Halden Kjernekraft SMR proposal at Femsjøen

Halden Kjernekraft (a Norsk Kjernekraft venture with local partners) sent a formal notification to the Energy Ministry in June 2025 for a nuclear plant on about 600 decares bordering Femsjøen.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 1 of 5 listed sources has a publication or document date recorded here: 15 Aug 2024. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

Technology is not selected; capacity statements were not reconciled and are not stored. Halden Kjernekraft reported on 15 August 2024 that it selected Multiconsult and Jacobs for supplier-industry mapping and preparation of an impact-assessment plan and other study milestones. Its June 2025 notification also identifies a commissioned Menon Economics impact analysis. These are preparatory assignments, not construction or EPC awards.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Norsk Kjernekraft
Vendor for linked design
No selected-design vendor recorded
Location
Femsjøen area, Halden · Norway · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate geolocation stated in Halden Kjernekraft's June 2025 notification, Table 1-1 (59.13912 N, 11.51667 E, property 143/1), for a proposed area of about 600 decares beside Femsjøen. This is a proposed area for assessment, not a site approval.
Coordinates
59.13912, 11.51667 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Halden Kjernekraft SMR proposal at Femsjøen is recorded at Femsjøen area, Halden, Østfold, Norway. Operator: Norsk Kjernekraft. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: Halden Kjernekraft: melding med forslag til utredningsprogram, Table 1-1 'Fakta om lokaliteten', printed page 3: Geolokalitet (ca.) 59,13912°N 11,51667°Ø, property 143/1

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Contractor

Source-backed project statement Halden Kjernekraft reported on 15 August 2024 that it selected Multiconsult and Jacobs for supplier-industry mapping and preparation of an impact-assessment plan and other study milestones. Its June 2025 notification also identifies a commissioned Menon Economics impact analysis. These are preparatory assignments, not construction or EPC awards. Halden Kjernekraft: Multiconsult and Jacobs to assess the Norwegian nuclear supplier industry; Halden Kjernekraft: melding med forslag til utredningsprogram

Not found in the sources we checked (4): Customer or offtaker; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

The reviewed sources do not establish a named project-specific power or heat purchaser, contractual quantity or completed offtake. Intended uses, host municipalities and general company customer plans are not buyer commitments. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Halden Kjernekraft: melding med forslag til utredningsprogram; Halden Kjernekraft news (melding til Energidepartementet); Norsk Kjernekraft: locations (ten project companies); Norsk Kjernekraft: Taftøy assessment programme set by the government

Funding and government decisions

The reviewed sources do not establish a project-specific financing commitment or amount. General company backing, ownership and policy support do not by themselves establish allocated or paid project funding. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Halden Kjernekraft: melding med forslag til utredningsprogram; Norsk Kjernekraft: Taftøy assessment programme set by the government

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

The reviewed sources do not establish a project-specific fuel supplier commitment or delivery. General supply-market plans and reactor-design fuel requirements are kept separate. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Halden Kjernekraft: melding med forslag til utredningsprogram

Comparable schedule revision

Comparable schedule revision not established. The reviewed sources do not establish two dated statements revising the same project milestone. A single target, a fleet-level ambition or a different project’s timetable is not a schedule revision. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Halden Kjernekraft: melding med forslag til utredningsprogram; Halden Kjernekraft news (melding til Energidepartementet); Norsk Kjernekraft: Taftøy assessment programme set by the government

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Reactor supplier; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(7 notes)
  • Evidence review. One or more SMRs up to 1,200 MW are proposed; two 300 MW units per phase are an example, not a selection. The notification identifies proposed property 143/1 near Femsjøen; an option and named property do not establish approved nuclear siting. No new coordinate is assigned. Final reactor technology selection is explicitly dependent on the assessment. The project company ownership is municipality 20%, Østfold Energi 40%, Norsk Kjernekraft 40%; this does not appoint the reactor operator. The June 2025 document is a notification with a proposed assessment program, separate from later license applications. Establishment of the assessment program is a prospective step in the proposer’s timetable; its estimated 2026 date is not proof it occurred. Last checked 20 Oct 2026. Halden Kjernekraft: melding med forslag til utredningsprogram
    What would change this

    A project-specific adopted assessment program, final site/design selection or permission instrument; preserve the distinction between proposal and approval. Next scheduled check: 20 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. The Halden news index describes a proposed plant and a waste store. It names no reactor model. Last checked 19 Oct 2026. Halden Kjernekraft news (melding til Energidepartementet)
    What would change this

    Halden Kjernekraft names a reactor vendor or model. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The index says a landowner agreement identifies a possible location in Halden. It publishes no parcel or coordinates. Last checked 19 Oct 2026. Halden Kjernekraft news (melding til Energidepartementet)
    What would change this

    A Halden notice that identifies the parcel or publishes a facility point. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. Under the process the June 2025 notification describes, the next step is a public hearing on the proposed assessment program and a decision by the authorities setting it; the separate waste-facility notification follows the same path. The sources reviewed give no date for either. Last checked 23 Oct 2026. Halden Kjernekraft: melding med forslag til utredningsprogram
    What would change this

    The ministry's decision setting the Halden program. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. Halden Kjernekraft sent its notification with a proposed impact-assessment program to the Energy Ministry in June 2025. The notification calls this the first of several regulatory steps, followed by a public hearing and the authorities setting the program, and says a neighbours' meeting and an open public meeting were held when the site was announced in January 2025. No adopted program or license is recorded in these sources. Last checked 23 Oct 2026. Halden Kjernekraft: melding med forslag til utredningsprogram
    What would change this

    The ministry's hearing or decision setting the Halden assessment program. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). The June 2025 notification says Halden Kjernekraft holds an option agreement with the landowner, that the site lies 6 km from Statnett's Halden substation along an existing power-line corridor crossing the site, and that cooling towers are the likely cooling method, still to be assessed. An option is not a land purchase, and no grid or water agreement is described. Last checked 23 Oct 2026. Halden Kjernekraft: melding med forslag til utredningsprogram
    What would change this

    An impact assessment, land purchase or grid-connection agreement for the Halden site. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. The June 2025 notification says Halden Kjernekraft is running a parallel process for an interim storage and disposal facility for radioactive waste within the same Halden site, covered by a separate notification. That facility is a proposal under assessment; no storage, disposal or funding arrangement is established. Last checked 23 Oct 2026. Halden Kjernekraft: melding med forslag til utredningsprogram
    What would change this

    The impact assessment or a decision on the separate Halden waste-facility notification. Next scheduled check: 21 Jan 2027.

Evidence dates

(1 of 5 sources with a publication or document date)
Latest dated listed source publication: Halden Kjernekraft: Multiconsult and Jacobs to assess the Norwegian nuclear supplier industry: 15 Aug 2024.Latest dated recorded event: no date recorded.4 of 5 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(5)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Halden Kjernekraft SMR proposal at Femsjøen — https://smrmap.com/projects/halden-smr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Halden Kjernekraft SMR proposal at Femsjøen”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/halden-smr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.