Projects / China · Construction
Xuwei nuclear heating and power plant Unit 3 (HTGR)
Xuwei Phase I pairs two large Hualong One units with Unit 3, a multi-module high-temperature gas-cooled reactor plant for steam and power.
Current status
- How current
- General record check . Bounded evidence review . 8 of 14 listed sources have a publication or document date recorded here; the newest is 10 Nov 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: NNSA construction license 国核安证字第2621号 for Xuwei Phase I Unit 3 (HTGR) (2 Nov 2026); NNSA approval of the Xuwei HTGR safety design criteria (31 Aug 2026); MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit) (17 Apr 2024). No operating license or other operating authority is recorded as issued. All permissions and applications
- Latest development
- 6 Nov 2026 · First concrete: Xuwei Unit 3 HTGR pours first nuclear-island concrete. Construction of the Unit 3 high-temperature gas-cooled reactor formally started on 6 November 2026 with the first nuclear-island concrete. Source: Tsinghua University: 'Chilong-1' high-temperature gas-cooled reactor formally starts construction (published 10 Nov 2026); China National Nuclear Power announcement 2026-066: first nuclear-island concrete for Xuwei Phase I Unit 3 (dated 6 Nov 2026). Updates entry
More on this development
Reported by the technology developer and the owner's parent company; no regulator or IAEA PRIS record of the pour has been read.
- Next dated milestone
- Planned step: 2031 (target). Xuwei Phase I (all three units) full completion expected. This is not an achieved milestone. Source: paper.people.com.cn: Xuwei Phase I full completion expected (published 3 Aug 2026).
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Design identified; Module/unit count (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Operation or grid target (type stated) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
NNSA identifies CNNC Sueneng Nuclear Power Company as the operating organization. The Unit 3 construction-license review began in June 2025; its safety design criteria were approved on 31 August 2026. NNSA’s 9 October 2026 report on a 15–18 September pre-construction inspection found that site management and technical preparations met the conditions for issuing a construction license, and set seven corrective requirements. Neither document grants a construction license or records first concrete. On 2 November 2026 NNSA issued Unit 3 construction license 国核安证字第2621号 to CNNC Sueneng, valid to 1 November 2036, and said the company may begin pouring the first concrete for the nuclear-island foundation. China National Nuclear Power's exchange announcement of 6 November 2026 said first nuclear-island concrete was planned for that day, and Tsinghua University, the technology developer, reported on 10 November that Unit 3 (“炽龙一号”) formally started construction on 6 November with the first nuclear-island concrete poured, so the stage is Construction. The announcement rates the unit at 660 MW with a 60-year design life. The regulator classifies the HTGR as a small nuclear power reactor. The ecology ministry's siting-stage environmental approval of 17 April 2024 (环审〔2024〕43号) names the HTGR unit as an HTR-PM600S unit; whether that designation is the HTR-PM600 design profile or a variant is not established, so no design link is added. Its module count and output basis remain unresolved; reported plant output is not assigned to a module. The Hualong One units are outside scope. An unapproved later HTGR is not added as a deployment.
Key facts
- Design
- Design profile not linked (SMR)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- CNNC Sueneng Nuclear Power Company
- Vendor for linked design
- No selected-design vendor recorded
- Location
- Jiangsu Xuwei nuclear heating and power plant · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Xuwei plant's HTR-PM entry (unit 3) (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); plant-area point at the Xuwei nuclear heating and power plant, not a surveyed unit position. - Coordinates
- 34.625076, 119.508261 · site-area point (approximate)
- Electrical capacity
- 660 MWe (gross/net unspecified) · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded. NNSA describes the Xuwei HTGR as a multi-module plant with one turbine and sets a per-module probabilistic safety target, but does not state the number of reactor modules.
- Purpose
- Power plant
- Construction start
- 6 Nov 2026Xuwei Unit 3 (HTGR) first nuclear-island concrete
- Inclusion basis
- SMR by regulator classification
- Confidence
- high
- Record reviewed
- 18 Oct 2026Evidence review 4 Nov 2026. How current names both.
Site and capacity notes
Xuwei nuclear heating and power plant Unit 3 (HTGR) is recorded at Jiangsu Xuwei nuclear heating and power plant, Jiangsu, China. Operator: CNNC Sueneng Nuclear Power Company. Recorded vendor: No selected-design vendor is recorded. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'jiangsu-xuwei-nuclear-power-plant-1-3' (34.625076, 119.508261)
Recorded electrical output is 660 MWe (gross/net unspecified), scope plant. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerCNNC Sueneng Nuclear Power Company · source
- Operator or intended licensed owner
- Customer or offtaker
Source-backed project statement China Energy News reported on 27 May 2024, citing the siting-stage environmental report, that the Xuwei nuclear heating plant will supply industrial steam to the petrochemical base in Lianyungang's Xuwei New Area and use spare heat for power. Phase I is two Hualong One units and one high-temperature gas-cooled unit, so that steam role includes this unit and is not this unit alone. No individual buyer or steam contract is named. China Energy News: Jiangsu Xuwei nuclear heating plant Phase I
- Contractor
- Planned construction contractorChina Energy Engineering Jiangsu Electric Power Construction No 3 Company · sourceWith CNNC Huachen, awarded the CNY4.2 billion conventional-island construction contract for the three Phase I units in September 2025; the nuclear island is not included.
- Planned construction contractorChina National Nuclear Huachen Construction Engineering Company · sourceWith Jiangsu Electric Power Construction No 3, awarded the CNY4.2 billion conventional-island construction contract for the three Phase I units in September 2025; the nuclear island is not included.
Source-backed project statement
World Nuclear News reported on 13 August 2026 that a consortium won the conventional-island construction contract for all three Phase I units in September 2025, so unit 3's conventional island sits inside a three-unit award. The same report says CNNC planned to procure the unit 3 high-temperature reactor engineering contract from CNNC Energy Technology, with a shareholder review set for 17 August 2026. That procurement is a plan, not a confirmed award, and it is separate from the Shidaowan demonstration. WNN: CNNC to procure contract for high-temperature reactor
- Funding and government decisions
- Funder or lender named for this projectChina National Nuclear Power Co., Ltd. · sourceControlling shareholder (51%) of Phase I, which covers two Hualong One units and this HTGR unit; amounts not stated.
- Funder or lender named for this projectLianyungang Jinlian Energy Investment Co., Ltd. · sourceShareholder (29%) of Phase I, which covers two Hualong One units and this HTGR unit; amounts not stated.
- Funder or lender named for this projectJiangsu Guoxin Group Co., Ltd. · sourceShareholder (20%) of Phase I, which covers two Hualong One units and this HTGR unit; amounts not stated.
Source-backed project statement
China Energy News reported on 27 May 2024 that Phase I, two Hualong One units and one high-temperature gas-cooled unit, is jointly invested by China National Nuclear Power, Lianyungang Jinlian Energy Investment and Jiangsu Guoxin Group in shares of 51, 29 and 20 percent. No amount paid is stated. A 13 August 2026 report of an RMB 10.3 billion estimate for the proposed unit 3 engineering contract is a cost estimate still subject to an agreement, not money paid. China Energy News: Jiangsu Xuwei nuclear heating plant Phase I; WNN: CNNC to procure contract for high-temperature reactor
Not found in the sources we checked (2): Fuel; Comparable schedule revision
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
The 13 August 2026 procurement report, NNSA's June 2025 and 2026 unit 3 notices, and the 27 May 2024 project report describe the high-temperature unit's role, contract plan and licensing. None names a fuel supplier, fabricator or delivery for unit 3. WNN: CNNC to procure contract for high-temperature reactor; NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; China Energy News: Jiangsu Xuwei nuclear heating plant Phase I
- Comparable schedule revision
Comparable schedule revision not established. World Nuclear News reported on 13 August 2026 that first concrete for the unit 3 high-temperature reactor was expected by the end of 2026. NNSA's September 2026 inspection was still a pre-concrete check and does not state a second date. NNSA's 2 November 2026 construction license lets the company begin that pour and gives no date for it. One stated target is not a revision, and unit 1's January 2026 concrete belongs to a different unit. WNN: CNNC to procure contract for high-temperature reactor; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
Not recorded in SMRMap's reviewed evidence (3): Reactor supplier; Site host or owner; Programs and agreements naming the project
- Reactor supplier
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · First concrete
Xuwei Unit 3 HTGR pours first nuclear-island concrete - · Construction permission recorded
Construction license issued for Xuwei Unit 3 - Report dated · Recorded development
Xuwei preparations meet construction-license conditions - · Other regulatory action recorded
NNSA approves safety design criteria for the Xuwei high-temperature reactor - · Environmental decision recorded
Environmental decision recorded: MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit)
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · First concrete · Met on
Xuwei Unit 3 (HTGR) first concrete expected - Target · Planned step
Xuwei Phase I, all three units, expected to be fully completed in 2031
Dates on the project record: Construction permit: 2 Nov 2026.
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- NNSA construction license 国核安证字第2621号 for Xuwei Phase I Unit 3 (HTGR)
Construction permission · Issued / approved · NNSA · decided 2 Nov 2026 · permit 国核安证字第2621号
China's nuclear regulator reported on 26 June 2025 that it had started the construction-license review for Unit 3 of the Xuwei nuclear heating and power plant, covering the preliminary safety analysis report and the construction-stage environmental impact report, with CNNC Sueneng Nuclear Power presenting the high-temperature gas-cooled reactor. That notice gives no filing day and no license decision. The 9 October 2026 pre-construction inspection report found that preparations met the conditions for issuing a construction license and set seven corrective requirements; it does not itself issue the license. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction license 国核安证字第2621号 for Unit 3 to CNNC Sueneng, valid to 1 November 2036, and says the company may begin pouring the first concrete for the nuclear-island foundation. The license requires an operating-license application before first fuel loading. It is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Sources: NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
Environmental decision
- MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit)
Environmental decision · Issued / approved · MEE · decided 17 Apr 2024
The Ministry of Ecology and Environment approved the siting-stage environmental impact report for Xuwei Phase I on 17 April 2024 (环审〔2024〕43号). The approval describes Phase I as two Hualong One pressurized-water units and one HTR-PM600S high-temperature gas-cooled reactor unit with supporting facilities at Xizoushan, Xuwei New Area, Lianyungang. It is an environmental decision for the siting stage covering the whole Phase I project, of which Unit 3 is the HTGR; it is not a construction license. The Hualong One units are outside SMRMap's scope.
Sources: MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号
Other applications and decisions
- NNSA approval of the Xuwei HTGR safety design criteria
Other regulatory action · Issued / approved · NNSA · decided 31 Aug 2026
NNSA instrument 国核安发〔2026〕161号, signed 31 August 2026, approves B-version safety design criteria for the Xuwei HTGR. Its later 29 September announcement describes a small nuclear power reactor with multiple modules and one turbine. The criteria guide safety review and are not a construction license.
Sources: NNSA: safety design criteria for the Xuwei high-temperature gas-cooled reactor; NNSA: Xuwei HTGR safety design criteria approval, instrument 161
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(10 notes)
- Evidence review. The siting approval names one HTR-PM600S unit at Xizoushan, Xuwei, that the module count inside the plant is not stated, and that no coordinates are given. Later pages start a construction-license review, accept safety design criteria, and record a pre-concrete inspection. None of those pages grants the construction license or states a module count. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction license 国核安证字第2621号 for Unit 3 to CNNC Sueneng as operating organization, valid to 1 November 2036, and says the company may begin the first nuclear-island foundation concrete after an inspection found the site ready. It states no reactor type, design name, module count or rating, and it identifies the unit by the same title as NNSA's instrument for the Unit 3 HTGR design criteria. It does not report the pour, and no opened source does. Last checked 4 Nov 2026. MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号; NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; NNSA: safety design criteria for the Xuwei high-temperature gas-cooled reactor; NNSA: Xuwei HTGR safety design criteria approval, instrument 161; NNSA: Xuwei Unit 3 pre-construction inspection report; WNN: China starts construction of innovative nuclear project; WNN: CNNC to procure contract for high-temperature reactor; Huaihe River Commission water-abstraction permit for the Xuwei plant; Lianyungang government: Xuwei nuclear heating and power plant; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
What would change this
A report of first concrete for the Unit 3 nuclear-island foundation, or a notice that states how many modules that unit contains. Next scheduled check: 20 Jan 2027.
- Design identified. The ecology ministry's siting-stage approval of 17 April 2024 names the HTGR unit as one HTR-PM600S high-temperature gas-cooled reactor unit, and its construction-stage environmental approval of 2 November 2026 (环审〔2026〕123号) again describes Unit 3 as one planned HTR-PM600S unit with supporting facilities. CNNP's announcement of 6 November 2026 says the unit uses domestic high-temperature gas-cooled reactor technology, and Tsinghua's 10 November 2026 notice names Unit 3 as the 'Chilong-1' (炽龙一号) high-temperature gas-cooled reactor, a technology brand built by Tsinghua University and CNNC. None of these, and not the 2 November 2026 construction license, says whether HTR-PM600S or 'Chilong-1' is the same as the HTR-PM600 design profile, so a design label is identified but no design link is proposed. Last checked 13 Nov 2026. MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号; Ministry of Ecology and Environment: construction-stage environmental approval for Xuwei Phase I Unit 3 (环审〔2026〕123号); Tsinghua University: 'Chilong-1' high-temperature gas-cooled reactor formally starts construction; China National Nuclear Power announcement 2026-066: first nuclear-island concrete for Xuwei Phase I Unit 3; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
What would change this
A CNNC, Tsinghua or NNSA document stating the Unit 3 reactor design and its relation to HTR-PM600 or the 'Chilong-1' brand. Next scheduled check: 12 Feb 2027.
- Site location recorded as disclosed. The official environmental approval places Phase I at Xizoushan, Xuwei New Area, Lianyungang, Jiangsu. No coordinates are given. Last checked 18 Oct 2026. MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号
What would change this
A license or environmental report giving the Unit 3 site boundary or coordinates. Next scheduled check: 18 Jan 2027.
- Module/unit count: Not disclosed in the reviewed evidence. NNSA describes the Xuwei HTGR as a multi-module plant with one turbine and sets a per-module probabilistic safety target, but does not state the number of reactor modules. The ministry approval and the trade report give one HTGR unit and a 660 MWe plant figure without a module count. The 2 November 2026 construction license and its notice do not state a module count either. Last checked 4 Nov 2026. NNSA: safety design criteria for the Xuwei high-temperature gas-cooled reactor; WNN: CNNC to procure contract for high-temperature reactor; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
What would change this
A PSAR summary or CNNC release stating the number of reactor modules. Next scheduled check: 18 Jan 2027.
- Map coordinates: Not disclosed in the reviewed evidence. The siting-stage approval names Xizoushan but gives no coordinates; no opened source gives coordinates for Unit 3. Last checked 18 Oct 2026. MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号
What would change this
A construction-stage environmental report or license giving site coordinates. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. NNSA issued the unit 3 construction license on 2 November 2026 and said the company may begin pouring the first concrete for the nuclear-island foundation, which is the next consequential step; no opened source reports it. The license also requires an operating-license application before first fuel loading. NNSA's 9 October 2026 letter, which did not issue the license, had said preparations met the conditions for one and required seven corrective actions to be reported to NNSA and the East China supervision station. World Nuclear News reported on 13 August 2026 that signing the high-temperature reactor engineering contract was a prerequisite for first concrete and that shareholders were to review that procurement on 17 August; that meeting's result is not in the sources read. Last checked 4 Nov 2026. NNSA: Xuwei Unit 3 pre-construction inspection report; WNN: CNNC to procure contract for high-temperature reactor; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
What would change this
A report of first concrete for unit 3's nuclear-island foundation, an operating-license application, or a CNNC notice that the engineering contract was signed. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Ministry of Ecology and Environment approved the Phase I siting-stage environmental report on 17 April 2024 for two Hualong One units and one HTR-PM600S unit. NNSA opened the unit 3 construction-license review on 26 June 2025 and on 31 August 2026 accepted that unit's high-temperature reactor safety design criteria. An NNSA inspection on 15–18 September 2026, reported in a letter of 9 October 2026, found that preparations met the conditions for a construction license and set seven corrective requirements; the letter does not issue the license. NNSA issued construction license 国核安证字第2621号 on 2 November 2026. No decision on the unit's construction-stage environmental report was opened. Last checked 4 Nov 2026. MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号; NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; NNSA: Xuwei HTGR safety design criteria approval, instrument 161; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
What would change this
An NNSA operating-license decision for Xuwei unit 3, or a ministry decision on its construction-stage environmental report. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The 17 April 2024 approval places Phase I, including the one HTR-PM600S unit, at Xizoushan in Lianyungang's Xuwei New Area and says the siting is compatible with land-use planning, water-resource planning and nearshore marine zoning. It also requires a feasibility study of cooling-water source design. No land title, grid connection or water-withdrawal permit is stated. Last checked 23 Oct 2026. MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号
What would change this
A land instrument, grid-connection agreement or water permit for the Xuwei unit 3 site. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The 17 April 2024 approval says that, when the plant's low and intermediate level waste disposal plan is set, the final destination of that waste must be stated. The unit 3 design-criteria approval, the October 2026 inspection and the November 2026 construction license do not state a spent-fuel, waste-contract or closure arrangement. An instruction to specify a destination later is not an arrangement. Last checked 4 Nov 2026. MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号; NNSA: Xuwei HTGR safety design criteria approval, instrument 161; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
What would change this
An NNSA or operator document naming spent-fuel or waste arrangements for Xuwei unit 3. Next scheduled check: 21 Jan 2027.
- Operation or grid target (type stated): Not disclosed in the reviewed evidence. No source read states an operation, grid-connection or commercial-operation date for Unit 3 alone. China National Nuclear Power's announcement 2026-066 (6 November 2026) states the planned first-concrete date (6 November), a rated power of 66.0万千瓦 (660 MW) and a 60-year design life, but no operation date. Tsinghua's 10 November 2026 notice of the start of construction gives no operation date. NNSA's license 2621 (2 November 2026) runs to 1 November 2036 and requires an operating-license application before first fuel loading; that is a license term, not an operation target (carried from the 4 November 2026 capture, not re-read). The only dated figure on record is a whole-Phase-I completion expected in 2031 (China Energy News, 3 August 2026, stored as an event of type other); that newspaper PDF could not be re-read this session, and it is not a Unit 3 date. Searched in Chinese on 13 November 2026. Last checked 13 Nov 2026. China National Nuclear Power announcement 2026-066: first nuclear-island concrete for Xuwei Phase I Unit 3; Tsinghua University: 'Chilong-1' high-temperature gas-cooled reactor formally starts construction; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3
What would change this
A CNNP or CNNC periodic report or announcement, a Jiangsu or NNSA document, or a State Council approval text giving a Unit 3 operation or commercial-operation year. Next scheduled check: 12 Feb 2027.
Evidence dates
(8 of 14 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(14)
- NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched (regulator, accessed 2 Oct 2026)
- NNSA: safety design criteria for the Xuwei high-temperature gas-cooled reactor (regulator, accessed 2 Oct 2026)
- Lianyungang government: Xuwei nuclear heating and power plant (government, accessed 2 Oct 2026)
- Huaihe River Commission water-abstraction permit for the Xuwei plant (government, accessed 2 Oct 2026)
- WNN: China starts construction of innovative nuclear project (news report, accessed 2 Oct 2026)
- WNN: CNNC to procure contract for high-temperature reactor (news report, accessed 17 Oct 2026)
- NNSA: Xuwei HTGR safety design criteria approval, instrument 161 (regulator, dated 31 Aug 2026, accessed 13 Oct 2026)
- NNSA: Xuwei Unit 3 pre-construction inspection report (regulator, dated 9 Oct 2026, accessed 13 Oct 2026)
- MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号 (government, dated 17 Apr 2024, accessed 16 Oct 2026)
- China Energy News: Jiangsu Xuwei nuclear heating plant Phase I (news report, published 27 May 2024, accessed 21 Oct 2026)
- NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3 (regulator, dated 2 Nov 2026, accessed 4 Nov 2026)
- China National Nuclear Power announcement 2026-066: first nuclear-island concrete for Xuwei Phase I Unit 3 (company, dated 6 Nov 2026, accessed 10 Nov 2026)
- Tsinghua University: 'Chilong-1' high-temperature gas-cooled reactor formally starts construction (academic, published 10 Nov 2026, accessed 10 Nov 2026)
- Ministry of Ecology and Environment: construction-stage environmental approval for Xuwei Phase I Unit 3 (环审〔2026〕123号) (government, dated 2 Nov 2026, accessed 13 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Xuwei nuclear heating and power plant Unit 3 (HTGR) — https://smrmap.com/projects/xuwei-htgr-unit3/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Xuwei nuclear heating and power plant Unit 3 (HTGR)”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/xuwei-htgr-unit3/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.