Projects / Indonesia · Suspended
BATAN/BRIN RDE experimental reactor at Serpong (PeLUIt-40 predecessor)
The RDE is a proposed experimental reactor of 10 MWth at the Puspiptek complex in Serpong, Indonesia, with BATAN named as applicant, now recorded as suspended.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- No operator is recorded.
- No map pin is shown for this record.
- Expected for this stage but not recorded as a structured fact: Design identified; Developer or proposer (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
BAPETEN's account says it issued a site permit on 23 January 2017 for the RDE at Serpong, and ANTARA quotes that permit as 10 megawatts thermal, equivalent to 3.3 megawatts, without saying electric, gross or net. The 10 MWth figure is the stored module rating. The 3.3 megawatt equivalence and a later hope of raising the design to 150 MWth are not stored as output. BATAN is the applicant named in those accounts. The 2024 ARIS report says RDE was the initial name of PeLUIt-40 and that licensing was halted after a policy change while research continued. BRIN and ITB are named there as the PeLUIt-40 design organization, not as the RDE operator, so they are not stored in that role. PeLUIt-40 is not itself sited at Serpong in the opened sources.
Key facts
- Design
- Design profile not linked (SMR)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- Not recorded
- Vendor for linked design
- No selected-design vendor recorded
- Location
- RDE site, Puspiptek complex, Serpong · Indonesia · precision: site area (named plant, laboratory, base, port, campus or parcel)
The sources name this place but publish no coordinate for it, so no pin is shown. - Coordinates
- Named site, no map pin
- Electrical capacity
- Not recorded · scope: module
The site-permit accounts state 10 MWth for this one reactor. - Thermal capacity
- 10 MWth (nameplate; basis unspecified)
- Inclusion basis
- SMR by regulator classification
- Confidence
- medium
- Record reviewed
- 19 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
BATAN/BRIN RDE experimental reactor at Serpong (PeLUIt-40 predecessor) is recorded at RDE site, Puspiptek complex, Serpong, Banten, Indonesia. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Suspended. Location precision: site area (named plant, laboratory, base, port, campus or parcel); named site, no map pin.
Electrical output is not recorded on this project. The site-permit accounts state 10 MWth for this one reactor. Modules planned: 1. Recorded thermal output is 10 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Contractor
Source-backed project statement ANTARA reported on 7 February 2017 that for the Serpong site evaluation BATAN involved the energy ministry's Geological Survey Centre and Centre for Volcanology and Geological Disaster Mitigation, the meteorology agency BMKG, Universitas Indonesia and Institut Teknologi Bandung. That was preparatory site-evaluation work, not a construction contract or operating appointment. BAPETEN's 2019 article records BATAN's own design submissions. ANTARA: BATAN obtains RDE site permit; BAPETEN: handover of RDE detail engineering design
- Funding and government decisions
Source-backed project statement BAPETEN's 29 January 2019 article says construction funds for the Serpong RDE would come from the state budget allocation (DIPA) and from non-DIPA sources, namely research cooperation with Tsinghua University and INSINAS funding, without amounts. ANTARA's 7 February 2017 report says construction would require Rp 2.2 trillion, which is a cost estimate, not an appropriation. These sources do not establish a budget approval or disbursement. BAPETEN: handover of RDE detail engineering design; ANTARA: BATAN obtains RDE site permit
- Programs and agreements naming the project
- Research program; status not establishedBRIN PeLUIt-40 HTGR development with PLN Nusantara Power (de-dieselisation target)
Not found in the sources we checked (3): Customer or offtaker; Fuel; Comparable schedule revision
- Customer or offtaker
ANTARA's 7 February 2017 report on the Serpong experimental power reactor names no buyer of its power or heat. This is a finding about that project's reviewed report; arrangements for another design or site do not establish a Serpong offtake. ANTARA: BATAN obtains RDE site permit
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
The October 2024 IAEA ARIS account of PeLUIt-40 says the earlier RDE design and the current PeLUIt-40 design are based on HTR-10 pebble fuel, and that BRIN is discussing possible supply with Tsinghua INET, with talks also opened with Rosatom and South African fabricators. Those are current design-supply discussions, not a contract, quantity or delivery for the suspended Serpong reactor. IAEA ARIS status report: PeLUIt-40
- Comparable schedule revision
Comparable schedule revision not established. ANTARA and BAPETEN date the Serpong site permit to 23 January 2017, and BAPETEN says it is valid four years unless construction starts. These reviewed passages do not supply two dated forecasts for the same Serpong milestone. Targets for a successor design are not substituted for this project's schedule. ANTARA: BATAN obtains RDE site permit; BAPETEN: handover of RDE detail engineering design
Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Reactor supplier; Site host or owner
- Project proposer or applicant
- Reviewed 19 Oct 2026: not disclosed in the reviewed evidence.
- Operator or intended licensed owner
- Reactor supplier
- Site host or owner
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(9 notes, 1 not yet reviewed)
- Evidence review. The 23 January 2017 site permit and the 2019 design handover support the suspended experimental project, its 10 MWth rating, and a count of one. The 3.3 megawatt phrase is an equivalence, not a stored electrical rating. The ARIS sentence is used only as the stated licensing status already in that review, not as a rating or a deployment description. Last checked 20 Oct 2026. IAEA ARIS status report: PeLUIt-40; BAPETEN: handover of RDE detail engineering design; ANTARA: BATAN obtains RDE site permit
What would change this
A BAPETEN instrument showing whether the Serpong site permit was renewed, expired, or replaced. Next scheduled check: 20 Jan 2027.
- Developer or proposer: Not disclosed in the reviewed evidence. BATAN is the applicant named by BAPETEN and ANTARA. No BATAN organization record is linked. BRIN and ITB are the later PeLUIt-40 design organization, not the RDE operator or vendor. Last checked 19 Oct 2026. BAPETEN: handover of RDE detail engineering design
What would change this
An organization record for BATAN, or a later instrument naming the RDE operator. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified). The site-permit accounts state 10 MWth for this one reactor. ANTARA's equivalent 3.3 megawatts does not say electric, gross or net, and the 150 MWth figure is a later hope, so neither is stored. Last checked 19 Oct 2026. ANTARA: BATAN obtains RDE site permit
What would change this
A permit that states an electrical output and whether it is gross or net. Next scheduled check: 19 Jan 2027.
- Module/unit count. The site permit is for one experimental reactor at Serpong. The count stored is 1. Last checked 19 Oct 2026. BAPETEN: handover of RDE detail engineering design
What would change this
A permit amendment that changes the number of reactors at Serpong. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. The permit names the Puspiptek complex at Serpong and gives no coordinates. The complex is recorded as a named site without a pin. Last checked 19 Oct 2026. ANTARA: BATAN obtains RDE site permit
What would change this
A site document with coordinates or a mapped footprint. Next scheduled check: 19 Jan 2027.
- Design identified. The sources identify the RDE's own design: a pebble-bed high-temperature gas-cooled reactor of 10 MWth, whose detail engineering design BATAN handed to BAPETEN on 28 January 2019. ARIS says RDE was the initial name of PeLUIt and describes PeLUIt-40 as a later uprate of the same core. The 10 MWth RDE version has no design profile, and linking PeLUIt-40 would assign the uprated version, so no design is linked. Last checked 19 Oct 2026. IAEA ARIS status report: PeLUIt-40; BAPETEN: handover of RDE detail engineering design
What would change this
A design profile for the 10 MWth RDE version, or a BRIN or BAPETEN document that names the Serpong plant's design as PeLUIt-40. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. In 2017 BATAN named construction and commissioning permits as the next steps, and its detailed-design documents reached BAPETEN in January 2019. The opened regulator and press sources record no later application, decision or restart for this reactor at Serpong. Last checked 23 Oct 2026. ANTARA: BATAN obtains RDE site permit; BAPETEN: handover of RDE detail engineering design
What would change this
A BRIN or BAPETEN statement on resuming, replacing or ending the Serpong experimental reactor licensing. Next scheduled check: 21 Jan 2027.
- Permissions and public process. BAPETEN issued a site permit for the experimental reactor on 23 January 2017, as BATAN's chairman told ANTARA, and BAPETEN reported receiving BATAN's stage II detailed-design documents on 28 January 2019. A site permit and a design submission are not a construction or commissioning permit, and none is recorded. Last checked 23 Oct 2026. ANTARA: BATAN obtains RDE site permit; BAPETEN: handover of RDE detail engineering design
What would change this
A BAPETEN construction-permit application or decision for a reactor at Serpong. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). BATAN said in 2017 that the reactor would use land in the Puspiptek research complex at Serpong next to the Merah Putih gamma irradiator, chosen with care because the project was sensitive. No grid, cooling-water or land agreement is described in the opened sources. Last checked 23 Oct 2026. ANTARA: BATAN obtains RDE site permit
What would change this
A BRIN or BAPETEN document on site infrastructure for a reactor at Serpong. Next scheduled check: 21 Jan 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- BAPETEN: handover of RDE detail engineering design (regulator, accessed 2 Oct 2026)
- IAEA ARIS status report: PeLUIt-40 (IAEA/NEA, accessed 2 Oct 2026)
- ANTARA: BATAN obtains RDE site permit (news report, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: BATAN/BRIN RDE experimental reactor at Serpong (PeLUIt-40 predecessor) — https://smrmap.com/projects/rde-serpong/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “BATAN/BRIN RDE experimental reactor at Serpong (PeLUIt-40 predecessor)”. Record reviewed 19 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/rde-serpong/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.