Policy and licensing / Poland

Poland: Act on preparing and carrying out investments in nuclear power facilities and accompanying investments (2011 special act)

Poland's 2011 special act sets the permit path for nuclear power facilities. An investor needs a decision in principle from the energy raw materials minister, then a location decision and a building permit from the regional voivode. A 2026 amendment adds an early permit for preliminary construction works. The act also funds the state company building the first large plant. It approves no SMR project or design.

Category
Laws, rules and executive directives
Status
In effect
Instrument
statute · Ustawa z dnia 29 czerwca 2011 r. o przygotowaniu i realizacji inwestycji w zakresie obiektów energetyki jądrowej oraz inwestycji towarzyszących (Dz.U. 2011 nr 135 poz. 789); consolidated text Dz.U. 2025 poz. 1156; amended by Dz.U. 2026 poz. 1097
Issued by
Sejm Rzeczypospolitej Polskiej (Parliament of Poland)
Jurisdiction
Poland
Affects
Siting, Project funding
In effect from
1 Jul 2011
Expiry or completion
None recorded
Operative text
Poland: Ustawa z dnia 29 czerwca 2011 r. o przygotowaniu i realizacji inwestycji w zakresie obiektów energetyki jądrowej oraz inwestycji towarzyszących, consolidated text (Dz.U. 2025 poz. 1156) (Consolidated text announced on 5 August 2025 (Dz.U. 2025 poz. 1156, published 22 August 2025), read with the amending Act of 3 July 2026 (Dz.U. 2026 poz. 1097))
Record reviewed · next review
29 Oct 2026 · 29 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)

Legal and geographic scope

Special act setting the rules, conditions and competent authorities for preparing and building nuclear power facilities and accompanying investments (art. 1), which are public-purpose investments (art. 3). As amended in 2026, a nuclear power facility is a nuclear power plant or a listed fuel-cycle, storage or waste facility serving nuclear power, with the infrastructure needed to run it (art. 2 pkt 2). An investor first needs a decision in principle (decyzja zasadnicza) from the minister responsible for energy raw materials, decided on public-interest grounds after opinions including that of the Internal Security Agency (arts. 3a-3d), and must apply within 10 years for a location decision, which the competent voivode issues (art. 4). The voivode also issues the building permit (art. 15), and the 2026 amendment adds an earlier building permit for preliminary construction works (art. 17a). Arts. 53a-53m designate the first nuclear power plant (EJ1, up to 3,750 MWe, in Choczewo or Gniewino and Krokowa) and provide State Treasury capital support to Polskie Elektrownie Jądrowe within annual budget limits for 2025 to 2030. The Act does not override Prawo atomowe (art. 1 ust. 2). Beyond the EJ1 provisions it sites no plant and approves no SMR project or design.

Not approved or still pending

Decisions in principle, location decisions and permits issued to individual investors were not reviewed and none is recorded here. The EJ1 provisions name only the first large plant. Transitional provisions of the 2026 amendment were not analyzed. (Record checked .)