Idaho PUC Order 37049: Kemmerer Unit 1 solicitation waiver

On 22 May 2026 the Idaho Public Utilities Commission waived its solicitation procedure for Rocky Mountain Power's power-purchase agreement for Kemmerer Unit 1, the Natrium reactor. The utility must still provide project information before any later rate filing in which it asks the commission to judge prudence. The order does not permit the reactor and does not approve rate recovery.

Category
Laws, rules and executive directives
Status
In effect
Instrument
commission order · Idaho Public Utilities Commission Order No. 37049, Case No. PAC-E-25-20
Issued by
Idaho Public Utilities Commission
Jurisdiction
Idaho
Affects
State program administration
Effective date
Not recorded
Expiry or completion
None recorded
Operative text
Idaho PUC Order No. 37049, Case PAC-E-25-20 (Final order PDF opened 4 October 2026)
Record reviewed · next review
4 Oct 2026 · 15 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)

Legal and geographic scope

Final commission order served 22 May 2026. It grants Rocky Mountain Power a waiver of the commission's solicitation procedure for a power-purchase agreement for Kemmerer Power Station Unit 1. It also requires project information at least 90 days before a later general rate case or ECAM filing in which the company seeks a prudence determination, and status updates in future integrated resource plans. Staff discussion of ordinary power-purchase cost recovery is not the order.

Not approved or still pending

The order recites the company's description of a 345-megawatt sodium-cooled plant with molten-salt storage. That recital is not a commission capacity finding. No construction permit, operating license, or prudence determination is granted. Idaho funding and an INL siting permit were not opened. (Record checked .)