Projects / South Africa · Announced

Necsa SMR demonstration reactor at Pelindaba

Necsa issued an expression of interest in March 2026 for a technology partner to co-develop and operate South Africa's first SMR demonstration reactor.

Current status

Stage
Announced
How current
General record check . Bounded evidence review . 1 of 7 listed sources has a publication or document date recorded here: 31 Mar 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

Reporting places it at the Pelindaba complex with operation targeted by 2036. No technology or license application is established. The compulsory briefing of 16 April 2026 drew 54 potential partners from 12 countries; the expression of interest closed on 29 May 2026 and Necsa expects to identify a partner within a year. A July 2026 non-binding memorandum with Siemens Energy covers the power island. No partner, design or license application is established.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Necsa
Vendor for linked design
No selected-design vendor recorded
Location
Necsa Pelindaba complex · South Africa · precision: site area (named plant, laboratory, base, port, campus or parcel)
OpenStreetMap Nominatim point for Pelindaba (suburb feature); site-area point for the Necsa complex, not a reactor plot.
Coordinates
-25.7987, 27.9194 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Necsa SMR demonstration reactor at Pelindaba is recorded at Necsa Pelindaba complex, North West, South Africa. Operator: Necsa. Recorded vendor: No selected-design vendor is recorded. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Pelindaba' (suburb feature for the Necsa complex)

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

Necsa's 31 March 2026 announcement says the demonstration would produce power, process heat and isotopes, and Engineering News on 5 and 17 June 2026 reports that Necsa would keep Eskom informed so it can decide whether to adopt the technology. None of the sources read names a buyer of power, heat, hydrogen or isotopes from the Pelindaba demonstration, and Eskom is described as a possible future adopter, not a customer. Necsa seeks SMR partnership; Engineering News: Necsa to play a central role; Engineering News: Necsa expects to identify SMR partner within a year (17 June 2026)

Contractor

Necsa's 31 March and 17 April 2026 pages and Engineering News on 5 and 17 June 2026 describe an expression of interest that closed on 29 May 2026 as prequalification before a competitive bid, with a technology partner expected to be identified by about mid-2027. No partner is selected in those sources. The July 2026 Energize report of a non-binding Siemens Energy memorandum for the power island could not be read, because the page returns only a site template. Necsa seeks SMR partnership; Necsa: Necsa attracts global interest in small modular reactor programme (17 April 2026); Engineering News: Necsa expects to identify SMR partner within a year (17 June 2026); NEI: South Africa revives PBMR project; Energize: Siemens Energy eyes power-island role in Necsa SMRs (July 2026)

Funding and government decisions

Engineering News reported on 5 June 2026 that Necsa is pursuing a partner route to explore funding options and that its expression of interest offered to co-fund, for example by contributing equity rather than cash. No funder, amount or commitment is stated for the Pelindaba demonstration, and the 30 billion rand figure reported in November 2025 concerns commercialising the separate pebble-bed technology. Engineering News: Necsa to play a central role; NEI: South Africa revives PBMR project

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

Engineering News on 5 June 2026 says the demonstration design is still open and that Necsa producing fuel would be an obvious step only if a high-temperature design were chosen, and its fuel-cycle and SAFARI-1 passages concern research reactors and future plants generally. No fuel supplier, quantity or delivery is stated for the Pelindaba demonstration. Engineering News: Necsa to play a central role; Engineering News: Necsa expects to identify SMR partner within a year (17 June 2026)

Comparable schedule revision

Comparable schedule revision not established. Necsa's 31 March 2026 call for partners cites the national plan's goal of demonstrating multi-purpose reactors by 2032, and Engineering News quoted Necsa's chief executive on 17 June 2026 saying the plan puts the demonstration reactor on line by 2032. Engineering News reported on 5 June 2026 that the plan was operation by 2036 at the latest, possibly sooner. Neither source says a target was moved, and the record's events hold no revision pair. Engineering News: Necsa to play a central role; Engineering News: Necsa expects to identify SMR partner within a year (17 June 2026)

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Reactor supplier; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. Necsa's expression of interest is a prequalification and market-sounding stage before a competitive request for proposals, not a reactor award. Reporting identifies Necsa as the intended builder/operator at Pelindaba, while technology selection and a project license remain unestablished. Opened accounts give different operating forecasts, 2032 and no later than 2036; neither is achieved operation. Funding arrangements are being explored with a future technology partner, including possible equity rather than cash. The demonstration is separate from revival of the historical PBMR program. Last checked 19 Oct 2026. Necsa seeks SMR partnership; Necsa: Necsa attracts global interest in small modular reactor programme (17 April 2026); Engineering News: Necsa to play a central role; Engineering News: Necsa expects to identify SMR partner within a year (17 June 2026)
    What would change this

    The competitive RFP, selected-partner award or license application resolving the demonstration technology, schedule and binding delivery commitments. Next scheduled check: 19 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. The EOI is followed by competitive technology-partner selection. No reactor design is selected in the opened documents. Last checked 19 Oct 2026. Necsa seeks SMR partnership; Necsa: Necsa attracts global interest in small modular reactor programme (17 April 2026)
    What would change this

    The competitive RFP, selected-partner award or license application resolving the demonstration technology, schedule and binding delivery commitments. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. Necsa's chief executive said in June 2026 that Necsa expects to select a development partner for the demonstration SMR within about a year, following its expression-of-interest process and a later request for proposals. Target dates differ: he cited the Integrated Resource Plan as putting the reactor online by 2032, while another June 2026 report gives operation by 2036 at the latest. Both are targets. Last checked 23 Oct 2026. Engineering News: Necsa expects to identify SMR partner within a year (17 June 2026); Engineering News: Necsa to play a central role
    What would change this

    Necsa's request for proposals or its selection of an SMR technology partner. Next scheduled check: 23 Apr 2027.

  • Permissions and public process: Not disclosed in the reviewed evidence. Necsa's 31 March 2026 statement describes an expression-of-interest process to prequalify technology partners before a formal request for proposals for an SMR demonstration plant. That is procurement, not permission, and neither it nor the June 2026 Engineering News reports mention an environmental authorization or National Nuclear Regulator license application for the demonstration SMR. Last checked 23 Oct 2026. Necsa seeks SMR partnership
    What would change this

    An environmental authorization application or NNR license application for the Pelindaba demonstration SMR. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Engineering News reported in June 2026 that the demonstration SMR called for in the Integrated Resource Plan will be built and operated by Necsa at its Pelindaba complex west of Pretoria, focused on power, hydrogen, process heat and desalination. The report names the existing Necsa site but no plot, grid connection or water arrangement for the reactor. Last checked 23 Oct 2026. Engineering News: Necsa to play a central role
    What would change this

    Selection of a technology partner and a site plan for the demonstration SMR at Pelindaba. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Necsa's March 2026 expression-of-interest document for the Pelindaba SMR demonstration plant lists, within the strategic partner's indicative scope, integrating the plant with local capability for fuel development, manufacturing processes and waste management solutions. It assigns no spent-fuel responsibility and names no storage or disposal arrangement for the plant. Last checked 23 Oct 2026. Expression of Interest (EOI): SMR Development Partner, EOI Number FIN-SCM-EOI-0001 (file 'NECSA SMR EOI - Final.pdf' in the published tender package)
    What would change this

    A request for proposals, partner agreement, license application or environmental assessment for the Pelindaba demonstration plant that sets spent-fuel and waste arrangements would change this answer. Next scheduled check: 23 Apr 2027.

Evidence dates

(1 of 7 sources with a publication or document date)
Latest dated listed source publication: Expression of Interest (EOI): SMR Development Partner, EOI Number FIN-SCM-EOI-0001 (file 'NECSA SMR EOI - Final.pdf' in the published tender package): 31 Mar 2026.Latest dated recorded event: no date recorded.6 of 7 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(7)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Necsa SMR demonstration reactor at Pelindaba — https://smrmap.com/projects/necsa-pelindaba-smr-demo/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Necsa SMR demonstration reactor at Pelindaba”. Record reviewed 6 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/necsa-pelindaba-smr-demo/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.