FPL plan to begin early site permitting for a potential SMR next to an existing nuclear plant (Florida)
FPL's 2026-2035 Ten Year Site Plan says the utility plans to begin the initial stages of NRC early site permitting in 2026-2027 for a potential SMR at a site adjacent to one of its existing nuclear plants, taking a stepwise approach. No site, technology, application or in-service date within the plan period is stated.
- Type
- Feasibility or siting study
- Countries concerned
- United States
- Region named by the sources
- Florida
- Participants and roles
- Utility: Florida Power & Light Company (FPL)
- Designs named
- —
- Scale as stated
- Not stated by the sources
- Announced or first reported
- Apr 2026
- Status
- Active
Utility ten-year site plan states a plan to begin initial early site permitting stages in 2026-2027, no site, technology or filing named, SMR in-service beyond the ten-year horizon. - Confidence
- medium
- Last checked
- 2026-10-14 (record review date, not proof of current activity)
Related deployment projects
- No related deployment project is recorded here.
Sources
- Ten Year Power Plant Site Plan 2026-2035 (company_primary, published Apr 2026, accessed 2026-10-14)