Projects / Norway · Siting

Lister Kjernekraft SMR proposal (Lyngdal and Farsund)

Lister Kjernekraft AS, set up in September 2025 by Norsk Kjernekraft with Farsund and Lyngdal municipalities, sent a planning initiative to Norwegian authorities and began assessment work in 2026.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 1 of 4 listed sources has a publication or document date recorded here: 17 Dec 2025. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Site location recorded as disclosed (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

Technology and capacity are not stored.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Not recorded
Vendor for linked design
No selected-design vendor recorded
Location
Lister region (Lyngdal and Farsund) · Norway · precision: region only
Searchable without an invented map pin.
Coordinates
Region only, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Lister Kjernekraft SMR proposal (Lyngdal and Farsund) is recorded at Lister region (Lyngdal and Farsund), Agder, Norway. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: region only; region only, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

The reviewed sources do not establish a named project-specific power or heat purchaser, contractual quantity or completed offtake. Intended uses, host municipalities and general company customer plans are not buyer commitments. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Lister Kjernekraft AS igangsetter utredning av kjernekraft; Norsk Kjernekraft: locations (ten project companies); Norsk Kjernekraft: Taftøy assessment programme set by the government

Contractor

The reviewed sources do not establish an additional project-specific engineering, preparatory-work or construction assignment. A supplier’s general capabilities or an industry-wide agreement do not establish a contract for this site. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Lister Kjernekraft AS igangsetter utredning av kjernekraft

Funding and government decisions

The reviewed sources do not establish a project-specific financing commitment or amount. General company backing, ownership and policy support do not by themselves establish allocated or paid project funding. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Lister Kjernekraft AS igangsetter utredning av kjernekraft; Norsk Kjernekraft: Taftøy assessment programme set by the government

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

The reviewed sources do not establish a project-specific fuel supplier commitment or delivery. General supply-market plans and reactor-design fuel requirements are kept separate. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Lister Kjernekraft AS igangsetter utredning av kjernekraft

Comparable schedule revision

Comparable schedule revision not established. The reviewed sources do not establish two dated statements revising the same project milestone. A single target, a fleet-level ambition or a different project’s timetable is not a schedule revision. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Lister Kjernekraft AS igangsetter utredning av kjernekraft; Norsk Kjernekraft: locations (ten project companies); Norsk Kjernekraft: Taftøy assessment programme set by the government

Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(7 notes, 1 not yet reviewed)
  • Evidence review. Studies have started for a possible plant in the Lister region, that they are not a license application, and that no design, output or parcel is stored. The same page says Norsk Kjernekraft earlier filed a notification and proposed study program for a possible plant in the Lister region, and that Lister Kjernekraft AS has decided to start the investigation. Lyngdal and Farsund are named as municipal backers. No reactor model or parcel is named. The participating organizations retain only their source-supported roles; a reactor operator is not assigned from the study, proposer, parent, existing-fleet or proposed-owner relationship. Last checked 20 Oct 2026. Lister Kjernekraft AS igangsetter utredning av kjernekraft
    What would change this

    A Lister report that names a parcel or a reactor model, or a license application. Next scheduled check: 20 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. Lister Kjernekraft has started studies, beginning with security and fuel. The notice selects no reactor model. Last checked 19 Oct 2026. Lister Kjernekraft AS igangsetter utredning av kjernekraft
    What would change this

    Lister Kjernekraft names a reactor vendor or model. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The notice concerns a possible plant in the Lister region. It publishes no parcel. Last checked 19 Oct 2026. Lister Kjernekraft AS igangsetter utredning av kjernekraft
    What would change this

    A Lister notice that identifies a parcel or alternative sites by property designation. Next scheduled check: 19 Jan 2027.

  • Operator or intended licensed owner: Not disclosed in the reviewed evidence. The reviewed sources establish other participant roles, but do not appoint the recorded party as this reactor’s operator. The operator remains unassigned; this does not assert that no operator exists. Last checked 20 Oct 2026. Lister Kjernekraft AS igangsetter utredning av kjernekraft
    What would change this

    A project-specific filing, operating agreement or developer statement explicitly names the proposed reactor operator. Next scheduled check: 20 Jan 2027.

  • Next decision and prerequisites. Lister Kjernekraft's April 2026 release describes staged assessment work, starting with security, nuclear fuel and the fuel cycle, to inform later decisions on the project; it notes the Aure and Heim framework requires alternative locations to be assessed. It names no date for the authorities to set Lister's own program. Last checked 23 Oct 2026. Lister Kjernekraft AS igangsetter utredning av kjernekraft
    What would change this

    The ministry's decision on Lister's assessment program, or a site selection. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. The April 2026 release says Norsk Kjernekraft previously sent the Energy Ministry a notification with a proposed impact-assessment program for the Lister region, and that Lister Kjernekraft has begun assessment work using the program the ministries set for the separate Aure and Heim project. It does not say Lister's own program has been set, and no license or consultation outcome is recorded. Last checked 23 Oct 2026. Lister Kjernekraft AS igangsetter utredning av kjernekraft
    What would change this

    The ministry's hearing or decision setting the Lister assessment program. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). Norsk Kjernekraft's April 2026 release, in a photo caption taken from the planning initiative submitted to the authorities, says the Hausvik industrial area in Lyngdal is one of the areas to be assessed for a possible SMR plant in Lyngdal and Farsund; World Nuclear News reported the same in December 2025, and the company's locations page says the project has many possible locations. Hausvik is a candidate area under study, not a chosen or secured site. The sources reviewed describe no grid connection, cooling water or land arrangement. Last checked 23 Oct 2026. Lister Kjernekraft AS igangsetter utredning av kjernekraft; Norsk Kjernekraft: locations (ten project companies); Norwegian towns take stakes in nuclear project company
    What would change this

    The Energy Ministry's published notification or set assessment program for Lister, or a Lister Kjernekraft decision naming the site, grid connection or cooling arrangement. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(1 of 4 sources with a publication or document date)
Latest dated listed source publication: Norwegian towns take stakes in nuclear project company: 17 Dec 2025.Latest dated recorded event: no date recorded.3 of 4 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(4)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Lister Kjernekraft SMR proposal (Lyngdal and Farsund) — https://smrmap.com/projects/lister-smr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Lister Kjernekraft SMR proposal (Lyngdal and Farsund)”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/lister-smr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.