Projects / Ukraine · Announced

Energoatom SMR at the Trypilska thermal plant site

In December 2024 Energoatom named the Trypilska thermal power plant site in Kyiv Oblast as the first prospective SMR location, with design documentation in preparation.

Current status

Stage
Announced
How current
General record check . Bounded evidence review . The listed source has no publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

No design, capacity or license is established.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Energoatom
Vendor for linked design
No selected-design vendor recorded
Location
Trypilska thermal power plant · Ukraine · precision: site area (named plant, laboratory, base, port, campus or parcel)
Plant point from the Wikipedia article for the Trypilska thermal power plant, the site Energoatom names as the first prospective SMR location; plant-area point, not a selected plot.
Coordinates
50.13506, 30.74811 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Energoatom SMR at the Trypilska thermal plant site is recorded at Trypilska thermal power plant, Kyiv Oblast, Ukraine. Operator: Energoatom. Recorded vendor: No selected-design vendor is recorded. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: Wikipedia: Trypilska thermal power plant (article coordinates), Article coordinate 50.13506, 30.74811 on 'Trypilska thermal power plant', read 30 October 2026

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

Energoatom's 11 December 2024 statement, republished by the Kolomyia district administration, says SMRs could supplement Energoatom's own fleet and names the Trypilska thermal plant site as the first prospective location, replacing old or damaged thermal units. It names no buyer of power or heat from a Trypilska reactor. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)

Contractor

Energoatom's 11 December 2024 statement says project documentation and calculations for the Trypilska site are being prepared, without saying who prepares them, and lists separate cooperation agreements with Holtec, EDF, Westinghouse, Rolls-Royce and NuScale that it does not assign to Trypilska. No design, vendor, engineering or construction contractor is named for the site. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)

Funding and government decisions

Energoatom's 11 December 2024 statement says Energoatom, wholly state-owned, takes full responsibility for deploying SMR technology in Ukraine, but states no amount, budget or financing for a reactor at the Trypilska site or for the cooperation agreements it lists. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

Energoatom's 11 December 2024 statement says Ukrainian law allows nuclear material only in state ownership, a general legal point, and names no fuel supplier, quantity or delivery for a Trypilska reactor. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)

Comparable schedule revision

Comparable schedule revision not established. Energoatom's 11 December 2024 statement says SMRs could join its fleet in the next decade, a general horizon, and dates only past cooperation agreements. It gives no construction or operation date for Trypilska, so no revision is shown. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Reactor supplier; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes, 1 not yet reviewed)
  • Evidence review. The 11 December 2024 Energoatom statement, republished by the Kolomyia district administration, says the Trypilska thermal plant site is being considered as the first prospective place for small modular reactors and that project documentation and calculations are already being prepared. The same statement lists separate Holtec, EDF, Westinghouse, Rolls-Royce and NuScale cooperation items and does not select one of them for Trypilska. The general ceiling of up to 400 MW is a definition of the technology class, not this plant's rating. No license is stated. Last checked 20 Oct 2026. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)
    What would change this

    A design selection or a permit that names the Trypilska plant site and a reactor model. Next scheduled check: 20 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. The Trypilska sentence names no reactor model. The Holtec, NUWARD, AP300, Rolls-Royce and NuScale sentences are separate cooperation items, and the up-to-400 MW phrase is a class definition. Last checked 20 Oct 2026. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)
    What would change this

    A document that selects one model for the Trypilska site. Next scheduled check: 20 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The statement says the Trypilska thermal plant site is being considered as the first prospective place. Consideration is not a selected plot, and the page gives no coordinates. The map shows a plant-area point for the named thermal plant. Last checked 20 Oct 2026. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)
    What would change this

    A siting decision that fixes a plot at the Trypilska plant. Next scheduled check: 20 Jan 2027.

  • Next decision and prerequisites. The next step Energoatom names in its December 2024 statement is preparing design documentation and calculations for the Trypilska site; no design, vendor, capacity or date is given. Energoatom lists memoranda with several vendors elsewhere in the statement, none tied to Trypilska. Last checked 23 Oct 2026. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)
    What would change this

    Energoatom's selection of a design or vendor for Trypilska, or completion of its design documentation. Next scheduled check: 23 Apr 2027.

  • Permissions and public process: Not disclosed in the reviewed evidence. Energoatom's December 2024 statement on SMR deployment names Trypilska as the first prospective site and says Energoatom takes full responsibility for deploying SMR technology because nuclear material in Ukraine may only be state-owned. It does not mention a license application to the nuclear regulator, an environmental assessment or public consultation for Trypilska. Last checked 23 Oct 2026. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)
    What would change this

    A regulatory filing, environmental assessment or public hearing for an SMR at the Trypilska site. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Energoatom's statement, republished by a Ukrainian regional administration in December 2024, says Ukrenergo gave Energoatom a list of 18 sites where small modular reactors could replace old or damaged thermal-plant units, and that the Trypilska thermal plant site is considered the first prospective location, with design documentation and calculations being prepared. A prospective site with documents in preparation is not a secured land, grid or water arrangement. Last checked 23 Oct 2026. Energoatom: SMR technologies in Ukraine (Trypilska TPP site)
    What would change this

    Completion of the Trypilska design documentation or a site decision by Energoatom. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 1 source with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: no date recorded.1 of 1 listed source has no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(1)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Energoatom SMR at the Trypilska thermal plant site — https://smrmap.com/projects/trypilska-smr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Energoatom SMR at the Trypilska thermal plant site”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/trypilska-smr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.