstration of a Prototype Mobile Microreactor

United StatesEnvironmental decisionIssued / approvedU.S. Department of Defense, Strategic Capabilities Office
Oklo Aurora custom combined license application (2020), denied without prejudice
Document and scope

Oklo Power applied on 11 March 2020 for a custom combined license, which covers construction and operation, for one Aurora microreactor at Idaho National Laboratory. The NRC denied it without prejudice by letter of 6 January 2022 because requested information was not provided, and said Oklo may resubmit. This is an earlier application than the current Aurora powerhouse, which is following DOE authorization under the Reactor Pilot Program. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only (project 99902095) and no docketed application.

Sources: Federal Register 87 FR 1441 (11 Jan 2022): Oklo Aurora combined license application, denial; NRC pre-application activities: Oklo Aurora Powerhouse

United StatesOther regulatory actionDeniedNRC
DOE finding of no significant impact for MARVEL (DOE/EA-2146)
Document and scope

Issued at Idaho Falls on 12 November 2021 for environmental assessment DOE/EA-2146. DOE found that designing and demonstrating MARVEL in the north high bay of the Transient Reactor Test facility would not significantly affect the human environment, so no environmental impact statement is required. It is an environmental finding. It is not approval of a safety analysis and not authority to load fuel or operate. The 2021 text describes about 20 kW electric; DOE's current project page gives 85 kW thermal and about 10 kW electric.

Sources: DOE/EA-2146 Finding of No Significant Impact: MARVEL microreactor

United StatesEnvironmental decisionIssued / approvedU.S. Department of Energy, Idaho Operations Office
Renewal of Darlington New Nuclear Project site preparation license (PRSL 18.00/2031)
Document and scope

Record of Decision DEC 21-H4; application received 29 June 2020.

Sources: CNSC: Renewal of Darlington New Nuclear Project site preparation licence (PRSL 18.00/2031)

CanadaSite application / decisionIssued / approvedCNSC
NNSA operating license for the Shidaowan HTR-PM demonstration
Document and scope

NNSA issued operating license 国核安证字第2119号 on 20 August 2021 for the high-temperature gas-cooled demonstration (CN-44) at Ningjin Town, Rongcheng, Shandong. The holder and operating organization is Huaneng Shandong Shidao Bay Nuclear Power Company, Ltd. Validity runs through 19 August 2061. First fuel loading is the start of operation. Condition 23 sets control points at 15 percent and 65 percent of plant rated electrical power and states no megawatt number. The legal representative named on the license is not stored.

Sources: NNSA operating licence for the Shidaowan high-temperature gas-cooled demonstration (Guohe Anzheng Zi No. 2119); NNSA operating-unit database: Shidaowan high-temperature gas-cooled demonstration

ChinaOperating application / decisionIssued / approvedNNSA
NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One)
Document and scope

NNSA issued construction license 国核安证字第2117号 on 1 July 2021, valid to 30 June 2031, after reviewing the construction application and inspecting readiness for the first nuclear-island concrete. The license names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations. IAEA PRIS reports a different construction-license date, 15 July 2019; the license document carries 1 July 2021, so the PRIS date is kept visible as a conflicting statement and is not treated as the license date. This is a construction license, not an operating license.

Sources: NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One)

ChinaConstruction application / decisionIssued / approvedNNSA
CNSC vendor design review, Phase 1 (SSR-W)
Document and scope

CNSC lists Phase 1 of its pre-licensing vendor design review of Moltex Energy's SSR-W300 among completed reviews, with an executive summary dated May 2021. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.

Sources: CNSC: vendor design review service agreements and completed reviews

CanadaDesign assessmentReview completed (not an approval)Phase 1. No later phase listed.CNSC
NRC standard design approval for the NuScale US600
Document and scope

The NRC records that NuScale requested a standard design approval for the US600 on 13 July 2020 and that it was approved on 11 September 2020 (ML20247J564). The design was later certified by rule in January 2023. A standard design approval approves a design independent of any site; it is not permission to build or operate.

Sources: NRC: Design Certification - NuScale US600 (past licensing activities)

United StatesDesign assessmentIssued / approvedApproved 11 September 2020, before the 2023 certification.NRC
CNSC vendor design review, Phase 1 (SMR-160)
Document and scope

CNSC lists Phase 1 of its pre-licensing vendor design review of the SMR-160 by SMR, LLC (Holtec International) among completed reviews, with an executive summary dated August 2020. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.

Sources: CNSC: vendor design review service agreements and completed reviews

CanadaDesign assessmentReview completed (not an approval)Phase 1. No later phase listed.CNSC
NRA decision to grant the HTTR installation-change permit
Document and scope

On 3 June 2020 the Nuclear Regulation Authority decided that the application to change the HTTR installation at Oarai meets the permit criteria and that the installation-change permit shall be granted under article 26(1) of the Reactor Regulation Act. The application was received on 26 November 2014. The draft letter has a blank number and a blank date, so no permit number is stored. This decision is not an operating license and is distinct from the July 2021 restart.

Sources: NRA commission paper deciding the HTTR installation-change permit (3 June 2020)

JapanOther regulatory actionIssued / approvedNRA
Clinch River Nuclear Site early site permit ESP-006
Document and scope

NRC: application for two or more SMR modules (up to 800 MWe, 2420 MWt) submitted 12 May 2016, docketed 30 Dec 2016; Commission decision 17 Dec 2019.

Sources: U.S. NRC: Clinch River Nuclear Site early site permit ESP-006

United StatesSite application / decisionIssued / approvedNRC
CNSC vendor design review, Phase 1 (USNC MMR)
Document and scope

CNSC lists Phase 1 of its pre-licensing vendor design review of the MMR by USNC-Power Ltd. (Ultra Safe Nuclear Corporation) among completed reviews, with an executive summary dated February 2019. No later phase is listed. CNSC's Chalk River project page names Ultra Safe Nuclear Corporation as the parent of Global First Power, whose proposed micro modular reactor this profile records. CNSC staff paused the Chalk River environmental assessment and licence-to-prepare-site application review as of August 2024. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.

Sources: CNSC: vendor design review service agreements and completed reviews; CNSC Global First Power project status

CanadaDesign assessmentReview completed (not an approval)Phase 1. No later phase listed.CNSC
HTR-10 operating license issued in 2014, valid through June 2024
Document and scope

NNSA notice 国核安发〔2014〕158号, dated 15 July 2014, issued operating license 国核安证字1405号 to Tsinghua University's Institute of Nuclear and New Energy Technology for the 10 MW high-temperature gas-cooled experimental reactor. The license is valid through 30 June 2024. Continued operation after that date requires a new application twelve months before expiry. No successor instrument was opened. The extracted license pages do not print a separate issue date; the decision-letter date is used. Personal names on the license are not stored.

Sources: NNSA notice issuing the HTR-10 operating licence (Guohe Anfa [2014] No. 158); NNSA operating licence for HTR-10 (Guohe Anzheng Zi No. 1405)

ChinaOperating application / decisionIssued / approvedNNSA
Korean standard design approval for SMART
Document and scope

KAERI's release says the Nuclear Safety and Security Commission issued a standard design approval for the original SMART (100 MWe, 330 MWth) on 4 July 2012 under Article 12 of the Nuclear Safety Act, after KAERI and KEPCO applied on 30 December 2010. The approval document itself was not opened. SMART100 holds a separate 2024 approval. A standard design approval is not a construction or operating permission.

Sources: KAERI: standard design approval issued for SMART (9 July 2012)

South KoreaDesign assessmentIssued / approvedOriginal SMART design. SMART100 has its own 2024 approval.NSSC (Republic of Korea)
Original Darlington New Nuclear Project site preparation license (PRSL 18.00/2022)
Document and scope

CNSC's project timeline records that Ontario Power Generation applied for a license to prepare site in September 2006, for the original Darlington New Nuclear Project. The 2021 renewal decision says the license was issued in 2012. The project timeline says the Joint Review Panel, as a panel of the Commission, issued a 10-year site preparation license in 2012. The license document itself was not opened, so the stored decision date stays at year precision.

Sources: CNSC: Renewal of Darlington New Nuclear Project site preparation licence (PRSL 18.00/2031); CNSC: Darlington New Nuclear Project timeline

CanadaSite application / decisionSupersededCNSC
NNSA first fuel loading license for HTR-10
Document and scope

Reported in NNSA's own 2014 letter attachment; the 2000 license instrument itself was not opened, so no license number.

Sources: NNSA: letter on the HTR-10 operating licence (Guohe Anhan [2014] No. 25)

ChinaOperating application / decisionIssued / approvedNNSA
Rolls-Royce SMR Generic Design Assessment
Document and scope

Generic Design Assessment of the Rolls-Royce SMR design by the UK regulators. ONR's page (read 3 October 2026) shows Step 1 from April 2022 to April 2023, Step 2 to July 2024 with published Step 2 statements, and Step 3 under way since July 2024. A GDA assesses the generic design only; it is not permission for any site, construction or operation, and no Step 3 conclusion is recorded here. The reactors index, fetched 5 October 2026, still lists this as the active assessment and does not record a Step 3 conclusion. Re-read on 28 October 2026, ONR's page still describes the assessment as ongoing.

Sources: ONR Generic Design Assessment: Rolls-Royce SMR

United KingdomDesign assessmentUnder reviewStep 3 under way since July 2024.ONR/EA (UK)
Doicești NuScale siting license application
Document and scope

CNCAN's August 2025 national report says an application for the NuScale VOYGR-6 design and Doicești siting licenses was submitted with only part of the supporting documents, and regulatory review was ongoing. The report does not date the filing or grant a license. A June 2026 report quoting CNCAN says no approval or permit had been issued. Nuclearelectrica's note for its 29 October 2026 shareholder meeting says the start of site-characterization studies required to obtain the site license has been delayed; that is the company's statement and reports no CNCAN decision. This action tracks the site application, not design certification or construction authority.

Sources: CNCAN: Romania tenth national nuclear-safety report, August 2025; DC Business: CNCAN reply on the Doicești SMR file (1 June 2026); Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English)

RomaniaSite application / decisionUnder reviewCNCAN
Natrium UK Generic Design Assessment
Document and scope

The UK regulators began a three-step Generic Design Assessment of TerraPower's Natrium on 5 June 2026, after ministers at the Department for Energy Security and Net Zero asked them to, following the department's review of TerraPower's application. Step 1 is preparatory. No step is recorded as completed, and the assessment is not permission for any UK site.

Sources: Environment Agency: assessing new nuclear reactor designs

United KingdomDesign assessmentUnder reviewStep 1 began 5 June 2026.ONR/EA (UK)
Xe-100 UK Generic Design Assessment (requested)
Document and scope

On 15 September 2026 ONR said the Department for Energy Security and Net Zero had asked it, the Environment Agency and Natural Resources Wales to begin a three-step Generic Design Assessment of X-energy UK Holdings Ltd's Xe-100 after a readiness review. The assessment begins once timescale and resource arrangements are in place, so no step is recorded as started. ONR's page, updated 28 September 2026 and re-read on 28 October 2026, still says so.

Sources: ONR: regulators asked to commence a Generic Design Assessment of Xe-100 (15 September 2026)

United KingdomDesign assessmentApplication receivedONR said on 15 September 2026 that regulators were asked to begin. Not started at its 28 September update.ONR/EA (UK)
CNSC vendor design review, Phase 2 (eVinci)
Document and scope

CNSC's table of current vendor design review agreements lists Westinghouse's eVinci (about 5 MWe) for Phase 2, with the review starting in June 2023 and its status on hold; Phase 1 objectives are addressed within the Phase 2 scope. The Canadian status does not describe eVinci's separate US test and deployment paths. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.

Sources: CNSC: vendor design review service agreements and completed reviews

CanadaDesign assessmentOn holdPhase 2 started June 2023 and is on hold.CNSC
International document summaries

Permissions outside the United States

Recorded project-specific documents and design assessments, with their issuing authorities. A design assessment is not site permission. These records are not an international policy inventory.

Brazil

Construction applications and decisions

Canada

Design assessment

  • CNSC vendor design review, Phase 2 (ARC-100) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Jul 2025
    CNSC lists Phase 1 (executive summary dated October 2019) and Phase 2 (executive summary dated July 2025) of its pre-licensing vendor design review of ARC Clean Technology's ARC-100 among completed reviews. CNSC entered into the Phase 2 agreement with ARC on 9 March 2022; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barriers to licensing at that time and listed further design work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. NB Power's Point Lepreau site application is a separate process.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: ARC-100 Phase 2 vendor design review executive summary
  • CNSC vendor design review, Phases 1 and 2 (Xe-100) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Dec 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of X-energy's Xe-100 among its completed reviews, with an executive summary dated December 2023. CNSC entered into the agreement with X-energy to conduct the review on 20 July 2020; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: X-energy Xe-100 vendor design review executive summary
  • CNSC vendor design review, Phase 2 (IMSR400) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Apr 2023
    CNSC lists Phase 1 (executive summary dated November 2017) and Phase 2 (executive summary dated April 2023) of its pre-licensing vendor design review of Terrestrial Energy's IMSR400 among completed reviews. CNSC entered into the Phase 2 agreement with Terrestrial Energy on 9 May 2018; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barrier to licensing within the reviewed topics and required further design and safety work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: IMSR400 Phase 2 pre-licensing vendor design review summary
  • CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary
  • CNSC vendor design review, Phase 1 (SSR-W) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed May 2021
    CNSC lists Phase 1 of its pre-licensing vendor design review of Moltex Energy's SSR-W300 among completed reviews, with an executive summary dated May 2021. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews
  • CNSC vendor design review, Phase 1 (SMR-160) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Aug 2020
    CNSC lists Phase 1 of its pre-licensing vendor design review of the SMR-160 by SMR, LLC (Holtec International) among completed reviews, with an executive summary dated August 2020. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews
  • CNSC vendor design review, Phase 1 (USNC MMR) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Feb 2019
    CNSC lists Phase 1 of its pre-licensing vendor design review of the MMR by USNC-Power Ltd. (Ultra Safe Nuclear Corporation) among completed reviews, with an executive summary dated February 2019. No later phase is listed. CNSC's Chalk River project page names Ultra Safe Nuclear Corporation as the parent of Global First Power, whose proposed micro modular reactor this profile records. CNSC staff paused the Chalk River environmental assessment and licence-to-prepare-site application review as of August 2024. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC Global First Power project status
  • CNSC vendor design review, Phase 2 (eVinci) — applies to the design, not to a site
    Design assessment · On hold · CNSC
    CNSC's table of current vendor design review agreements lists Westinghouse's eVinci (about 5 MWe) for Phase 2, with the review starting in June 2023 and its status on hold; Phase 1 objectives are addressed within the Phase 2 scope. The Canadian status does not describe eVinci's separate US test and deployment paths. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews

    Status confirmed on against CNSC: vendor design review service agreements and completed reviews. This confirms the recorded status only; the general record check date remains separate.

Site applications and decisions

Construction applications and decisions

Operating-license applications and decisions

China

Site applications and decisions

Construction applications and decisions

  • NNSA construction license 国核安证字第2621号 for Xuwei Phase I Unit 3 (HTGR) — Xuwei nuclear heating and power plant Unit 3 (HTGR)
    Construction permission · Issued / approved · NNSA · decided 2 Nov 2026 · permit 国核安证字第2621号
    China's nuclear regulator reported on 26 June 2025 that it had started the construction-license review for Unit 3 of the Xuwei nuclear heating and power plant, covering the preliminary safety analysis report and the construction-stage environmental impact report, with CNNC Sueneng Nuclear Power presenting the high-temperature gas-cooled reactor. That notice gives no filing day and no license decision. The 9 October 2026 pre-construction inspection report found that preparations met the conditions for issuing a construction license and set seven corrective requirements; it does not itself issue the license. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction license 国核安证字第2621号 for Unit 3 to CNNC Sueneng, valid to 1 November 2036, and says the company may begin pouring the first concrete for the nuclear-island foundation. The license requires an operating-license application before first fuel loading. It is not an operating license. No construction start is recorded; a permit is not a physical construction start.
    Sources: NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
  • NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One) — Linglong One (ACP100) Changjiang
    Construction permission · Issued / approved · NNSA · decided 1 Jul 2021 · permit 国核安证字第2117号
    NNSA issued construction license 国核安证字第2117号 on 1 July 2021, valid to 30 June 2031, after reviewing the construction application and inspecting readiness for the first nuclear-island concrete. The license names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations. IAEA PRIS reports a different construction-license date, 15 July 2019; the license document carries 1 July 2021, so the PRIS date is kept visible as a conflicting statement and is not treated as the license date. This is a construction license, not an operating license.
    Sources: NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One)

Operating-license applications and decisions

Environmental decision

  • MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit) — Xuwei nuclear heating and power plant Unit 3 (HTGR)
    Environmental decision · Issued / approved · MEE · decided 17 Apr 2024
    The Ministry of Ecology and Environment approved the siting-stage environmental impact report for Xuwei Phase I on 17 April 2024 (环审〔2024〕43号). The approval describes Phase I as two Hualong One pressurized-water units and one HTR-PM600S high-temperature gas-cooled reactor unit with supporting facilities at Xizoushan, Xuwei New Area, Lianyungang. It is an environmental decision for the siting stage covering the whole Phase I project, of which Unit 3 is the HTGR; it is not a construction license. The Hualong One units are outside SMRMap's scope.
    Sources: MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号

Other applications and decisions

France

Design assessment

  • HEXANA first safety-options request — applies to the design, not to a site
    Design assessment sought · Application received · ASNR · submitted 30 Sep 2026
    ASNR reports that Hexana requested an opinion on a first safety option for its small modular reactor on 30 September 2026. The page places this in pre-instruction safety-options exchanges. This is a design assessment request, not a Gard Rhodanien site application, construction permission or issued opinion.
    Sources: ASNR, PRM projects and technical exchanges (14 October 2026 update)
  • OTRERA ONE safety-options request — applies to the design, not to a site
    Design assessment sought · Application received · ASNR · submitted 30 Jul 2026
    ASNR states that Otrera filed a safety-options request on 30 July 2026 for OTRERA ONE, listed on the 14 October 2026 page as a 200 MWth sodium-cooled demonstrator/prototype. The page does not record an opinion or a creation authorization. This is not a sited project.
    Sources: ASNR, PRM projects and their fuel-fabrication plants
  • newcleo LFR-AS-30 safety-options request — applies to the design, not to a site
    Design assessment sought · Application received · ASNR · submitted 19 Dec 2025
    ASNR states that newcleo filed a safety-options request on 19 December 2025 for LFR-AS-30. The page does not record an opinion or a creation authorization.
    Sources: ASNR, PRM projects and their fuel-fabrication plants
  • Calogena CAL30 safety-options requests — applies to the design, not to a site
    Design assessment sought · Under review · ASNR · submitted 31 Oct 2024
    ASNR records a CAL30 safety-options request on 31 October 2024 and further requests through 28 August 2026. Its 19 May 2026 opinion concerns shutdown-system diversification: principles are broadly satisfactory, with stronger electrical diversification, detailed design and qualification evidence, and a simple, robust alternative shutdown means required for possible common-mode rod blockage. These are requirements for a possible future creation-authorization application, not whole-design approval or a Cadarache site permission. The opinion dates the amended letter 19 June 2025, while the earlier listing records 20 June 2025.
    Sources: ASNR, PRM projects and their fuel-fabrication plants; ASNR, PRM projects and technical exchanges (14 October 2026 update); ASNR opinion 2026-AV-027: CAL30 shutdown-system safety options

    Could not be confirmed on . Attempted official source: ASNR opinion 2026-AV-027: CAL30 shutdown-system safety options. This is an access or status observation only; the record review date is unchanged.

Construction applications and decisions

Indonesia

Site applications and decisions

Japan

Other applications and decisions

  • NRA decision to grant the HTTR installation-change permit — HTTR test reactor with planned hydrogen coupling, Oarai
    Other regulatory action · Issued / approved · NRA · decided 3 Jun 2020 · submitted 26 Nov 2014
    On 3 June 2020 the Nuclear Regulation Authority decided that the application to change the HTTR installation at Oarai meets the permit criteria and that the installation-change permit shall be granted under article 26(1) of the Reactor Regulation Act. The application was received on 26 November 2014. The draft letter has a blank number and a blank date, so no permit number is stored. This decision is not an operating license and is distinct from the July 2021 restart.
    Sources: NRA commission paper deciding the HTTR installation-change permit (3 June 2020)

Romania

Site applications and decisions

South Korea

Design assessment

  • Korean standard design approval for SMART100 — applies to the design, not to a site
    Design assessment · Issued / approved · NSSC (Republic of Korea) · decided 26 Sep 2024 · submitted 30 Dec 2019
    The NSSC's 201st meeting approved SMART100's standard design on 26 September 2024. Printed minutes pp.121–123 distinguish standard-design approval from construction permission, direct administrative follow-up on power-system review during later licensing and continued verification improvements, and remove disputed wording asserting that a single off-site power circuit presents no safety impediment. The application date is recorded in the technical agenda. This does not authorize any project, construction or operation, does not approve SMART-C, and is not a Saudi or Canadian license. No separate issued certificate number was opened.
    Sources: NSSC: SMART100 approval agenda and technical review (26 September 2024, Korean); NSSC: 201st meeting minutes, SMART100 decision (26 September 2024, Korean); KAERI: SMART100 standard design approval and SMART upgrade (27 September 2024)
  • Korean standard design approval for SMART — applies to the design, not to a site
    Design assessment · Issued / approved · NSSC (Republic of Korea) · decided 4 Jul 2012 · submitted 30 Dec 2010
    KAERI's release says the Nuclear Safety and Security Commission issued a standard design approval for the original SMART (100 MWe, 330 MWth) on 4 July 2012 under Article 12 of the Nuclear Safety Act, after KAERI and KEPCO applied on 30 December 2010. The approval document itself was not opened. SMART100 holds a separate 2024 approval. A standard design approval is not a construction or operating permission.
    Sources: KAERI: standard design approval issued for SMART (9 July 2012)

Sweden

Site applications and decisions

United Kingdom

Design assessment

  • Holtec SMR-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed 31 Mar 2026 · submitted Jan 2023
    Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in January 2023, according to the Environment Agency's Step 1 summary; it was renamed SMR-300 in January 2024. The UK regulators began a two-step Generic Design Assessment of Holtec's SMR-300 on 18 October 2023 at the government's request. Step 1 ran from October 2023 to August 2024 and Step 2 from August 2024 to March 2026. The Environment Agency records completing Step 2 on 31 March 2026, and ONR's page records the assessment as completed that month with no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: Environment Agency: assessing new nuclear reactor designs; ONR, Holtec SMR-300 Generic Design Assessment; Environment Agency: GDA Step 1 of the Holtec SMR, statement of findings public summary
  • BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
    The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs
  • Rolls-Royce SMR UK Generic Design Assessment, Step 2 — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed 30 Jul 2024
    The UK regulators completed Step 2 of their three-step Generic Design Assessment of the Rolls-Royce SMR on 30 July 2024 and issued Step 2 statements. Step 2 began on 3 April 2023, after Step 1 from April 2022 to April 2023. Step 3, the detailed assessment, began in July 2024 and is recorded separately as under way. Completing Step 2 is not a Design Acceptance Confirmation or permission for any site.
    Sources: Environment Agency: assessing new nuclear reactor designs; ONR Generic Design Assessment: Rolls-Royce SMR; Environment Agency and Natural Resources Wales: GDA Step 2 of the Rolls-Royce SMR
  • Rolls-Royce SMR Generic Design Assessment — applies to the design, not to a site
    Design assessment sought · Under review · ONR/EA (UK)
    Generic Design Assessment of the Rolls-Royce SMR design by the UK regulators. ONR's page (read 3 October 2026) shows Step 1 from April 2022 to April 2023, Step 2 to July 2024 with published Step 2 statements, and Step 3 under way since July 2024. A GDA assesses the generic design only; it is not permission for any site, construction or operation, and no Step 3 conclusion is recorded here. The reactors index, fetched 5 October 2026, still lists this as the active assessment and does not record a Step 3 conclusion. Re-read on 28 October 2026, ONR's page still describes the assessment as ongoing.
    Sources: ONR Generic Design Assessment: Rolls-Royce SMR

    Status confirmed on against ONR Generic Design Assessment: Rolls-Royce SMR. This confirms the recorded status only; the general record check date remains separate.

  • Natrium UK Generic Design Assessment — applies to the design, not to a site
    Design assessment sought · Under review · ONR/EA (UK)
    The UK regulators began a three-step Generic Design Assessment of TerraPower's Natrium on 5 June 2026, after ministers at the Department for Energy Security and Net Zero asked them to, following the department's review of TerraPower's application. Step 1 is preparatory. No step is recorded as completed, and the assessment is not permission for any UK site.
    Sources: Environment Agency: assessing new nuclear reactor designs

    Status confirmed on against Environment Agency: assessing new nuclear reactor designs. This confirms the recorded status only; the general record check date remains separate.

  • Xe-100 UK Generic Design Assessment (requested) — applies to the design, not to a site
    Design assessment sought · Application received · ONR/EA (UK)
    On 15 September 2026 ONR said the Department for Energy Security and Net Zero had asked it, the Environment Agency and Natural Resources Wales to begin a three-step Generic Design Assessment of X-energy UK Holdings Ltd's Xe-100 after a readiness review. The assessment begins once timescale and resource arrangements are in place, so no step is recorded as started. ONR's page, updated 28 September 2026 and re-read on 28 October 2026, still says so.
    Sources: ONR: regulators asked to commence a Generic Design Assessment of Xe-100 (15 September 2026)

    Could not be confirmed on . Attempted official source: ONR: regulators asked to commence a Generic Design Assessment of Xe-100 (15 September 2026). This is an access or status observation only; the record review date is unchanged.

Uzbekistan

Site applications and decisions

  • Permit to use the site for nuclear installations (Farish district NPP site) — RITM-200N Jizzakh
    Site permission · Issued / approved · Committee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of the Republic of Uzbekistan · decided 23 Mar 2026
    Regulator's own news item dated 4 June 2026 states the permit was issued on 23 March 'of the current year'. The notice reports permission to use the site designated for nuclear installations for NPP construction. It does not give a permit number.
    Sources: Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026

Construction applications and decisions

US research coverage: Of these 50, 29 have a bounded review concluded, 21 are concluded with access gaps still open, and 0 are unfinished because a source class has not been reviewed. A concluded review is not exhaustive coverage. This bounded review is not an exhaustive policy inventory. See all 50 states, DC and five territories, sources and access limits.

Research coverage: 50 states, the District of Columbia and five territories

This table shows what SMRMap's policy review has and has not read, as of 5 Oct 2026. It is a record of research, not a rating of any jurisdiction. One outcome per jurisdiction and source class, for the sources named in each note. A bounded review is concluded when each agreed class has an outcome recorded. That conclusion does not require an instrument in every class. A source that could not be read remains an access gap. A class marked not reviewed means the bounded review is unfinished. Coverage status is separate from published instruments, and nothing here is a finding that a jurisdiction has no policy.

  • Evidence read: An official instrument of this class that addresses nuclear energy was opened and read. It does not mean the class is complete.
  • None found in sources checked: Official sources of this class were opened and readable, and none was an instrument of this class addressing nuclear energy. It is not a finding that none exists.
  • Access blocked: The official source could not be read: an HTTP error, a failed certificate check, a page shell or an image without text.
  • Not reviewed: No source of this class was opened. Where the only text read is an instrument already counted in another class, the note says so.
50 states by source class
Source classEvidence readNone found in sources checkedAccess blockedNot reviewed
Statutes, session laws and bills44240
Governor or energy instruments1327100
Commission or siting instruments1425110
Funding measures and awards202370

Of these 50, 29 have a bounded review concluded, 21 are concluded with access gaps still open, and 0 are unfinished because a source class has not been reviewed. A concluded review is not exhaustive coverage.

The 50 states
JurisdictionStatutes, session laws and billsGovernor or energyCommission or sitingFunding and awardsRecords
AlabamaEvidence readNone found in sources checkedNone found in sources checkedNone found in sources checkedNone published
AlaskaEvidence readEvidence readAccess blockedAccess blocked1 published
ArizonaEvidence readEvidence readAccess blockedEvidence read3 published
ArkansasEvidence readNone found in sources checkedNone found in sources checkedEvidence read2 published
CaliforniaEvidence readNone found in sources checkedEvidence readEvidence read2 published
ColoradoEvidence readAccess blockedAccess blockedNone found in sources checked1 published
ConnecticutAccess blockedEvidence readNone found in sources checkedAccess blockedNone published
DelawareEvidence readNone found in sources checkedNone found in sources checkedNone found in sources checkedNone published
FloridaEvidence readNone found in sources checkedEvidence readNone found in sources checked1 published
GeorgiaEvidence readNone found in sources checkedNone found in sources checkedNone found in sources checkedNone published
HawaiiEvidence readNone found in sources checkedNone found in sources checkedNone found in sources checked1 published
IdahoEvidence readEvidence readEvidence readNone found in sources checked5 published
IllinoisAccess blockedEvidence readEvidence readEvidence read1 published
IndianaEvidence readEvidence readEvidence readAccess blocked5 published
IowaEvidence readEvidence readNone found in sources checkedNone found in sources checked2 published
KansasEvidence readAccess blockedAccess blockedEvidence read2 published
KentuckyEvidence readNone found in sources checkedEvidence readEvidence read4 published
LouisianaEvidence readEvidence readNone found in sources checkedNone found in sources checked3 published
MaineEvidence readNone found in sources checkedNone found in sources checkedEvidence read1 published
MarylandEvidence readEvidence readNone found in sources checkedNone found in sources checkedNone published
MassachusettsEvidence readAccess blockedAccess blockedNone found in sources checkedNone published
MichiganEvidence readAccess blockedAccess blockedEvidence read4 published
MinnesotaEvidence readNone found in sources checkedEvidence readNone found in sources checked2 published
MississippiAccess blockedAccess blockedNone found in sources checkedNone found in sources checkedNone published
MissouriEvidence readAccess blockedEvidence readEvidence read2 published
MontanaEvidence readEvidence readNone found in sources checkedNone found in sources checked1 published
NebraskaEvidence readNone found in sources checkedNone found in sources checkedEvidence read1 published
NevadaEvidence readNone found in sources checkedNone found in sources checkedEvidence read1 published
New HampshireEvidence readAccess blockedNone found in sources checkedAccess blocked1 published
New JerseyEvidence readEvidence readEvidence readEvidence read2 published
New MexicoNone found in sources checkedNone found in sources checkedNone found in sources checkedNone found in sources checked1 published
New YorkEvidence readNone found in sources checkedEvidence readAccess blocked1 published
North CarolinaEvidence readNone found in sources checkedAccess blockedNone found in sources checked2 published
North DakotaEvidence readNone found in sources checkedNone found in sources checkedEvidence read1 published
OhioEvidence readAccess blockedNone found in sources checkedEvidence read3 published
OklahomaEvidence readNone found in sources checkedNone found in sources checkedNone found in sources checked1 published
OregonEvidence readNone found in sources checkedEvidence readEvidence read1 published
PennsylvaniaEvidence readNone found in sources checkedAccess blockedNone found in sources checked1 published
Rhode IslandEvidence readNone found in sources checkedEvidence readNone found in sources checked3 published
South CarolinaEvidence readEvidence readEvidence readNone found in sources checked3 published
South DakotaNone found in sources checkedNone found in sources checkedNone found in sources checkedNone found in sources checked1 published
TennesseeEvidence readAccess blockedAccess blockedEvidence read1 published
TexasEvidence readEvidence readNone found in sources checkedEvidence read3 published
UtahAccess blockedNone found in sources checkedAccess blockedAccess blockedNone published
VermontEvidence readNone found in sources checkedNone found in sources checkedEvidence read1 published
VirginiaEvidence readNone found in sources checkedEvidence readEvidence read3 published
WashingtonEvidence readNone found in sources checkedNone found in sources checkedNone found in sources checked1 published
West VirginiaEvidence readNone found in sources checkedAccess blockedNone found in sources checked1 published
WisconsinEvidence readNone found in sources checkedNone found in sources checkedAccess blocked2 published
WyomingEvidence readAccess blockedNone found in sources checkedEvidence read2 published

District of Columbia and territories

These six jurisdictions are not states and are not counted in the 50. Each entry below says which regulator or rule-maker was checked, where one was identified. Of these 6, 3 have a bounded review concluded, 3 are concluded with access gaps still open, and 0 are unfinished because a source class has not been reviewed. A concluded review is not exhaustive coverage.

District of Columbia and the five inhabited territories
JurisdictionStatutes, session laws and billsGovernor or energyCommission or sitingFunding and awardsRecords
District of ColumbiaNone found in sources checkedNone found in sources checkedNone found in sources checkedNone found in sources checkedNone published
Puerto RicoEvidence readNone found in sources checkedNone found in sources checkedNone found in sources checked1 published
GuamEvidence readNone found in sources checkedAccess blockedNone found in sources checkedNone published
U.S. Virgin IslandsAccess blockedNone found in sources checkedNone found in sources checkedNone found in sources checkedNone published
American SamoaNone found in sources checkedNone found in sources checkedNone found in sources checkedNone found in sources checkedNone published
Northern Mariana IslandsEvidence readNone found in sources checkedAccess blockedNone found in sources checked1 published

How the classes are counted

  • A class counts only when the opened text is an instrument of that class. A news release, index, report or synopsis is not an instrument.
  • An instrument is counted in one class only. A statute cited for a second class does not become evidence for that class.
  • A source that could not be read is an access limit, never a finding that nothing exists.
  • A bounded review is concluded when every agreed class has an outcome. It does not require an instrument in every class. An access gap stays open. A class not reviewed means the review is unfinished.
  • The District of Columbia and the territories are listed separately and are not part of the 50 states.

What was checked, by jurisdiction

Open a jurisdiction to see the note for each source class and every source address checked, with the date it was checked and whether it could be read. A link from the table above opens its entry.

Alabama — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Enrolled Senate Joint Resolution 88 (2026), supporting a federal nuclear-lifecycle request, was read; it appropriates nothing. The code pages for sections 22-14-1 and 22-14-9 returned only a navigation shell.
  • Governor or energy instruments: None found in sources checked. The governor's 21 June 2023 news release on a private micro-reactor assembly plant was read. It is not an executive instrument, and no executive order was opened.
  • Commission or siting instruments: None found in sources checked. The Public Service Commission's 2025 annual report and radiation-control rule 420-3-26-.01 (general provisions) were read. Neither is a commission or siting instrument on nuclear generation; section 37-4-28, which the report describes, was not opened.
  • Funding measures and awards: None found in sources checked. Enrolled Senate Bill 304 (2025) was read. It creates a strategic energy infrastructure fund with a $50,000,000 deposit and does not mention nuclear or reactors.

Sources read (5):

Sources that could not be read (2):

Alaska — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Chapter 4, SLA 2022 (microreactor siting, signed 24 May 2022, effective 22 August 2022) and the current Title 18 compilation with AS 18.45.025 were read.
  • Governor or energy instruments: Evidence read. Administrative Order No. 340 was read. It names nuclear energy among energy sources and prints a signature date of 30 September 2022.
  • Commission or siting instruments: Access blocked. The Department of Environmental Conservation's regulations page for 18 AAC 87 returned an access refusal (HTTP 403).
  • Funding measures and awards: Access blocked. A capital-appropriation status report on the state budget office site failed TLS certificate verification. No appropriation was read.

Sources read (5):

Sources that could not be read (3):

Arizona — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Current A.R.S. 40-360 and 40-360.03 (siting certificates) were read; the definition of a plant covers a nuclear generating unit of 100 megawatts or more. A fact sheet on vetoed S.B. 1418 (2026) was also read; it is a synopsis, not the bill, and the enrolled bill and the veto letter were not opened. The sections print no history date.
  • Governor or energy instruments: Evidence read. Executive Order 2025-13 (energy task force) was read. It confers no legal rights and appropriates nothing.
  • Commission or siting instruments: Access blocked. The Secretary of State file for Title 14, Chapter 7 returned an access refusal (HTTP 403). A Corporation Commission decision file failed TLS certificate verification. The eDocket item page returned a title shell without the decision. No commission rule or decision text was read.
  • Funding measures and awards: Evidence read. 2025 Session Laws chapter 56 (S.B. 1009), approved 18 April 2025, was read: appropriations from the nuclear emergency management fund for fiscal years 2025-26 and 2026-27.

Sources read (6):

Sources that could not be read (3):

Arkansas — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Act 707 of 2025 (a feasibility study that includes small modular reactors and microreactors, approved 16 April 2025) and Act 373 of 2025 (approved 20 March 2025) were read from the enrolled texts. The current code page for section 23-4-1308 returned a server error (HTTP 500).
  • Governor or energy instruments: None found in sources checked. The governor's page for Executive Order 26-04 (permitting for economic development projects) was read. It does not mention nuclear.
  • Commission or siting instruments: None found in sources checked. Public Service Commission Order No. 6 in Docket 26-003-U, a power-purchase decision, was read. It names existing nuclear units and sets no nuclear policy.
  • Funding measures and awards: Evidence read. The legislative-research consulting agreement for the Act 707 nuclear feasibility study was read: maximum payment $305,000. It is a contract, not an appropriation act.

Sources read (5):

Sources that could not be read (1):

California — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Current Public Resources Code sections 25524.1 and 25524.2 were read; both show a 1994 amendment effective 1 January 1995. The 1994 chapter itself was not opened.
  • Governor or energy instruments: None found in sources checked. A 2026 Energy Commission staff report on Diablo Canyon operations was read. It is a report, not an executive order or adopted energy instrument; no governor instrument was opened.
  • Commission or siting instruments: Evidence read. Public Utilities Commission Decision 23-12-036, conditionally approving extended operations at Diablo Canyon, was read. It concerns an existing plant, not a small modular reactor.
  • Funding measures and awards: Evidence read. Senate Bill 846 (2022), which establishes the Diablo Canyon Extension Fund, was read. It concerns an existing plant, not new-reactor funding.

Sources read (5):

Colorado — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. 2025 Session Laws chapter 45 (HB 25-1040), approved 31 March 2025, the bill page (effective 6 August 2025) and the Senate Journal history were read.
  • Governor or energy instruments: Access blocked. The governor's executive-order pages returned an access refusal (HTTP 403) on 4 and 5 October 2026, and the Colorado Energy Office site returned an access refusal (HTTP 403).
  • Commission or siting instruments: Access blocked. The Public Utilities Commission's electric-rules page and a commission order summary returned an access refusal (HTTP 403).
  • Funding measures and awards: None found in sources checked. The Joint Budget Committee's FY 2025-26 appropriations report was read. It does not mention nuclear.

Sources read (5):

Sources that could not be read (6):

Connecticut — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Access blocked. The General Assembly's statute pages failed TLS certificate verification on 4 and 5 October 2026, so section 22a-136 and Public Act 25-173 were not read. A court-filed working draft that would amend section 22a-136 was read; it is not the chaptered act.
  • Governor or energy instruments: Evidence read. The Department of Energy and Environmental Protection's notice of a proceeding to explore new nuclear capacity was read. It says section 33 of Public Act 25-173 lets a municipality opt in to lifting the construction moratorium for an advanced nuclear facility, and that the department will design a site-readiness funding program. The notice prints no date and decides nothing.
  • Commission or siting instruments: None found in sources checked. Connecticut Siting Council Docket No. 540 (2 April 2026), a telecommunications certificate, was read. It adopts no nuclear policy. The utility-regulation browse page returned a shell.
  • Funding measures and awards: Access blocked. The funding measure is section 34 of Public Act 25-173, which the department's notice describes as a site-readiness program backed by up to $5,000,000 in state bonds; the act itself could not be read and no award is recorded. State Bond Commission minutes for 29 May 2026 were read and do not mention nuclear.

Sources read (5):

Sources that could not be read (1):

Delaware — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Title 16, chapter 74 (out-of-state radioactive waste) and Senate Concurrent Resolution 18 (a nuclear feasibility task force) were read. The copy of the resolution does not print passage.
  • Governor or energy instruments: None found in sources checked. The Department of Natural Resources and Environmental Control's climate-plan page on electricity generation was read. It prints no adoption date and is not an executive instrument.
  • Commission or siting instruments: None found in sources checked. Public Service Commission Order No. 10816 (3 September 2025), opening a large-load tariff docket, was read. It states no nuclear policy. The regulations page for Title 26, section 3008 returned a shell.
  • Funding measures and awards: None found in sources checked. The body of House Bill 225, the appropriations act for the year ending 30 June 2026, was read. It does not mention nuclear or reactors; no approval date was read.

Sources read (6):

Sources that could not be read (1):

Florida — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Section 366.93 of the 2026 Florida Statutes (cost recovery for nuclear and gasification plants) was read. The host for the 2006 session law did not resolve.
  • Governor or energy instruments: None found in sources checked. The governor's executive-order index and Executive Order 26-200 were read. Order 26-200 is a State Attorney assignment, not an energy order.
  • Commission or siting instruments: Evidence read. Florida Administrative Code rule 25-6.0423 (nuclear and gasification plant cost recovery) was read.
  • Funding measures and awards: None found in sources checked. Laws of Florida chapter 2025-198, the General Appropriations Act, was read. It does not mention nuclear or reactors.

Sources read (6):

Sources that could not be read (1):

Georgia — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Adopted Senate Resolution 482, creating the Senate Nuclear Power Study Committee (ends 1 December 2026), was read.
  • Governor or energy instruments: None found in sources checked. The 2025 and 2026 executive-order indexes were read and show no nuclear title. The one order opened is an image with no readable text.
  • Commission or siting instruments: None found in sources checked. A Public Service Commission certification order in Dockets 56298 and 56310 was read. It names Plant Vogtle among previously certified resources and adopts no new nuclear policy; no issuance date was read. The 2009 and 2017 Vogtle orders were not opened.
  • Funding measures and awards: None found in sources checked. The Senate committee substitute to House Bill 68 (FY 2026 appropriations) was read. It does not mention nuclear and is not the enrolled act.

Sources read (5):

Hawaii — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Article XI, section 8 of the Hawaii Constitution (nuclear fission plants) was read. Current HRS 269-91 was also read and does not mention nuclear.
  • Governor or energy instruments: None found in sources checked. The Hawaii State Energy Office's 2025 report was read. It recommends no constitutional or portfolio amendment and proposes no legislation; it is a report, not an executive instrument.
  • Commission or siting instruments: None found in sources checked. The Public Utilities Commission's renewable-portfolio page was read. Its source list does not include nuclear. No commission order was opened.
  • Funding measures and awards: None found in sources checked. Act 250 of 2025, the General Appropriations Act (approved 30 June 2025), was read. It does not mention nuclear or reactors.

Sources read (2):

Sources that could not be read (1):

Idaho — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Idaho Code sections 39-3020 (Western Interstate Nuclear Compact, added 1969) and 39-3027 were read.
  • Governor or energy instruments: Evidence read. Executive Orders 2021-02 and 2025-06 (Advanced Nuclear Energy Task Force) were read. Executive Order 2024-10 is an image with no readable text.
  • Commission or siting instruments: Evidence read. Public Utilities Commission Order No. 37049 (served 22 May 2026) was read. It waives solicitation for a power-purchase agreement tied to Kemmerer Unit 1 and permits no reactor.
  • Funding measures and awards: None found in sources checked. House Bill 248 (2025), a natural-resources appropriations act, was read. It does not mention nuclear.

Sources read (9):

Sources that could not be read (1):

Illinois — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Access blocked. The General Assembly's site failed TLS certificate verification on 4 and 5 October 2026 for the nuclear statute and for Public Acts 103-0569 and 104-0458. Only an agency synopsis was read; it is not the statute.
  • Governor or energy instruments: Evidence read. Executive Order 2026-01 (18 February 2026), directing inquiries into new nuclear generation, was read. It takes effect on filing and permits no plant.
  • Commission or siting instruments: Evidence read. Illinois Commerce Commission Notice of Inquiry 26-NOI-01 (9 April 2026), on nuclear development, expansion and uprates, was read. The commission states the inquiry is not an enforceable order.
  • Funding measures and awards: Evidence read. The Illinois Power Agency's zero-emission-credit payment calculation for delivery year 2026-27 (10 June 2026) was read. It concerns ratepayer-funded credits for existing plants and is not an appropriation.

Sources read (4):

Sources that could not be read (5):

Indiana — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Indiana Code 8-1-8.5-12.1 (small modular reactor certificates) was read, and Senate Enrolled Acts 423 and 424 (2025) are published from the enrolled texts. On 5 October 2026 the legislature's site returned only a script shell for the enrolled Senate Bill 423.
  • Governor or energy instruments: Evidence read. Executive Order 25-48 (Nuclear Indiana Coalition) was read from the order copy; its number and date are not legible there. The Office of Energy Development's December 2025 annual report gives the issue date as 10 April 2025.
  • Commission or siting instruments: Evidence read. The Utility Regulatory Commission's final rule in RM 23-03 (approved 22 May 2024), amending 170 IAC 4-11 for small modular reactor certificates, was read.
  • Funding measures and awards: Access blocked. The enrolled House Bill 1007 (small modular reactor manufacturing credit) and the fiscal note for Senate Bill 423 returned a script shell. A Department of Revenue bulletin describing the credit was read; it is not the act.

Sources read (6):

Sources that could not be read (5):

Iowa — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. House File 2757 (2026) and the governor's approval letter dated 1 June 2026 were read. The bill-history page returned an empty table.
  • Governor or energy instruments: Evidence read. Executive Order 17, creating a nuclear energy task force (signed 5 January 2026), was read.
  • Commission or siting instruments: None found in sources checked. Iowa Utilities Commission rule 199—24.4, on the contents of an application for a generation certificate, was read and does not mention nuclear. The commission's judicial-proceedings page was also opened. It is a case list, not a rule or order.
  • Funding measures and awards: None found in sources checked. The Fiscal Services Division's final-action fiscal note on House File 2757 was read. It estimates that act, including the nuclear energy workforce fund already counted under statutes, and is not a separate appropriation. Other appropriation acts were not opened.

Sources read (6):

Sources that could not be read (1):

Kansas — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. K.S.A. 66-1,158 and 66-1,159 (nuclear generation facility siting permit) were read.
  • Governor or energy instruments: Access blocked. The governor's executive-order page returned an access refusal (HTTP 403) and the Secretary of State's order page led to a not-found page. Executive Directive No. 07-373 (energy conservation) and the Kansas Energy Office page were read; neither addresses nuclear generation.
  • Commission or siting instruments: Access blocked. The commission's electronic docket page timed out, and the KCC-Connect page returned an error shell with no order. The commission homepage was readable and is not an order.
  • Funding measures and awards: Evidence read. K.S.A. 79-266, a property-tax exemption for certain new electric generation, including nuclear, was read.

Sources read (3):

Sources that could not be read (4):

Kentucky — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. 2026 Kentucky Acts chapter 56 (signed 8 April 2026), with KRS 164.2805 and 278.615, was read.
  • Governor or energy instruments: None found in sources checked. The Kentucky Nuclear Energy Development Authority's 2025 annual report was read. It is a report, not an executive order.
  • Commission or siting instruments: Evidence read. The Public Service Commission order opening Case No. 2025-00186, an investigation of nuclear energy and related matters, was read. The copy prints no issuance date.
  • Funding measures and awards: Evidence read. 2025 Kentucky Acts chapter 51 (signed 24 March 2025) was read: up to $8,000,000 for the nuclear energy development grant program in fiscal year 2025-26. No award is recorded.

Sources read (6):

Louisiana — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Act 111 of 2025 (small modular reactor environmental permitting) and Act 462 of 2025 (green energy includes nuclear reactors) were read. Act 462 prints no approval day.
  • Governor or energy instruments: Evidence read. Executive Order JML 25-074 (24 June 2025) was read.
  • Commission or siting instruments: None found in sources checked. Public Service Commission minutes for 16 September 2026 were read; they record that the advanced-nuclear rule docket was deferred. Minutes are not a rule or order, and no adopted rule or order was opened.
  • Funding measures and awards: None found in sources checked. Enrolled House Bill 1, the FY 2025-26 appropriations act, was read. It does not mention nuclear or reactors; no approval day was read.

Sources read (6):

Maine — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Title 35-A, section 4302 (a statewide referendum before construction of a nuclear power plant) was read; the compilation is current through 1 October 2025.
  • Governor or energy instruments: None found in sources checked. The governor's 31 March 2026 news release and the joint New England governors' statement on nuclear energy were read. Neither is a Maine executive order.
  • Commission or siting instruments: None found in sources checked. The Public Utilities Commission's laws-and-rules page was read. It is a chapter-title index, and the page says some rule links may not work. The titles on that page do not mention nuclear. The text of each chapter was not opened.
  • Funding measures and awards: Evidence read. Title 35-A, chapter 43, including the Nuclear Decommissioning Financing Act, was read. It concerns decommissioning finance, not new-reactor funding.

Sources read (6):

Maryland — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. 2025 Laws chapter 626 (House Bill 1035), approval line 20 May 2025, was read. Its effective-date line is printed as markup, so no effective date is recorded.
  • Governor or energy instruments: Evidence read. Executive Order 01.01.2025.27 (signed 19 December 2025) was read. It names nuclear among industries for an advisory council.
  • Commission or siting instruments: None found in sources checked. A Public Service Commission staff report on nuclear procurement regulations and the commission's ten-year plan were read. The regulations were described as conceptual; no adopted rule was opened.
  • Funding measures and awards: None found in sources checked. The commission's March 2026 compliance report on nuclear zero-emission credits was read. It says no procurement has been held; it is not an appropriation.

Sources read (5):

Massachusetts — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. 1956 Acts chapter 645 and General Laws chapter 6, sections 85, 88, 91 and 92 (atomic energy) were read. Sections 86, 87, 89 and 90 returned a not-found error (HTTP 404).
  • Governor or energy instruments: Access blocked. The state's pages for Executive Orders No. 654 and No. 594 returned an access refusal (HTTP 403) on 4 October 2026, and the list of the governor's executive orders returned an access refusal (HTTP 403) on 5 October 2026.
  • Commission or siting instruments: Access blocked. The Energy Facilities Siting Board's 980 CMR 2 file and its laws-and-regulations page both returned an access refusal (HTTP 403). The Department of Public Utilities file room returned an application shell with no rule or docket text.
  • Funding measures and awards: None found in sources checked. General Laws chapter 23J, section 9 (Renewable Energy Trust Fund) was read. It names nuclear power only as excluded from the fund; no nuclear funding measure was opened.

Sources read (14):

Sources that could not be read (10):

Michigan — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. 2023 Public Act 235, 2022 Public Act 218 (nuclear feasibility study), MCL 780.941 and House-passed 2025 House Bill 4128 were read. The bill is not law.
  • Governor or energy instruments: Access blocked. The governor's pages for Executive Order 2026-6 and two news releases returned an access refusal (HTTP 403) on 4 October 2026, and the executive-orders list returned an access-denied page on 5 October 2026.
  • Commission or siting instruments: Access blocked. The Public Service Commission's nuclear feasibility study file returned an access refusal (HTTP 403).
  • Funding measures and awards: Evidence read. 2024 Public Act 121, section 811 (approved 24 July 2024), was read: a $150,000,000 one-time line to restart an unnamed reactor, contingent on a federal commitment that was not opened.

Sources read (5):

Sources that could not be read (5):

Minnesota — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Minnesota Statutes section 216B.243, subdivision 3b (no certificate of need for a new nuclear plant) and Laws 1994, chapter 641 were read.
  • Governor or energy instruments: None found in sources checked. The Department of Commerce energy page and its nuclear energy study page were read. They are agency pages; the session law that authorizes the study was not opened.
  • Commission or siting instruments: Evidence read. Minnesota Rules 7855.0030 and 7855.0600, Public Utilities Commission certificate-of-need rules, were read. Rule 7855.0030 includes a new nuclear fuel processing facility and a new nuclear waste storage or disposal facility among large energy facilities. Rule 7855.0600 states the contents of an application for a nuclear waste storage or disposal facility. The revisor marks the part published electronically on 14 November 2003. The rules do not permit a power reactor. The certificate-of-need statute is counted separately under statutes.
  • Funding measures and awards: None found in sources checked. 2003 First Special Session chapter 11 was read. Its account funds renewable development and is paid by the Prairie Island owner; it is not nuclear-generation funding.

Sources read (8):

Mississippi — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Access blocked. The legislature's bill page failed TLS certificate verification. Health-department radiation regulations were read; they are not the code section.
  • Governor or energy instruments: Access blocked. The Secretary of State's executive-order index was read, but it prints no order text, and the one order opened (No. 1596) is an image with no readable text.
  • Commission or siting instruments: None found in sources checked. The Public Service Commission's rules, including the facilities-certificate rule, were read. A certificate is required before construction of a generating facility; nuclear appears only in fuel-cost provisions, and the rules set no nuclear-specific siting policy.
  • Funding measures and awards: None found in sources checked. The FY 2026 budget bulletin and a State Auditor report on legislative expenses were read. A search of the bulletin found no nuclear or reactor appropriation; neither document is the appropriations act.

Sources read (5):

Sources that could not be read (2):

Missouri — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. RSMo 393.135 and 393.1400 (effective 28 August 2025) were read. They exclude new nuclear units from the gas and qualifying-plant provisions.
  • Governor or energy instruments: Access blocked. Executive Order 26-04 (Missouri Advanced Nuclear Energy Task Force) is listed on the governor's catalog page with the date 13 January 2026; the order text returned an access refusal (HTTP 403). A 2026 state energy plan brief was read.
  • Commission or siting instruments: Evidence read. Public Service Commission File No. EO-2024-0056 was read. The order was issued 4 January 2024 and is effective 3 February 2024. It approves a 15 December 2023 agreement and finds that Evergy Missouri Metro's annual Wolf Creek decommissioning accrual and trust payment continue at the existing level. It does not permit a new reactor. The decommissioning statute is counted separately under funding.
  • Funding measures and awards: Evidence read. RSMo 393.292 (effective 28 August 1989), on a nuclear decommissioning trust, was read. It concerns decommissioning finance, not new-reactor funding.

Sources read (6):

Sources that could not be read (1):

Montana — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Montana Code Annotated section 75-20-206 (conditions for uranium conversion and enrichment siting) and section 50-79-101 were read. Sections 50-79-102 to 50-79-108 were not opened.
  • Governor or energy instruments: Evidence read. Executive Order No. 6-2025 (signed 10 September 2025, effective immediately) was read. It creates an energy task force and names advanced nuclear modular reactors among emerging technologies; it permits no reactor.
  • Commission or siting instruments: None found in sources checked. DEQ Circular MFSA-2 (2023), on applications for linear facilities, was read. It does not mention nuclear.
  • Funding measures and awards: None found in sources checked. Legislative audit 24-01 was read. Its nuclear line is a federal-award schedule for the year ended 30 June 2024, not a state appropriation.

Sources read (5):

Nebraska — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Sections 70-627.02 (nuclear-plant management indemnification) and 71-3501 (radioactive-waste policy) were read.
  • Governor or energy instruments: None found in sources checked. Executive Order 26-01 (meeting power demands in a state of emergency) and a 23 July 2026 governor news release were read. Neither addresses nuclear generation.
  • Commission or siting instruments: None found in sources checked. The Power Review Board orders page and regulations page were read and do not use the word nuclear. Generation-order titles on the orders page include wind, gas, diesel, coal and storage. Those titles and the regulations page were read. The linked order files were not each opened.
  • Funding measures and awards: Evidence read. Section 71-3505 was read: capped fees for nuclear-plant emergency response and surveillance. The compilation prints no effective date.

Sources read (6):

Nevada — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. NRS 459.910 (prohibition on storing high-level radioactive waste) was read.
  • Governor or energy instruments: None found in sources checked. The Agency for Nuclear Projects page was read. It describes a governor's-office agency and is not an executive order. The agency's own site did not resolve.
  • Commission or siting instruments: None found in sources checked. Nevada Administrative Code chapter 704, posted by the Legislative Counsel Bureau, was read. The only use of the word nuclear is item 7 of the customer-disclosure list in NAC 704.2785, beside coal, gas, oil, hydroelectric, geothermal, solar, wind and other sources. The rule does not site or approve a reactor. A separate commission docket search was not done.
  • Funding measures and awards: Evidence read. Enrolled Assembly Bill 591 (2025) was read: $1,520,464 and $1,516,594 for the Agency for Nuclear Projects. The chapter line on the copy is blank.

Sources read (2):

Sources that could not be read (1):

New Hampshire — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. RSA 162-F (decommissioning funding) and RSA 162-H (energy facility certificates) were read. RSA 162-F:1 prints an effective date of 3 September 2001 for its latest amendment.
  • Governor or energy instruments: Access blocked. The governor's page announcing an executive order on next-generation nuclear and the Secretary of State's copy of Executive Order 2026-01 returned an access refusal (HTTP 403) on 4 October 2026; the governor's executive-orders page returned an access-denied page on 5 October 2026.
  • Commission or siting instruments: None found in sources checked. The General Court's compilation of Site 100, 200 and 300 was read. The text includes the site-evaluation definitions and application rules and does not contain the word nuclear. An adoption-letter file on the Site Evaluation Committee site returned an access refusal (HTTP 403) and was not read.
  • Funding measures and awards: Access blocked. The Nuclear Decommissioning Financing Committee page and its 2025 order returned an access refusal (HTTP 403). The fund statute, RSA 162-F:19, is part of the chapter counted under statutes.

Sources read (3):

Sources that could not be read (5):

New Jersey — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. P.L. 2026, chapter 9 (approved 8 April 2026, effective immediately), amending the coastal permit finding for nuclear facilities, was read. The pre-2026 code text returned a script shell.
  • Governor or energy instruments: Evidence read. Executive Order No. 2 (signed 20 January 2026), establishing the Nuclear Power Task Force, was read. It appropriates nothing and permits no reactor.
  • Commission or siting instruments: Evidence read. The Board of Public Utilities order closing the third zero-emission-certificate eligibility period (Docket EO23080548, 21 February 2024) was read.
  • Funding measures and awards: Evidence read. P.L. 2018, chapter 16 (approved 23 May 2018), the Zero Emission Certificate Act, was read. It imposes a customer charge for existing plants and is not a construction appropriation.

Sources read (5):

Sources that could not be read (1):

New Mexico — Bounded review concluded
  • Statutes, session laws and bills: None found in sources checked. An agency copy of the Radiation Protection Act and an introduced 2010 bill (House Bill 101) were read. Neither is a signed chapter on nuclear generation; the statutes cited by the location rule were not opened.
  • Governor or energy instruments: None found in sources checked. Executive Order 2026-023 (signed 22 April 2026), creating an energy affordability and grid reliability council, was read. It does not mention nuclear.
  • Commission or siting instruments: None found in sources checked. Rule 17.9.592 NMAC (location approval for a large capacity plant) was read. It applies at 300 megawatts or more and does not name nuclear.
  • Funding measures and awards: None found in sources checked. The General Appropriation Act of 2026 (House Bill 2) was read. It does not mention nuclear; the copy prints no chapter number or approval day.

Sources read (9):

New York — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Assembly Bill A.6705 (introduced 7 March 2025, a small modular reactor feasibility study bill) was read; it is not enacted. The state's pages for Real Property Tax Law section 485 and Public Authorities Law section 1005 returned an access refusal (HTTP 403).
  • Governor or energy instruments: None found in sources checked. The governor's 1 June 2026 announcement on developing at least 1 gigawatt of nuclear energy upstate and the Department of Public Service release of 11 June 2026 were read. Both are releases, not executive orders.
  • Commission or siting instruments: Evidence read. The Public Service Commission's Order Establishing a Nuclear Reliability Backbone Process (Case 26-E-0335, issued and effective 11 June 2026) was read. It opens a process toward 4 gigawatts of new advanced nuclear and is not a construction permit.
  • Funding measures and awards: Access blocked. The FY 2026 financial plan timed out, so no appropriation was read. NYSERDA's Advanced Nuclear Energy program page was read on 5 October 2026; it describes a master plan in development and is not a funding instrument. An older address for that page returned a not-found page.

Sources read (6):

Sources that could not be read (4):

North Carolina — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. G.S. 62-133.8 (clean energy portfolio standard) and G.S. 166A-29 were read, with Session Laws 2023-138 and 2020-83. Session Law 2025-25 was also read and does not mention nuclear.
  • Governor or energy instruments: None found in sources checked. The Energy Policy Council's 2024 biennial report was read. It recommends an authority and enacts nothing; it is a report, not an executive instrument.
  • Commission or siting instruments: Access blocked. Two Utilities Commission files in the carbon-plan docket returned an access refusal (HTTP 403). A commission news release of 1 November 2024 was read; it is not the order.
  • Funding measures and awards: None found in sources checked. Session Law 2025-2 (additional hurricane appropriations) was read. It does not mention nuclear.

Sources read (8):

Sources that could not be read (2):

North Dakota — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Century Code chapters 38-23 and 49-22 were read. The opened sections print no enactment date.
  • Governor or energy instruments: None found in sources checked. The Department of Mineral Resources page on radioactive waste was read. It is an agency page with no date; no governor order was opened.
  • Commission or siting instruments: None found in sources checked. Public Service Commission rules on a certificate of site compatibility, chapter 69-06-04, and on siting criteria, chapter 69-06-08, were read. They do not mention nuclear. A legislative committee index names an Advanced Nuclear Energy Committee. That index is not a commission order, and the committee's documents were not opened.
  • Funding measures and awards: Evidence read. 2025 House Bill 1025 was read: an interim study of advanced nuclear plants with up to $300,000 in general funds and up to $300,000 in nonstate funds through 30 June 2027. The enrolled signature lines are blank.

Sources read (4):

Ohio — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Revised Code chapter 4164 (Nuclear Development Authority, effective 3 October 2023), enrolled House Bill 33 and sections 4906.01 and 4906.04 were read.
  • Governor or energy instruments: Access blocked. The governor's executive-order pages returned a not-found error (HTTP 404) on 4 and 5 October 2026, and a Department of Development page returned a not-found error (HTTP 404).
  • Commission or siting instruments: None found in sources checked. Power Siting Board rule 4906-3-01 (certificate application procedure) was read. It sets no nuclear-specific policy. A board fees page returned a not-found error (HTTP 404).
  • Funding measures and awards: Evidence read. Revised Code section 4937.05 (effective 17 October 2019) was read: assessments on nuclear utilities for a nuclear safety fund.

Sources read (4):

Sources that could not be read (4):

Oklahoma — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. 2025 session law chapter 491 (a nuclear energy feasibility study) and enrolled Senate Bill 130 were read. The enrolled bill's approval lines are blank.
  • Governor or energy instruments: None found in sources checked. Executive Order 2025-06 (a wildfire emergency) and a 28 July 2026 governor news release on a federal finalist selection were read. Neither is a nuclear order.
  • Commission or siting instruments: None found in sources checked. Corporation Commission minutes of 5 March 2026 were read; they record approval to deliver the nuclear feasibility study. Minutes are not a rule or order, and no commission rule or order was opened.
  • Funding measures and awards: None found in sources checked. No enacted appropriation was read. A $375,000 study line appears only in an engrossed amendment to Senate Bill 130, not in the enrolled act.

Sources read (5):

Oregon — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. ORS 469.594 to 469.601 (conditions for a nuclear-fueled thermal power plant) were read in the Public Utility Commission's 2025 law book. The legislature's chapter page timed out.
  • Governor or energy instruments: None found in sources checked. The Department of Energy's nuclear emergency preparedness page was read. It is an agency page, not an executive instrument.
  • Commission or siting instruments: Evidence read. Energy Facility Siting Council rule OAR 345-001-0010 (definitions, 23 April 2026 version) was read. It defines nuclear terms and excludes nuclear plants from one facility category; it certificates nothing.
  • Funding measures and awards: Evidence read. Enrolled Senate Bill 5518 (2025) was read: $179,870 for nuclear safety and emergency response. The chapter and approval lines on the copy are blank.

Sources read (6):

Sources that could not be read (1):

Pennsylvania — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Radiation Protection Act section 402.1 (small modular reactors) was read in the official compilation and on the Act 37 of 2026 page. The page prints 'Effective 60 days' and no calendar date.
  • Governor or energy instruments: None found in sources checked. Executive Order 2024-04 (permit fast-track program) was read. It is a general permitting order, not a nuclear instrument.
  • Commission or siting instruments: Access blocked. A Public Utility Commission document timed out on 4 October 2026 and the commission's site timed out on 5 October 2026. No commission rule or order was read.
  • Funding measures and awards: None found in sources checked. Radiation Protection Act section 403, which appropriates fee revenue for existing duties, was read. It is part of the act counted under statutes; no separate appropriation or award was opened.

Sources read (4):

Sources that could not be read (2):

Rhode Island — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. General Laws sections 39-31-5 (participation in nuclear-power procurement) and 42-98-4 (energy facility siting license) were read.
  • Governor or energy instruments: None found in sources checked. Executive Order 26-01 (energy costs and ratepayer transparency), a 31 March 2026 news release on a New England governors' nuclear statement and the Office of Energy Resources page were read. None is an executive instrument on nuclear generation.
  • Commission or siting instruments: Evidence read. Energy Facility Siting Board rule 445-RICR-00-00-1 was read on the Department of State rules site. The rule is active, with an effective date of 4 January 2022. Its definition of a major energy facility includes a facility for the processing, enrichment, storage or disposal of nuclear fuels and nuclear byproducts. The rule does not grant a permit. The siting statute is counted separately.
  • Funding measures and awards: None found in sources checked. General Laws section 39-26-7 (renewable energy development fund) was read. It is a renewable-energy fund; no nuclear appropriation was opened.

Sources read (5):

South Carolina — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. 2025 Act No. 41 (Governor's Nuclear Advisory Council; advanced nuclear facilities policy) and Title 58, chapter 33 (including section 58-33-196 and the Base Load Review Act) were read.
  • Governor or energy instruments: Evidence read. Executive Order 2023-18 (signed 9 June 2023) was read. It directs an energy working group to assess nuclear-power production among other resources.
  • Commission or siting instruments: Evidence read. Public Service Commission Order No. 2024-767 (25 November 2024), approving integrated resource plans, was read. It addresses license renewal for the existing fleet and certificates no new reactor.
  • Funding measures and awards: None found in sources checked. The status page for the 2025-26 appropriations bill (H. 4025) and a conference proviso on advisory-council travel were read. Neither is the enrolled appropriations act.

Sources read (6):

Sources that could not be read (1):

South Dakota — Bounded review concluded
  • Statutes, session laws and bills: None found in sources checked. Codified Laws sections 49-41B-2 and 49-41B-4 (energy facility construction permit) were read. They do not name nuclear.
  • Governor or energy instruments: None found in sources checked. Executive Order 2025-09 (a fuel-supply emergency) was read. It is not a nuclear order. A governor news page returned a script shell.
  • Commission or siting instruments: None found in sources checked. A utility petition in Public Utilities Commission docket EL26-019 was read. It is a rate petition, not a commission order. The administrative-rule page returned a loading shell.
  • Funding measures and awards: None found in sources checked. The FY 2026 Budget in Brief was read. It is a summary, not the appropriations act.

Sources read (5):

Sources that could not be read (4):

Tennessee — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Senate Joint Resolution 887 (adopted by the Senate 29 to 1 on 2 April 2026, supporting the state's response to a federal nuclear-lifecycle request) was read. It is a resolution, not a statute; the history then shows a referral to the Delayed Bills Committee and no House vote. Public-chapter files on the Secretary of State's site returned an access refusal (HTTP 403).
  • Governor or energy instruments: Access blocked. The Secretary of State's copy of Executive Order 101 (signed 16 May 2023, per the state's nuclear council report) returned an access refusal (HTTP 403) on 4 October 2026. On 5 October 2026 the Secretary of State's executive-orders page returned an access refusal (HTTP 403) and the governor's executive-orders page returned a not-found error (HTTP 404). Governor's news releases were read; they are not the order.
  • Commission or siting instruments: Access blocked. A radiation-control rule file returned an access refusal (HTTP 403) and a rulemaking file's connection was reset.
  • Funding measures and awards: Evidence read. Public Chapter No. 530 (2025 appropriations act) was read: a nuclear supply-chain carry-forward capped at $60,000,000. The approval day is not legible on the copy. The appropriation text for a later addition to the Nuclear Energy Fund was not located.

Sources read (7):

Sources that could not be read (9):

Texas — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Enrolled House Bill 14 (2025), signed 20 June 2025 and effective 1 September 2025, was read.
  • Governor or energy instruments: Evidence read. Governor Greg Abbott's 16 August 2023 letter to the interim chair of the Public Utility Commission, filed as Item 2 in Project No. 55421, was read. It instructs the commission to establish a working group to study and plan for advanced nuclear reactors in Texas, including the state's role, incentives, grid changes, permitting, supply chain and safety, and asks for a plan by 1 December 2024. The letter does not approve a reactor or grant a construction permit. The filed copy is a scan.
  • Commission or siting instruments: None found in sources checked. Public Utility Commission rule 25.101 (certification criteria) was read. It does not mention nuclear.
  • Funding measures and awards: Evidence read. The Texas Advanced Nuclear Energy Office's adopted grant rules for the Texas Advanced Nuclear Development Fund (Texas Register, 13 March 2026; effective 19 March 2026) and the fund's office page were read. The appropriation itself was not opened.

Sources read (5):

Utah — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Access blocked. The legislature's bill, enrolled-act and code pages failed TLS certificate verification on 4 and 5 October 2026, so 2025 House Bill 249 and the code were not read.
  • Governor or energy instruments: None found in sources checked. The governor's executive-order register for 2022 to 2026, the governor's 8 October 2024 news release on Operation Gigawatt and the Office of Energy Development pages were read. No order title concerns nuclear or advanced reactors; the order texts were not each opened, and a news release is not an instrument.
  • Commission or siting instruments: Access blocked. One administrative-rule page returned a not-found error (HTTP 404) and another an empty response. The Public Service Commission's home page was read, but its docket search did not load, so no order or rule was read.
  • Funding measures and awards: Access blocked. A state budget page returned a script shell, the budget host failed TLS certificate verification, and the legislature's enrolled-act file failed TLS certificate verification. No appropriation was read.

Sources read (7):

Sources that could not be read (7):

Vermont — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. 2018 Act 113, read from the enrolled copy, amends 30 V.S.A. section 254 on construction or extended operation of a nuclear plant; ellipses mark text not shown. The legislature's online statute pages say they are an unofficial copy and were not used as operative text.
  • Governor or energy instruments: None found in sources checked. Executive Order 04-25 (vehicle emission standards) and Department of Public Service decommissioning slides of 22 September 2025 were read. Neither is a nuclear order.
  • Commission or siting instruments: None found in sources checked. Public Utility Commission Rule 5.400 (petitions to construct electric and gas facilities, effective 1 March 2024) was read. It does not mention nuclear.
  • Funding measures and awards: Evidence read. 2021 Act 52 (signed 3 June 2021) was read: sections 12 to 17, including the radiological emergency response plan fund, took effect 1 July 2021.

Sources read (7):

Virginia — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. Code sections 56-585.1:14 and 56-585.1:15, with 2024 Acts chapters 789 and 836, were read; sections 45.2-2101 and 45.2-2103 (nuclear strategic plan and consortium authority) were also read.
  • Governor or energy instruments: None found in sources checked. The Department of Energy's nuclear page was read. It is an agency page, not a governor or energy instrument.
  • Commission or siting instruments: Evidence read. The State Corporation Commission's final order in Case PUR-2025-00085 (12 November 2025) was read. It approves early development costs for a possible small modular reactor at Joshua Falls, not construction or cost recovery. It is a project order; no general commission rule was opened.
  • Funding measures and awards: Evidence read. Code section 45.2-1734 (Virginia Power Innovation Fund) was read. It states no dollar amount and names no recipient.

Sources read (7):

Washington — Bounded review concluded
  • Statutes, session laws and bills: Evidence read. RCW 80.50 (energy facility site certification, which covers fission plants) and House Bill 1018 as passed by the legislature were read. The bill copy prints no chapter number.
  • Governor or energy instruments: None found in sources checked. Executive Order 79-09 (19 November 1979), on the Hanford low-level waste site, was read. It does not address reactors.
  • Commission or siting instruments: None found in sources checked. Energy Facility Site Evaluation Council rules WAC 463-14-020 and 463-60-010 were read. They are general siting rules; the rule text read does not mention nuclear, and neither is a project certificate.
  • Funding measures and awards: None found in sources checked. The 2025-27 fiscal act (ESSB 5167) and a clean-energy siting grants page were read. The act mentions nuclear physics only in a research clause; neither funds reactors.

Sources read (10):

West Virginia — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. Enrolled Senate Bill 4 (2022), repealing the nuclear-construction ban, and the current code pages for the repealed sections were read.
  • Governor or energy instruments: None found in sources checked. The governor's executive-order index was read. It is an index, and no individual order was opened.
  • Commission or siting instruments: Access blocked. The Secretary of State catalog page for rule 150-03 was opened. The rule file is an image scan without a text layer, so the rule text was not read. A commission docket link returned an error response (HTTP 400).
  • Funding measures and awards: None found in sources checked. Code sections 5B-2N-2a (a grid fund for coal and natural-gas generation) and 5B-2N-2b (an energy strategy that includes nuclear-fueled energy) were read. Neither funds nuclear projects; the signed 2026 bill was not opened.

Sources read (8):

Sources that could not be read (2):

Wisconsin — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. 2015 Wisconsin Act 344, 2025 Wisconsin Act 12 (nuclear power siting study) and section 196.025 were read. Section 196.493 returned a not-found error (HTTP 404).
  • Governor or energy instruments: None found in sources checked. The governor's executive-orders list was read on 5 October 2026 (it had returned access refused, HTTP 401 the day before). No order title mentions nuclear; the order texts were not each opened.
  • Commission or siting instruments: None found in sources checked. Administrative Code chapter PSC 111 (effective 1 July 2000) was read. It lists nuclear only as a generating-unit data category and approves no site.
  • Funding measures and awards: Access blocked. The page for 2025 Wisconsin Act 15 returned a landing shell without section text. A Legislative Fiscal Bureau memorandum on releasing funds for a nuclear feasibility study was read; it is not the appropriations act.

Sources read (9):

Sources that could not be read (2):

Wyoming — Bounded review concluded with access gaps
  • Statutes, session laws and bills: Evidence read. 2022 Session Laws chapter 103 and the current compilation of W.S. 35-11-2101 (advanced nuclear reactors) were read.
  • Governor or energy instruments: Access blocked. The governor's executive-order page and a news page returned a script shell on 4 October 2026, and the governor's home page returned an empty shell on 5 October 2026.
  • Commission or siting instruments: None found in sources checked. The Department of Environmental Quality's industrial-siting jurisdiction page was read. It is a page, not a rule, and issues no permit.
  • Funding measures and awards: Evidence read. Enrolled Act No. 50 (2024 budget session) was read: $2,000,000 for nuclear scholarship, research and training. The date-approved line on the copy is blank.

Sources read (7):

Sources that could not be read (3):

District of Columbia — Bounded review concluded

The District of Columbia is not a state. Its executive power is vested in the Mayor (D.C. Code § 1-204.22), so the governor-or-energy class here means mayoral and District energy-office instruments. Electric utilities are regulated by the Public Service Commission of the District of Columbia, whose commissioners the Mayor appoints with the Council's consent (D.C. Code § 34-801). This review did not read how the federal Atomic Energy Act's geographic definition treats the District.

  • Statutes, session laws and bills: None found in sources checked. D.C. Code sections 8-171.02 (energy definitions), 34-1431 (renewable portfolio definitions) and 34-1517 (fuel-mix reporting) and D.C. Law 25-277 (Radiation Protection Act of 2024) were read. Sections 8-171.02 and 34-1517 mention nuclear fuels or nuclear electricity only in a definition and a reporting category; section 34-1431 does not mention nuclear; and the radiation act excludes radiation regulated by the Nuclear Regulatory Commission. None addresses siting or building a reactor.
  • Governor or energy instruments: None found in sources checked. Clean Energy DC 2.0, dated 18 August 2026, was read. It mentions nuclear only as part of the PJM supply mix. It is an energy plan, not a mayoral order on nuclear generation.
  • Commission or siting instruments: None found in sources checked. Order No. 20227, dated 26 September 2019, was read. It mentions nuclear only while explaining a federal process on state subsidies for nuclear and renewable generation, and it does not certificate a reactor. The commission site search still returned only navigation.
  • Funding measures and awards: None found in sources checked. The approved Fiscal Year 2026 Department of Energy and Environment budget chapter was read. It does not mention nuclear energy or a nuclear appropriation.

Sources read (9):

Sources that could not be read (1):

Puerto Rico — Bounded review concluded

Puerto Rico is a territory, not a state. The utility regulator checked was the Puerto Rico Energy Bureau. The federal Atomic Energy Act defines the United States, in a geographical sense, to include all territories and possessions and Puerto Rico (42 U.S.C. 2014(bb), 2021 edition read). This review did not read how federal licensing has been applied here.

  • Statutes, session laws and bills: Evidence read. House Bill 1092 (P. de la C. 1092) was read as filed on 29 January 2026 and as passed by the House on 15 June 2026, with the legislature's tracker page. It would write nuclear energy and small modular reactors into Act 82-2010 and repeal local restrictions on nuclear generation. It passed the House 35 to 11, had its first Senate reading on 19 June 2026, and was referred to the Government Committee the same day. The tracker shows no later Senate action. It is a bill, not law.
  • Governor or energy instruments: None found in sources checked. Executive Orders OE-2025-005 and OE-2025-006, both signed 9 January 2025, were read. They create an energy office and an energy transformation committee and do not mention nuclear energy.
  • Commission or siting instruments: None found in sources checked. The Puerto Rico Energy Bureau's site search for nuclear returned no results, and its integrated-resource-plan pages show no nuclear instrument. A site search covers posted pages, not the text of every order.
  • Funding measures and awards: None found in sources checked. The 15 May 2026 budget transmittal for Fiscal Year 2027 and the Senate's account of the operating-budget resolution were read. Neither mentions nuclear energy. They are not a line-by-line reading of every appropriation.

Sources read (11):

Guam — Bounded review concluded with access gaps

Guam is a territory, not a state. The utility regulator checked was the Guam Public Utilities Commission. The federal Atomic Energy Act defines the United States, in a geographical sense, to include all territories and possessions and Puerto Rico (42 U.S.C. 2014(bb), 2021 edition read). This review did not read how federal licensing has been applied here.

  • Statutes, session laws and bills: Evidence read. The legislature's committee report on Bill No. 151-37 (30 October 2023), which reproduces the bill text as introduced and as amended in committee, was read. The bill would prohibit the production and use of nuclear energy on Guam, including small modular reactors and microreactors. The report does not show passage, veto or enactment. A clerk status sheet printed 1 November 2023 stops at the committee report and states no floor vote or public-law number.
  • Governor or energy instruments: None found in sources checked. Executive Order No. 2026-03, transmitted 24 April 2026, and the Guam Energy Office homepage were read. They address efficiency, solar and net-zero emissions and do not mention nuclear energy.
  • Commission or siting instruments: Access blocked. The Public Utilities Commission's site lists GPA Docket 10-07, Small Nuclear Power Reactors, but the docket page shows no document that could be read. A different commission-hosted file, the Guam Power Authority integrated resource plan dated 22 February 2013, was read. It develops planning characteristics for a possible small modular reactor. That plan is not a commission order, and the docket remains unreadable.
  • Funding measures and awards: None found in sources checked. The Guam Energy Office assistance and weatherization pages were read. They describe household energy help and do not identify a nuclear award.

Sources read (9):

Sources that could not be read (1):

U.S. Virgin Islands — Bounded review concluded with access gaps

The U.S. Virgin Islands are a territory, not a state. The utility regulator checked was the Virgin Islands Public Services Commission. The federal Atomic Energy Act defines the United States, in a geographical sense, to include all territories and possessions and Puerto Rico (42 U.S.C. 2014(bb), 2021 edition read). This review did not read how federal licensing has been applied here.

  • Statutes, session laws and bills: Access blocked. The Department of Planning and Natural Resources points to a public code collection. That collection returned a script rather than the code, and the legislature's bill-tracking site still returned only a search form. No statute text was read.
  • Governor or energy instruments: None found in sources checked. The Virgin Islands Energy Office homepage was read. It describes rebates, weatherization and battery storage and does not mention nuclear energy.
  • Commission or siting instruments: None found in sources checked. The Public Services Commission's site search for nuclear returned no match, and a June 2025 meeting page concerns other utility matters. A site search covers posted pages, not the text of every order.
  • Funding measures and awards: None found in sources checked. The same Energy Office homepage says electric-mobility rebates depend on SEPBIL Grant EE0010105 and does not identify a nuclear award.

Sources read (5):

Sources that could not be read (3):

American Samoa — Bounded review concluded

American Samoa is a territory, not a state. The rules checked were those published by the American Samoa Power Authority; no separate utility commission was identified in the sources opened. The federal Atomic Energy Act defines the United States, in a geographical sense, to include all territories and possessions and Puerto Rico (42 U.S.C. 2014(bb), 2021 edition read). This review did not read how federal licensing has been applied here.

  • Statutes, session laws and bills: None found in sources checked. American Samoa Code Annotated section 15.0101 establishes the Power Authority and does not mention nuclear generation. Section 13.0303 defines an emergency to include a nuclear attack or accident. That definition is not a nuclear-energy statute.
  • Governor or energy instruments: None found in sources checked. The Territorial Energy Office page and the executive-order index were read. The office page describes efficiency, conservation and renewable energy. The opened index does not list a nuclear order.
  • Commission or siting instruments: None found in sources checked. The American Samoa Power Authority's published copy of administrative code title 12 (electric, water, wastewater and solid waste) was read. It does not mention nuclear.
  • Funding measures and awards: None found in sources checked. The Territorial Energy Office page says it administers federal energy funding and does not identify a nuclear award.

Sources read (7):

Northern Mariana Islands — Bounded review concluded with access gaps

The Northern Mariana Islands are a territory, not a state. The Commonwealth's code was read on the Commonwealth Law Revision Commission's site; the utilities commission's site could not be reached. The federal Atomic Energy Act defines the United States, in a geographical sense, to include all territories and possessions and Puerto Rico (42 U.S.C. 2014(bb), 2021 edition read). This review did not read how federal licensing has been applied here.

  • Statutes, session laws and bills: Evidence read. 2 CMC § 1326 and § 1313 were read. The Commonwealth's nuclear and chemical free zone law does not apply to radioactive materials for small modular reactors used solely for electricity that meet federal safety certification; the exemption came from Public Law 17-10, in effect since 28 July 2010.
  • Governor or energy instruments: None found in sources checked. The CNMI Strategic Energy Plan 2023-2028, dated 21 April 2023, was read. It lists nuclear technologies among generation options. The contractor states that it did not assess nuclear, coal or natural gas, and that nonrenewable technologies of interest to the task force should be investigated further. The plan is a report, not an executive order.
  • Commission or siting instruments: Access blocked. https://puc.gov.mp/ did not resolve, and an earlier commission address also did not resolve. A readable government directory did not supply a commission order. No commission rule or order was read.
  • Funding measures and awards: None found in sources checked. The Commonwealth Utilities Corporation citizen-centric report for October 2024 through September 2025 was read. It describes solar, batteries and other utility spending and does not identify a nuclear award.

Sources read (6):

Sources that could not be read (3):

Research coverage: countries and the EU outside the United States

As of 30 Oct 2026. The countries outside the United States with a published project at licensing, construction, commissioning or operating stage on 18 October 2026 were reviewed once across three national source classes, using official legal portals, regulator pages and program pages. A provincial, regional or municipal measure is described in a note only. A failed or blocked official source is an access limit, not a finding that no instrument exists. On 29 October 2026 the countries outside the United States hosting any published SMRMap project but without a national policy page, and the European Union, were reviewed once across the same three source classes, and France was reviewed again. Later on 29 October 2026 Ukraine was reviewed again through official routes only, after the parliament's legislation portal had not responded in the first pass. On 30 October 2026 the United Kingdom was reviewed across the same three source classes for the first time, and Canada gained a siting instrument. Of these 23, 17 have a bounded review concluded, 6 are concluded with access gaps still open, and 0 are unfinished because a source class has not been reviewed. A concluded review is not exhaustive coverage.

Countries by national source class
CountryControlling reactor licensing frameworkSiting restrictions or rulesDirectly relevant support measuresRecords
ArgentinaEvidence readEvidence readEvidence read2 published
BrazilEvidence readEvidence readAccess blocked2 published
CanadaEvidence readEvidence readEvidence read6 published
ChinaEvidence readEvidence readEvidence read3 published
CzechiaEvidence readEvidence readAccess blocked2 published
FinlandEvidence readEvidence readNone found in sources checked2 published
FranceEvidence readEvidence readEvidence read3 published
IndiaEvidence readEvidence readEvidence read4 published
IndonesiaEvidence readEvidence readEvidence read4 published
JapanEvidence readEvidence readEvidence read3 published
NetherlandsEvidence readEvidence readEvidence read3 published
NorwayEvidence readEvidence readAccess blocked2 published
PolandEvidence readEvidence readEvidence read3 published
RomaniaEvidence readEvidence readAccess blocked2 published
RussiaEvidence readEvidence readEvidence read3 published
RwandaEvidence readEvidence readEvidence read3 published
South AfricaEvidence readEvidence readAccess blocked3 published
South KoreaEvidence readEvidence readEvidence read4 published
SwedenEvidence readEvidence readEvidence read3 published
UkraineEvidence readAccess blockedAccess blocked1 published
United KingdomEvidence readEvidence readEvidence read7 published
UzbekistanEvidence readEvidence readEvidence read3 published
European UnionEvidence readNone found in sources checkedEvidence read4 published
  • A class counts as evidence read only when an official text of that class addressing nuclear energy was opened and read; press reports and company statements do not count.
  • An instrument is counted in one class only. Project permits remain separate regulatory records, and a country page is published only where at least one instrument was opened.
  • This bounded review does not rank or compare countries and does not state that any project is eligible for, or approved under, a measure.

What was checked, by country

Argentina — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The updated text of Law 24.804 on Argentina's official legal portal was read. Its implementing decree, the regulator's standards and the hundreds of later linked norms, recently mostly regulator resolutions, were not reviewed one by one.
  • Siting restrictions or rules: Evidence read. No separate national siting instrument was found. Article 11 of Law 24.804, recorded under the licensing framework, requires a regulator construction license authorizing the location of any new relevant nuclear installation, with approval of the host province. The regulator's siting standards were not opened.
  • Directly relevant support measures: Evidence read. Resolution 282/2025, the 2025-2027 science and technology guidelines that mention the Plan Nuclear Argentino and an SMR, was read. No official decree adopting the nuclear plan or an SMR program was found. The Official Gazette site did not respond, so two 2025-2026 decrees on the atomic energy commission and the regulator could not be checked.

Sources read (3):

Sources that could not be read (2):

Brazil — Bounded review concluded with access gaps (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. Law 14.222/2021 was read in its original Diário Oficial text in the Senate legislation database together with the ANSN legal-basis page; the Planalto compiled texts of this law and of Law 6.189/1974 refused connections, so later amendments are not verified.
  • Siting restrictions or rules: Evidence read. Articles 225 § 6, 21 XXIII and 49 XIV of the Federal Constitution were read in the Supreme Federal Court's annotated compilation; no federal law locating a new nuclear plant and no pending amendment proposal was reviewed.
  • Directly relevant support measures: Access blocked. The MCTI and FINEP website searches returned pages whose results did not render without scripts, so no official SMR or microreactor funding text was opened; press reports of a June 2025 MCTI and FINEP subsidy contract for microreactor technologies remain unmatched to an official document.

Sources read (5):

Sources that could not be read (4):

Canada — Bounded review concluded (reviewed 30 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The consolidated Nuclear Safety and Control Act and Class I Nuclear Facilities Regulations on the Justice Laws Website (both current to 30 September 2026) were read; amendments not yet in force and the General Nuclear Safety and Control Regulations were not assessed.
  • Siting restrictions or rules: Evidence read. The consolidated Physical Activities Regulations on the Justice Laws Website (current to 30 September 2026) were read: schedule item 27 makes new fission or fusion reactors designated projects for federal impact assessment when their combined thermal capacity is more than 900 MWth within an existing Class IA nuclear facility's licensed boundaries, or more than 200 MWth elsewhere. This is national siting and environmental-assessment coverage, not a site approval or any project's assessment determination. British Columbia's Clean Energy Act (current to 6 October 2026) lists achieving the province's energy objectives without nuclear power as an energy objective; it is a provincial measure outside this national review, and other provinces were not reviewed. The Building Canada Act, current to 30 September 2026, was read. It addresses nuclear projects through required consultation with, and confirmation by, the Canadian Nuclear Safety Commission. No project was listed in its schedule. Provincial measures were not reviewed.
  • Directly relevant support measures: Evidence read. The Natural Resources Canada Enabling Small Modular Reactors Program page and funded-projects page were read; the clean technology investment tax credit is already recorded, and Canada Infrastructure Bank or other federal financing was not reviewed.

Sources read (7):

China — Bounded review concluded (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The Nuclear Safety Law (in force 1 January 2018) and the Atomic Energy Law (adopted 12 September 2025, in force 15 January 2026) were read on the National People's Congress website; the national law database page returned no readable text.
  • Siting restrictions or rules: Evidence read. The Ministry of Ecology and Environment's 2019 safety licensing procedure rule (site selection review and the combined route for factory-built floating or mobile units) was read; the Nuclear Safety Law's siting and restricted-zone articles are counted under the licensing class, and NNSA technical siting regulations were not opened.
  • Directly relevant support measures: Evidence read. The NDRC plan for the new energy system in the 15th Five-Year Plan period names small-reactor technology research and advanced-reactor demonstration but no program budget, project or site, so no record is proposed; the 15th Five-Year Plan Outline itself was not opened, and the Atomic Energy Law's support article is counted under the licensing class.

Sources read (4):

Sources that could not be read (1):

Czechia — Bounded review concluded with access gaps (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The official Czech collection of laws works only with scripts, so the authentic text could not be read. The regulator's working English translation of the Atomic Act, current only to 2021 amendments, was read. Later amendments listed by the Chamber of Deputies, including Act 83/2025, were not read.
  • Siting restrictions or rules: Evidence read. The regulator's working English translation of its 2016 decree on siting of a nuclear installation was read. The authentic Czech text and laws on accelerating energy infrastructure could not be read because the official collection of laws works only with scripts.
  • Directly relevant support measures: Access blocked. Act 367/2021 on measures for the transition to low-carbon energy could not be read: both official copies of the collection of laws load only with scripts. A May 2023 working-group plan on small and medium reactors published by the Ministry of Industry and Trade was read as context, but it is not itself a support measure.

Sources read (3):

Sources that could not be read (2):

Finland — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. Finlex's consolidated Nuclear Energy Act 990/1987 (to amendment 590/2026, last day in force 31 December 2026) and the new Nuclear Energy Act 775/2026 (in force 1 January 2027) were read. Implementing decrees, STUK regulations and the parliamentary papers were not reviewed.
  • Siting restrictions or rules: Evidence read. Finland's siting procedures sit inside the two Nuclear Energy Acts recorded under the licensing framework: the decision-in-principle with the host municipality's support and, from 2027, a siting chapter with protective and emergency planning zones and a STUK site-suitability statement. No separate siting instrument was found, and land-use planning law was not reviewed.
  • Directly relevant support measures: None found in sources checked. The energy aid decree 262/2023 (in force 2 March 2023 to 31 December 2027) sets general conditions for energy aid and does not mention nuclear energy. A government page on the 2026 call for large demonstration projects refused automated access, so no official text on whether small modular reactors can receive that aid was read.

Sources read (3):

Sources that could not be read (4):

France — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The nuclear safety authority's regulatory site explains the basic nuclear installation regime of the Environment Code (page updated 16 December 2025). The Code's own text could not be read because the official legal portal refused automated access, so the record rests on the regulator's explanation.
  • Siting restrictions or rules: Evidence read. The promulgated text of Law 2023-491 of 22 June 2023 was read in the Senate's comparative table of the bill's versions. The decree defining 'immediate vicinity' and any later amendments were not read because the official legal portal refused automated access.
  • Directly relevant support measures: Evidence read. Two ministry pages and the Government's March 2022 communiqué describe the France 2030 innovative nuclear reactors call, its 500 million euro program and its eleven laureates. The call terms published by Bpifrance were not read, and later calls under the program were not checked.

Sources read (7):

Sources that could not be read (1):

India — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The SHANTI Act, 2025 was read in the Gazette copy on the Department of Atomic Energy website, with the draft SHANTI Rules of August 2026. India Code, the regulator's website and the Gazette portal could not be read, so the Atomic Energy Act, 1962 was not opened and the SHANTI Act's entry into force is unverified.
  • Siting restrictions or rules: Evidence read. The regulator's draft SHANTI Regulations of August 2026, published for comment by the Department of Atomic Energy, would create a separate safety authorization for siting. They are a draft. The regulator's current siting codes could not be read because its website did not respond.
  • Directly relevant support measures: Evidence read. Two Press Information Bureau publications describe the Nuclear Energy Mission's Rs 20,000 crore allocation for small modular reactors announced in the Union Budget 2025-26. A budget announcement is not a law. The Budget documents and press release pages refused automated access, and no scheme guidelines were found.

Sources read (7):

Sources that could not be read (7):

Indonesia — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The 1997 Nuclear Energy Law, its 2020 amendments in the Job Creation Law and the 2014 Government Regulation on nuclear installation licensing were read on BAPETEN's legal portal. The national audit agency's legal database refused automated access. No consolidated text is offered, and later amendments and the 2025 risk-based licensing regulation were not assessed.
  • Siting restrictions or rules: Evidence read. BAPETEN Regulation No. 4 of 2018 on site evaluation safety was read. BAPETEN's separate regulations on specific site hazards (seismic, volcanic, weather and water, dispersion, human-induced events) were listed on its portal but not opened.
  • Directly relevant support measures: Evidence read. Government Regulation No. 40 of 2025 on National Energy Policy was read on the energy ministry's legal portal. The presidential regulations it calls for on the nuclear program organization and nuclear co-generation, and the national electricity supply plan, were not reviewed.

Sources read (6):

Sources that could not be read (1):

Japan — Bounded review concluded (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The Reactor Regulation Act was read in the official e-Gov database in its current text and its prior revision, which shows that the 2023 decarbonized power supply amendments replaced the 40-year operating period article with long-term facility management plans from 6 June 2025; the Electricity Business Act was not reviewed.
  • Siting restrictions or rules: Evidence read. The Nuclear Regulation Authority rule on location, structure and equipment standards for commercial power reactors was read in the e-Gov database; the separate rule for test and research reactors and the NRA's non-binding review guides were not reviewed.
  • Directly relevant support measures: Evidence read. OCCTO's final FY2026 application rules of 2 September 2026 and its July 2026 overview of the long-term decarbonization auction were read; the Agency for Natural Resources and Energy guideline and committee papers on METI sites refused access, and the 2026 next-generation reactor development support is recorded separately as a program.

Sources read (7):

Sources that could not be read (2):

Netherlands — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The consolidated Nuclear Energy Act on the government legislation portal (version in force from 1 July 2024) was read. Amendments that have no in-force date yet and the decree on nuclear installations, fissile materials and ores were not assessed.
  • Siting restrictions or rules: Evidence read. The Environmental Quality Decree, which reserves two locations for a nuclear power plant, was read. Government notices of February 2024 and February 2026 on choosing locations for two new large plants through a project procedure were read as context. They contain no location decision.
  • Directly relevant support measures: Evidence read. Three Government Gazette regulations of the climate minister that add and fund a nuclear energy theme, covering SMRs and microreactors, in the MOOI innovation subsidy were read. Awards and other national nuclear funding were not reviewed.

Sources read (2):

Norway — Bounded review concluded with access gaps (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The consolidated Atomic Energy Act on Lovdata (last amended by LOV-2018-06-22-76, from 1 January 2026) was read. The central regulations made under it cover exemptions, nuclear material, physical protection, liability and fees, and none sets a licensing procedure. Delegation decisions under the Act were not reviewed.
  • Siting restrictions or rules: Evidence read. The impact assessment regulations (amended to FOR-2026-03-06-353) were read. Site-specific licenses, advance site approval and Storting consent sit in sections 4 and 7 of the Atomic Energy Act, recorded under the licensing framework. The Planning and Building Act itself and assessment programs for individual proposals were not reviewed.
  • Directly relevant support measures: Access blocked. The government portal refused automated access, so government decisions and the nuclear commission report NOU 2026: 4 could not be read. Parliament's site shows a members' proposal of 19 March 2026 asking the government to prepare for nuclear power, which is not an adopted measure. The final vote on it was not read.

Sources read (6):

Sources that could not be read (2):

Poland — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The consolidated Atomic Law (Journal of Laws 2026 item 1) and the amending Act of 3 July 2026 were read from the Sejm's legal acts service. The Sejm's ISAP portal refused automated access, so its copy was not used. Council of Ministers implementing regulations were not reviewed.
  • Siting restrictions or rules: Evidence read. The consolidated 2011 special act on nuclear power investments (Journal of Laws 2025 item 1156) and its 2026 amendment were read. Siting requirements in the Atomic Law are covered by the licensing record. Individual decisions in principle and location decisions were not reviewed.
  • Directly relevant support measures: Evidence read. The Council of Ministers' 2026 update of the Polish Nuclear Power Programme (Monitor Polski 2026 item 977) was read. State capital support for the first large plant under the 2011 special act is described in the siting record. The SMR roadmap that the program announces was not found or read.

Sources read (2):

Sources that could not be read (1):

Romania — Bounded review concluded with access gaps (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. Law 111/1996 was read in the consolidated text of 19 August 2023 published by CNCAN; the national legislation portal refused connections, so amendments after August 2023 are not verified.
  • Siting restrictions or rules: Evidence read. CNCAN's NSN-01 norms on nuclear power plant siting (Monitorul Oficial 836 of 14 December 2010) and the regulator's current list of nuclear safety norms were read; the approving order and any later amendment were not shown.
  • Directly relevant support measures: Access blocked. The national legislation portal refused connections, and the Nuclearelectrica statement of May 2026 describes shareholder-approved investment conditions rather than a Romanian state support instrument, so no official Romanian support text for new reactors was opened.

Sources read (5):

Sources that could not be read (1):

  • legislatie.just.ro/ · checked 18 Oct 2026 · not readable: Remote end closed connection without response for the portal root and a document page (three attempts each). The CNCAN-published consolidati
Russia — Bounded review concluded (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. Federal Law No. 170-FZ was read in the consolidated text on the President's website (amendments through No. 98-FZ of 21 April 2025); the official legal portal's consolidated database and a commercial legal copy did not respond, and the decrees designating the safety regulator were not opened.
  • Siting restrictions or rules: Evidence read. Rostekhnadzor's NP-032-19 site safety requirements were read in the scanned official publication with the regulator's technical-support catalog for scope and entry into force; the siting chapter of Federal Law No. 170-FZ is counted under the licensing class and later amendments to NP-032-19 were not verified.
  • Directly relevant support measures: Evidence read. Government Order No. 4153-r approving the General Scheme for power facilities to 2042 was read, including its small nuclear plant entries and consumer-agreement conditions; the state program for the nuclear industry and federal project texts were not opened, and Rosatom's program statements are company sources recorded as programs.

Sources read (6):

Sources that could not be read (2):

Rwanda — Bounded review concluded (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. Law N° 59/2017 on radiation protection, which empowers the utilities regulator, was read in the Official Gazette copy posted by RURA; press reporting of the March 2026 IAEA review states that a comprehensive nuclear law was still being drafted.
  • Siting restrictions or rules: Evidence read. RURA Regulation No 013/2024 on licensing nuclear installations, which sets the site license requirement, was read; RURA's list of nuclear and radiation regulations shows no separate regulation with siting criteria.
  • Directly relevant support measures: Evidence read. Presidential Order N° 127/01 of 3 December 2020 establishing the Rwanda Atomic Energy Board was read in the Official Gazette copy posted by RAEB; RAEB's small modular reactor page is descriptive and no official national nuclear program roadmap was found on RAEB's site.

Sources read (6):

Sources that could not be read (1):

South Africa — Bounded review concluded with access gaps (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The National Nuclear Regulator Act and the Nuclear Energy Act (both 1999, as enacted) were read from the regulator's website, with the Government Gazette copy of the regulator act on the government portal. No consolidated text showing later amendments was found.
  • Siting restrictions or rules: Evidence read. The 2011 Regulations on Licensing of Sites for New Nuclear Installations (Gazette No. 34735) were read from the regulator's website. The regulator's siting guidance document was not opened.
  • Directly relevant support measures: Access blocked. The Integrated Resource Plan 2025, gazetted on 28 October 2025 (Gazette No. 53596, Notice 6767), was opened on the government portal, but its pages are images with no readable text except the contents list, which names nuclear sections. The energy department's page loads files only through scripts. A text copy of the gazetted plan would settle this.

Sources read (2):

Sources that could not be read (3):

South Korea — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The Nuclear Safety Act was read in the Korea Legislation Research Institute's Korean and English text, current to October 2025. The national law portal shows the current May 2026 version only with scripts, so the 2026 amendment is described from the regulator's press release.
  • Siting restrictions or rules: Evidence read. The radiological emergency law's article on emergency planning zones around nuclear reactors was read in a text matching the version in force since 1 January 2026. The general power plant siting law was read but has no provision specific to nuclear plants, and site approval under the Nuclear Safety Act is covered in the licensing record.
  • Directly relevant support measures: Evidence read. The SMR Special Act, in force since 11 September 2026, is described from the science ministry's announcement because the law portal shows its articles only with scripts. The i-SMR development program is described from the ministries' 2022 announcement and the portal record of its joint directive.

Sources read (7):

Sources that could not be read (6):

Sweden — Bounded review concluded (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The Riksdag consolidated texts of the Act on Nuclear Activities (1984:3, amended to SFS 2026:1365) and its Ordinance (1984:14, amended to SFS 2026:1782) were read; the amending acts and the Radiation Safety Authority's regulations were not opened separately.
  • Siting restrictions or rules: Evidence read. The Act (2026:585) on Government approval of nuclear facilities and chapter 17 of the consolidated Environmental Code were read; the current texts show no reactor-number cap or existing-site restriction, and the earlier amending acts that changed chapter 17 were not opened.
  • Directly relevant support measures: Evidence read. The Act (2025:587) on state support for investment in new nuclear power, as published and as consolidated after SFS 2026:1079, and its Ordinance (2025:808) were read; no Government support decision under the Act was reviewed.

Sources read (7):

Ukraine — Bounded review concluded with access gaps (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The Cabinet regulation on the State Nuclear Regulatory Inspectorate and its 2023 amendment were read on the government portal. The Law on the Use of Nuclear Energy and Radiation Safety (No. 39/95-ВР) is not yet recorded: the parliament's legislation portal did not respond again, and its 2022 amendment is published only as a scanned image. The Law's official consolidated text would complete this class.
  • Siting restrictions or rules: Access blocked. The 2005 law on decisions about the siting, design and construction of nuclear installations (No. 2861-IV) could not be opened in Ukrainian or English because the parliament's legislation portal did not respond again. No online copy, and no adopted special siting law, was found in the official newspapers. That law's official consolidated text would settle this class.
  • Directly relevant support measures: Access blocked. The Cabinet order approving the Energy Strategy to 2050 still has no strategy text attached. The 2025 law on buying equipment for Khmelnytskyi units 3 and 4 is published only as a scanned image. The text of bill No. 14164 on small modular reactors, still awaiting first reading, is offered only as an interactive download. The strategy text and that bill's text would settle this class.

Sources read (13):

Sources that could not be read (10):

United Kingdom — Bounded review concluded (reviewed 30 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The revised Nuclear Installations Act 1965 (sections 1, 3 and 26) and Energy Act 2013 sections 67, 68 and 77 were read on legislation.gov.uk, with the March 2026 government response on regulatory reform. License conditions, Schedule 7 and the Taskforce's full report were not reviewed.
  • Siting restrictions or rules: Evidence read. EN-7, the planning policy for nuclear fission projects in England and Wales in force since 18 December 2025, was read. Its supplementary information and EN-1 were not reviewed. Scotland and Northern Ireland siting rules were not reviewed.
  • Directly relevant support measures: Evidence read. Government pages on GBE-N's SMR competition, the June 2025 selection and the April 2026 contract with Rolls-Royce SMR were read. The Advanced Nuclear Framework is already held under Programs and was not duplicated here.

Sources read (3):

Uzbekistan — Bounded review concluded (reviewed 18 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. Law No. ZRU-565 of 9 September 2019 and its amending Law No. ZRU-1140 of 21 April 2026 were read in the national legislation database in Russian, where the 2026 wording is marked as an unofficial translation of the Uzbek text; the Atomic Energy Agency news page did not display its text.
  • Siting restrictions or rules: Evidence read. The nuclear safety committee's resolution No. 39 of 16 February 2026 on nuclear power plant site and territory requirements was read in the Uzbek original in the national legislation database; the siting articles of Law No. ZRU-565 are counted under the licensing class.
  • Directly relevant support measures: Evidence read. Presidential Resolution PP-188 of 24 May 2024 (Atomic Energy Agency and its development fund) and Decree UP-5484 of 19 July 2018 (creation of the Uzatom agency) were read in the national legislation database; no presidential act on the Jizzakh small nuclear plant was found in the database's national-legislation results.

Sources read (5):

Sources that could not be read (1):

European Union — Bounded review concluded (reviewed 29 Oct 2026)
  • Controlling reactor licensing framework: Evidence read. The consolidated Nuclear Safety Directive (version of 14 August 2014) and the consolidated Euratom Treaty (2016) were read through the EU Publications Office because EUR-Lex refused automated access. National transposing laws and the Basic Safety Standards Directive were not reviewed.
  • Siting restrictions or rules: None found in sources checked. No EU act read chooses, bans or zones reactor sites. The Nuclear Safety Directive requires a site-specific assessment before licenses, and the Euratom Treaty requires data on radioactive waste disposal plans for a Commission opinion; both are recorded under the licensing framework. The Environmental Impact Assessment Directive was not reviewed.
  • Directly relevant support measures: Evidence read. The Net-Zero Industry Act and the 2022 taxonomy delegated act were read. The Commission's SMR strategy COM(2026) 117 of 10 March 2026 and its page on the European Industrial Alliance on SMRs were read as context only: both are non-binding policy texts rather than legal or funding instruments, so no record is proposed for them.

Sources read (6):

Sources that could not be read (3):