United Kingdom: National Policy Statement for nuclear energy generation (EN-7)
England and Wales planning policy for nuclear fission power projects, in force since 18 December 2025. Together with EN-1 it guides the Energy Secretary's decisions on development consent, and it opens siting to a wider range of locations than the eight sites named in the older EN-6. It grants no consent and approves no site.
- Category
- Regulatory guidance and inspector policies
- Status
- Published guidance — not a law or project permission
- Instrument
- regulatory guidance · National Policy Statement for nuclear energy generation (EN-7), presented to Parliament under s. 9(8) Planning Act 2008, ISBN 978-1-5286-6073-0; in force 18 December 2025
- Issued by
- Department for Energy Security and Net Zero (Secretary of State for Energy Security and Net Zero)
- Jurisdiction
- United Kingdom
- Affects
- Siting
- Effective date
- 18 Dec 2025
- Expiry or completion
- None recorded
- Operative text
- GOV.UK: National Policy Statement for nuclear energy generation (EN-7), accessible webpage (Accessible webpage of the designated statement, updated 18 December 2025)
- Record reviewed · next review
- 30 Oct 2026 · 13 Mar 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
National Policy Statement under the Planning Act 2008 which, with the overarching energy statement EN-1, provides the primary policy for the Secretary of State's decisions on development consent applications for infrastructure using nuclear fission to generate energy in England and Wales (paras 1.1.5, 1.4.1). It covers projects that are nationally significant under the Act and projects directed into the development consent regime under sections 35 and 35ZA (para 1.6). It is designed to support development on a more diverse range of sites than the eight sites listed in the earlier EN-6, which keep their advantages (paras 1.7.1-1.7.3), and sets factors for site selection, including the Semi-Urban Population Density Criterion (paras 2.7.5-2.7.6). The Secretary of State does not examine applications for nuclear generating stations in Scotland or Northern Ireland (paras 1.4.2, 1.4.4). Development consent and the relevant regulatory permits, licenses and authorizations must still be obtained (para 1.7.4). It grants no consent and approves no site, design or project.
Not approved or still pending
Grants no development consent. The supplementary information, the Welsh text and EN-1 were not reviewed. In its 13 March 2026 response to the Nuclear Regulatory Review the government said it would aim within 12 months to update EN-7 with a criterion supporting fleet rollout; no update was checked here. (Record checked .)
Dated lifecycle
- 12 Nov 2025 · Published (GOV.UK: National Policy Statement for nuclear energy generation (EN-7), publication page)
- 18 Dec 2025 · Effective date recorded (GOV.UK: National Policy Statement for nuclear energy generation (EN-7), publication page)
Definitions in this instrument
- nuclear infrastructure (para 1.6.1): Infrastructure using nuclear fission to generate energy, with ancillary infrastructure, that is a Nationally Significant Infrastructure Project under the Planning Act 2008 or is directed to require development consent under sections 35 and 35ZA.
Definition used by this policy statement only; SMRMap's inclusion rule for SMRs is separate and unchanged.
Related instruments
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- GOV.UK: National Policy Statement for nuclear energy generation (EN-7), publication page (government, page updated 18 Dec 2025, accessed 30 Oct 2026)
- GOV.UK: National Policy Statement for nuclear energy generation (EN-7), accessible webpage (government, page updated 18 Dec 2025, accessed 30 Oct 2026)
- GOV.UK: Building our nuclear nation: government response to the Nuclear Regulatory Review 2025 (accessible webpage) (government, published 13 Mar 2026, accessed 30 Oct 2026)