Helen nuclear energy program plant in Helsinki

Helen launched a nuclear energy program in 2024 for district heat and possibly electricity.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 2 of 6 listed sources have a publication or document date recorded here; the newest is 5 Nov 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No map pin is shown for this record.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

Helen Nuclear Ltd published an environmental impact assessment program in November 2026, with public comment open from 3 November 2026 to 4 January 2027. The assessment covers three alternative Helsinki sites (Salmisaari, Vuosaari and Norrberget), several plant options and a no-build option, and heat-only or combined heat and power plants. It examines maximum outputs of 630 MW reactor heat for a heat-only plant, and 1,400 MW reactor heat with 500 MW electricity for a combined plant; Helen says the final plant may be smaller. Technology, output and site are not decided. Helen's stated goal is a site decision in 2028. The assessment is not a license application, a government decision in principle or a permit.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Helen
Vendor for linked design
No selected-design vendor recorded
Location
Helsinki (Vuosaari, Salmisaari or Norrberget) · Finland · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Town named, no map pin
Electrical capacity
Not recorded · scope: plant
Helen's November 2026 project description says the assessment examines maximum outputs: reactor heat of 630 MW and district heat of 600 MW for a heat-only plant, and reactor heat of 1,400 MW, district heat of 700 MW and electricity of 500 MW for a combined plant.
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Helen nuclear energy program plant in Helsinki is recorded at Helsinki (Vuosaari, Salmisaari or Norrberget), Uusimaa, Finland. Operator: Helen. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: town or locality only; town named, no map pin.

Electrical output is not recorded on this project. Helen's November 2026 project description says the assessment examines maximum outputs: reactor heat of 630 MW and district heat of 600 MW for a heat-only plant, and reactor heat of 1,400 MW, district heat of 700 MW and electricity of 500 MW for a combined plant. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Customer or offtaker

Source-backed project statement World Nuclear News of 9 September 2024 says Helen's program aims to build a small nuclear plant producing heat for Helsinki, and the City of Helsinki's 6 November 2025 release says the options are heat-only or combined heat and power plants inside the district-heating network area. The heat would serve Helen's own Helsinki district-heating system. No external buyer, quantity or electricity offtake is named, and the plant type is not yet chosen. WNN: Finnish energy firm Helen launches nuclear programme; Helen: three alternative plant sites studied in Helsinki

Contractor

Source-backed project statement World Nuclear News reported on 9 September 2024 that Helen signed a letter of intent with Steady Energy in October 2023, valid until 2027, covering work towards a siting license and technology permit and fixing a contract price for a district-heating plant, and allowing Helen to procure up to ten 50 MW units. The same article says Helen will still evaluate plant suppliers, so this is a preparatory agreement, not a supplier selection or construction contract. Helen has since set up Helen ydinvoima Oy as its license-holder company. WNN: Finnish energy firm Helen launches nuclear programme; Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026

Not found in the sources we checked (3): Funding and government decisions; Fuel; Comparable schedule revision
Funding and government decisions

The 9 September 2024 World Nuclear News article, the 6 November 2025 City of Helsinki release and Helen's 25 March 2026 Vuosaari meeting memo name no funder, amount or financing for the Helsinki plant. The memo describes the price tag only as a few billion, a cost scale rather than funding, and the article says Helen would negotiate with unnamed potential partner shareholders. Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026; WNN: Finnish energy firm Helen launches nuclear programme

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

Helen's 25 March 2026 Vuosaari meeting memo says a nuclear plant would be refuelled only about once a year, and World Nuclear News of 9 September 2024 describes the LDR-50 design. Neither names a fuel supplier, fabrication or delivery for the Helsinki plant, whose technology is not yet chosen. Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026; WNN: Finnish energy firm Helen launches nuclear programme

Comparable schedule revision

Comparable schedule revision not established. World Nuclear News of 9 September 2024 says the program's first phase was due to finish in 2026 and quotes Helen's chief executive aiming for the first SMR to provide heat no later than the early 2030s if everything falls into place. The 6 November 2025 release and the 25 March 2026 memo do not restate either date. Each target is stated once, so no revision is shown. Helen's November 2026 project description gives a goal of starting production during the 2030s, against the chief executive's 2024 aim of heat no later than the early 2030s. Helen does not describe this as a delay. WNN: Finnish energy firm Helen launches nuclear programme; Helen: three alternative plant sites studied in Helsinki; Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026; Helen Nuclear Ltd: description of the nuclear energy project (EIA)

Not recorded in SMRMap's reviewed evidence (3): Reactor supplier; Site host or owner; Programs and agreements naming the project
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(8 notes)
  • Evidence review. A release published on 6 November 2025 by the City of Helsinki's Urban Environment Division says Helen and the city are studying a nuclear plant in Helsinki and that Helen's nuclear energy program has chosen three alternative sites for further study: the Vuosaari and Salmisaari power plant areas and the Norrberget area in western Östersundom. It says an environmental impact assessment of the alternatives starts next, that actual site decisions will be made in coming years, and that the plant types under study produce heat only or electricity alongside heat. World Nuclear News (9 September 2024) reports that the program's first phase, due to finish in 2026, covers partner negotiations, evaluation of plant suppliers and site mapping, and mentions an earlier letter of intent allowing up to ten 50 MW Steady Energy units, a ceiling rather than a selection. Helen's memo of a resident meeting in Vuosaari on 25 March 2026 says Helen Ydinvoima Oy has been established as the license-holder organization, that heat-only versus combined heat and power is still open, that economics will be assessed once plant suppliers' descriptions are refined, and that the plant has not yet been chosen (gloss of 'kun laitosta ei ole vielä valittu'). The next documentary decisions are the EIA report with a site choice and the selection of a plant supplier. The stored siting stage stays; design and site stay open and output stays unknown. Last checked 19 Oct 2026. Helen: three alternative plant sites studied in Helsinki; Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026; WNN: Finnish energy firm Helen launches nuclear programme
    What would change this

    Helen's EIA report for the three Helsinki alternatives or Helen's announcement of a selected plant supplier and site. Next scheduled check: 19 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. No opened source names a reactor design or supplier for the Helsinki plant. WNN says the first phase includes evaluating plant suppliers, and Helen's 25 March 2026 memo says economics will be assessed once suppliers' descriptions and plans are refined and that the plant has not yet been chosen. The Steady Energy letter of intent reported by WNN allows up to ten 50 MW units but is not a selection for this plant. Last checked 19 Oct 2026. Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026; WNN: Finnish energy firm Helen launches nuclear programme
    What would change this

    Helen's announcement of a selected plant supplier or design, or its EIA report naming the plant alternatives by design. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. Three alternative sites in Helsinki (Vuosaari, Salmisaari and Norrberget) are under study and none is chosen; the city's release says site decisions will be made in coming years on the basis of the EIA. Helen's March 2026 memo adds that it is open which area is chosen or whether any of the alternatives is chosen (gloss). A single plant site is therefore not disclosed. Last checked 19 Oct 2026. Helen: three alternative plant sites studied in Helsinki; Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026
    What would change this

    Helen's EIA report and the subsequent site decision, with the city's zoning start, naming one plant site. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. Helen's November 2026 project description says the assessment report is due in 2027 and that its goal is a decision on a possible plant site in 2028. Master planning is intended to begin for all three areas in 2027 and finish in 2029–2030, with detailed planning in about 2030–2031. Starting construction also requires a government decision in principle, building permits and STUK's approval. These are Helen's stated targets, not decisions. Last checked 11 Nov 2026. Helen: three alternative plant sites studied in Helsinki; Helen Nuclear Ltd: description of the nuclear energy project (EIA)
    What would change this

    Completion of Helen's EIA, a Helsinki zoning decision, or STUK approval of a site. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. Helen published its environmental impact assessment program in November 2026. The City of Helsinki says opinions go to the Ministry of Economic Affairs and Employment from 3 November 2026 to 4 January 2027, and lists four public events organized by Helen on 16, 19, 24 and 26 November. Helen's project description says the ministry is the competent authority and will issue a reasoned conclusion after the assessment report, which Helen expects in 2027. The city plans to begin master planning for all three areas in 2027. These are consultation steps; no license application is recorded. Last checked 11 Nov 2026. Helen: three alternative plant sites studied in Helsinki; Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026; City of Helsinki: nuclear project environmental assessment has started; Helen Nuclear Ltd: description of the nuclear energy project (EIA)
    What would change this

    The assessment report, a zoning decision or a license application. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Helen's March 2026 resident-meeting memo says the three candidate sites were chosen on criteria including enough space, room for protection zones, population density, district-heat and power-transmission connections, and proximity to the sea, because a combined heat-and-power plant would need seawater for cooling. No site has been chosen, and the City of Helsinki says site decisions will follow the assessment and other studies in coming years. Last checked 23 Oct 2026. Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026; Helen: three alternative plant sites studied in Helsinki
    What would change this

    Helen's EIA report or a site decision naming the chosen site and its cooling and grid arrangements. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure. The City of Helsinki's planning page for Helen's small nuclear plant, read in October 2026, says the plant's high-level spent fuel would likely go to a final repository to be built for that purpose in Finnish bedrock, that the plant would also produce intermediate- and low-level waste, and that final-disposal and interim-storage solutions will be decided later under the Nuclear Energy Act. This is a stated expectation, not a waste-management agreement, a repository arrangement or a licensed plan. Helen's November 2026 project description says the assessment examines on-site treatment and interim storage of spent fuel and treatment, storage and potential on-site disposal of low- and intermediate-level waste, and that final disposal of spent fuel is excluded from this assessment. Last checked 11 Nov 2026. Ydinvoima (City of Helsinki planning page for the small nuclear plant project); Helen Nuclear Ltd: description of the nuclear energy project (EIA)
    What would change this

    Helen's environmental impact assessment program or report, or a waste-management agreement, setting out spent-fuel storage and disposal for the plant. Next scheduled check: 23 Apr 2027.

  • Plant capacity (scope qualified). Helen's November 2026 project description says the assessment examines maximum outputs: reactor heat of 630 MW and district heat of 600 MW for a heat-only plant, and reactor heat of 1,400 MW, district heat of 700 MW and electricity of 500 MW for a combined plant. These are assessment ceilings for undecided plant options, and Helen says the final plant may be smaller, so no point rating is stored. Last checked 11 Nov 2026. Helen Nuclear Ltd: description of the nuclear energy project (EIA)
    What would change this

    Helen's EIA report or plant-supplier selection fixing the plant type and rating. Next scheduled check: 23 Apr 2027.

Evidence dates

(2 of 6 sources with a publication or document date)
Latest dated listed source publication: City of Helsinki: nuclear project environmental assessment has started: 5 Nov 2026.Latest dated listed source document: Keskustelumuistio Helenin pienydinvoimalahankkeen asukastilaisuudesta Vuosaaressa 25.3.2026: 25 Mar 2026.Latest dated recorded event: no date recorded.4 of 6 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(6)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Helen nuclear energy program plant in Helsinki — https://smrmap.com/projects/helen-helsinki-smr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Helen nuclear energy programme plant in Helsinki”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/helen-helsinki-smr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.