Indiana SEA 423 (2025): SMR pilot program and partnerships

Signed on 1 May 2025 and effective 1 July 2025. It adds IC 8-1-44, a small modular nuclear reactor partnership pilot program, and section 17 says that chapter expires on 1 July 2035. Section 11 cross-references IC 8-1-8.5-12.1(a), whereas the enrolled SEA 424 amendment places the reactor definition in (b). Reconciliation with current compiled chapter text remains unresolved. Signature, effectiveness and expiry are different dates.

Category
Laws, rules and executive directives
Status
In effect
Instrument
statute · Senate Enrolled Act 423 (2025)
Issued by
Indiana General Assembly
Jurisdiction
Indiana
Affects
Utility cost recovery
In effect from
1 Jul 2025
Expiry or completion
2035-07-01 — SEA 423 section 17 states that IC 8-1-44 expires on 1 July 2035. That expiry has not occurred.
Operative text
Indiana Senate Enrolled Act 423 (2025) (Enrolled act (Senate Enrolled Act No. 423))
Record reviewed · next review
11 Nov 2026 · 9 Feb 2027 (dates our review of this record; not a statement of the measure's present legal effect)

Legal and geographic scope

State law adding IC 8-1-44, a partnership pilot for utility-led small modular reactor projects. A project's presence in Indiana does not make it part of the pilot. SEA 423's enrolled SMR cross-reference uses IC 8-1-8.5-12.1(a), while the enrolled SEA 424 amendment moves the definition to (b). The current compiled chapter has not been independently confirmed.

Not approved or still pending

Any project still needs an IURC order and NRC licenses; none is recorded here. The act does not itself approve a partnership or a reactor. (Record checked .)

Dated lifecycle

Definitions in this instrument

Related instruments

Projects or designs named by the source