Canada: Building Canada Act (S.C. 2025, c. 2, s. 4), national interest projects
Canadian law of June 2025 that lets the federal cabinet list national interest projects and then issue a single document standing in for listed federal approvals. For a project covered by the Nuclear Safety and Control Act, the Canadian Nuclear Safety Commission must be consulted and must confirm safety and security first. No project was listed in the version current to 30 September 2026, and it grants no license.
- Category
- Laws, rules and executive directives
- Status
- In effect
- Instrument
- statute · Building Canada Act, S.C. 2025, c. 2, s. 4 (assented to 26 June 2025)
- Issued by
- Parliament of Canada
- Jurisdiction
- Canada
- Affects
- National reactor licensing, State program administration
- In effect from
- 26 Jun 2025
- Expiry or completion
- None recorded
- Operative text
- Justice Laws Website: Building Canada Act (S.C. 2025, c. 2, s. 4), consolidated full text (Consolidated Act current to 2026-09-30, last amended on 2026-03-26 (Justice Laws Website))
- Record reviewed · next review
- 30 Oct 2026 · 30 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
Federal statute under which the Governor in Council may, by order, add a project it considers in the national interest to Schedule 1 (s. 5), after a 30-day Canada Gazette notice and consultation, and with the written consent of the province or territory where the project falls within its exclusive jurisdiction. For a listed project every determination, finding and opinion needed for an authorization under an Act or regulation listed in Schedule 2 is deemed favorable, although no authorization is granted solely on that basis (s. 6), and the Minister must issue a document deemed to be the specified authorizations, with conditions (s. 7). For a project to which the Nuclear Safety and Control Act applies, the Minister must consult the Canadian Nuclear Safety Commission and may issue or amend such a document only after the Commission confirms it will not compromise health or safety, national security or Canada's international obligations (ss. 11-14). In the consolidation current to 30 September 2026 Schedule 1 lists no project and Schedule 2 does not list the Nuclear Safety and Control Act. The Act designates no reactor project and grants no license.
Not approved or still pending
No project is listed in Schedule 1 of the consolidation read. The order defining the national interest under section 4.1 and the 26 March 2026 amendment were not reviewed. The power to add projects ends on the fifth anniversary of section 5 coming into force (s. 5(2)). (Record checked .)
Dated lifecycle
- 26 Jun 2025 · Enacted — Assented to and in force on assent. (Justice Laws Website: Building Canada Act (S.C. 2025, c. 2, s. 4), consolidated full text)
- 26 Mar 2026 · Amended — Last amendment shown in the consolidation; not reviewed separately. (Justice Laws Website: Building Canada Act (S.C. 2025, c. 2, s. 4), consolidated full text)
Definitions in this instrument
- authorization (s. 2): For a national interest project, an approval, decision, permit, license or other instrument required by an Act or regulation listed in Schedule 2 (or the listed portion of it) to permit the project to be carried out.
Legal definition used by this statute only; SMRMap's inclusion rule for SMRs is separate and unchanged.
Related instruments
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Justice Laws Website: Building Canada Act (S.C. 2025, c. 2, s. 4), consolidated full text (government, revised 30 Sep 2026, accessed 30 Oct 2026)