Policy and licensing / Czechia
Czechia: Atomic Act (Act No. 263/2016 Coll., atomový zákon)
Czechia's Atomic Act requires a license from the State Office for Nuclear Safety (SÚJB) for each stage of a nuclear installation with a reactor, from siting and construction through start-up, operation and decommissioning. The Office decides siting licenses within 12 months and construction licenses within 18 months. It approves no site, design or project.
- Category
- Laws, rules and executive directives
- Status
- In effect
- Instrument
- statute · Zákon č. 263/2016 Sb., atomový zákon, of 14 July 2016; in force 1 January 2017
- Issued by
- Parlament České republiky (Parliament of the Czech Republic)
- Jurisdiction
- Czechia
- Affects
- National reactor licensing
- In effect from
- 1 Jan 2017
- Expiry or completion
- None recorded
- Operative text
- Czechia: Act No. 263/2016 Coll., Atomic Act (SÚJB working English translation, amended to Act No. 261/2021 Coll.) (SÚJB working, unauthorised English translation as amended by Acts 183/2017, 403/2020 and 261/2021 Coll. (file dated 11 March 2022), not the authentic Czech text)
- Record reviewed · next review
- 29 Oct 2026 · 29 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
Czech framework statute on the peaceful use of nuclear energy and ionising radiation, which replaced Act No. 18/1997 Coll. from 1 January 2017. Section 9(1) requires a license from the State Office for Nuclear Safety (Státní úřad pro jadernou bezpečnost, SÚJB) for the siting, construction, first physical start-up and first power-generation start-up of a nuclear installation with a reactor, for its operation and decommissioning phases and for modifications affecting nuclear safety. A nuclear installation includes a facility or plant comprising a nuclear reactor using a fission or other nuclear chain reaction (s. 3(2)(e)). Under s. 19(2) the Office decides within 12 months on a siting license and within 18 months on a construction license, and s. 208 makes the Office responsible for issuing licenses. The Act does not license, site or approve any reactor, design or project. This record rests on the regulator's working, unauthorised English translation, which reflects amendments up to Act No. 261/2021 Coll. only.
Not approved or still pending
Later amendments, including Act No. 284/2021 Coll. and Act No. 83/2025 Coll. (a government amendment of the Atomic Act listed by the Chamber of Deputies), are not reflected and were not read. The authentic consolidated Czech text on e-Sbírka could not be opened. SÚJB decrees other than the siting decree were not reviewed. (Record checked .)
Dated lifecycle
- 14 Jul 2016 · Issued — Act No. 263/2016 of Coll. of 14th July 2016. (Czechia: Act No. 263/2016 Coll., Atomic Act (SÚJB working English translation, amended to Act No. 261/2021 Coll.))
- 1 Jan 2017 · Took effect — Effect clause: in force on 1 January 2017. (Czechia: Act No. 263/2016 Coll., Atomic Act (SÚJB working English translation, amended to Act No. 261/2021 Coll.))
Definitions in this instrument
- nuclear installation (jaderné zařízení) (s. 3(2)(e)): Includes a facility or plant comprising a nuclear reactor using a fission or other nuclear chain reaction, spent and fresh fuel storage facilities, enrichment, fuel fabrication and reprocessing plants, and listed radioactive waste facilities (as rendered in the regulator's translation).
Legal definition used by this statute only; SMRMap's inclusion rule for SMRs is separate and unchanged.
Related instruments
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Czechia: Act No. 263/2016 Coll., Atomic Act (SÚJB working English translation, amended to Act No. 261/2021 Coll.) (regulator, accessed 29 Oct 2026)
- Czechia: SÚJB, Legal Framework – Nuclear law (English page listing translations) (regulator, accessed 29 Oct 2026)
- Czechia: SÚJB, Legislativa – Atomové právo (Czech page) (regulator, accessed 29 Oct 2026)
- Czechia: Chamber of Deputies, proposed and enacted changes to Act No. 263/2016 Coll. (government, accessed 29 Oct 2026)