Policy and licensing / Indonesia
Indonesia: Government Regulation No. 2 of 2014 on Licensing of Nuclear Installations and Use of Nuclear Material (Peraturan Pemerintah Nomor 2 Tahun 2014)
Indonesia's 2014 Government Regulation on nuclear installation licensing sets the reactor license sequence of site license, construction license, commissioning license and operating license, plus decommissioning. Applications go to the Head of BAPETEN, who issues each license. A commercial nuclear power plant is determined by the electricity minister after consulting parliament. It approves no site, design or project.
- Category
- Laws, rules and executive directives
- Status
- In effect
- Instrument
- final rule · Peraturan Pemerintah Republik Indonesia Nomor 2 Tahun 2014 tentang Perizinan Instalasi Nuklir dan Pemanfaatan Bahan Nuklir; enacted and promulgated 16 January 2014 (Lembaran Negara 2014 No. 8); in force on promulgation
- Issued by
- President of the Republic of Indonesia
- Jurisdiction
- Indonesia
- Affects
- National reactor licensing, Siting
- In effect from
- 16 Jan 2014
- Expiry or completion
- None recorded
- Operative text
- Indonesia: Peraturan Pemerintah Nomor 2 Tahun 2014 tentang Perizinan Instalasi Nuklir dan Pemanfaatan Bahan Nuklir (BAPETEN JDIH copy) (Certified copy (salinan) of the 2014 text on the BAPETEN legal portal, status 'Baru'; no consolidated text offered)
- Record reviewed · next review
- 29 Oct 2026 · 29 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
Government regulation implementing Law No. 10 of 1997 on licensing of nuclear installations. Article 3 divides nuclear reactors into power and non-power reactors, each commercial or non-commercial. Article 4 requires a license for construction, operation and decommissioning of a nuclear reactor: the construction license covers a site license (izin Tapak) and a construction license, and the operation license covers a commissioning license and an operating license. Article 5 assigns non-commercial reactors to BATAN and commercial reactors to state-owned enterprises, cooperatives and/or incorporated companies, and provides that construction of a commercial power reactor as a nuclear power plant is determined by the minister responsible for electricity after consulting the House of Representatives. Applications go in writing to the Head of BAPETEN (Article 6). Site evaluation may begin only after the Head of BAPETEN approves it (Article 15), and the Head of BAPETEN issues the site license when the technical assessment is met (Article 19). Article 133 revoked Government Regulation No. 43 of 2006 on reactor licensing. It does not itself license, site or approve any reactor, design or project.
Not approved or still pending
Grants no license. Whether Government Regulation No. 28 of 2025 on risk-based business licensing, listed on the BAPETEN portal, changes these procedures was not assessed. BAPETEN implementing regulations other than the 2018 site-evaluation regulation were not opened. (Record checked .)
Dated lifecycle
- 16 Jan 2014 · Issued — Ditetapkan di Jakarta pada tanggal 16 Januari 2014. (Indonesia: Peraturan Pemerintah Nomor 2 Tahun 2014 tentang Perizinan Instalasi Nuklir dan Pemanfaatan Bahan Nuklir (BAPETEN JDIH copy))
- 16 Jan 2014 · Took effect — Article 134: in force on promulgation; promulgated 16 January 2014. (Indonesia: Peraturan Pemerintah Nomor 2 Tahun 2014 tentang Perizinan Instalasi Nuklir dan Pemanfaatan Bahan Nuklir (BAPETEN JDIH copy))
Definitions in this instrument
- Reaktor Nuklir (nuclear reactor) (Article 1 point 2): A device or installation run on nuclear fuel that can produce a controlled nuclear chain reaction and is used for power generation, research and/or radioisotope production.
Legal definition used by this Indonesian regulation only; SMRMap's inclusion rule for SMRs is separate and unchanged.
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Indonesia: Peraturan Pemerintah Nomor 2 Tahun 2014 tentang Perizinan Instalasi Nuklir dan Pemanfaatan Bahan Nuklir (BAPETEN JDIH copy) (regulator, dated 16 Jan 2014, accessed 29 Oct 2026)