Policy and licensing / Indiana
Indiana: SMR policy and licensing
Selected federal, state, territory, and national measures whose official text was opened. This is not a complete list of laws, rules, programs or guidance for any jurisdiction. A jurisdiction without a page here is not a finding that it has no policy, and these pages do not rate or prefer any jurisdiction. Nothing here implies that a project is eligible for, or approved under, any measure.
89 projects in United States →
Federal measures apply in Indiana as everywhere in the United States and are listed once on the federal page. They are not counted here.
Where licensing stands
Built only from the records on this page. It is not a complete account of the law and not legal advice.
- Authorities named in recorded applications, reviews and decisions
- None recorded: no application or decision for a tracked project here is recorded.
- Licensing law or framework in the record
- NRC licensing measures are recorded once, on the federal page (9 records).
- Latest recorded step
- Took effect : Indiana SEA 424 (2025): SMR development cost recovery
- Open coverage gaps
- Funding measures and awards (access blocked). What the review of 5 Oct 2026 read.
Laws, rules and executive directives
- Indiana Code 8-1-8.5-12.1: small modular nuclear reactor certificates · In effect
IC 8-1-8.5-12.1 (added by P.L.155-2022; amended through P.L.48-2025) · Indiana General Assembly · affects: Utility cost recovery, State program administration
Indiana's definition and certificate framework for small modular reactors. The enrolled SEA 424 amendment places the definition in subsection (b), at not more than 470 megawatts. The saved IURC PDF is an older 350 MW copy. Current compiled-code reconciliation is pending; no separate effective date is recorded for the section as a whole.
Not approved or pending: Approves no reactor; a utility needs an IURC certificate and NRC licenses for any project. The original effective date of the 2022 statute is not recorded on this record. (Record checked .) - Indiana Executive Order 25-48: Nuclear Indiana Coalition · In effect
Indiana Executive Order 25-48 (10 April 2025) · Governor of Indiana · affects: State program administration
Indiana Executive Order 25-48, issued 10 April 2025 according to the state's own annual report, directs the Secretary of Energy and Natural Resources to establish the Nuclear Indiana Coalition to advance nuclear energy and small modular reactors in the state. It does not license, fund or site a reactor.
Not approved or pending: The order creates a coalition and directs coordination. It does not license, fund or site a reactor. Pursuing state primacy on federal permitting is a direction to pursue it, not a grant of primacy. No effective date separate from the issue date was read. No project is linked. (Record checked .) - Indiana SEA 423 (2025): SMR pilot program and partnerships · In effect
Senate Enrolled Act 423 (2025) · Indiana General Assembly · affects: Utility cost recovery
Signed on 1 May 2025 and effective 1 July 2025. It adds IC 8-1-44, a small modular nuclear reactor partnership pilot program, and section 17 says that chapter expires on 1 July 2035. Section 11 cross-references IC 8-1-8.5-12.1(a), whereas the enrolled SEA 424 amendment places the reactor definition in (b). Reconciliation with current compiled chapter text remains unresolved. Signature, effectiveness and expiry are different dates.
Not approved or pending: Any project still needs an IURC order and NRC licenses; none is recorded here. The act does not itself approve a partnership or a reactor. (Record checked .) - Indiana SEA 424 (2025): SMR development cost recovery · In effect
Senate Enrolled Act 424 (2025) · Indiana General Assembly · affects: Utility cost recovery
Signed on 10 April 2025 and effective 1 July 2025. It amends IC 8-1-8.5-12.1: project development costs are defined in subsection (a), and the small modular nuclear reactor definition moves to subsection (b) at not more than 470 megawatts of rated electric generating capacity. A public utility may petition the IURC before a certificate to incur those costs and to recover 80 percent through a periodic rate adjustment, with 20 percent deferred. Signature and effectiveness are different dates.
Not approved or pending: Cost recovery needs a utility petition and an IURC order; none is recorded here. The act does not license a reactor. (Record checked .)
Bills, proposed rules and consultations
- None recorded.
Funding and support programs
- None recorded as a policy measure. Related government programs are listed below.
Regulatory guidance and inspector policies
- Indiana tax guidance on the SMR manufacturing expense credit · Published guidance — not a law or project permission
Income Tax Information Bulletin 124 (June 2025), citing IC 6-3.1-45 · Indiana Department of Revenue · affects: Project funding
Indiana Revenue's June 2025 bulletin explains a tax credit under IC 6-3.1-45 for qualified Indiana SMR manufacturing investment. It describes a 20 percent credit, carryforward of unused credit, no carryback or refund, and a submission followed by a department award letter. The cited source is nontechnical guidance, not the enacted statute. It does not establish that Breed, AEP, Amazon or X-energy received a credit, and it establishes no reactor permission.
Not approved or pending: No tax credit, payment, eligibility decision or reactor permission is established for Breed or any other named project. The underlying enacted/current statutory text was not read in this pass. Manufacturing expenditure is distinct from buying, building or operating a reactor. This guidance is not an enacted law. (Record checked .)
Related government programs
Government plans and programs recorded under Agreements, newest first. They are followed there by who takes part and what they cover; they are not policy records and do not license, site or fund a reactor by themselves.
- Indiana Advanced Nuclear Ready Communities program
Government program · announced or first reported — · Active
Recorded permissions and applications for tracked projects located in Indiana
Listed by project location only, with each action's issuing authority recorded. The jurisdiction measures above do not themselves authorize reactor construction or operation.
- None recorded.
What this review has read for Indiana
As of 5 Oct 2026. Bounded review concluded with access gaps. A published record above is separate from research coverage: a class can be blocked or unreviewed even where records are published. Coverage for every state and territory.
- Statutes, session laws and bills: Evidence read. Indiana Code 8-1-8.5-12.1 (small modular reactor certificates) was read, and Senate Enrolled Acts 423 and 424 (2025) are published from the enrolled texts. On 5 October 2026 the legislature's site returned only a script shell for the enrolled Senate Bill 423.
- Governor or energy instruments: Evidence read. Executive Order 25-48 (Nuclear Indiana Coalition) was read from the order copy; its number and date are not legible there. The Office of Energy Development's December 2025 annual report gives the issue date as 10 April 2025.
- Commission or siting instruments: Evidence read. The Utility Regulatory Commission's final rule in RM 23-03 (approved 22 May 2024), amending 170 IAC 4-11 for small modular reactor certificates, was read.
- Funding measures and awards: Access blocked. The enrolled House Bill 1007 (small modular reactor manufacturing credit) and the fiscal note for Senate Bill 423 returned a script shell. A Department of Revenue bulletin describing the credit was read; it is not the act.
Sources read (6):
- www.in.gov/iurc/files/IC-8-1-8.5-12.1.pdf · checked 4 Oct 2026
- www.in.gov/dA/820cc154b5/2024-05-22-IURC-Order-Approving-Final-Rule-RM23-03… · checked 4 Oct 2026
- www.in.gov/dor/files/ib124.pdf · checked 4 Oct 2026
- www.in.gov/gov/files/Executive-Order-25-48-Annual-Report-Nuclear-Final-Repo… · checked 4 Oct 2026
- www.in.gov/dA/a25c78b870/EO-25-48-.pdf?language_id=1 · checked 5 Oct 2026
- www.in.gov/gov/newsroom/executive-orders/ · checked 5 Oct 2026
Sources that could not be read (5):
- www.in.gov/gov/files/EO-25-48.pdf · checked 4 Oct 2026 · a not-found error (HTTP 404)
- iga.in.gov/pdf-documents/124/2025/house/bills/HB1007/HB1007.08.ENRS.pdf · checked 4 Oct 2026 · page shell without the document
- iga.in.gov/pdf-documents/124/2025/senate/bills/SB0423/SB0423.04.ENRH.pdf · checked 5 Oct 2026 · page shell without the document
- iga.in.gov/legislative/2025/bills/senate/423/details · checked 5 Oct 2026 · page shell without the document
- iga.in.gov/pdf-documents/124/2025/senate/bills/SB0423/fiscal-notes/SB0423.0… · checked 5 Oct 2026 · page shell without the document