Policy and licensing / United States (federal)
NRC final rule: Increased Flexibility in the Mandatory Hearing Process
NRC rule in force since 15 May 2026 that makes the mandatory hearings held on reactor construction permit applications more flexible, in response to the ADVANCE Act and Executive Order 14300. It removes two environmental-finding provisions for presiding officers and clarifies that other references to hearings mean contested hearings. It licenses no reactor.
- Category
- Laws, rules and executive directives
- Status
- In effect
- Instrument
- final rule · 91 FR 20063 (final rule, 15 April 2026), FR Doc. 2026-07301, docket NRC-2025-1502
- Issued by
- U.S. Nuclear Regulatory Commission
- Jurisdiction
- United States (federal)
- Affects
- NRC licensing, Environmental review
- In effect from
- 15 May 2026
- Expiry or completion
- None recorded
- Operative text
- Federal Register 91 FR 20063 (15 April 2026): NRC final rule, Increased Flexibility in the Mandatory Hearing Process (GovInfo text) (Federal Register final rule text (GovInfo HTML), 91 FR 20063)
- Record reviewed · next review
- 30 Oct 2026 · 30 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
NRC regulation revising its rules of practice and procedure, in response to the ADVANCE Act and Executive Order 14300, to increase flexibility in conducting the mandatory (uncontested) hearings that section 189 of the Atomic Energy Act requires for construction permit applications. It removes 10 CFR 51.105 and 51.107, which specified environmental findings to be made by presiding officers, makes conforming changes, and revises provisions in 10 CFR parts 2, 50, 51, 52 and 53 to clarify that references to hearings in those parts apply only to contested hearings. It decides no license and approves no reactor, design, site or project.
Not approved or still pending
Procedural rule only. How the hearing on any particular application is run is decided by the Commission and is not recorded here. Commission orders on individual hearings were not reviewed. (Record checked .)
Dated lifecycle
- 15 Apr 2026 · Published (Federal Register 91 FR 20063 (15 April 2026): NRC final rule, Increased Flexibility in the Mandatory Hearing Process (GovInfo text))
- 15 May 2026 · Took effect (Federal Register 91 FR 20063 (15 April 2026): NRC final rule, Increased Flexibility in the Mandatory Hearing Process (GovInfo text))
Related instruments
- Executive Order 14300: reform of the Nuclear Regulatory Commission (responds to)
- ADVANCE Act of 2024 (related)
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Federal Register 91 FR 20063 (15 April 2026): NRC final rule, Increased Flexibility in the Mandatory Hearing Process (GovInfo text) (regulator, published 15 Apr 2026, accessed 30 Oct 2026)