How small reactor types work · Designs of this type

How a molten salt reactor works

IMSR400 is a molten salt reactor (MSR): the molten fuel salt is both the fuel and the primary coolant, and the whole primary circuit sits inside the reactor vessel.[1, pp. 337, 338] Two more salt circuits, in series, carry the heat on to steam generators in a separate building.[1, pp. 338, 339]

This page explains the type on one documented design, simplified; other designs of the type can differ. It describes the design, not a project: see the IMSR (Integral Molten Salt Reactor) record. SMRMap tracks 3 projects using it, and each project's record carries its status.

IMSR400 molten salt reactor, simplified side section with numbered partsOn the left, a tall reactor vessel holds graphite with fuel channels low down and primary heat exchangers above it, with pump motors and shutdown drives on top. Solid arrows run from the bottom of the vessel up through the channels, up a central passage, out across the heat exchangers, and down the vessel's outer edge. A second line carries heat out of the top of the vessel to an exchanger on the right, and a third line runs from there to steam generators, which send steam away. Dashed lines bring the second and third circuits back and follow the catalog's schematic, not its text.12345678Core in, 610 °CCore out, 700 °CSteam
Simplified from the IAEA SMR Technology Catalogue 2026, IMSR400 section (printed pages 337–342). Parts and proportions not stated in the source are schematic. The numbers of channels, tubes and pumps are schematic, and emergency heat exchangers are not drawn. The vessel's height and diameter are the catalog's; everything to its right is not to scale. The order of the parts inside the vessel follows the catalog's drawing on printed page 337, and the outer position of the downcomer its schematic on printed page 338. Numbers match the sections below; arrows show the coolant path.
  • Fuel salt, on the route the section's text gives
  • Secondary salt carrying heat out, as the section's text gives
  • Secondary salt coming back, not described in the section's text: drawn from the catalog's schematic
  • Tertiary salt going to the steam generators, as the section's text gives
  • Tertiary salt coming back, not described in the section's text: drawn from the catalog's schematic
  • Steam going on to make electricity or process heat

The parts, numbered as in the figure

1. Reactor vessel

The catalog's table gives the vessel as 18 m high and 4.1 m in diameter, weighing 385 metric tons.[1, p. 337] It holds the fuel salt, the graphite moderator and the heat exchangers, and it runs at low pressure, so there is no pressurizer.[1, p. 339] With what it holds, the vessel forms the Core-unit, which the section says is replaced whole every 7 years, with the fuel salt reused in the next one.[1, p. 339]

2. Graphite moderator with fuel channels

Graphite is the moderator and reflector, and channels through it are the passages the fuel salt flows up.[1, p. 338] Fission happens in the salt as it passes through the graphite; the section says the energy is deposited mainly in the salt itself and in the graphite, which the salt cools.[1, pp. 338, 339]

3. Primary pumps

The pump motors sit above the vessel head, with shafts reaching down and the pump volutes, the pumps' casings, immersed in the fuel salt.[1, p. 339] The primary circuit has several parallel loops, each with its own primary heat exchanger, pump and piping.[1, p. 338] The figure puts the volutes just above the graphite, following the catalog's drawing, which labels upper and lower units of a pumping system.[1, p. 337]

4. Primary heat exchangers

These sit above the graphite core; the heated fuel salt is pumped through them and passes its heat to the secondary salt.[1, p. 339] The section also lists emergency heat exchangers in the Core-unit and says little more about them.[1, p. 339] The catalog's drawing labels them among these exchangers; the figure does not draw them.[1, p. 337]

5. Thimbles and shutdown mechanism

Thimbles house the shutdown mechanism and instruments.[1, p. 339] The section says this mechanism can shut the reactor down promptly by itself, from any plant state.[1, p. 339] The drives on top and the thimbles' reach down into the graphite follow the catalog's drawing.[1, p. 337]

6. Secondary Coolant System

The secondary circuit takes the heat out of the Core-unit and hands it to the tertiary circuit, through an exchanger the catalog's text does not name.[1, p. 339] It has its own pumps, shutoff valves and pipes, and its fluid is a molten salt, though not the fuel salt.[1, p. 339]

7. Tertiary Coolant System

Pumps carry the tertiary salt from the nuclear island to another building.[1, p. 339] The section says two intermediate circuits in series are there to enhance safety and operability.[1, p. 338]

8. Steam generators

The tertiary salt heats these, and they make superheated steam for electricity or process heat.[1, p. 339] They are nitrate salt to water and steam heat exchangers, which the section compares to a solar steam generator.[1, p. 338]

The coolant path

  1. In normal operation the fuel salt comes in at the bottom of the core, at 610 °C, and rises through its upright channels, leaving at 700 °C.[1, pp. 337, 338]
  2. The primary pumps drive the heated salt through the primary heat exchangers above the core.[1, pp. 338, 339]
  3. Cooled, it goes back to the core inlet through a downcomer duct, a passage going down.[1, p. 339]
  4. Secondary salt carries the heat from those exchangers to the tertiary salt, which is pumped to a separate building and heats the steam generators.[1, p. 339]
  5. The section's text does not describe how the secondary and tertiary salts come back.[1, pp. 337–342]
  6. The dashed lines for them follow the catalog's schematic, which also shows the downcomer at the vessel's outer edge and the fuel salt crossing the exchangers from the center outward.[1, p. 338]

Where are the fuel rods and the control rods?

IMSR400 has no fuel rods, and the section says it has no control rods for power control.[1, pp. 337, 340] This is IMSR400. Other molten salt reactors can differ, and the interactive view shows IMSR400 only.

  • Fuel. The fuel is the salt itself: low-enriched uranium fluoride melted together with other fluoride salts.[1, pp. 337, 341]
  • Power control. The section says core temperature does this job, adjusting reactor power to match demand.[1, p. 340]
  • Adding fuel. The section describes regular additions of makeup fuel salt, to make up for the fuel used, instead of changing fuel assemblies.[1, p. 341]
  • Shutdown. A separate shutdown mechanism sits in thimbles, as described above.[1, p. 339]

Design values

These are values listed in the catalog section, which the developer supplied.[1, p. 337] SMRMap's record for IMSR stores no output figure, so its line in the list below shows a dash; the figures here are the catalog section's own.

  • Power. 442 MW(t) of heat and 195 MW(e) of electricity for each operating Core-unit, which is one reactor.[1, pp. 337, 341]
  • The reference plant. Two Core-units, at 884 MW(t) of heat and 390 MW(e) of electricity; the text calls the electrical figure net.[1, p. 337]
  • Pressure. 0.4 MPa in the primary circuit and 0.45 MPa in the secondary.[1, p. 337]
  • Fuel salt temperature. 610 °C at the core inlet and 700 °C at the core outlet.[1, p. 337]
  • Fuel. Uranium enriched under 5%.[1, p. 337]

Designs on SMRMap recorded as this type

24 designs, with 14 tracked projects between them. Each design's type comes from its own record on SMRMap; the example above is one of them, and the others can differ from it.

DesignClassElectrical output Tracked projects
Alvin experimental molten-salt reactorSMR—1
ARC Generator (ARC Reactor)Microreactor—None tracked here
BALDER experimental configurationSMR—1
CMSRSMR—None tracked here
Copenhagen Atomics Waste BurnerSMR—None tracked here
FLEXSMR—None tracked here
FUJISMR—None tracked here
IMSR (Integral Molten Salt Reactor)SMR—3
Jereh Micro Reactor (JMR)Microreactor—None tracked here
LFTRSMR—None tracked here
MARINA (marine molten-salt reactor)SMR35 MWe (gross/net unspecified) · moduleNone tracked here
MCSFR (molten chloride salt fast reactor)SMR—None tracked here
MegAlvinSMR10 MWe (gross/net unspecified) · moduleNone tracked here
Natura MSR-1SMRthermal only (no MWe)1
Natura MSR-100SMR—1
SINAP small modular thorium molten-salt research reactor (10 MWe)SMR10 MWe (gross/net unspecified) · module1
SSR-WSMR—1
Stable Salt Reactor - Thermal Spectrum (SSR-U with optional SSR-Th blanket)SMR300 MWe (gross/net unspecified) · moduleNone tracked here
StellariumSMR—1
Thorcon 500 (TMSR500)SMR250 MWe (gross/net unspecified) · module1
Thorizon OneSMRapproximately 100 MWe (gross/net unspecified) · module1
Thorizon PIONEER nuclear demonstratorSMR—1
TMSR-LF1 experimental molten-salt reactorSMR—1
XAMRSMR—None tracked here

Sources

  1. Small Modular Reactor Technology Catalogue, 2026 edition (contributor material; printed September 2026) — IAEA ARIS (catalog host; profiles supplied by contributors). IMSR400 section, printed pages 337–342. Each section is contributor material; the IMSR400 section was supplied by Terrestrial Energy.