China SMR projects
Projects · Agreements · Permissions
22 tracked projects and proposals in this directory. Named proposals, demonstrations and achieved deployments retain their recorded stages.
Announced: 9 · Siting: 6 · Licensing: 1 · Construction: 1 · Commissioning: 1 · Operating: 3 · Canceled: 1
Open these projects in Projects (on the map) · Coverage and stage definitions
Counts describe the selected dataset, not a complete national or worldwide census. Sources and check dates are linked from each record.
Country brief
Policy and licensing in China →
Recorded answers for these 22 projects — customer or offtaker: 0 of 22; contractor: 3 of 22; funding and government decisions: 1 of 22; fuel supplier named for this project: 1 of 22; programs and agreements naming the project: 4 of 22. Who is involved, project by project.
Latest recorded developments
Newest first: steps of these projects, the latest step of each of this country's policy measures, and agreements or programs that concern it.
- 6 Nov 2026 · Project · Xuwei nuclear heating and power plant Unit 3 (HTGR): Xuwei Unit 3 HTGR pours first nuclear-island concrete. Updates entry
- 2 Nov 2026 · Project · Xuwei nuclear heating and power plant Unit 3 (HTGR): Construction license issued for Xuwei Unit 3. Updates entry
- 2 Nov 2026 · Project · Huakun One floating reactor platform demonstration at the Taipingling site: NNSA issues site-selection opinion for Huakun One. Updates entry
- Report dated 9 Oct 2026 · Project · Xuwei nuclear heating and power plant Unit 3 (HTGR): Xuwei preparations meet construction-license conditions. Updates entry
- Reported 1 Oct 2026 · Project · Linglong One (ACP100) Changjiang: Linglong One reported in hot functional testing. Updates entry
Next documented targets
Targets are plans, not achievements or commitments.
- Target 2026 · Linglong One (ACP100) Changjiang: Reported target: Linglong One fuel loading and grid connection within 2026. Updates entry
- Target 2031 · Xuwei nuclear heating and power plant Unit 3 (HTGR): Xuwei Phase I, all three units, expected to be fully completed in 2031. Updates entry
Projects
Showing 22 of 22 projects
No projects match these filters. Reset filters
| Project and category | Stage | Design | Capacity | Recorded organizations | Location | Record reviewed |
|---|---|---|---|---|---|---|
| CGN Bohai ACPR50S floating SMR demonstration proposalSMREarlier-plan record | Announced | ACPR50S | — | Bohai Searegion only, no map pin | 2 Oct 2026Latest source 18 Jan 2016Latest event: none dated | |
| CNEC / Zheneng Sanmen HTGR power stationSMR | Siting | HTR-PM600 | — |
| Sanmen HTGR siteZhejiang · town named, no map pin | 2 Oct 2026Latest source: none datedLatest event: none dated |
| CNNC floating SMR demonstration proposal (2016)SMREarlier-plan record | Announced | ACP100S | — |
| Undisclosed | 14 Oct 2026Latest source 15 Jan 2016Latest event: none dated |
| Daqing NHR-200 nuclear heating plant (1990s)SMREarlier-plan record | Licensing | Design profile not linked | 200 MWth (thermal only; nameplate; basis unspecified) |
| Daqing nuclear heating plant siteHeilongjiang · town named, no map pin | 18 Oct 2026Latest source: none datedLatest event 1993 |
| HAPPY200 nuclear heating project at Baishan, JilinSMR | Announced | HAPPY200 | thermal only |
| Baishan nuclear heating project siteJilin · town named, no map pin | 2 Oct 2026Latest source 9 Dec 2019Latest event: none dated |
| HTR-10 high-temperature gas-cooled test reactor, Tsinghua INETSMR | Operating | HTR-10 | 2 MWe (gross/net unspecified) · plant · 10 MWth (nameplate; basis unspecified) |
| INET, Tsinghua University (Changping)Beijing · site-area point (approximate) | 18 Oct 2026Latest source, document dated 7 Apr 2024Latest event Oct 2004 |
| HTR-PM Shidaowan demonstrationSMR | Operating | HTR-PM | 210 MWe (gross) · plant · 500 MWth (nameplate; basis unspecified) |
| Shidaowan / Shidao BayShandong · site-area point (approximate) | 19 Oct 2026Latest source, document dated 20 Aug 2021Latest event 6 Dec 2023 |
| Huakun One floating reactor platform demonstration at the Taipingling siteSMR | Siting | Huakun One floating reactor platform | 50 MWe (gross/net unspecified) · plant · 200 MWth (nameplate; basis unspecified) |
| Taipingling site operations base (harbour basin), HuidongGuangdong · site-area point (approximate) | 6 Oct 2026Latest source, document dated 2 Nov 2026Latest event 2 Nov 2026 |
| Huaneng Xiapu 600 MW HTGR unit (site plan)SMR | Announced | Design profile not linked | — |
| Xiapu nuclear site (Changbiao Island)Fujian · site-area point (approximate) | 2 Oct 2026Latest source: none datedLatest event: none dated |
| Huizhou HuaPeng-1 heating demonstration proposalSMR | Siting | HuaPeng-1 | thermal only |
| Huizhou HuaPeng-1 demonstration location (undisclosed)Guangdong · town named, no map pin | 13 Oct 2026Latest source 8 Jan 2026Latest event: none dated |
| Liaoyuan DHR-400 heating demonstration proposalSMREarlier-plan record | Announced | Yanlong DHR-400 | thermal only |
| Liaoyuan DHR-400 demonstration location (undisclosed)Jilin · town named, no map pin | 13 Oct 2026Latest source, document dated 4 Sep 2023Latest event: none dated |
| Linglong One (ACP100) ChangjiangSMR | Commissioning | ACP100 (Linglong One) | 125 MWe (gross) · module · 385 MWth (nameplate; basis unspecified) |
| Changjiang Nuclear Power Plant siteHainan · site-area point (approximate) | 18 Oct 2026Latest source 1 Oct 2026Latest event 1 Oct 2026 |
| Maoming Green Energy HTGR proposal (Phase 1 planning)SMR | Announced | Design profile not linked | — | Not recorded | Maoming Green Energy / Zero-Carbon Industrial Park (HTGR component)Guangdong · named site, no map pin | 2 Oct 2026Latest source: none datedLatest event: none dated |
| Ningdu multipurpose modular proposal (14th Five-Year plan)SMREarlier-plan record | Announced | Design profile not linked | 600 MWe (gross/net unspecified) · plant | Not recorded | Ningdu multipurpose modular proposal (historical plan)Jiangxi · town named, no map pin | 2 Oct 2026Latest source: none datedLatest event: none dated |
| Ruijin HTR nuclear power proposal (Jiangxi)SMR | Announced | Design profile not linked | — | Not recorded | RuijinJiangxi · town named, no map pin | 2 Oct 2026Latest source: none datedLatest event: none dated |
| Shandong Haiyang integrated small reactor demonstration project (heat only)SMR | Siting | Design profile not linked | 200 MWth (thermal only; nameplate; basis unspecified) | Haiyang nuclear power plant, south-west cornerShandong · site-area point (approximate) | 6 Oct 2026Latest source: none datedLatest event 10 Sep 2024 | |
| Shenyang 2 x 200 MW nuclear heating project (NHR200-I, 2001)SMREarlier-plan record | Canceled | Design profile not linked | thermal only | Not recorded | Shenyang (site not stated)Liaoning · town named, no map pin | 6 Oct 2026Latest source 2024Latest event Apr 2001 |
| SINAP small modular thorium molten-salt research reactor (10 MWe), MinqinSMR | Siting | SINAP small modular thorium molten-salt research reactor (10 MWe) | 10 MWe (gross/net unspecified) · plant · 30 MWth (nameplate; basis unspecified) |
| SINAP Wuwei campus, Hongshagang zone, Minqin countyGansu · site-area point (approximate) | 6 Oct 2026Latest source 12 Mar 2026Latest event Jan 2026 |
| SPIC Jiamusi nuclear heating demonstration (Hongxing site)SMR | Siting | Design profile not linked | 200 MWth (thermal only; nameplate; basis unspecified) |
| Hongxing site, Simajia town, Huachuan county (Jiamusi)Heilongjiang · site-area point (approximate) | 3 Oct 2026Latest source 9 Dec 2019Latest event: none dated |
| TMSR-LF1 thorium molten-salt experimental reactor, WuweiSMR | Operating | TMSR-LF1 experimental molten-salt reactor | 2 MWth (thermal only; nameplate; basis unspecified) |
| Hongshagang industrial cluster, Minqin countyGansu · site-area point (approximate) | 18 Oct 2026Latest source 13 Jan 2026Latest event 1 Nov 2025 |
| Xuwei nuclear heating and power plant Unit 3 (HTGR)SMR | Construction | Design profile not linked | 660 MWe (gross/net unspecified) · plant |
| Jiangsu Xuwei nuclear heating and power plantJiangsu · site-area point (approximate) | 18 Oct 2026Latest source 10 Nov 2026Latest event 6 Nov 2026 |
| Yantai nuclear seawater desalination project (NHR200-I, 2003)SMREarlier-plan record | Announced | Design profile not linked | thermal only | Not recorded | Yantai (site not stated)Shandong · town named, no map pin | 6 Oct 2026Latest source Sep 2005Latest event Mar 2003 |
Research coverage for the 22 matching projects: of 198 answers to nine review questions, 98 have a supported statement, 81 were reviewed with a stated limit and 19 are not reviewed yet. This counts recorded research, not readiness or the likelihood of construction.
No projects match, so there are no answers to count.
Coverage by question
Each project is asked the same nine questions: five commercial questions and four reader questions. Only completed source reviews are counted. A supported statement can describe a conditional plan or preparatory work; read it on the project page. Not disclosed, not applicable, conflicting evidence and source unavailable are reviewed limits. Not reviewed is unfinished research, not a finding that nothing exists. The counts cover every page of matching projects, not only the page shown or the projects chosen for comparison.
| Question | Supported statement | Not disclosed | Not applicable | Conflicting evidence | Source unavailable | Not reviewed | Projects |
|---|---|---|---|---|---|---|---|
| Customer or offtaker | 6 | 16 | 0 | 0 | 0 | 0 | 22 |
| Contractor | 12 | 10 | 0 | 0 | 0 | 0 | 22 |
| Funding | 11 | 11 | 0 | 0 | 0 | 0 | 22 |
| Project fuel commitment | 4 | 18 | 0 | 0 | 0 | 0 | 22 |
| Comparable schedule revision | 2 | 20 | 0 | 0 | 0 | 0 | 22 |
| Permissions and public process | 21 | 0 | 0 | 0 | 0 | 1 | 22 |
| Site dependencies (land, grid, water) | 19 | 2 | 0 | 0 | 0 | 1 | 22 |
| Spent fuel, waste and closure | 8 | 2 | 0 | 0 | 0 | 12 | 22 |
| Next decision and prerequisites | 15 | 1 | 1 | 0 | 0 | 5 | 22 |
| All nine questions | 98 | 80 | 1 | 0 | 0 | 19 | 198 |
Agreements (5)
Agreements, plans, studies and government programs that concern this country. They are not deployment projects and are not counted as projects or reactors.
- China's HTGR Modern Industrial Chain Alliance led by CNNC's Chinergy (2025) — Research program · Active · announced 11 Dec 2025
- SINAP thorium molten-salt reactor program: 100 MWt prototype targeted by 2035 — Research program · Active · announced Nov 2025
- CGN and Tsinghua NHR200-II nuclear district-heating demonstration: NEA-approved preliminary work (2018) — Feasibility or siting study · Status not established · announced Jan 2018
- Guizhou provincial plan for a CGN small-reactor nuclear demonstration (4 x 100 MW, 13th Five-Year Plan draft) — Government program · Status not established · announced Apr 2016
- CNNC ACP100S floating nuclear power plant demonstration program (2016 plan inclusion) — Government program · Status not established · announced Jan 2016
Recorded project permissions and applications
(10)
These documents concern the linked projects only. A country-wide approval is not inferred; design assessments, site permissions, construction permissions and operating authority remain separate.
Site applications and decisions
- NNSA site-selection review opinion No. 2620, Huakun One science and technology demonstration project — Huakun One floating reactor platform demonstration at the Taipingling site
Site permission · Issued / approved · NNSA · decided 2 Nov 2026 · permit 国核安证字第2620号
The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2620号) on 2 November 2026 to CGN Ocean Energy for the Huakun One floating reactor platform and maintenance base at the Taipingling nuclear base in Huidong county. The review found no disqualifying site factor affecting safety that engineering measures could not resolve, and the opinion agrees that design work may proceed on the stated site parameters. It is not a construction license: before holding one the company may not pour seismic Category I foundation concrete or build other safety-important structures.
Sources: NNSA: site-selection review opinion No. 2620 for the Huakun One science and technology demonstration project (2 November 2026) - NNSA site-selection review opinion No. 2414, Haiyang integrated small reactor demonstration — Shandong Haiyang integrated small reactor demonstration project (heat only)
Site permission · Issued / approved · NNSA · decided 10 Sep 2024
The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2414号) on 10 September 2024 for one 200 MWt integrated natural-circulation small PWR and auxiliary facilities at the southwest corner of the Haiyang nuclear plant site. The opinion agrees that design work may proceed on the stated site parameters.
Sources: NNSA: site-selection review opinion No. 2414 for the Shandong Haiyang integrated small reactor demonstration project (10 September 2024)
Construction applications and decisions
- NNSA construction license 国核安证字第2621号 for Xuwei Phase I Unit 3 (HTGR) — Xuwei nuclear heating and power plant Unit 3 (HTGR)
Construction permission · Issued / approved · NNSA · decided 2 Nov 2026 · permit 国核安证字第2621号
China's nuclear regulator reported on 26 June 2025 that it had started the construction-license review for Unit 3 of the Xuwei nuclear heating and power plant, covering the preliminary safety analysis report and the construction-stage environmental impact report, with CNNC Sueneng Nuclear Power presenting the high-temperature gas-cooled reactor. That notice gives no filing day and no license decision. The 9 October 2026 pre-construction inspection report found that preparations met the conditions for issuing a construction license and set seven corrective requirements; it does not itself issue the license. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction license 国核安证字第2621号 for Unit 3 to CNNC Sueneng, valid to 1 November 2036, and says the company may begin pouring the first concrete for the nuclear-island foundation. The license requires an operating-license application before first fuel loading. It is not an operating license. No construction start is recorded; a permit is not a physical construction start.
Sources: NNSA: Xuwei nuclear heating and power plant Phase I Unit 3 construction licence review launched; NNSA: Xuwei Unit 3 pre-construction inspection report; NNSA construction licence 国核安证字第2621号: Xuwei nuclear heating and power plant Phase I Unit 3 - NNSA construction license 国核安证字第2117号 for the Hainan Changjiang multi-purpose modular small reactor demonstration project (Linglong One) — Linglong One (ACP100) Changjiang
Construction permission · Issued / approved · NNSA · decided 1 Jul 2021 · permit 国核安证字第2117号
NNSA issued construction license 国核安证字第2117号 on 1 July 2021, valid to 30 June 2031, after reviewing the construction application and inspecting readiness for the first nuclear-island concrete. The license names 中核海南核电有限公司 and 海南核电有限公司 jointly as the operating organizations. IAEA PRIS reports a different construction-license date, 15 July 2019; the license document carries 1 July 2021, so the PRIS date is kept visible as a conflicting statement and is not treated as the license date. This is a construction license, not an operating license.
Sources: NNSA construction licence 国核安证字第2117号: Hainan Changjiang modular small reactor demonstration project (Linglong One)
Operating-license applications and decisions
- TMSR-LF1 operating license 2307 — TMSR-LF1 thorium molten-salt experimental reactor, Wuwei
Operating authority · Issued / approved · NNSA · decided 7 Jun 2023 · docket 国, 核, 安, 证, 字, 第, 2, 3, 0, 7, 号
NNSA issued operating license 国核安证字第2307号 to SINAP on 7 June 2023, expiring 6 June 2033. The instrument includes separate commissioning hold points; it does not prove their release.
Sources: NNSA: TMSR-LF1 operating licence 2307 - NNSA operating license for the Shidaowan HTR-PM demonstration — HTR-PM Shidaowan demonstration
Operating authority · Issued / approved · NNSA · decided 20 Aug 2021 · permit 国核安证字第2119号
NNSA issued operating license 国核安证字第2119号 on 20 August 2021 for the high-temperature gas-cooled demonstration (CN-44) at Ningjin Town, Rongcheng, Shandong. The holder and operating organization is Huaneng Shandong Shidao Bay Nuclear Power Company, Ltd. Validity runs through 19 August 2061. First fuel loading is the start of operation. Condition 23 sets control points at 15 percent and 65 percent of plant rated electrical power and states no megawatt number. The legal representative named on the license is not stored.
Sources: NNSA operating licence for the Shidaowan high-temperature gas-cooled demonstration (Guohe Anzheng Zi No. 2119); NNSA operating-unit database: Shidaowan high-temperature gas-cooled demonstration - HTR-10 operating license issued in 2014, valid through June 2024 — HTR-10 high-temperature gas-cooled test reactor, Tsinghua INET
Operating authority · Issued / approved · NNSA · decided 15 Jul 2014 · permit 国核安证字1405号
NNSA notice 国核安发〔2014〕158号, dated 15 July 2014, issued operating license 国核安证字1405号 to Tsinghua University's Institute of Nuclear and New Energy Technology for the 10 MW high-temperature gas-cooled experimental reactor. The license is valid through 30 June 2024. Continued operation after that date requires a new application twelve months before expiry. No successor instrument was opened. The extracted license pages do not print a separate issue date; the decision-letter date is used. Personal names on the license are not stored.
Sources: NNSA notice issuing the HTR-10 operating licence (Guohe Anfa [2014] No. 158); NNSA operating licence for HTR-10 (Guohe Anzheng Zi No. 1405) - NNSA first fuel loading license for HTR-10 — HTR-10 high-temperature gas-cooled test reactor, Tsinghua INET
Operating authority · Issued / approved · NNSA · decided 2000
Reported in NNSA's own 2014 letter attachment; the 2000 license instrument itself was not opened, so no license number.
Sources: NNSA: letter on the HTR-10 operating licence (Guohe Anhan [2014] No. 25)
Environmental decision
- MEE siting-stage environmental impact report approval for Xuwei Phase I (including the HTR-PM600S unit) — Xuwei nuclear heating and power plant Unit 3 (HTGR)
Environmental decision · Issued / approved · MEE · decided 17 Apr 2024
The Ministry of Ecology and Environment approved the siting-stage environmental impact report for Xuwei Phase I on 17 April 2024 (环审〔2024〕43号). The approval describes Phase I as two Hualong One pressurized-water units and one HTR-PM600S high-temperature gas-cooled reactor unit with supporting facilities at Xizoushan, Xuwei New Area, Lianyungang. It is an environmental decision for the siting stage covering the whole Phase I project, of which Unit 3 is the HTGR; it is not a construction license. The Hualong One units are outside SMRMap's scope.
Sources: MEE approval of the Jiangsu Xuwei nuclear heating plant Phase I environmental impact report (siting stage), 环审〔2024〕43号
Other applications and decisions
- NNSA approval of the Xuwei HTGR safety design criteria — Xuwei nuclear heating and power plant Unit 3 (HTGR)
Other regulatory action · Issued / approved · NNSA · decided 31 Aug 2026
NNSA instrument 国核安发〔2026〕161号, signed 31 August 2026, approves B-version safety design criteria for the Xuwei HTGR. Its later 29 September announcement describes a small nuclear power reactor with multiple modules and one turbine. The criteria guide safety review and are not a construction license.
Sources: NNSA: safety design criteria for the Xuwei high-temperature gas-cooled reactor; NNSA: Xuwei HTGR safety design criteria approval, instrument 161
Designs developed here (17)
Designs whose developer organization is based in this country. A design developed here is not a deployment here.
The first 12 of 17, alphabetically. All 17 designs in the directory.
Organizations here (27)
The first 12 of 27, alphabetically. All 27 organizations in the directory.
Cite or share this page
SMRMap. “China SMR projects”. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/countries/cn/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.