Policy and licensing / United States (federal)
DOE HALEU Availability Program and HALEU allocation process
DOE program set up under the Energy Act of 2020 to supply high-assay low-enriched uranium from federal sources to advanced reactor developers while commercial supply is built. Developers apply under DOE's allocation process, and DOE has announced allocations or conditional commitments in three rounds from April 2025 to July 2026. A commitment is not a fuel delivery or a license.
- Category
- Funding and support programs
- Status
- In effect
- Instrument
- funding program · DOE HALEU Availability Program (Energy Act of 2020, sec. 2001, 42 U.S.C. 16281) and its HALEU Allocation Process document
- Issued by
- U.S. Department of Energy, Office of Nuclear Energy
- Jurisdiction
- United States (federal)
- Affects
- State program administration
- Effective date
- Not recorded
- Expiry or completion
- None recorded
- Operative text
- DOE: High-Assay Low-Enriched Uranium (HALEU) Allocation Process (PDF) (DOE HALEU Allocation Process PDF (no date in its text, file created 28 August 2025))
- Record reviewed · next review
- 30 Oct 2026 · 29 Jan 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
DOE program, established under section 2001 of the Energy Act of 2020, to make high-assay low-enriched uranium available for civilian domestic research, development, demonstration and commercial use. Under the allocation process developers request HALEU from DOE sources, and DOE weighs whether the project is government-funded or cost-shared, its licensing schedule, the requester's capability to use the material and the material's availability. Section 3131(h) of the FY2024 National Defense Authorization Act requires priority for the two ARDP Pathway 1 demonstration reactors (X-energy and TerraPower Natrium). Before transfer the requester must, among other things, execute contracts with DOE and obtain an NRC license for possession, and DOE may rescind allocations after significant delays. DOE announced first allocations to five companies in April 2025 and conditional commitments to three companies on 26 August 2025 and to NASA and Radiant on 23 July 2026, each followed by contracting. A conditional commitment is not a fuel delivery, and the program licenses, sites or approves no reactor or project.
Not approved or still pending
Conditional commitments depend on contracts, NRC possession licenses and fuel fabrication, and are not deliveries. The first-round announcement of April 2025 and the allocated quantities were not opened. No project's allocation is recorded here as an approval. (Record checked .)
Dated lifecycle
- Apr 2025 · Milestone — First HALEU amounts announced for five companies. (DOE: Energy Department to Distribute Third Round of HALEU to NASA and Radiant)
- 26 Aug 2025 · Selections announced — Second round: conditional commitments to three companies. (DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry)
- 23 Jul 2026 · Selections announced — Third round: conditional commitments to NASA and Radiant. (DOE: Energy Department to Distribute Third Round of HALEU to NASA and Radiant)
Related instruments
- DOE Advanced Reactor Demonstration Program (demonstration awards) (related)
- Executive Order 14299: advanced reactors for national security (related)
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- DOE: High-Assay Low-Enriched Uranium (HALEU) Allocation Process (PDF) (government, accessed 30 Oct 2026)
- DOE Office of Nuclear Energy: HALEU Availability Program (government, accessed 30 Oct 2026)
- DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry (government, published 26 Aug 2025, accessed 30 Oct 2026)
- DOE: Energy Department to Distribute Third Round of HALEU to NASA and Radiant (government, published 23 Jul 2026, accessed 30 Oct 2026)