India: Draft SHANTI Rules, 2026 (Department of Atomic Energy consultation)
India's Department of Atomic Energy published draft SHANTI Rules dated 14 August 2026 for comment until 4 September 2026. They would require licensees to obtain design approval and stage-by-stage safety authorizations from the Atomic Energy Regulatory Board and to meet license hold points before construction and fuel loading. A draft has no legal effect.
- Category
- Bills, proposed rules and consultations
- Status
- Proposed — not in effect
- Instrument
- consultation · Draft Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Rules, 2026, draft dated 14 August 2026, under s. 84(1) of Act No. 39 of 2025
- Issued by
- Department of Atomic Energy (Central Government)
- Jurisdiction
- India
- Affects
- National reactor licensing
- Effective date
- Not recorded
- Expiry or completion
- None recorded
- Operative text
- Department of Atomic Energy: Draft SHANTI Rules, 2026 (draft of 14 August 2026) (Consultation draft dated 14 August 2026 (G.S.R. number not yet assigned))
- Record reviewed · next review
- 29 Oct 2026 · 29 Jan 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
Draft rules the Central Government proposes under s. 84(1) of the SHANTI Act, 2025, superseding several Atomic Energy rules and the 2011 nuclear liability rules. Draft rule 9(1) would require a licensee, once licensed, to obtain design approval and safety authorizations from the Atomic Energy Regulatory Board for siting, construction, commissioning, operation and decommissioning of the plant or reactor. Draft rule 9(2) sets licensing hold points to be demonstrated before construction (including ownership or possessory rights of the site and Board design approval), before receipt of fuel, before first fuel loading and before license renewal. Draft rule 9(3) would allow civil liability obligations to be exempted under s. 44 of the Act for research reactors and other low-power reactors whose integrated power at the site and exclusion zone do not exceed a value the Central Government notifies. The rules would come into force on publication in the Official Gazette. The Department invited comments until 4 September 2026. A draft has no legal effect and licenses, exempts or approves nothing.
Not approved or still pending
Not adopted. Whether final rules were notified after the 4 September 2026 deadline was not checked because the Gazette portal could not be read. Grants no license or liability exemption to any reactor or project. (Record checked .)
Dated lifecycle
- 14 Aug 2026 · Proposed — Draft dated 14 August 2026 and placed on the Department's consultation page. (Department of Atomic Energy: Draft SHANTI Rules, 2026 (draft of 14 August 2026))
- 4 Sep 2026 · Comment period closed — Deadline for submission: 8:00 PM on 4 September 2026. (Department of Atomic Energy: Public Consultation on Draft SHANTI Rules and Draft SHANTI Regulations)
Related instruments
- India: Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Act, 2025 (No. 39 of 2025) (implements)
- India: Draft SHANTI Regulations, 2026 (Atomic Energy Regulatory Board consultation) (companion)
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.