Policy and licensing / Indiana
Indiana Code 8-1-8.5-12.1: small modular nuclear reactor certificates
Indiana's definition and certificate framework for small modular reactors. The enrolled SEA 424 amendment places the definition in subsection (b), at not more than 470 megawatts. The saved IURC PDF is an older 350 MW copy. Current compiled-code reconciliation is pending; no separate effective date is recorded for the section as a whole.
- Category
- Laws, rules and executive directives
- Status
- In effect
- Instrument
- statute · IC 8-1-8.5-12.1 (added by P.L.155-2022; amended through P.L.48-2025)
- Issued by
- Indiana General Assembly
- Jurisdiction
- Indiana
- Affects
- Utility cost recovery, State program administration
- Effective date
- Not recorded
- Expiry or completion
- None recorded
- Operative text
- Indiana Senate Enrolled Act 424 (2025) (Enrolled SEA 424 amendment of IC 8-1-8.5-12.1; effective 1 July 2025)
- Record reviewed · next review
- 4 Oct 2026 · 4 Nov 2026 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
State law defining small modular nuclear reactors for Indiana utility certificates and requiring the IURC to adopt rules on certificates for building, buying or leasing them. SEA 424 (P.L.48-2025) also lets a utility seek recovery of project-development costs before a certificate. NRC licensing remains required.
Not approved or still pending
Approves no reactor; a utility needs an IURC certificate and NRC licenses for any project. The original effective date of the 2022 statute is not recorded on this record. (Record checked .)
Dated lifecycle
- 20 Apr 2023 · Amended — Caucus release: SEA 176 signed; it reports the capacity limit raised from 350 MW to 470 MW. Not the code text. (Indiana Senate Majority Caucus: SEA 176 signed (20 Apr 2023))
- 1 Jul 2025 · Amended — SEA 424's amendment of this section took effect. The definition moved from subsection (a) to (b). Signature of SEA 424 is a separate date on that act's record. (Indiana Senate Enrolled Act 424 (2025))
Definitions in this instrument
- small modular nuclear reactor (IC 8-1-8.5-12.1(b)): SEA 424 places the definition in subsection (b): a nuclear reactor with a rated electric generating capacity of not more than 470 megawatts, capable of being constructed and operated alone or with similar reactors at one site, and required to be licensed by the NRC. The term includes such a reactor that uses a process to produce hydrogen. The enrolled amendment is effective 1 July 2025. An undated IURC copy still states the pre-2023 limit of not more than 350 MW in former subsection (a). Current compiled-code text has not been independently confirmed from a preserved rendered capture.
Legal definition used by this instrument only; SMRMap's inclusion rule for SMRs is separate and unchanged.
Related instruments
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Indiana Senate Enrolled Act 424 (2025) (government, accessed 4 Oct 2026)
- IURC copy of Indiana Code 8-1-8.5-12.1 (small modular nuclear reactors) (regulator, accessed 4 Oct 2026)
- Indiana Senate Majority Caucus: SEA 176 signed (20 Apr 2023) (government, accessed 3 Oct 2026)