Projects / United States · Construction

Natrium Kemmerer Unit 1

TerraPower's Natrium demonstration at Kemmerer, Wyoming, is recorded as under construction.

Current status

Stage
Construction
How current
General record check . Bounded evidence review . 15 of 26 listed sources have a publication or document date recorded here; the newest is 23 Sep 2026. A listed page was last updated 7 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: TerraPower Natrium construction permit (9 Mar 2026); Kemmerer Unit 1 exemption for energy-island work before a construction permit (7 May 2025). No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
Reported Sep 2026 · Contract: Bechtel steps away from Natrium Kemmerer Unit 1; TerraPower to rebid EPC contract. Bechtel and TerraPower said in September 2026 that they would move forward separately; Bechtel will finish the on-site Sodium Test & Fill Facility. Source: World Nuclear News: Bechtel steps away from TerraPower project (published 22 Sep 2026); NucNet: TerraPower and Bechtel part ways on Natrium-1 nuclear project in Wyoming (published 23 Sep 2026). Updates entry
More on this development

TerraPower said it would rebid the engineering, procurement and construction contract. No replacement contractor is named; the company's statement that the schedule is unaffected is not a verified milestone.

Next dated milestone
Planned commercial operation: 2031 (planned). Planned step: 2030 (target). TerraPower target: Kemmerer Unit 1 construction completion in 2030. These are not commitments or achieved milestones. Source: NucNet: TerraPower and Bechtel part ways on Natrium-1 nuclear project in Wyoming (published 23 Sep 2026); POWER: TerraPower's Kemmerer 1 enters construction - timeline of the Natrium project (published 23 Apr 2026).
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
Same design
2 tracked: 1 construction, 1 announced. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Sodium-cooled fast reactor. How it works, with a 3D view.
Schematic of Natrium. On the left, a wide reactor vessel inside a guard vessel holds the core low down, with control rods from above, an upper structure, one heat exchanger and one pump.
Schematic of Natrium.

Description

The NRC issued construction permit CPAR-1 on 9 March 2026 to US SFR Owner, LLC, a wholly owned TerraPower subsidiary; TerraPower filed the application on its behalf. The permit authorizes construction only. TerraPower's release of 23 April 2026 announces the official start of construction on Kemmerer Unit 1 and says it is mobilizing roughly 1,600 workers to begin plant construction. SMRMap records that company announcement as the construction start. The release says TerraPower broke ground on the site in June 2024 and began construction on non-nuclear support facilities. It does not say that safety-related or nuclear-island work began in April 2026, and a senator quoted in it refers to the start of construction on the energy island. No primary source recorded here documents a dated first safety-related concrete. An NRC inspection report dated 22 April 2026, the day before TerraPower's announcement, on a quality inspection at TerraPower's facilities on 23 to 26 March, gives as one reason for calling a supplier-evaluation issue minor that construction of the unit has not started. It does not define construction and dates nothing later. Secondary sources disagree: EnergyNote's 2026 overview dates nuclear construction from 23 April, while World Nuclear Association's USA profile, a directory updated 7 October 2026, says TerraPower began non-nuclear plant construction in April 2026, with first safety-related concrete planned for 2027. Neither settles whether safety-related work has begun. Recorded output is 345 MWe, with gross/net unspecified, with 500 MWe recorded separately as a peak. An operating license is not recorded. The NRC lists the unit at 840 MWth (power level on its application page), matching the linked design record. The IAEA’s 2026 reactor tables, which list the unit as planned at 31 December 2025, give 1,040 MWth and 342 MWe gross and net; those figures differ from the NRC thermal rating and the 345 MWe recorded here, and the difference is preserved rather than resolved. The NRC says the unit is supported by DOE's Advanced Reactor Demonstration Program. On 7 May 2025 the NRC issued an exemption allowing specified non-safety-related work on the energy island before a construction permit; it was not a construction permit. In January 2025 TerraPower reported Wyoming Industrial Siting Council approval of its state permit for activities outside NRC jurisdiction. In September 2026 Bechtel, which TerraPower had named in 2020 as its design, licensing, procurement and construction partner, and TerraPower said they would move forward separately. Bechtel said its work had been under an earlier contract phase, before full engineering, procurement and construction (EPC) scope, and that it would stay on site to complete the Sodium Test & Fill Facility. TerraPower said it would rebid the EPC contract; no replacement contractor is named. TerraPower's stated schedule is construction completion in 2030 and commercial operation in 2031; these are targets. POWER's 23 April 2026 timeline says US SFR Owner told the NRC it expects to complete construction by February 2031. The two statements are not reconciled here.

Key facts

Design
Natrium (SMR)
Technology
Sodium-cooled fast reactor (SFR) · sodium
Reactor vessel of this design
20.4 m tall, 11.6 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 295.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
US SFR Owner, LLC
Vendor for linked design
TerraPower
Location
Kemmerer Natrium site · United States · precision: town or locality only
NuclearChain reactors export point for Kemmerer unit 1 (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker). The point lies in the town of Kemmerer; the plant site near the retiring coal plant is outside the town, so this is a town-level point, not the site.
Coordinates
41.7924, -110.5374 · town-level point (approximate)
Electrical capacity
345 MWe (gross/net unspecified) · scope: module
Peak electrical output
500 MWe, recorded separately from the electrical figure above
Thermal capacity
840 MWth (nameplate; basis unspecified)
Modules planned
1
Purpose
Power plant
Construction start
23 Apr 2026TerraPower announces the official start of construction at Kemmerer Unit 1
Inclusion basis
SMR by design class
Confidence
high
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.

Could not be confirmed on . Attempted official source: U.S. NRC: Natrium Kemmerer Unit 1. This is an access or status observation only; the record review date is unchanged.

Site and capacity notes

Natrium Kemmerer Unit 1 is recorded at Kemmerer Natrium site, Wyoming, United States. Operator: US SFR Owner, LLC. Recorded vendor: TerraPower. Stage: Construction. Location precision: town or locality only; town-level point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'kemmerer-nuclear-power-plant-1' (41.7924, -110.5374)

Recorded electrical output is 345 MWe (gross/net unspecified), scope module. Modules planned: 1. A peak of 500 MWe is recorded separately from that figure. Recorded thermal output is 840 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Customer or offtaker
  • Customer / offtakerPacifiCorp (Rocky Mountain Power) · sourceUtah regulators (1 June 2026) found Rocky Mountain Power's decision to enter into a power purchase agreement with US SFR Owner, LLC in the public interest; earlier testimony called it proposed; signature not confirmed.
Source-backed project statement

The Public Service Commission of Utah's 1 June 2026 order approved Rocky Mountain Power's application and a settlement concerning a power purchase agreement with US SFR Owner, the TerraPower subsidiary building Kemmerer Unit 1, to buy energy from the plant. The order approves the utility's decision. It does not state when the agreement was signed. Public Service Commission of Utah: order approving Rocky Mountain Power's Natrium PPA waiver application (Docket 25-035-55)

Contractor

Source-backed project statement World Nuclear News reported on 22 September 2026 that Bechtel, TerraPower's design, licensing, procurement and construction partner since 2020, and TerraPower would move forward separately; Bechtel would complete the Sodium Test & Fill Facility, and TerraPower would rebid the EPC contract; that report named no replacement EPC contractor. Separately, TerraPower announced on 31 August 2026 the selection of 12 supplier awards for equipment and design for Kemmerer Unit 1 and the sodium test and fill facility, such as control rod drive design by BWXT Canada. These are equipment and design supplier awards; the release does not identify an EPC appointment. World Nuclear News: Bechtel steps away from TerraPower project; TerraPower Awards Next Round of Vendor Contracts for Natrium Reactor

Funding and government decisions
Source-backed project statement

DOE's article on the March 2026 construction permit says Natrium is one of two Advanced Reactor Demonstration Program projects and was awarded cost-shared DOE funding for design and licensing, fuel development and two supporting facilities. DOE's 13 October 2020 announcement awarded TerraPower 80 million dollars in initial funding and said DOE would invest 3.2 billion dollars over seven years across the program, subject to future appropriations, with industry matching funds. The current Natrium cost-share total and amounts disbursed are not stated in the sources read. DOE Natrium construction permit; DOE: first awards under the Advanced Reactor Demonstration Program (13 Oct 2020)

Fuel
  • Fuel supplier named for this projectASP Isotopes Inc. · sourceASP Isotopes announced definitive initial-core HALEU supply agreements for Natrium on 19 May 2025, dependent on a planned Pelindaba enrichment facility; the announcement is not evidence of delivery or current facility status.
  • Fuel form stated for NatriumMetallic uranium-zirconium (U-10Zr) HALEU fuel column with a sodium bond to HT9 cladding
  • Enrichment stated for NatriumHALEU
Source-backed project statement

ASP Isotopes announced on 19 May 2025 that it and certain subsidiaries had entered into definitive agreements with TerraPower, including an initial-core HALEU supply agreement intended to support the first fuel cores for the Natrium project in Wyoming. A separate ten-year agreement covers up to 150 metric tonnes of HALEU supplied to TerraPower from 2028 through 2037; that total is not allocated entirely to this project. The announcement described a proposed enrichment facility at Pelindaba, South Africa, with initial production expected in 2027 subject to required permits and licenses. This is an attributed supply-agreement announcement, not evidence of completed fuel fabrication or delivery. The cited announcement does not establish the facility's current construction or licensing status. TerraPower's own statement on these agreements was not read. TerraPower announces strategic agreement (ASP Isotopes HALEU); POWER: TerraPower's Kemmerer 1 enters construction - timeline of the Natrium project; ASP Isotopes Inc. enters into Definitive Agreements with TerraPower (GlobeNewswire release, Finviz copy)

Programs and agreements naming the project
Comparable schedule revision

Source-backed project statement GeekWire reported in December 2022 that TerraPower expected Kemmerer's start of operation to be delayed by at least two years from its original 2028 target because HALEU would not be ready. That reported delay concerns the same start-of-operation target and is a minimum, not an exact revised year. NucNet's September 2026 construction-completion and commercial-operation targets are different milestones and are not used to construct a 2028-to-2031 revision pair. TerraPower warns of 2-year minimum delay for launch of demo reactor due to Russia-Ukraine war – GeekWire; NucNet: TerraPower and Bechtel part ways on Natrium-1 nuclear project in Wyoming

Not recorded in SMRMap's reviewed evidence (1): Site host or owner
Site host or owner

Timeline

Recorded developments

Earlier developments (7)

Targets

Planned, target and estimated dates are not achievements or commitments.

Dates on the project record: Planned commercial operation: 2031 (planned); Construction permit: 9 Mar 2026.

Permissions and applications

Construction applications and decisions

Other applications and decisions

Assessments of the design (not of this site)

(1)
  • Natrium UK Generic Design Assessment — applies to the design, not to a site
    Design assessment sought · Under review · ONR/EA (UK)
    The UK regulators began a three-step Generic Design Assessment of TerraPower's Natrium on 5 June 2026, after ministers at the Department for Energy Security and Net Zero asked them to, following the department's review of TerraPower's application. Step 1 is preparatory. No step is recorded as completed, and the assessment is not permission for any UK site.
    Sources: Environment Agency: assessing new nuclear reactor designs

    Status confirmed on against Environment Agency: assessing new nuclear reactor designs. This confirms the recorded status only; the general record check date remains separate.

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes)
  • Evidence review. Kemmerer Unit 1 is TerraPower's Natrium sodium-cooled fast reactor demonstration in Lincoln County, Wyoming. It is supported by DOE's Advanced Reactor Demonstration Program. The NRC's project page lists 840 megawatts thermal. DOE describes a 345-megawatt electric reactor whose molten-salt storage can boost output to 500 megawatts. TerraPower's 23 April 2026 release says 345 MW, with storage up to 500 MW. TerraPower applied for a construction permit in March 2024 on behalf of US SFR Owner, LLC, its wholly owned subsidiary. On 9 March 2026 NRC staff issued construction permit CPAR-1 to US SFR Owner, authorizing construction of Unit 1. This followed a hearing on 4 March 2026. The Federal Register copy could not be opened when checked. The permit is for construction only, and DOE says TerraPower must file a separate operating license application before it can operate. Wyoming's Industrial Siting Council permit, announced 14 January 2025, covers only activities outside NRC jurisdiction. TerraPower's release mentions its June 2024 groundbreaking and non-nuclear support work as earlier development and announces an official start of construction on 23 April 2026, without saying that safety-related or nuclear-island work began. Bechtel said on 22 September 2026 that it had begun foundational work for Unit 1 under an earlier contract phase. No opened primary source documents a dated first safety-related concrete. NRC inspection report 99902100/2026-201, dated 22 April 2026, on a quality inspection at TerraPower's facilities on 23 to 26 March 2026, calls one issue minor in part because construction of Unit 1 has not started. It does not define construction. Both dates come before TerraPower's announcement, so it does not date or contradict the 23 April start. The companion report on US SFR Owner, 05000613/2026-201, quotes permit Condition 3.F, which applies before the start of construction as defined by 10 CFR 50.10, and says inspectors verified it was met. Neither report is a site construction inspection. The NRC's Kemmerer page, updated 14 September 2026, lists no inspection record, and the full ADAMS docket listing was not read. EnergyNote's 2026 overview, which gives the permit as 4 March 2026 (the date of the Commission's decision on the uncontested hearing; the NRC issued the permit on 9 March), dates nuclear construction from 23 April; World Nuclear Association's USA profile, a directory updated 7 October 2026, says non-nuclear plant construction began in April 2026 with first safety-related concrete planned for 2027. Neither is a primary record and they disagree. On 22 September 2026 Bechtel and TerraPower said they would move forward separately. TerraPower will rebid the EPC contract, and no replacement is named. Targets are construction completion in 2030 and commercial operation by 2031 (TerraPower via ANS and NucNet, 23 September 2026). POWER's 23 April 2026 timeline says US SFR Owner told the NRC it expects to complete construction by February 2031; no NRC filing with that date was opened, so the statements are not reconciled. TerraPower's January 2025 state application projected fuel load in fall 2030 and commercial operation in fall 2031. The cited DOE and TerraPower descriptions support 345 MWe without specifying gross or net. IAEA RDS-2/46 separately lists Kemmerer Unit 1 at 342 MWe gross and 342 MWe net; that differing rating does not establish the basis of the stored 345 MWe. Last checked 19 Oct 2026. NRC Natrium construction permit context; NRC: TerraPower, LLC — Kemmerer Power Station Unit 1 Application (page updated 14 September 2026); DOE Natrium construction permit; TerraPower construction start Kemmerer; World Nuclear News: Bechtel steps away from TerraPower project; NucNet: TerraPower and Bechtel part ways on Natrium-1 nuclear project in Wyoming; World Nuclear News: Wyoming approves permit for demo Natrium plant; TerraPower: TerraPower Awarded Pivotal State Permit for Natrium Plant (14 January 2025); Federal Register 91 FR 12628 (16 Mar 2026): Kemmerer Power Station Unit 1 construction permit and record of decision; World Nuclear Association — Nuclear Power in the USA; EnergyNote 2026 SMR licensing map; NRC: inspection report 99902100/2026-201, TerraPower (22 April 2026); NRC: inspection report 05000613/2026-201, US SFR Owner (22 April 2026); U.S. NRC: Natrium Kemmerer Unit 1
    What would change this

    TerraPower's operating license application for Kemmerer Unit 1, a named replacement EPC contractor, or an NRC inspection record or TerraPower statement dating first safety-related concrete. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. With the March 2026 construction permit in place, DOE's article says TerraPower must submit a separate operating license application before the plant can run. A TerraPower spokesperson, quoted by NucNet in September 2026 after Bechtel's exit, said the schedule calls for construction completion in 2030 and commercial operation by 2031. The application filing date is not given in these sources, and 2030-2031 are company targets. Last checked 23 Oct 2026. DOE Natrium construction permit; NucNet: TerraPower and Bechtel part ways on Natrium-1 nuclear project in Wyoming
    What would change this

    TerraPower's operating license application filing, or a revised construction or operation date. Next scheduled check: 23 Jan 2027.

  • Permissions and public process. The NRC issued construction permit CPAR-1 for Kemmerer Unit 1 in March 2026; DOE's article on that decision says TerraPower must still file a separate operating license application before the plant can operate. The NRC's October 2025 final environmental impact statement records a 60-day scoping period from June 2024 with a public meeting in Kemmerer, and a 45-day comment period on the draft from June 2025 with two Kemmerer meetings. TerraPower's January 2025 release says Wyoming's Industrial Siting Council permit covers construction and operation outside NRC jurisdiction. No operating license has been issued. Last checked 23 Oct 2026. DOE Natrium construction permit; NUREG-2268, Environmental Impact Statement for the Construction Permit Application for Kemmerer Power Station Unit 1, Final Report; TerraPower: TerraPower Awarded Pivotal State Permit for Natrium Plant (14 January 2025)
    What would change this

    An operating license application for Kemmerer Unit 1, or a challenge to the construction permit or state permit. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). The NRC's October 2025 final environmental impact statement says the site appears to be owned in fee simple by US SFR Owner, 3 miles south of Kemmerer and near PacifiCorp's Naughton Power Plant. It describes two new 5.9-mile 230 kV lines to the Naughton switchyard and a 6-mile pipeline to Naughton's raw-water settling basin, fed from the Hams Fork River. It says easements and land access for those lines and the pipeline were still being sought; a secured grid or water agreement is not shown. Last checked 23 Oct 2026. NUREG-2268, Environmental Impact Statement for the Construction Permit Application for Kemmerer Power Station Unit 1, Final Report
    What would change this

    Executed easements or an interconnection or water-supply agreement for the Naughton tie-ins. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure. The NRC's October 2025 final environmental impact statement says US SFR Owner has no plans to reprocess spent Natrium fuel and would store it onsite until final disposition. The fuel handling building would hold at least 10 years of spent fuel, after which fuel would move to dry storage at an onsite installation whose location is yet to be determined and which is expected by about 2040 under an NRC general license. This is the applicant's stated plan as reviewed for the construction permit, not a built or licensed storage facility; no offsite disposal arrangement is named. Last checked 23 Oct 2026. NUREG-2268, Environmental Impact Statement for the Construction Permit Application for Kemmerer Power Station Unit 1, Final Report
    What would change this

    Siting or licensing of the Kemmerer onsite dry-storage installation, or an operating license application stating a different arrangement. Next scheduled check: 23 Apr 2027.

Evidence dates

(15 of 26 sources with a publication or document date)
Latest dated listed source publication: NucNet: TerraPower and Bechtel part ways on Natrium-1 nuclear project in Wyoming: 23 Sep 2026.Latest dated listed source document: Public Service Commission of Utah: order approving Rocky Mountain Power's Natrium PPA waiver application (Docket 25-035-55): 1 Jun 2026.Latest dated recorded event: Bechtel and TerraPower part ways on Kemmerer Unit 1; EPC contract to be rebid: Sep 2026.11 of 26 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(26)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Natrium Kemmerer Unit 1 — https://smrmap.com/projects/natrium-kemmerer/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Natrium Kemmerer Unit 1”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/natrium-kemmerer/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.