Policy and licensing / United States (federal)
10 CFR Part 53: risk-informed, technology-inclusive licensing framework
The NRC's Part 53 licensing framework took effect on 29 April 2026. It sets how applications may be reviewed; it approves no design, site or reactor.
- Category
- Laws, rules and executive directives
- Status
- In effect
- Instrument
- final rule · 91 FR 15696 (final rule, 30 March 2026); docket NRC-2019-0062
- Issued by
- U.S. Nuclear Regulatory Commission
- Jurisdiction
- United States (federal)
- Affects
- NRC licensing
- In effect from
- 29 Apr 2026
- Expiry or completion
- None recorded
- Operative text
- Federal Register 91 FR 15696 (30 Mar 2026): Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (final rule) (Final rule as corrected (91 FR 18772; 91 FR 47128))
- Record reviewed · next review
- 30 Oct 2026 · 15 Jan 2027 (dates our review of this record; not a statement of the measure's present legal effect)
Legal and geographic scope
NRC regulation adding a risk-informed, performance-based and technology-inclusive licensing framework for commercial nuclear plants, issued in response to the Nuclear Energy Innovation and Modernization Act.
Not approved or still pending
Which applicants will use Part 53 is not recorded; no application under Part 53 is recorded here. The NRC corrected the final rule twice, on 13 April 2026 (errors and conflicting amendatory instructions with the categorical exclusions rule) and on 28 July 2026 (the Part 75 definition of facilities). (Record checked .)
Dated lifecycle
- 31 Oct 2024 · Proposed (Federal Register 89 FR 86918 (31 Oct 2024): Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (proposed rule))
- 30 Mar 2026 · Published (Federal Register 91 FR 15696 (30 Mar 2026): Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (final rule))
- 29 Apr 2026 · Took effect (Federal Register 91 FR 15696 (30 Mar 2026): Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (final rule))
Related instruments
- ADVANCE Act of 2024 (related)
Projects or designs named by the source
- None. Location in this jurisdiction does not make a project eligible for, or approved under, this measure.
Sources
- Federal Register 91 FR 15696 (30 Mar 2026): Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (final rule) (regulator, accessed 3 Oct 2026)
- Federal Register 89 FR 86918 (31 Oct 2024): Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (proposed rule) (regulator, accessed 3 Oct 2026)
- Federal Register API: NRC documents of type Rule published 23 May 2025 to 30 October 2026 (51 results) (government, page updated 30 Oct 2026, accessed 30 Oct 2026)