Projects / China · Construction

Xuwei nuclear heating and power plant Unit 3 (HTGR)

Xuwei Phase I pairs two large Hualong One units with Unit 3, a multi-module high-temperature gas-cooled reactor plant for steam and power.

Current status

Stage
Construction
How current
General record check . Bounded evidence review . 8 of 14 listed sources have a publication or document date recorded here; the newest is 10 Nov 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: NNSA construction license 国核安证字第2621号 for Xuwei Phase I Unit 3 (HTGR) (2 Nov 2026); NNSA approval of the Xuwei HTGR safety design criteria (31 Aug 2026); MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit) (17 Apr 2024). No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
6 Nov 2026 · First concrete: Xuwei Unit 3 HTGR pours first nuclear-island concrete. Construction of the Unit 3 high-temperature gas-cooled reactor formally started on 6 November 2026 with the first nuclear-island concrete. Source: Tsinghua University: 'Chilong-1' high-temperature gas-cooled reactor formally starts construction (published 10 Nov 2026); China National Nuclear Power announcement 2026-066: first nuclear-island concrete for Xuwei Phase I Unit 3 (dated 6 Nov 2026). Updates entry
More on this development

Reported by the technology developer and the owner's parent company; no regulator or IAEA PRIS record of the pour has been read.

Next dated milestone
Planned step: 2031 (target). Xuwei Phase I (all three units) full completion expected. This is not an achieved milestone. Source: paper.people.com.cn: Xuwei Phase I full completion expected (published 3 Aug 2026).
Selected limitations
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Design identified; Module/unit count (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Operation or grid target (type stated) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

NNSA identifies CNNC Sueneng Nuclear Power Company as the operating organization. The Unit 3 construction-license review began in June 2025; its safety design criteria were approved on 31 August 2026. NNSA’s 9 October 2026 report on a 15–18 September pre-construction inspection found that site management and technical preparations met the conditions for issuing a construction license, and set seven corrective requirements. Neither document grants a construction license or records first concrete. On 2 November 2026 NNSA issued Unit 3 construction license 国核安证字第2621号 to CNNC Sueneng, valid to 1 November 2036, and said the company may begin pouring the first concrete for the nuclear-island foundation. China National Nuclear Power's exchange announcement of 6 November 2026 said first nuclear-island concrete was planned for that day, and Tsinghua University, the technology developer, reported on 10 November that Unit 3 (“炽龙一号”) formally started construction on 6 November with the first nuclear-island concrete poured, so the stage is Construction. The announcement rates the unit at 660 MW with a 60-year design life. The regulator classifies the HTGR as a small nuclear power reactor. The ecology ministry's siting-stage environmental approval of 17 April 2024 (环审〔2024〕43号) names the HTGR unit as an HTR-PM600S unit; whether that designation is the HTR-PM600 design profile or a variant is not established, so no design link is added. Its module count and output basis remain unresolved; reported plant output is not assigned to a module. The Hualong One units are outside scope. An unapproved later HTGR is not added as a deployment.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
CNNC Sueneng Nuclear Power Company
Vendor for linked design
No selected-design vendor recorded
Location
Jiangsu Xuwei nuclear heating and power plant · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Xuwei plant's HTR-PM entry (unit 3) (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); plant-area point at the Xuwei nuclear heating and power plant, not a surveyed unit position.
Coordinates
34.625076, 119.508261 · site-area point (approximate)
Electrical capacity
660 MWe (gross/net unspecified) · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded. NNSA describes the Xuwei HTGR as a multi-module plant with one turbine and sets a per-module probabilistic safety target, but does not state the number of reactor modules.
Purpose
Power plant
Construction start
6 Nov 2026Xuwei Unit 3 (HTGR) first nuclear-island concrete
Inclusion basis
SMR by regulator classification
Confidence
high
Record reviewed
18 Oct 2026Evidence review 4 Nov 2026. How current names both.
Site and capacity notes

Xuwei nuclear heating and power plant Unit 3 (HTGR) is recorded at Jiangsu Xuwei nuclear heating and power plant, Jiangsu, China. Operator: CNNC Sueneng Nuclear Power Company. Recorded vendor: No selected-design vendor is recorded. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'jiangsu-xuwei-nuclear-power-plant-1-3' (34.625076, 119.508261)

Recorded electrical output is 660 MWe (gross/net unspecified), scope plant. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Customer or offtaker

Source-backed project statement China Energy News reported on 27 May 2024, citing the siting-stage environmental report, that the Xuwei nuclear heating plant will supply industrial steam to the petrochemical base in Lianyungang's Xuwei New Area and use spare heat for power. Phase I is two Hualong One units and one high-temperature gas-cooled unit, so that steam role includes this unit and is not this unit alone. No individual buyer or steam contract is named. China Energy News: Jiangsu Xuwei nuclear heating plant Phase I

Contractor
Source-backed project statement

World Nuclear News reported on 13 August 2026 that a consortium won the conventional-island construction contract for all three Phase I units in September 2025, so unit 3's conventional island sits inside a three-unit award. The same report says CNNC planned to procure the unit 3 high-temperature reactor engineering contract from CNNC Energy Technology, with a shareholder review set for 17 August 2026. That procurement is a plan, not a confirmed award, and it is separate from the Shidaowan demonstration. WNN: CNNC to procure contract for high-temperature reactor

Funding and government decisions
Source-backed project statement

China Energy News reported on 27 May 2024 that Phase I, two Hualong One units and one high-temperature gas-cooled unit, is jointly invested by China National Nuclear Power, Lianyungang Jinlian Energy Investment and Jiangsu Guoxin Group in shares of 51, 29 and 20 percent. No amount paid is stated. A 13 August 2026 report of an RMB 10.3 billion estimate for the proposed unit 3 engineering contract is a cost estimate still subject to an agreement, not money paid. China Energy News: Jiangsu Xuwei nuclear heating plant Phase I; WNN: CNNC to procure contract for high-temperature reactor

Not found in the sources we checked (2): Fuel; Comparable schedule revision
Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

The 13 August 2026 procurement report, NNSA's June 2025 and 2026 unit 3 notices, and the 27 May 2024 project report describe the high-temperature unit's role, contract plan and licensing. None names a fuel supplier, fabricator or delivery for unit 3. WNN: CNNC to procure contract for high-temperature reactor; NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; China Energy News: Jiangsu Xuwei nuclear heating plant Phase I

Comparable schedule revision

Comparable schedule revision not established. World Nuclear News reported on 13 August 2026 that first concrete for the unit 3 high-temperature reactor was expected by the end of 2026. NNSA's September 2026 inspection was still a pre-concrete check and does not state a second date. NNSA's 2 November 2026 construction license lets the company begin that pour and gives no date for it. One stated target is not a revision, and unit 1's January 2026 concrete belongs to a different unit. WNN: CNNC to procure contract for high-temperature reactor; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3

Not recorded in SMRMap's reviewed evidence (3): Reactor supplier; Site host or owner; Programs and agreements naming the project
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Targets

Planned, target and estimated dates are not achievements or commitments.

Dates on the project record: Construction permit: 2 Nov 2026.

Permissions and applications

Construction applications and decisions

Environmental decision

Other applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(10 notes)

Evidence dates

(8 of 14 sources with a publication or document date)
Latest dated listed source publication: Tsinghua University: 'Chilong-1' high-temperature gas-cooled reactor formally starts construction: 10 Nov 2026.Latest dated listed source document: China National Nuclear Power announcement 2026-066: first nuclear-island concrete for Xuwei Phase I Unit 3: 6 Nov 2026.Latest dated recorded event: Xuwei Unit 3 (HTGR) first nuclear-island concrete: 6 Nov 2026.6 of 14 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(14)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Xuwei nuclear heating and power plant Unit 3 (HTGR) — https://smrmap.com/projects/xuwei-htgr-unit3/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Xuwei nuclear heating and power plant Unit 3 (HTGR)”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/xuwei-htgr-unit3/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.