Policy and licensing / United States (federal)
United States (federal): SMR policy and licensing
Selected federal, state, territory, and national measures whose official text was opened. This is not a complete list of laws, rules, programs or guidance for any jurisdiction. A jurisdiction without a page here is not a finding that it has no policy, and these pages do not rate or prefer any jurisdiction. Nothing here implies that a project is eligible for, or approved under, any measure.
89 projects in United States →
All US policy steps, newest first →
Where licensing stands
Built only from the records on this page. It is not a complete account of the law and not legal advice.
- Authorities named in recorded applications, reviews and decisions
- NRC (20 records); U.S. Department of Energy, Idaho Operations Office (5 records); U.S. Department of Energy, Office of Nuclear Energy (2 records); U.S. Department of Defense, Strategic Capabilities Office (1 record)
- Licensing law or framework in the record
- Recorded NRC licensing measures: 10 CFR Part 53: risk-informed, technology-inclusive licensing framework; ADVANCE Act of 2024; Emergency preparedness rule for small modular reactors and other new technologies; Executive Order 14300: reform of the Nuclear Regulatory Commission; NRC direct final rule: NRC Modernization: Rulemaking Procedure, Federal Advisory Committee Act Alignment, Access, and Security; NRC direct final rule: Revising the Duration of Design Certifications; NRC final rule: Increased Flexibility in the Mandatory Hearing Process; NRC final rule: Streamlining Contested Adjudications in Licensing Proceedings; NRC reviews of reactor designs previously authorized by DOE or the Department of War
- Latest recorded step
- Comment period closed : Proposed regulatory enhancements for reactor licensing, decommissioning and operational oversight
- Open coverage gaps
- This jurisdiction is not part of SMRMap's bounded coverage reviews.
Laws, rules and executive directives
- 10 CFR Part 53: risk-informed, technology-inclusive licensing framework · In effect
91 FR 15696 (final rule, 30 March 2026); docket NRC-2019-0062 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
The NRC's Part 53 licensing framework took effect on 29 April 2026. It sets how applications may be reviewed; it approves no design, site or reactor.
Not approved or pending: Which applicants will use Part 53 is not recorded; no application under Part 53 is recorded here. The NRC corrected the final rule twice, on 13 April 2026 (errors and conflicting amendatory instructions with the categorical exclusions rule) and on 28 July 2026 (the Part 75 definition of facilities). (Record checked .) - ADVANCE Act of 2024 · In effect
Pub. L. 118-67, division B (approved 9 July 2024) · U.S. Congress · affects: Licensing review fees, NRC licensing
Federal law enacted on 9 July 2024. The NRC applies its reduced advanced-reactor review rate from 1 October 2025. The Act does not license, fund or approve any particular reactor.
Not approved or pending: Eligibility for the reduced rate is decided per applicant by the NRC; no project's eligibility is recorded here. (Record checked .) - Emergency preparedness rule for small modular reactors and other new technologies · In effect
88 FR 80050 (final rule, 16 November 2023); docket NRC-2015-0225 · U.S. Nuclear Regulatory Commission · affects: NRC licensing, Siting
Final NRC rule in effect since 18 December 2023 offering SMRs and other new technologies an alternative emergency preparedness framework. It approves no emergency plan for any site.
Not approved or pending: Each applicant's emergency plan is reviewed in its own licensing case. (Record checked .) - Executive Order 14299: advanced reactors for national security · In effect
Executive Order 14299, 90 FR 22581 (signed 23 May 2025) · President of the United States · affects: DOE test-reactor authorization, Siting
Directive to federal agencies, signed 23 May 2025. It sets agency goals; it does not license or approve any particular reactor.
Not approved or pending: Agency actions under the order are separate; none is recorded here as complete. (Record checked .) - Executive Order 14300: reform of the Nuclear Regulatory Commission · In effect
Executive Order 14300, 90 FR 22587 (signed 23 May 2025) · President of the United States · affects: NRC licensing
Directive to the NRC, signed 23 May 2025, with an 18-month target (late November 2026) for final revised rules. It grants no license itself.
Not approved or pending: The order licenses nothing itself. NRC final rules issued in response to it include the mandatory-hearing rule (in force 15 May 2026), the FY2026 fee rule with fixed fee caps (in force 17 August 2026) and the NRC Modernization direct final rule (in force 26 October 2026). A further final rule linked here, on prior DOE or defense authorizations, takes effect on 25 November 2026. The other revisions linked here remain proposed. (Record checked .) - Executive Order 14301: reactor testing at the Department of Energy · In effect
Executive Order 14301, 90 FR 22591 (signed 23 May 2025) · President of the United States · affects: DOE test-reactor authorization
Directive to DOE, signed 23 May 2025, that led to the DOE Reactor Pilot Program.
Not approved or pending: DOE authorization of a test reactor is not an NRC license for commercial operation. (Record checked .) - Executive Order 14302: nuclear industrial base · In effect
Executive Order 14302, 90 FR 22595 (signed 23 May 2025) · President of the United States · affects: Project funding
Directive to federal agencies, signed 23 May 2025. It appropriates no money and makes no project award.
Not approved or pending: Funding decisions under the order are separate records when made. (Record checked .) - Generic environmental impact statement rule for licensing new nuclear reactors · In effect
91 FR 22394 (final rule, 24 April 2026); docket NRC-2020-0101 · U.S. Nuclear Regulatory Commission · affects: Environmental review
Final NRC rule effective 26 May 2026 that lets environmental reviews of new reactor applications rely on generic findings. It is not an environmental decision on any project.
Not approved or pending: Each application still needs its own site-specific environmental review and decision. (Record checked .) - Internal Revenue Code sections 45Y and 48E: clean electricity production and investment credits, as amended by Public Law 119-21 · In effect
26 U.S.C. 45Y and 48E (added by Pub. L. 117-169, secs. 13701-13702, 16 August 2022), as amended by Pub. L. 119-21, secs. 70512-70513 (approved 4 July 2025) · U.S. Congress · affects: Project funding
Federal tax credits for zero-emission electricity generation placed in service from 2025. Public Law 119-21 of 4 July 2025 ended the credits for wind and solar facilities placed in service after 2027, tied the phase-down for other facilities to calendar year 2032, and added a nuclear energy community bonus test for advanced nuclear facilities under the production credit. It names no project.
Not approved or pending: No project's eligibility for either credit is recorded. Treasury guidance, the s. 45J definition referred to for advanced nuclear facilities, the s. 45U zero-emission nuclear credit and the prohibited-foreign-entity definitions were not reviewed. The current consolidated sections were not available from the Law Revision Counsel website when checked. (Record checked .) - NRC direct final rule: NRC Modernization: Rulemaking Procedure, Federal Advisory Committee Act Alignment, Access, and Security · In effect
91 FR 51555 (direct final rule, 11 August 2026), FR Doc. 2026-16374, docket NRC-2025-1139, RIN 3150-AL46; correction and confirmation of effective date FR Doc. 2026-19963 (30 September 2026) · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC rule in force since 26 October 2026, taken in response to Executive Order 14300. It simplifies how applicants ask the NRC to withhold proprietary information, makes some post-rule comment periods optional, aligns advisory committee rules with government-wide standards and updates security eligibility criteria. The NRC calls the changes administrative. It licenses no reactor.
Not approved or pending: Administrative and procedural changes only. The companion proposed rule (FR Doc. 2026-16373) and the text of the 30 September correction were not opened separately. Whether the NRC withholds any applicant's information is decided per request and is not recorded here. (Record checked .) - NRC direct final rule: Revising the Duration of Design Certifications · In effect
90 FR 28869 (direct final rule, 2 July 2025), FR Doc. 2025-12396, docket NRC-2025-0018, RIN 3150-AL26; effective date confirmed at 90 FR 41503 (26 August 2025) · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC rule in force since 15 September 2025 that makes US design certifications valid for 40 years instead of 15, both for the five certifications then in effect, including NuScale's, and for future ones. Issue dates are unchanged. It certifies no design and licenses no reactor.
Not approved or pending: Changes the duration of design certifications only. Whether a design is certified, or an application references a certification, is recorded among regulatory actions, not here. (Record checked .) - NRC final rule: Categorical Exclusions From Environmental Review · In effect
91 FR 15519 (final rule, 30 March 2026), FR Doc. 2026-06049, docket NRC-2018-0300, RIN 3150-AK54 · U.S. Nuclear Regulatory Commission · affects: Environmental review
NRC rule in force since 29 April 2026 that revises the list of NRC actions excluded from environmental assessment because they normally have no significant environmental effect. The NRC says it changes no requirements for applicants or licensees and left broader exclusions for new reactors outside its scope. It approves no reactor or site.
Not approved or pending: Whether an action falls within a categorical exclusion is decided by the NRC case by case and is not recorded here. The revised list of categories in s. 51.22 was not transcribed. A Part 53 correction of 13 April 2026 resolved conflicting amendatory instructions between the two rules published on 30 March 2026. (Record checked .) - NRC final rule: Fee Schedules; Fee Recovery for Fiscal Year 2026 (with Executive Order 14300 fixed fee caps) · In effect
91 FR 36470 (final rule, 16 June 2026), FR Doc. 2026-12067, docket NRC-2023-0212, RIN 3150-AL12; correction 91 FR 65941 (19 October 2026) · U.S. Nuclear Regulatory Commission · affects: Licensing review fees
NRC fee rule for fiscal year 2026, in force since 17 August 2026. It sets the full-cost review rate at $337 an hour and the reduced rate for advanced reactor applicants at $154, and adds fixed caps on review fees under Executive Order 14300 for applications that end in a final safety evaluation. It licenses no reactor and decides no applicant's eligibility.
Not approved or pending: Sets fees and caps only. Whether an applicant qualifies for the Reduced Hourly Rate, and the cap that applies to any application, are decided per application by the NRC and are not recorded here. The 19 October 2026 correction changed only a materials-license annual fee table. No FY2027 fee rule appeared in the NRC final-rule listing checked on 30 October 2026. (Record checked .) - NRC final rule: Increased Flexibility in the Mandatory Hearing Process · In effect
91 FR 20063 (final rule, 15 April 2026), FR Doc. 2026-07301, docket NRC-2025-1502 · U.S. Nuclear Regulatory Commission · affects: NRC licensing, Environmental review
NRC rule in force since 15 May 2026 that makes the mandatory hearings held on reactor construction permit applications more flexible, in response to the ADVANCE Act and Executive Order 14300. It removes two environmental-finding provisions for presiding officers and clarifies that other references to hearings mean contested hearings. It licenses no reactor.
Not approved or pending: Procedural rule only. How the hearing on any particular application is run is decided by the Commission and is not recorded here. Commission orders on individual hearings were not reviewed. (Record checked .) - NRC final rule: Streamlining Contested Adjudications in Licensing Proceedings · Adopted, not yet in effect
91 FR 69446-69490, FR Doc. 2026-22443, docket NRC-2025-1501, RIN 3150-AL58 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC published a final rule on 3 November 2026 to streamline contested adjudications in its licensing proceedings, in response to the ADVANCE Act and Executive Order 14300. It sets Standard, Focused and Expedited hearing pathways, which the Commission says are not rigid designations. It takes effect on 3 December 2026 for contested proceedings noticed on or after that date. It is separate from the mandatory (uncontested) hearing rule of April 2026.
Not approved or pending: Published on 3 November but not effective until 3 December 2026, and only for contested proceedings noticed on or after that date. It changes hearing procedure; it grants no license or permit and does not resolve any pending contention. (Record checked .) - NRC reviews of reactor designs previously authorized by DOE or the Department of War · Adopted, not yet in effect
91 FR 67195-67200, FR Doc. 2026-21801, docket NRC-2025-1503, RIN 3150-AL60 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC published a final rule allowing applicants to use relevant evidence from previously DOE- or Defense-authorized reactors that have been tested and demonstrated safe functioning. It takes effect on 25 November 2026. Applicants must show how that evidence satisfies NRC requirements and address differences in the commercial application. NRC retains independent review and licensing authority. The rule is an evidentiary pathway, not an automatic project approval.
Not approved or pending: Published on 26 October but not effective until 25 November 2026. This rule grants no project license or construction or operating authority, and does not automatically convert a DOE or defense authorization into an NRC license. Applicants must substantiate the relevant authorization, testing and demonstrated safe functioning. No project-specific eligibility is established here. (Record checked .)
Bills, proposed rules and consultations
- MARAD consultation: a marine SMR concept · Proposed — not in effect
91 FR 24961; FR Doc. 2026-09070; MARAD-2026-0729 · U.S. Maritime Administration · affects: State program administration
MARAD published a request for information on 7 May 2026 about a U.S.-built marine small modular reactor concept and its deployment framework. It sought public information, not bids for a completed reactor order. No vessel selection, license or deployment is established.
Not approved or pending: This is a request for information, not a vessel award, license or deployment. Its stated 5 August 2026 comment deadline is past; no later selection is established. No later final instrument or project-specific authorization was examined. (Record checked .) - NRC consultation: draft non-light-water reactor materials guidance · Proposed — not in effect
91 FR 59813; FR Doc. 2026-19217; NRC-2022-0215 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC published a request for comment on 21 September 2026 on draft DANU-ISG-2023-01, Revision 1, covering material compatibility for non-light-water reactors. This record establishes the consultation notice, not the contents or adoption of the underlying guidance.
Not approved or pending: The underlying interim staff guidance was not opened. The notice's 5 November 2026 comment deadline has passed; that does not establish adoption. It does not establish an effective guidance document or reactor permission. The Federal Register showed no extension or final guidance through 10 November 2026. (Record checked .) - NRC consultation: draft training-review guidance · Proposed — not in effect
91 FR 46175 and 91 FR 54407 (comment-period extension); FR Docs. 2026-14702 and 2026-17132; NRC-2026-1849 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC published a request for comment on draft NUREG-1220, Revision 2, on 22 July 2026. The notice describes training-review guidance covering stationary microreactors and small modular light-water reactors among other reactors. The underlying draft was not opened; no adopted guidance is established.
Not approved or pending: The underlying draft NUREG was not opened. The comment notice is not adopted guidance, a training-program approval or a reactor license. No later final instrument or project-specific authorization was examined. (Record checked .) - NRC proposal: modernizing materials licensing · Proposed — not in effect
91 FR 38124, 38135; FR Doc. 2026-12702; NRC-2025-1370; RIN 3150-AL56 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC proposed changes to materials licensing on 24 June 2026. Its Part 72 discussion would clarify the spent-fuel definition and damaged-fuel description for advanced reactor fuels. These are proposed changes, not an adopted rule, fuel approval or reactor permission.
Not approved or pending: The 24 June notice is a proposal, not an adopted amendment. Its stated 10 August 2026 comment deadline is past; that does not establish adoption. No fuel approval, materials license or reactor authorization follows. No later final instrument or project-specific authorization was examined. (Record checked .) - NRC proposal: package certification and microreactor transport · Proposed — not in effect
91 FR 46869, 46871; FR Doc. 2026-15117; NRC-2025-1667; RIN 3150-AL62 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC proposed changes to package certification on 27 July 2026. Under stated conditions, the proposal would allow increased radiation-level limits for certain Type B packages, primarily to facilitate potential microreactor transport-package designs submitted for review. It certifies no package and authorizes no deployment.
Not approved or pending: The changes are proposed and conditional on any designs being submitted for review. No package is certified and no microreactor is licensed. Its stated 26 August 2026 comment deadline is past; that does not establish adoption. No later final instrument or project-specific authorization was examined. (Record checked .) - Proposed licensing requirements for microreactors and comparable reactors · Proposed — not in effect
91 FR 23628 (proposed rule, 1 May 2026); docket NRC-2025-0379 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC proposal published 1 May 2026; the comment period closed on 15 June 2026. It is not in effect.
Not approved or pending: Not adopted: no final rule had been published when this record was last checked. A printed correction to the proposal appeared on 15 May 2026 (91 FR 27870). NRC's planned rulemaking list estimates 26 January 2027 for publishing the final rule, with no Federal Register citation yet. NRC says such dates are subject to change. That is a plan, not a rule. (Record checked .) - Proposed modernization of NRC radiation-protection standards · Proposed — not in effect
91 FR 43456, FR Doc. 2026-14208, docket NRC-2025-1140, RIN 3150-AL47 · U.S. Nuclear Regulatory Commission · affects: NRC licensing
NRC proposed revisions to its radiation-protection standards on 15 July 2026, with comments due 31 August. The proposal includes rules used in reactor licensing and draft implementing guidance. No final rule or effective date is established by this notice, and it grants no reactor permission.
Not approved or pending: The opened notice is a proposal. It establishes no final rule, effective date, approved design or project permission. The 31 August 2026 comment deadline it sets is in the past. No later extension notice was reviewed here. (Record checked .) - Proposed modernization of reactor licensing, safety oversight and siting practices · Proposed — not in effect
91 FR 44560 (proposed rule, 16 July 2026); docket NRC-2025-0975 · U.S. Nuclear Regulatory Commission · affects: NRC licensing, Siting
NRC proposal published 16 July 2026 under the Commission's revision of its rules ordered by Executive Order 14300; comments closed 31 August 2026. It is not in effect.
Not approved or pending: Not adopted: no final rule had been published when this record was last checked. A correction published on 27 July 2026 (91 FR 46869) withdrew a guidance document issued with the proposal because it contained outdated and incorrect information. NRC's planned rulemaking list estimates 26 February 2027 for publishing the final rule, with no Federal Register citation yet. NRC says such dates are subject to change. That is a plan, not a rule. (Record checked .) - Proposed regulatory enhancements for reactor licensing, decommissioning and operational oversight · Proposed — not in effect
91 FR 60702 (proposed rule, 24 September 2026), FR Doc. 2026-19568, docket NRC-2025-1138, RIN 3150-AL45 · U.S. Nuclear Regulatory Commission · affects: NRC licensing, Environmental review
NRC published a separate proposal on 24 September 2026 for reactor licensing, decommissioning and operational oversight; comments closed on 9 November. The proposed changes are not in effect. No reactor application, construction permission or operating authority follows from this proposal.
Not approved or pending: A proposal, not an effective rule, design approval or project permission. Its stated 9 November 2026 comment deadline has passed; that does not establish adoption. This is distinct from the July 2026 licensing/siting proposal in docket NRC-2025-0975. (Record checked .) - Proposed revisions to NRC implementation of NEPA · Proposed — not in effect
91 FR 42086, FR Doc. 2026-13687, docket NRC-2025-0478, RIN 3150-AL38 · U.S. Nuclear Regulatory Commission · affects: NRC licensing, Environmental review
NRC proposed changes to its NEPA environmental-review procedures on 7 July 2026, with comments due 21 August. Proposed changes concern review scope, procedures, categorical exclusions and draft guidance. The notice establishes no final rule or effective date and grants no project exemption, construction permit or operating authority.
Not approved or pending: The opened notice is a proposal, not an effective final rule or completed project review. The 21 August 2026 comment deadline it sets is in the past. No later extension notice was reviewed here. Project applicability needs its own assessment. (Record checked .)
Funding and support programs
- DOE Advanced Reactor Demonstration Program (demonstration awards) · In effect
DOE Advanced Reactor Demonstration Program · U.S. Department of Energy · affects: Project funding
DOE program that made its first demonstration awards on 13 October 2020; continued funding depends on appropriations and DOE approval.
Not approved or pending: Funding beyond the initial awards depends on future appropriations. (Record checked .) - ARDP demonstration award: TerraPower (Natrium) · Awarded
ARDP initial award to TerraPower, 13 October 2020 · U.S. Department of Energy · affects: Project funding - ARDP demonstration award: X-energy (Xe-100) · Awarded
ARDP initial award to X-energy, 13 October 2020 · U.S. Department of Energy · affects: Project funding - DOE Generation III+ Small Modular Reactor program · In effect
DOE Gen III+ SMR solicitation (16 October 2024; modified 24 March 2025) · U.S. Department of Energy · affects: Project funding
DOE program with two first-mover selections on 2 December 2025 (TVA and Holtec, up to $400 million each) and eight further selections on 14 May 2026 (more than $94 million for early site permits and supply chains). DOE's program page says applications closed on 23 April 2025.
Not approved or pending: Selections for federal cost-shared funding are not disbursements. DOE's Q&A says award milestones and payments are negotiated after selection; final award terms are not recorded here. (Record checked .) - Gen III+ SMR selection: TVA (Clinch River BWRX-300) · Selected — award terms not recorded as final
DOE Gen III+ SMR selection of TVA, 2 December 2025 · U.S. Department of Energy · affects: Project funding - Gen III+ SMR selection: Holtec (Palisades SMR-300) · Selected — award terms not recorded as final
DOE Gen III+ SMR selection of Holtec, 2 December 2025 · U.S. Department of Energy · affects: Project funding - Gen III+ SMR selections of May 2026: early site permits and supply chain · Selected — award terms not recorded as final
DOE Gen III+ SMR selections of eight companies, 14 May 2026 · U.S. Department of Energy · affects: Project funding, Siting - DOE HALEU Availability Program and HALEU allocation process · In effect
DOE HALEU Availability Program (Energy Act of 2020, sec. 2001, 42 U.S.C. 16281) and its HALEU Allocation Process document · U.S. Department of Energy, Office of Nuclear Energy · affects: State program administration
DOE program set up under the Energy Act of 2020 to supply high-assay low-enriched uranium from federal sources to advanced reactor developers while commercial supply is built. Developers apply under DOE's allocation process, and DOE has announced allocations or conditional commitments in three rounds from April 2025 to July 2026. A commitment is not a fuel delivery or a license.
Not approved or pending: Conditional commitments depend on contracts, NRC possession licenses and fuel fabrication, and are not deliveries. The first-round announcement of April 2025 and the allocated quantities were not opened. No project's allocation is recorded here as an approval. (Record checked .) - DOE Reactor Pilot Program · In effect
DOE request for applications DE-FOA-0003569 (18 June 2025) · U.S. Department of Energy · affects: DOE test-reactor authorization
DOE program opened in June 2025, with initial selections on 12 August 2025. DOE counts four zero-power criticality demonstrations toward its goal by July 2026, one of them under its Nuclear Energy Launch Pad. A DOE authorization is not an NRC commercial license.
Not approved or pending: Selection is not authorization to operate; each reactor needs its own DOE approvals, and commercial operation needs NRC licensing. (Record checked .)
No award or selection recorded.
No award or selection recorded.
Regulatory guidance and inspector policies
- Army adoption of DOE advanced-reactor categorical exclusion · Published guidance — not a law or project permission
91 FR 56135–56136; FR Doc. 2026-17818 · U.S. Department of the Army · affects: Environmental review
The Army published its adoption of DOE categorical exclusion B5.26 on 1 September 2026, effective and available for Army use that day. The notice refers to potential microreactor installations without naming a site. It is an administrative environmental-review procedure, not a reactor license or project approval.
Not approved or pending: Effective means the exclusion is available for Army use. The notice names no installation and approves no reactor site, construction, operation or license. Its administrative adoption does not eliminate the separate conditions for using an exclusion. No later final instrument or project-specific authorization was examined. (Record checked .)
Related government programs
Government plans and programs recorded under Agreements, newest first. They are followed there by who takes part and what they cover; they are not policy records and do not license, site or fund a reactor by themselves.
- DOE / NRIC Nuclear Energy Launch Pad (reactor and fuel-cycle developer selections)
Government program · announced or first reported Apr 2026 · Active - U.S. Army Janus Program for commercial microreactors on Army installations
Government program · announced or first reported 14 Oct 2025 · Active - DOE Reactor Pilot Program (DOE-authorized advanced test reactors)
Government program · announced or first reported 18 Jun 2025 · Active Also recorded as a policy measure: DOE Reactor Pilot Program.
Recorded permissions and applications for tracked US projects and designs
Project and design permissions are separate from the general measures above.
Design assessment
- NRC standard design approval for the NuScale US460 — applies to the design, not to a site
Design assessment · Issued / approved · NRC · decided 29 May 2025 · ADAMS ML25129A004, ML25086A073 · 90 FR 23716
The NRC issued a standard design approval to NuScale Power for the US460 small modular reactor design on 29 May 2025, completing its staff technical review. NuScale submitted the application in stages: the first part by letter dated 23 November 2022 and the remaining portions in stages between 29 November and 31 December 2022. The NRC notified NuScale by letter dated 31 July 2023 that the application was acceptable for docketing. The approval lets an applicant reference the design in a construction permit, operating license, combined license or manufacturing license application. It is a design approval only: it grants no permission for any site, construction or operation.
Sources: Federal Register 90 FR 23716 (4 Jun 2025): NuScale US460 standard design approval; Federal Register FR Doc. 2023-05457 (17 Mar 2023): NuScale US460 standard design approval application received; Federal Register FR Doc. 2023-16679 (4 Aug 2023): NuScale US460 standard design approval application accepted for docketing - NRC design certification of the NuScale US600 — applies to the design, not to a site
Design assessment · Issued / approved · NRC · decided 19 Jan 2023
The NRC lists the NuScale US600 among its issued design certifications. NuScale filed the application by letter dated 31 December 2016; the NRC lists it as tendered in December 2016, with the submission completed in January 2017. The certification rule, Appendix G to 10 CFR Part 52, was published on 19 January 2023 (88 FR 3306) and may be referenced for 40 years from 21 February 2023. The US600 is NuScale's earlier configuration of up to twelve modules of 50 MWe and 160 MWt each, which also received a standard design approval on 11 September 2020; the later US460 holds its own 2025 standard design approval. A design certification approves a design independent of any site and is not permission to build or operate.
Sources: eCFR: Appendix G to 10 CFR Part 52, Design Certification Rule for NuScale; NRC: Design Certification - NuScale US600 (past licensing activities); NRC: Design Certification Applications for New Reactors; Federal Register FR Doc. 2017-06309 (30 Mar 2017): NuScale design certification application accepted for docketing - NRC standard design approval for the NuScale US600 — applies to the design, not to a site
Design assessment · Issued / approved · NRC · decided 11 Sep 2020 · submitted 13 Jul 2020 · ADAMS ML20247J564
The NRC records that NuScale requested a standard design approval for the US600 on 13 July 2020 and that it was approved on 11 September 2020 (ML20247J564). The design was later certified by rule in January 2023. A standard design approval approves a design independent of any site; it is not permission to build or operate.
Sources: NRC: Design Certification - NuScale US600 (past licensing activities)
Site applications and decisions
- Belews Creek early site permit application — Duke Belews Creek technology-neutral SMR proposal
Site permission sought · Under review · NRC · submitted 30 Dec 2025 · docket 52-055 · ADAMS ML25364A004, ML26016A624, ML26259A008, ML26274A437 · 91 FR 5787 · 91 FR 542 · 91 FR 22549 · 91 FR 50896
Duke Energy Carolinas applied on 30 December 2025 for an early site permit for the Belews Creek site in Stokes and Forsyth counties, North Carolina. The NRC accepted and docketed the application in February 2026 under Docket No. 52-055, and it is under review. If issued, an early site permit approves a site independent of a specific plant design. It is not a construction permit or a combined license, and no reactor design is selected. The NRC gave notice on 27 April 2026 that it will prepare an environmental impact statement, and its project page marks the uncontested hearing of 17 September 2026 as held. On 29 September 2026, NRC letter ML26259A008 set a $2,178,000 cap on NRC review fees. That cap is not a project cost or a permit. The cap may be increased for applicant failure as defined in 10 CFR 170.3. The letter accelerates the 8 February 2026 schedule. NRC targets, not completed: advanced final safety evaluation report without open items December 2026 (from March 2027), draft environmental impact statement December 2026 (from February 2027), final safety evaluation February 2027 (from May 2027), and final environmental impact statement March 2027 (from May 2027). The decision date is listed as to be determined. Duke Energy Carolinas' Revision 2 cover letter (ML26274A437), dated 1 October 2026, states that Duke is not requesting a limited work authorization. The NRC project page lists the Revision 2 package as ML26274A436.
Sources: Federal Register 91 FR 5787 (9 Feb 2026): Belews Creek early site permit application, acceptance for docketing and opportunity to request a hearing; Federal Register 91 FR 542 (7 Jan 2026): Belews Creek early site permit application, notice of receipt; Federal Register 91 FR 22549 (27 Apr 2026): Belews Creek early site permit, notice of intent to prepare an environmental impact statement; Federal Register 91 FR 50896 (6 Aug 2026): Belews Creek early site permit application, notice of uncontested hearing; NRC: Duke Energy's Belews Creek early site permit application; NRC letter: fixed fee cap and revised schedule for the Belews Creek early site permit review (ADAMS ML26259A008); Duke Energy Carolinas letter RA-26-0157: Revision 2 of the Belews Creek early site permit application (ADAMS ML26274A437) - Clinch River Nuclear Site early site permit ESP-006 — TVA Clinch River BWRX-300
Site permission · Issued / approved · NRC · decided 19 Dec 2019 · submitted 12 May 2016 · permit ESP-006
NRC: application for two or more SMR modules (up to 800 MWe, 2420 MWt) submitted 12 May 2016, docketed 30 Dec 2016; Commission decision 17 Dec 2019.
Sources: U.S. NRC: Clinch River Nuclear Site early site permit ESP-006
Construction applications and decisions
- Long Mott construction permit — Long Mott Generating Station (Xe-100 at Dow Seadrift)
Construction permission · Issued / approved · NRC · decided 9 Nov 2026 · submitted 31 Mar 2025 · permit CPAR-3 · docket 50-614 · ADAMS ML26301A133 · 90 FR 24428 · 91 FR 53900 · 91 FR 72925
Long Mott Energy's construction permit application, dated 31 March 2025, was accepted and docketed by the NRC. NRC news release 26-083 of 9 November 2026 states that the NRC has issued the construction permit for the four-reactor Xe-100 Long Mott Generating Station in Calhoun County, Texas, that staff completed the safety evaluation in October, and that the permit authorizes building the facility but not operation; a separate operating license is required before fuel loading. The release gives no permit number; the permit itself is Construction Permit No. CPAR-3 (ADAMS ML26301A133), issued 9 November 2026, and the Federal Register notice of issuance (91 FR 72925, 12 November 2026) says it is immediately effective and authorizes construction of a power reactor facility in Calhoun County, Texas. The permit sets the earliest construction completion date as 1 July 2033 and the latest as 31 December 2033 and expires on that date. Its conditions include that Long Mott Energy notify the NRC when the site grading design and the passive engineered flooding protection design that may impact site grading are available for NRC staff examination, and that it perform geologic mapping of each foundation excavation for safety-related structures, evaluate it against the site characterization and notify the NRC when it is available for examination; the permit also incorporates an environmental protection plan. It says a license authorizing operation will not be issued unless the applicant submits the complete final safety analysis report, the Commission makes the stated findings on final design and environmental requirements, and the applicant submits proof of financial protection and executes an indemnity agreement. The NRC's project page, updated 12 November 2026, lists the hearing as held on 22 September 2026 and the construction permit decision as 8 November 2026; the permit and the Federal Register notice date issuance to 9 November 2026, and the one-day difference is unexplained in the sources read. Earlier steps: the uncontested (mandatory) hearing was held on 22 September 2026 in Port Lavaca; the Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review supports issuance; NRC issued an environmental assessment and finding of no significant impact plus related exemptions on 18 May 2026. In the contested proceeding, both admitted contentions were dismissed as moot in 2026 and on 7 August 2026 the Commission dismissed the applicant's appeal as moot; on 6 November 2026 the Commission denied the intervenor's separate petition for review (CLI-26-15). The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Sources: Federal Register 90 FR 24428 (10 Jun 2025): Long Mott Generating Station construction permit application; Federal Register 91 FR 53900 (20 Aug 2026): Long Mott Generating Station notice of hearing; NRC / ANS Dow Long Mott Xe-100 EA-FONSI; NRC Federal Register notice: Long Mott environmental assessment, FONSI and exemptions; NRC: Long Mott Generating Station Xe-100 application page; NRC Commission order CLI-26-10, Long Mott Energy, LLC (Docket 50-614-CP); NRC meeting notice: mandatory hearing on the Long Mott construction permit application; NRC Advisory Committee on Reactor Safeguards: report on the safety aspects of the Long Mott construction permit application (16 Oct 2026); Federal Register 2026-18898 (15 Sep 2026): 739th meeting of the Advisory Committee on Reactor Safeguards; X-energy: NRC completes safety review of the Xe-100 for Long Mott (final safety evaluation report), 30 Oct 2026; NRC news release 26-083: first construction permit in nearly 60 years for a high-temperature gas-cooled reactor (Long Mott); X-energy and Dow: proposed SMR project receives construction permit for nuclear-powered industrial site; Federal Register 91 FR 72925 (12 Nov 2026): Long Mott Generating Station construction permit CPAR-3, notice of issuance; NRC Construction Permit No. CPAR-3, Long Mott Generating Station (ML26301A133); NRC Commission order CLI-26-15, Long Mott Energy, LLC (Docket 50-614-CP) - Last Energy Caldwell site phased construction permit application, Part 1 (with limited work authorization request) — Last Energy first commercial PWR-20 site, Caldwell County
Construction permission sought · Application received · NRC · submitted 20 Oct 2026 · docket 99902140 · ADAMS ML26294A162 · 91 FR 69895
Last Energy filed Part 1 of a two-part phased construction permit application on 20 October 2026 for a PWR-20 facility at the Caldwell Site in Caldwell County, Texas. Part 1 includes a limited work authorization request under 10 CFR 50.10(d) covering early foundation work, with financial information, a preliminary safety analysis report for the LWA scope, an environmental report and a site redress plan. The NRC published a notice of receipt on 5 November 2026 (91 FR 69895). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction.
Sources: Federal Register 91 FR 69895 (5 Nov 2026): Last Energy phased construction permit application with limited work authorization request, Caldwell site (notice of receipt) - Clinch River Unit 1 construction permit — TVA Clinch River BWRX-300
Construction permission · Issued / approved · NRC · decided 28 Sep 2026 · submitted 28 Apr 2025 · permit CPAR-2 · docket 50-615 · ADAMS ML26244A257, ML26243A056 · 91 FR 63311
The Federal Register published this notice on 5 October 2026 at 91 FR 63311. It states that construction permit CPAR-2 was issued to TVA on 28 September 2026 for Clinch River Nuclear Unit 1, is immediately effective, and authorizes construction of a power reactor facility in Roane County, Tennessee. The notice says the conditions in early site permit ESP-006 had been met except those listed in the construction permit. The permit sets the earliest construction completion date as 1 October 2031 and the latest as 30 September 2032, expires on that latest date and does not restate an output rating. TVA announced the permit on 29 September 2026. The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Sources: Federal Register 91 FR 63311 (5 Oct 2026): Clinch River Nuclear Unit 1 construction permit and record of decision; TVA construction permit announcement; NRC: TVA Clinch River construction permit application; NRC Construction Permit No. CPAR-2, Clinch River Nuclear Unit 1 (ML26243A056) - Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application, Part 1 (with limited work authorization request) — Blue Energy BWRX-300 at Port of Victoria
Construction permission sought · Application received · NRC · submitted 15 Sep 2026 · docket 99902137 · ADAMS ML26265A371, ML26258A339 · 91 FR 64409
Blue Energy filed Part 1 of a phased construction permit application on 15 September 2026 for one BWRX-300 unit, Blue Energy Center–Port of Victoria Nuclear Unit 1, in Victoria, Texas. Part 1 includes a limited work authorization request, two related exemption requests and an environmental report. The NRC published a notice of receipt on 8 October 2026 (91 FR 64409). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction. The applicant intends to file the full construction permit application within 18 months of Part 1.
Sources: Federal Register 91 FR 64409 (8 Oct 2026): Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application with limited work authorization request (notice of receipt); Blue Energy letter submitting Construction Permit Application Part 1 (ADAMS ML26258A339); Federal Register 91 FR 64409 (8 Oct 2026), govinfo copy: Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application, notice of receipt - NRC construction permit application for the University of Illinois KRONOS MMR — University of Illinois KRONOS MMR
Construction permission sought · Under review · NRC · submitted 31 Mar 2026 · docket 50-618 · ADAMS ML26090A463, ML26120A548 · 91 FR 21321 · 91 FR 30730
The university applied for a construction permit for one research reactor by letter dated 27 March 2026; the NRC records it as tendered on 31 March 2026, accepted it for docketing on 18 May 2026 as Docket No. 50-618 and published the hearing opportunity on 26 May 2026. The stated application power level is 45 MWth. No permit has been issued; target review dates in 2027 are not decisions.
Sources: NRC: University of Illinois Urbana-Champaign KRONOS MMR construction permit application; Federal Register 91 FR 21321 (21 Apr 2026): University of Illinois construction permit application received; Federal Register 91 FR 30730 (26 May 2026): University of Illinois construction permit application docketedStatus confirmed on against NRC: University of Illinois Urbana-Champaign KRONOS MMR construction permit application. This confirms the recorded status only; the general record check date remains separate.
- TerraPower Natrium construction permit — Natrium Kemmerer Unit 1
Construction permission · Issued / approved · NRC · decided 9 Mar 2026 · submitted 28 Mar 2024 · permit CPAR-1 · docket 50-613 · ADAMS ML26034B247 · 91 FR 12628
The NRC issued construction permit CPAR-1 on 9 March 2026 to US SFR Owner, LLC (TerraPower) for Kemmerer Power Station Unit 1, after the Commission's 4 March 2026 decision on the uncontested hearing. The permit authorizes construction only; an operating license is a separate NRC decision.
Sources: Federal Register 91 FR 12628 (16 Mar 2026): Kemmerer Power Station Unit 1 construction permit and record of decision; NRC TerraPower Natrium / Kemmerer; U.S. NRC: Natrium Kemmerer Unit 1 - Pioneer Units 1 and 2 phased construction permit application (with limited work authorization request) — Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)
Construction permission sought · Under review · NRC · submitted 31 Dec 2025 · docket 50-616, 50-617 · 91 FR 62565 · 91 FR 66740 · 91 FR 72577
Holtec filed Part 1 of a phased construction permit application for two SMR-300 units (Pioneer 1 and 2) at the Palisades Energy Center on 31 December 2025, including a limited work authorization request. The NRC accepted it for docketing in February 2026 and began weekly notices of receipt on 1 October 2026. Its fourth notice, published 22 October, again records receipt and availability; it does not grant an LWA or construction permit. Part 2 (a complete preliminary safety analysis report, with an updated Quality Assurance Topical Report and exemption requests) was filed on 30 September 2026, according to the NRC's notice of receipt dated 5 November and published 10 November 2026 (91 FR 72577; ADAMS package ML26273A416), which began a second series of four weekly notices. The notice says the NRC staff was then undertaking its acceptance review of Part 2; no acceptance or docketing of Part 2 is recorded. The application remains recorded as under review; this receipt notice is not a new permission decision.
Sources: Federal Register 91 FR 62565 (1 Oct 2026): Pioneer Units 1 and 2 phased construction permit application with limited work authorization request; NRC news 26-008 Holtec Pioneer LWA; Holtec: Major regulatory developments in the Palisades Pioneer Unit 1 & 2 program (30 September 2026); NRC fourth weekly notice of receipt and availability: Pioneer Units 1 and 2 phased construction permit application; Federal Register 91 FR 72577 (10 Nov 2026): Pioneer Units 1 and 2, receipt of construction permit application (Part 2), first of four weekly notices; NRC Pioneer Units 1 and 2 LWA pageCould not be confirmed on . Attempted official source: NRC fourth weekly notice of receipt and availability: Pioneer Units 1 and 2 phased construction permit application. This is an access or status observation only; the record review date is unchanged.
- Kairos Hermes 2 construction permit — Kairos Hermes 2
Construction permission · Issued / approved · NRC · decided 21 Nov 2024 · submitted 14 Jul 2023 · permit CPTR-7, CPTR-8 · docket 50-611, 50-612 · ADAMS ML24324A021, ML24324A022 · 89 FR 94767
The NRC issued construction permits CPTR-7 and CPTR-8 for the two-unit Hermes 2 test reactor facility on 21 November 2024. Operation needs separate operating licenses.
Sources: Federal Register 89 FR 94767 (29 Nov 2024): Hermes 2 test reactor facility construction permits; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 2 construction permit - ACU Molten Salt Research Reactor construction permit — Natura MSR-1 demonstration at Abilene Christian University
Construction permission · Issued / approved · NRC · decided 16 Sep 2024 · submitted 12 Aug 2022 · permit CPRR-124 · docket 50-610 · ADAMS ML24243A040 · 89 FR 77197
The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center on its Abilene campus. ACU's application is dated 12 August 2022; the NRC notified ACU by letter dated 18 November 2022 that it was acceptable for docketing. Operation needs a separate operating license.
Sources: Federal Register 89 FR 77197 (20 Sep 2024): ACU Molten Salt Research Reactor construction permit; Federal Register 89 FR 18678 (14 Mar 2024): ACU Molten Salt Research Reactor environmental assessment; Federal Register 87 FR 73051 (28 Nov 2022): ACU construction permit application accepted for docketing - Kairos Hermes 1 construction permit — Kairos Hermes 1
Construction permission · Issued / approved · NRC · decided 14 Dec 2023 · submitted 29 Sep 2021 · permit CPTR-6 · docket 50-7513 · ADAMS ML23338A258 · 88 FR 88137 · 91 FR 28629
The NRC issued construction permit CPTR-6 for the Hermes non-power test reactor on 14 December 2023. A 13 May 2026 order extended the latest construction completion date from 31 December 2026 to 30 April 2029. Operation needs a separate operating license.
Sources: Federal Register 88 FR 88137 (20 Dec 2023): Hermes test reactor construction permit; Federal Register 91 FR 28629 (18 May 2026): Hermes test reactor construction completion date extension; NRC Kairos Hermes construction permit materials; U.S. NRC: Kairos Hermes 1 construction permit
Environmental decision
- DOE PWR-5 Phase 1 environmental categorical exclusion — Last Energy PWR-5 pilot at Texas A&M-RELLIS
Environmental decision · Issued / approved · U.S. Department of Energy, Office of Nuclear Energy · decided 30 Sep 2026
DOE approved NEPA determination DOE-ID-26-008 on 30 September 2026 for proposed PWR-5 Phase 1 initial criticality and low-power testing at RELLIS. The Phase 1 research configuration is bounded at 100 kWth, fewer than 1,000 cumulative operating hours and no grid export. The 19.5 MWth PWR-5 design point applies to later phases. This environmental decision is not DOE startup authorization, proof of achieved criticality, or authorization for later phases.
Sources: DOE PWR-5 Phase 1 NEPA categorical exclusion, DOE-ID-26-008 - NRC environmental assessment and FONSI for Pioneer excavation-wall exemption — Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)
Environmental decision · Issued / approved · NRC · decided 25 Aug 2026 · docket 50-616, 50-617 · 91 FR 54890
The NRC made an environmental assessment and finding of no significant impact available on 24 August 2026; its later exemption notice describes the finding as issued on 25 August. It addresses environmental effects of the requested support-of-excavation-wall exemption; it is not the 28 August exemption and does not issue an LWA or construction permit.
Sources: NRC environmental assessment and FONSI for Pioneer excavation-wall exemption; NRC exemption for specified Pioneer support-of-excavation walls - DOE Aurora-INL B5.26 environmental categorical exclusion — Oklo Aurora-INL
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 20 Jul 2026
DOE Idaho approved environmental determination DOE-ID-INL-26-018 on 20 July 2026 for the proposed Aurora-INL reactor construction, installation and operation scope under B5.26. The document describes anticipated activities and a planned construction period; it is an environmental determination, not evidence that reactor construction occurred, an approval of the preliminary safety analysis, or authority to load fuel or operate.
Sources: DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018 - Long Mott environmental assessment, FONSI and review exemptions — Long Mott Generating Station (Xe-100 at Dow Seadrift)
Environmental decision · Issued / approved · U.S. Nuclear Regulatory Commission · decided 18 May 2026 · 91 FR 29515
The NRC notice says the Long Mott construction-permit environmental assessment and finding of no significant impact were available on 18 May 2026 and that exemptions permitting this review in place of an environmental impact statement were issued the same day. The construction-permit application remains under review; this decision is not a construction permit or authority to operate.
Sources: NRC Federal Register notice: Long Mott environmental assessment, FONSI and exemptions - DOE categorical exclusion CX-271015 for the Ward250 research reactor — Valar Atomics Ward 250
Environmental decision · Issued / approved · U.S. Department of Energy, Office of Nuclear Energy · decided 22 Apr 2026
Signed 22 April 2026 under NEPA identification DOE-ID-26-005. Determines that the 250 kWth Ward250 research reactor at USREL fits a categorical exclusion. It states no authorization number and no electrical output, and it does not confirm the company's later electricity claim.
Sources: DOE categorical exclusion CX-271015 PDF: Ward250 research reactor - DOE Idaho categorical exclusion CX-271007 for the Unity zero-power test — Deployable Energy Unity at Idaho National Laboratory
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 15 Apr 2026
Approved 15 April 2026 under posting DOE-ID-INL-26-011. Covers a zero-power criticality test bounded at 0 MWth and 0 kWe. It does not authorize the future 1 MWe configuration and is not an operating license.
Sources: DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality - DOE Idaho categorical exclusion CX-271002 for the Aalo-X critical assembly — Aalo-X at Idaho National Laboratory
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 14 Apr 2026
Approved 14 April 2026 under posting DOE-ID-INL-26-013. Covers installation and zero-power operation of the critical assembly at no more than 10 watts thermal. It is an environmental categorical exclusion, not a construction permit or operating license, and it does not authorize a later power reactor.
Sources: DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly - DOE Idaho categorical exclusion CX-035340 for the Antares Mark-0 experiment — Antares Mark-0 at Idaho National Laboratory
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 26 Jan 2026
Approved 26 January 2026 under posting DOE-ID-INL-25-037. Covers the zero-power Mark-0 heat-pipe experiment in MFC-793. No measurable thermal output is claimed. This is not an operating license, and it does not approve the later Mark-1 reactor.
Sources: DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0 - Project Pele record of decision (prototype mobile microreactor environmental impact statement) — Project Pele (INL microreactor demonstration)
Environmental decision · Issued / approved · U.S. Department of Defense, Strategic Capabilities Office · decided 5 Apr 2022 · 87 FR 22521
Signed 5 April 2022 and published 15 April 2022 at 87 FR 22521. The Strategic Capabilities Office decided to implement the proposed action of its final environmental impact statement: fabricate the prototype mobile microreactor and its fuel at existing off-site commercial facilities and demonstrate it at the Idaho National Laboratory Site. This is a National Environmental Policy Act decision. This record addresses the environmental decision; it does not establish the status of any separate DOE safety authorization. No such authorization document was opened.
Sources: Federal Register 87 FR 22521 (15 Apr 2022): Record of Decision, Construction and Demonstration of a Prototype Mobile Microreactor - DOE finding of no significant impact for MARVEL (DOE/EA-2146) — MARVEL microreactor test bed at INL's TREAT facility
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 12 Nov 2021
Issued at Idaho Falls on 12 November 2021 for environmental assessment DOE/EA-2146. DOE found that designing and demonstrating MARVEL in the north high bay of the Transient Reactor Test facility would not significantly affect the human environment, so no environmental impact statement is required. It is an environmental finding. It is not approval of a safety analysis and not authority to load fuel or operate. The 2021 text describes about 20 kW electric; DOE's current project page gives 85 kW thermal and about 10 kW electric.
Sources: DOE/EA-2146 Finding of No Significant Impact: MARVEL microreactor
Other applications and decisions
- NRC exemption for specified Pioneer support-of-excavation walls before LWA — Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)
Other regulatory action · Issued / approved · NRC · decided 28 Aug 2026 · docket 50-616, 50-617 · 91 FR 55628
The NRC issued a narrow exemption on 28 August 2026 allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization. The notice does not issue or commit to an LWA or construction permit. The exemption does not show that physical work began or authorize all construction.
Sources: NRC exemption for specified Pioneer support-of-excavation walls - Kemmerer Unit 1 exemption for energy-island work before a construction permit — Natrium Kemmerer Unit 1
Other regulatory action · Issued / approved · NRC · decided 7 May 2025 · submitted 28 Feb 2025 · docket 50-613 · 90 FR 20692
The Federal Register notice (90 FR 20692, 15 May 2025) states that the NRC issued an exemption on 7 May 2025, in response to TerraPower's 28 February 2025 request for US SFR Owner, LLC, modifying the definition of construction for Kemmerer Unit 1. It allows specified work for non-safety-related structures, systems and components on the energy island, such as pile driving and foundations, before a construction permit and without a limited work authorization. It is not a construction permit or operating authority.
Sources: Federal Register 90 FR 20692 (15 May 2025): US SFR Owner, LLC; Kemmerer Power Station, Unit 1; Exemption - Oklo Aurora custom combined license application (2020), denied without prejudice — Oklo Aurora-INL
Other regulatory action · Denied · NRC · decided 6 Jan 2022 · submitted 11 Mar 2020 · docket 52-049 · ADAMS ML20075A001, ML21357A034 · 87 FR 1441
Oklo Power applied on 11 March 2020 for a custom combined license, which covers construction and operation, for one Aurora microreactor at Idaho National Laboratory. The NRC denied it without prejudice by letter of 6 January 2022 because requested information was not provided, and said Oklo may resubmit. This is an earlier application than the current Aurora powerhouse, which is following DOE authorization under the Reactor Pilot Program. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only (project 99902095) and no docketed application.
Sources: Federal Register 87 FR 1441 (11 Jan 2022): Oklo Aurora combined license application, denial; NRC pre-application activities: Oklo Aurora Powerhouse