Projects / France · Announced
Otrera precursor (first demonstration) reactor at CEA Marcoule
This demonstration proposal is from Otrera New Energy, a CEA spin-off developing a sodium-cooled fast reactor, which aims to start a first demonstrator in 2032.
Current status
- How current
- General record check . Bounded evidence review . None of the 4 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Regional press reported in September 2026 that it presented its ambition to build this precursor at the CEA Marcoule site by 2032-2035. Otrera's own releases and the CEA page do not name the site, CEA has not confirmed it as host, and the precursor's specifications are not published.
Key facts
- Design
- Design profile not linked (SMR)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- Not recorded
- Vendor for linked design
- No selected-design vendor recorded
- Location
- CEA Marcoule center · France · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Marcoule site (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); center-area point for the CEA Marcoule center that press reports name, not a selected parcel. - Coordinates
- 44.1433, 4.7094 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: module
- Thermal capacity
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- low
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Otrera precursor (first demonstration) reactor at CEA Marcoule is recorded at CEA Marcoule center, Occitanie, France. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'marcoule-nuclear-power-plant-g1' (44.1433, 4.7094)
Electrical output is not recorded on this project. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerOtrera New Energy · source
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
- Customer or offtaker
CEA's Otrera start-up page says each Otrera reactor could cogenerate 110 MWe and 180 MWth for factories and towns through local energy loops. That is the general business model. Neither that page, Sfen's 14 April 2026 article nor TV Sud's 4 September 2026 report names a recipient of heat or power from a Marcoule precursor. CEA: Otrera, réacteur à neutrons rapides refroidi au sodium
- Contractor
CEA's start-up page says Otrera signed a France 2030 collaboration contract with CEA, which licensed it five patents, and Sfen's 14 April 2026 article says Otrera envisages the CEA Marcoule site for its first demonstration unit. The CEA collaboration is company-level technology licensing, and CEA's possible role as host is not confirmed. No engineering or construction contractor is named for a Marcoule precursor. CEA: Otrera, réacteur à neutrons rapides refroidi au sodium; Sfen RGN: Otrera et Hexana s'installent dans les territoires historiques du nucléaire
- Funding and government decisions
TV Sud reported on 4 September 2026 that Otrera presented an ambition to build a precursor at Marcoule by 2032-2035 with an investment of about 1.5 billion euros mentioned, and that EDF joined Otrera's capital in 2026. The figure is an estimate and EDF's stake is company equity. No funder or instrument for the Marcoule precursor is stated. TV Sud Magazine: Hexana, Otrera, MGH Energy, plusieurs milliards d'euros de projets autour de Marcoule
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
CEA's Otrera start-up page says Otrera's reactors would reuse spent fuel assemblies now stored in pools and can also use HALEU, running ten years without refuelling. That is a design and business description. No fuel supplier, quantity or delivery is named for a Marcoule precursor. CEA: Otrera, réacteur à neutrons rapides refroidi au sodium
- Comparable schedule revision
Comparable schedule revision not established. Sfen reported on 14 April 2026 that Otrera's first demonstration unit should come in 2032, and CEA's start-up page gives 2032 for a first industrial demonstrator. TV Sud on 4 September 2026 reported an ambition for a Marcoule precursor by 2032-2035. The later horizon still includes 2032 and no source says the date was moved, so this is not a recorded revision. Sfen RGN: Otrera et Hexana s'installent dans les territoires historiques du nucléaire; TV Sud Magazine: Hexana, Otrera, MGH Energy, plusieurs milliards d'euros de projets autour de Marcoule
Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes, 1 not yet reviewed)
- Evidence review. TV Sud on 4 September 2026 reported that Otrera presented an ambition to place a precursor site at Marcoule in 2032-2035. Sfen on 14 April 2026 says the first demonstration unit should appear in 2032 at a separate site and that Otrera notably envisages the CEA site at Marcoule. The CEA startup page says Otrera counts on starting a first industrial demonstrator in 2032 and does not name that site in the project text. The same page describes a business model of selling the technology and operating or co-operating reactors, which does not identify the operator of a Marcoule unit. Its per-reactor figure of 110 MWe and 180 MWth is not stored for this precursor. Stored operator Otrera is not established in this source scope; Otrera stays the proposer, and the single demonstrator count stays. Last checked 19 Oct 2026. TV Sud Magazine: Hexana, Otrera, MGH Energy, plusieurs milliards d'euros de projets autour de Marcoule; Sfen RGN: Otrera et Hexana s'installent dans les territoires historiques du nucléaire; CEA: Otrera, réacteur à neutrons rapides refroidi au sodium
What would change this
A CEA or Otrera instrument that names the demonstrator site and the host or operator, rather than a press ambition or an envisaged implantation. Next scheduled check: 19 Jan 2027.
- Design identified: Not disclosed in the reviewed evidence. The CEA page describes Otrera’s sodium-cooled fast reactor and a per-reactor cogeneration figure. It does not name a design version for the Marcoule precursor, so no design id or 110 MWe rating is proposed. Last checked 19 Oct 2026. CEA: Otrera, réacteur à neutrons rapides refroidi au sodium
What would change this
An Otrera or CEA specification that ties a named design version and output to this precursor. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Sources conflict. Cited press identifies Marcoule as an envisaged location. The earlier CEA page does not name a site, which is not contrary evidence. No selected parcel, coordinates or CEA hosting commitment is established. Last checked 19 Oct 2026. TV Sud Magazine: Hexana, Otrera, MGH Energy, plusieurs milliards d'euros de projets autour de Marcoule; Sfen RGN: Otrera et Hexana s'installent dans les territoires historiques du nucléaire; CEA: Otrera, réacteur à neutrons rapides refroidi au sodium
What would change this
A CEA host confirmation, or an Otrera decision that either selects Marcoule or names a different site. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next regulatory step is ASNR's opinion on the OTRERA ONE safety options Otrera filed on 30 July 2026; Otrera told the French nuclear society's journal in April 2026 that its first demonstration unit should follow in 2032 on a separate site, possibly CEA Marcoule. The 2032 date is a company target and no site decision is recorded in these sources. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants; Sfen RGN: Otrera et Hexana s'installent dans les territoires historiques du nucléaire
What would change this
ASNR's safety-options opinion, a Marcoule hosting agreement, or a revised Otrera schedule. Next scheduled check: 23 Apr 2027.
- Permissions and public process. ASNR's small-reactor page, updated 14 October 2026, says Otrera filed on 30 July 2026 a request for ASNR's opinion on the safety options chosen for its OTRERA ONE small modular reactor, listed as a 200 MWth demonstrator or prototype. A safety-options opinion is a pre-application step, not an authorization, and these sources show no creation-authorization application or public consultation for a demonstration unit at CEA Marcoule. Last checked 23 Oct 2026. ASNR, PRM projects and their fuel-fabrication plants
What would change this
ASNR's opinion on the OTRERA ONE safety options, or a site agreement or consultation for Marcoule. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). The French nuclear society's journal reported on 14 April 2026 that Otrera's first demonstration unit should be built in 2032 on a site separate from its planned Les Pieux factory, and that Otrera is considering in particular the CEA site at Marcoule. That is a site under consideration; the source names no agreement with CEA, plot, grid or water arrangement. Last checked 23 Oct 2026. Sfen RGN: Otrera et Hexana s'installent dans les territoires historiques du nucléaire
What would change this
An agreement between Otrera and CEA on hosting the demonstrator at Marcoule, or a site announcement. Next scheduled check: 23 Apr 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- TV Sud Magazine: Hexana, Otrera, MGH Energy, plusieurs milliards d'euros de projets autour de Marcoule (news report, accessed 2 Oct 2026)
- Sfen RGN: Otrera et Hexana s'installent dans les territoires historiques du nucléaire (news report, accessed 2 Oct 2026)
- CEA: Otrera, réacteur à neutrons rapides refroidi au sodium (government, accessed 2 Oct 2026)
- ASNR, PRM projects and their fuel-fabrication plants (regulator, accessed 3 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Otrera precursor (first demonstration) reactor at CEA Marcoule — https://smrmap.com/projects/otrera-marcoule/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Otrera precursor (first demonstration) reactor at CEA Marcoule”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/otrera-marcoule/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.