Policy and licensing / Netherlands
Netherlands: Environmental Quality Decree (Besluit kwaliteit leefomgeving), nuclear power plant locations
The Netherlands' Environmental Quality Decree reserves two locations for a nuclear power plant, Borssele/Vlissingen and Maasvlakte I, in municipal environment plans. Within 1 km of them, plans may not allow housing that would push the population above 5,000 or other vulnerable buildings. It grants no permit and approves no reactor or project.
- Category
- Laws, rules and executive directives
- Status
- In effect
- Instrument
- final rule · Besluit kwaliteit leefomgeving, Besluit van 3 juli 2018 (BWBR0041313), arts. 5.156 and 5.158 and Annex XV part B; consolidated version in force from 1 October 2026
- Issued by
- Government of the Netherlands (royal decree on the proposal of the Minister of Infrastructure and the Environment)
- Jurisdiction
- Netherlands
- Affects
- Siting
- Effective date
- Not recorded
- Expiry or completion
- None recorded
- Operative text
- Netherlands: Besluit kwaliteit leefomgeving (Environmental Quality Decree), consolidated text in force from 1 October 2026 (Consolidated text on wetten.overheid.nl in force from 1 October 2026 (consulted 29 October 2026))
- Record reviewed · next review
- 29 Oct 2026 · 29 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
National decree setting rules that municipal environment plans must follow. Article 5.156(2) designates the locations for a nuclear power plant (kernenergiecentrale) as those listed in Annex XV part B, Borssele/Vlissingen (municipalities of Borsele and Vlissingen) and Maasvlakte I (Rotterdam), with boundaries fixed by ministerial regulation, while Article 5.156(1) excludes nuclear power plants from the general large-scale generation locations. Article 5.158 bars an environment plan covering such a location and the area within 1 km of it from allowing housing that would raise the area's population above 5,000, or other vulnerable buildings or locations except the plant itself and those the competent authority finds necessary. The decree reserves space in local plans but grants no license or permit. A February 2026 government notice says locations for two new large plants will be fixed in a project decision under the project procedure. The decree approves no reactor, design or project.
Not approved or still pending
The ministerial regulation fixing the location boundaries was not opened. The project procedure for two new large plants had produced no location decision in the notices read. Future and undated amendments flagged by the portal were not assessed. (Record checked .)
Dated lifecycle
- 3 Jul 2018 · Issued — Besluit van 3 juli 2018. Article 13.1 leaves entry into force to royal decree. (Netherlands: Besluit kwaliteit leefomgeving (Environmental Quality Decree), consolidated text in force from 1 October 2026)
Related instruments
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Netherlands: Besluit kwaliteit leefomgeving (Environmental Quality Decree), consolidated text in force from 1 October 2026 (government, revised 1 Oct 2026, accessed 29 Oct 2026)
- Netherlands: Staatscourant 2026, 3288 – Kennisgeving Nieuwbouw Kerncentrales, vaststelling Notitie Reikwijdte en Detailniveau (government, published 5 Feb 2026, accessed 29 Oct 2026)