South Korea: Innovative SMR (i-SMR) Technology Development Programme (혁신형 소형모듈원자로 기술개발사업)
South Korea's science and industry ministries run a joint program to develop an innovative small modular reactor, the i-SMR, with 399.2 billion won planned from 2023 to 2028 for technology development and standard design, aiming for standard design approval in 2028. It funds development work and approves no reactor or project.
- Category
- Funding and support programs
- Status
- In effect
- Instrument
- funding program · 혁신형 소형모듈원자로(i-SMR) 기술개발 사업 (preliminary feasibility study passed, announced 1 June 2022); 혁신형 소형모듈원자로 기술개발사업 공동운영관리규정 (MSIT Directive No. 227 and MOTIE Directive No. 246, 30 January 2023)
- Issued by
- Ministry of Science and ICT and Ministry of Trade, Industry and Energy
- Jurisdiction
- South Korea
- Affects
- Project funding
- In effect from
- 30 Jan 2023
- Expiry or completion
- 2028 — The ministries said the budget runs to 2028. Whether the program period or budget changed later was not checked.
- Operative text
- Korea.kr policy news (MSIT and MOTIE): i-SMR technology development programme passes preliminary feasibility study (2 June 2022) (Korea.kr policy news of 2 June 2022 on the joint MSIT and MOTIE announcement)
- Record reviewed · next review
- 29 Oct 2026 · 29 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
Joint research and development program of the Ministry of Science and ICT and the Ministry of Trade, Industry and Energy for an innovative small modular reactor (i-SMR), which the ministries describe as a reactor of 300 MW or less with modular construction. The ministries announced on 1 June 2022 that the program had passed the preliminary feasibility study, with a total budget of 399.2 billion won planned from the following year to 2028 for innovative technology development and standard design, and standard design approval expected in 2028. A joint operation and management directive for the program (MSIT Directive No. 227 and MOTIE Directive No. 246) took effect on 30 January 2023. The program funds technology development and design work. It does not license, site or approve any reactor or project, and standard design approval is a separate decision of the Nuclear Safety and Security Commission.
Not approved or still pending
The directive's article text was not readable and the version shown is the original of 30 January 2023, so later amendments, yearly budgets and the program's current status were not checked. No award to any company or project is recorded, and the Commission's design review is not an approval. (Record checked .)
Dated lifecycle
- 1 Jun 2022 · Milestone — MSIT and MOTIE announced that the program passed the preliminary feasibility study. (Korea.kr policy news (MSIT and MOTIE): i-SMR technology development programme passes preliminary feasibility study (2 June 2022))
- 30 Jan 2023 · Took effect — Joint operation and management directive in force (MSIT Directive No. 227, MOTIE Directive No. 246). (National Law Information Center: 혁신형 소형모듈원자로 기술개발사업 공동운영관리규정 (administrative rule record))
Related instruments
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Korea.kr policy news (MSIT and MOTIE): i-SMR technology development programme passes preliminary feasibility study (2 June 2022) (government, published 2 Jun 2022, accessed 29 Oct 2026)
- National Law Information Center: 혁신형 소형모듈원자로 기술개발사업 공동운영관리규정 (administrative rule record) (government, accessed 29 Oct 2026)