Programmes and agreements / prg-ec-nuclear-plan-modular-reactor
Ecuador nuclear power plan: first-stage 300 MW modular reactor (Ministry of Energy)
In February 2025 Ecuador's electricity vice-minister said the government's roadmap would first provide 300 MW of nuclear power through a modular reactor, later followed by a 1 GW plant, with a tender to select a builder planned for 2026. In December 2025 the ministry created a nuclear programme implementing organisation and set a horizon of about ten years for the first reactor (RNE1). No design, vendor, site or tender award has been announced.
- Type
- National plan
- Countries concerned
- Ecuador
- Participants and roles
- Government: Ministerio de Energía y Minas / Ministerio de Ambiente y Energía (Ecuador)
- Government: Organismo de Implementación del Programa Nuclear (NEPIU)
- Designs named
- —
- Scale as stated
- First stage: 300 MW of nuclear through a modular reactor, later a 1 GW plant (as stated in February 2025) · 1 unit stated
- Announced or first reported
- 21 Feb 2025
- Status
- Active
Plan, tender was scheduled for 2026 but not verified as issued, 2029 first-power target superseded by a ~10-year horizon (Dec 2025) - Confidence
- low
- Last checked
- 2026-10-14 (record review date, not proof of current activity)
Related deployment projects
- No related deployment project is recorded here.
Sources
- Qué se sabe del plan para construir una planta nuclear en Ecuador que propone el Gobierno de Noboa (reputable_press, published 22 Feb 2025, accessed 2026-10-14)
- El Gobierno apunta a que Ecuador tenga su primer reactor nuclear en 10 años (reputable_press, published 27 Dec 2025, accessed 2026-10-14)
- WNA Emerging Nuclear Energy Countries profile listing (directory_or_aggregator, accessed 2026-10-06)