Policy and licensing / United States (federal)

DOE Generation III+ Small Modular Reactor program

DOE program with two first-mover selections on 2 December 2025 (TVA and Holtec, up to $400 million each) and eight further selections on 14 May 2026 (more than $94 million for early site permits and supply chains). DOE's program page says applications closed on 23 April 2025.

Category
Funding and support programs
Status
In effect
Instrument
funding program · DOE Gen III+ SMR solicitation (16 October 2024; modified 24 March 2025)
Issued by
U.S. Department of Energy
Jurisdiction
United States (federal)
Affects
Project funding
Effective date
Not recorded
Expiry or completion
None recorded
Operative text
DOE Generation III+ SMR programme questions and answers (DOE program Q&A)
Record reviewed · next review
4 Nov 2026 · 2 Feb 2027 (dates our review of this record; not a statement of the measure's present legal effect)

Legal and geographic scope

Federal cost-shared funding for first deployments of light-water Gen III+ SMRs (Tier 1, up to $800 million in federal funds) and for supply-chain and other barriers (Tier 2), from a $900 million solicitation; DOE pays no more than 50% of project costs.

Not approved or still pending

Selections for federal cost-shared funding are not disbursements. DOE's Q&A says award milestones and payments are negotiated after selection; final award terms are not recorded here. (Record checked .)

Dated lifecycle

Related instruments

Projects or designs named by the source