Pennsylvania Radiation Protection Act section 402.1: small modular reactor and microreactor fees

Pennsylvania's official compilation of the Radiation Protection Act adds section 402.1 for reactors the statute defines as a microreactor (100 MWe nameplate or less) or a small modular reactor (400 MWe nameplate or less). A person who already holds an NRC construction permit or operating license for such a reactor on a Pennsylvania site pays the Department $10,000 to $50,000 per site, plus two further bands of the same size for emergency-response planning and for nonagency equipment, planning, training, and exercises. The fee is per site regardless of reactor count. The compilation says those payments are deposited into the Radiation Protection Fund and the named emergency-response funds and are appropriated for the act's duties. The official act page says Act 37 of 2026 is effective in 60 days and does not print the calendar day. The fee does not grant the federal permit. Those megawatt definitions are the statute's, not SMRMap's inclusion rule.

Category
Laws, rules and executive directives
Status
In effect
Instrument
statute · Radiation Protection Act, Act of July 10, 1984, P.L. 688, No. 147, § 402.1
Issued by
Pennsylvania General Assembly
Jurisdiction
Pennsylvania
Affects
State program administration
Effective date
Not recorded
Expiry or completion
None recorded
Operative text
Pennsylvania Radiation Protection Act, official compilation (Act of July 10, 1984, P.L. 688, No. 147) (Official compilation and Act 37 law-information page opened 4 October 2026; calendar effective date not printed)
Record reviewed · next review
4 Oct 2026 · 15 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)

Legal and geographic scope

Official compilation of the Radiation Protection Act, plus the official Act 37 of 2026 law-information page. Section 402.1 charges a person who already holds an NRC construction permit or operating license for a microreactor or small modular reactor on a Pennsylvania site. The fee is per site, not per reactor, and the compilation appropriates the receiving funds for duties under the act. It does not grant the NRC permit. The act page prints an enactment date of July 20, 2026, and Effective 60 DAYS, without a calendar effective date.

Not approved or still pending

The act page prints Effective 60 DAYS and does not print a calendar day, so no effective date is stored and the 30-day payment clock is not dated. The fee applies only to a person who already holds an NRC construction permit or operating license; it does not grant that permit. No implementing fee regulation was opened. No project is linked. Governor, commission, and siting sources for Pennsylvania were not opened in the bounded review. (Record checked .)

Dated lifecycle