Stellarium
Land-based multi-module fast reactor planned after ALVIN and MegaAlvin stages. This is a dated NEA catalog profile (assessment cutoff February 2025), not confirmation of current availability, a named deployment, or authorization. Capacity is not assigned where module and plant scope or output basis has not been reconciled.
- Reactor type
- Molten salt reactor. How it works, with a 3D view.
- Projects
- Announced: Stellarium reactors for the Fos-sur-Mer integrated energy hub (2026 MoU). Development status as stated in the catalog dated 14 Feb 2025: Conceptual design.
- Evidence
- 3 sources; first primary source: NEA Small Modular Reactor Dashboard — Third Edition (2025). Record reviewed 2 Oct 2026.
Key facts · Tracked projects · Agreements · Sources · Evidence · Its projects in the table · Compare with other designs
Catalog identity snapshot: 14 Feb 2025 (NEA assessment cutoff). Later technical descriptions, where recorded, are dated separately below. Source review does not establish current availability or a deployment.
Key facts
- Class
- SMR
- Technology
- Molten salt reactor (MSR)
- Coolant
- Molten salt
- Spectrum
- Fast
- Developer / vendor(s) as of 14 Feb 2025
- Stellaria
- Fuel form
- Molten Uranium, Plutonium Chloride (optional minor actinides)
- Development status (as stated)
- Conceptual design
- Reactor vessel
- 7 m tall, 2.3 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 369.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.All vessels to scale10 m bar; a person 1.8 m tallStellarium
7 m tall, 2.3 m across - Inclusion basis
- SMR by design class
- Confidence
- medium
- Not yet recorded
- Expected but not recorded as a structured fact: Module rating. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Record reviewed
- 2 Oct 2026 (record review date, not proof of current availability or a deployment)
All fields
(2 without a known value)
- Module electrical
- Not recorded
- Module thermal
- Not recorded
Tracked deployment projects
- Stellarium reactors for the Fos-sur-Mer integrated energy hub (2026 MoU) — Announced · France
Agreements naming this design (1)
Agreements, plans, studies and government programs whose sources name this design. They are not deployment projects.
- Stellaria and Equinix pre-order agreement for power from Stellarium reactors (2025) — Customer agreement · Active · announced Nov 2025
Concerns France
Design sources
(3)
- NEA Small Modular Reactor Dashboard — Third Edition (2025) (IAEA/NEA, accessed 2 Oct 2026)
Catalog page 224 - IAEA ARIS design record: Stellarium (IAEA/NEA, accessed 2 Oct 2026)
- Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition) (IAEA/NEA, published Jun 2025, accessed 2 Oct 2026)
Evidence and open questions
(2 notes)
- Evidence review. Stellaria's section of the 2024 IAEA SMR Technology Catalogue (third edition, June 2025; contributor material) describes the Stellarium as a 250 MWth / 110 MWe molten chloride salt fast breeder reactor developed by Stellaria, a spin-off of CEA and Schneider Electric, supplying electricity and/or steam to energy-intensive industry and utilities. The fuel salt circulates by natural convection with no moderator, and the typical plant houses two 250 MWth reactors each producing 110 MWe, so 110 MWe is a per-reactor figure with an unstated gross or net basis and the plant holds two reactors. As dated by that edition, a Stellaria, Orano and CEA consortium had a France 2030 grant and had begun discussions with ASN in the preliminary screening framework, which is design-stage engagement, not a project permission. The NEA dashboard (assessment cutoff February 2025) reports no siting information from site owners, and no opened source names Fos-sur-Mer, so the linked Fos-sur-Mer deployment is not connected by these sources. The stored Stellaria vendor, MSR family, molten-salt coolant, fast spectrum, fuel form and 'Conceptual Design' status match the catalog; the rating stays off this identity profile. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition); NEA Small Modular Reactor Dashboard — Third Edition (2025)
What would change this
An ASNR filing or opinion on the commercial Stellarium (as distinct from the ALVIN experimental reactor), a published Fos-sur-Mer siting agreement, or a newer catalog edition. Next scheduled check: 19 Jan 2027.
- Module rating. The 2024 IAEA catalog gives 250 MWth / 110 MWe per Stellarium reactor, and a typical plant of two 250 MWth reactors each producing 110 MWe; the electrical basis (gross or net) is not stated. By standing rule the figure is not stored on this identity profile. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition)
What would change this
A Stellaria design document or ASNR filing for the commercial Stellarium stating a revised rating and its gross or net basis. Next scheduled check: 19 Jan 2027.