KHNP SMR at the Gijang-gun candidate site (11th Basic Plan)

On 17 June 2026 KHNP's new nuclear site selection committee chose Gijang-gun in Busan as the candidate site for the one SMR in Korea's 11th Basic Plan (Gyeongju also applied).

Current status

Stage
Siting
How current
General record check . Bounded evidence review . None of the 5 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No map pin is shown for this record.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: sources conflict; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

Reporting gives 700 MW of SMR capacity by 2038 as a plan-level figure. KHNP's release names no design; Asia Economy and the government's 14 July 2026 growth strategy, as reported by Kookje Shinmun, name i-SMR for the site, with targets of standard design approval by 2028, construction in 2030 and commercial operation in 2035. Gijang county promoted the use of idle KHNP-owned land at the Kori plant; the parcel is not disclosed. The i-SMR standard design approval application was filed on 27 February 2026, and the regulator received KINS's review plan on 27 August 2026.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Korea Hydro & Nuclear Power
Vendor for linked design
No selected-design vendor recorded
Location
Gijang-gun SMR candidate site · South Korea · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Town named, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
high
Record reviewed
6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

KHNP SMR at the Gijang-gun candidate site (11th Basic Plan) is recorded at Gijang-gun SMR candidate site, Busan, South Korea. Operator: Korea Hydro & Nuclear Power. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: town or locality only; town named, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Programs and agreements naming the project
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

KHNP's 17 June 2026 release and Asia Economy's 18 June 2026 report name Gijang-gun as the candidate host and KHNP as the company pursuing the SMR, and say the county promoted idle KHNP land at the Kori plant. They name no buyer of the reactor's power or heat, and the July and August 2026 reports read also name none. Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026)

Contractor

Asia Economy reported on 28 August 2026 that the i-SMR technology development group, KHNP and the Korea Atomic Energy Research Institute applied on 27 February 2026 for i-SMR standard design approval. That application is for the reactor design, not a Gijang engineering or construction appointment. KHNP's 17 June 2026 release and the June and July 2026 reports read name no engineering, procurement or construction contractor for the Gijang plant. Asia Economy: NSSC receives KINS review plan for the i-SMR standard design approval (28 August 2026); KHNP: candidate sites for new nuclear plants selected; Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026)

Funding and government decisions

World Nuclear News reported on 18 June 2026 that the science ministry plans to invest KRW 1,200 billion by 2030 in core designs for three domestic SMR types, which is national technology funding, not money for the Gijang plant. Kookje Shinmun's 14 July 2026 report says the government can support funds and sites for SMR demonstration under the new SMR act, without an amount for Gijang. No source read states a Gijang funder or amount. WNN: Sites selected for Korean nuclear new build; Government growth strategy report naming i-SMR for Gijang (14 July 2026, via Daum)

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

The reports read describe i-SMR as a 170 MW-class integral pressurised water reactor and discuss its standard design approval. Neither they, KHNP's 17 June 2026 release nor World Nuclear News' 18 June 2026 report name a fuel supplier, quantity or delivery for the Gijang reactor. WNN: Sites selected for Korean nuclear new build; Government growth strategy report naming i-SMR for Gijang (14 July 2026, via Daum)

Comparable schedule revision

Comparable schedule revision not established. Asia Economy reported on 18 June 2026 that the Gijang i-SMR targets standard design approval by 2028, construction in 2030 and commercial operation in 2035, and Kookje Shinmun's 14 July 2026 report repeats 2035 for commercialisation. Asia Economy's 28 August 2026 report says the 2028 and 2035 plan may slip and that 2035 operation would need a 2029 permit application and an early-2030s start. A warned possible slip is not a revised target, and no later date replaces 2035. Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026); Government growth strategy report naming i-SMR for Gijang (14 July 2026, via Daum); Asia Economy: NSSC receives KINS review plan for the i-SMR standard design approval (28 August 2026)

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Reactor supplier; Site host or owner
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Reactor supplier
Site host or owner

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes, 1 not yet reviewed)
  • Evidence review. KHNP's release of 17 June 2026 says the new nuclear site selection committee chose Yeongdeok-gun for two large reactors and Gijang-gun for the one SMR in the 11th Basic Plan, Gijang scoring 87.11 against Gyeongju's 84.56 after site and environmental surveys, site inspections and a resident opinion survey; the release names no reactor design. Asia Economy (18 June 2026) calls Gijang the final site for KHNP's i-SMR construction project, the first in Korea, says the county promoted the use of idle KHNP-owned land at the Kori plant, and reports targets of standard design approval by 2028, construction in 2030 and commercial operation in 2035. Kookje Shinmun via Daum (14 July 2026), reporting the government's second-half growth strategy, says i-SMR, a 170 MW-class integral PWR, will be built at Gijang. World Nuclear News gives 700 MW of SMR capacity to be built by 2038 under the plan, a plan-level figure, and Asia Economy (28 August 2026) reports the i-SMR standard design approval application of 27 February 2026 and the review plan received by the regulator. The next documentary decisions are the i-SMR standard design approval and a construction permit application naming the Gijang parcel. KHNP as operator, the Gijang site and the siting stage stay; capacity and module count stay unstated for the project. The stored claims of a parcel of about 220,000 square metres next to Shin-Kori 1 and 2 are not in any opened text. Last checked 19 Oct 2026. KHNP: candidate sites for new nuclear plants selected; Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026); Government growth strategy report naming i-SMR for Gijang (14 July 2026, via Daum)
    What would change this

    The NSSC's i-SMR standard design approval, or KHNP's construction permit application or electric power development plan for Gijang naming the design and parcel. Next scheduled check: 19 Jan 2027.

  • Design identified: Sources conflict. KHNP's 17 June 2026 release names Gijang as the SMR candidate site without naming a reactor model. Asia Economy, and Kookje Shinmun's account of the government's 14 July 2026 growth strategy, name i-SMR for the site. No KHNP or government primary text naming the design was opened, so no design is linked. Last checked 19 Oct 2026. KHNP: candidate sites for new nuclear plants selected; Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026); Government growth strategy report naming i-SMR for Gijang (14 July 2026, via Daum)
    What would change this

    KHNP's construction-permit application or a government ministry document naming i-SMR for the Gijang site, which would give primary confirmation. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. KHNP names Gijang-gun, a county in Busan, as the candidate site; no locality, parcel or coordinates are given. Asia Economy reports only that the county promoted the use of idle KHNP-owned land at the Kori plant, which is the applicant's argument, not a disclosed parcel. A county-level name is not recorded here as a named site. Last checked 19 Oct 2026. KHNP: candidate sites for new nuclear plants selected; Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026)
    What would change this

    A KHNP electric power development plan, environmental impact scoping document or construction permit application naming the Gijang parcel. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. Asia Economy reported in June 2026 that the Gijang SMR is to obtain standard design approval by 2028 and then go through resident consultation and licensing under the Electric Source Development Promotion Act and Nuclear Safety Act, with construction targeted for 2030 and commercial operation for 2035. Standard design approval is the next consequential regulatory step; all dates are targets. Last checked 23 Oct 2026. Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026)
    What would change this

    An NSSC standard design approval decision for i-SMR, or a site designation for the Gijang project. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. KHNP's 17 June 2026 release says its independent site selection committee chose Gijang-gun as the candidate site for the SMR in the 11th Basic Plan after a municipal call for applications, site and environmental baseline surveys, field inspections and a residents' opinion poll. Asia Economy reports that the Gijang county council unanimously approved a hosting-consent motion in March 2026. Candidate-site selection is not a permit; resident consultation and licensing under the power-development and nuclear safety laws are still to come. Last checked 23 Oct 2026. KHNP: candidate sites for new nuclear plants selected; Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026)
    What would change this

    Designation of the site under the Electric Source Development Promotion Act or a construction permit application to the NSSC. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Asia Economy reported in June 2026 that Gijang county promoted the use of idle KHNP-owned land at the Kori nuclear plant and the link to existing plant infrastructure. KHNP's release names only the county, and the specific parcel, grid connection and cooling arrangements are not disclosed in the sources reviewed. Last checked 23 Oct 2026. Asia Economy: Gijang SMR site and i-SMR plan (18 June 2026); KHNP: candidate sites for new nuclear plants selected
    What would change this

    A KHNP site designation or environmental assessment naming the parcel and its infrastructure. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 5 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: no date recorded.5 of 5 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(5)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: KHNP SMR at the Gijang-gun candidate site (11th Basic Plan) — https://smrmap.com/projects/gijang-smr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “KHNP SMR at the Gijang-gun candidate site (11th Basic Plan)”. Record reviewed 6 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/gijang-smr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.