Policy and licensing / Poland

Poland: Polish Nuclear Power Programme, 2026 update (Council of Ministers Resolution No. 198 of 29 September 2026)

Poland's 2026 nuclear power program aims for about 6 to 9 GWe of large Generation III(+) reactors over 2026 to 2038 and describes state support for the first plant. For SMR and other projects outside the program it promises case-by-case, technology-neutral decisions on optional state support and a future SMR roadmap. It funds, licenses or sites no SMR project.

Category
Laws, rules and executive directives
Status
In effect
Instrument
executive order · Uchwała nr 198 Rady Ministrów z dnia 29 września 2026 r. w sprawie aktualizacji programu wieloletniego pod nazwą „Program polskiej energetyki jądrowej” (M.P. 2026 poz. 977)
Issued by
Rada Ministrów (Council of Ministers)
Jurisdiction
Poland
Affects
State program administration, Project funding
In effect from
7 Oct 2026
Expiry or completion
2038 — § 2 sets the program's implementation period at 2026–2038, with a perspective to 2046. The resolution itself states no expiry.
Operative text
Poland: Uchwała nr 198 Rady Ministrów z dnia 29 września 2026 r. w sprawie aktualizacji programu wieloletniego pod nazwą „Program polskiej energetyki jądrowej” (M.P. 2026 poz. 977) (Monitor Polski 2026 poz. 977 (resolution and annexed program, published 6 October 2026))
Record reviewed · next review
29 Oct 2026 · 29 Apr 2027 (dates our review of this record; not a statement of the measure's present legal effect)

Legal and geographic scope

Council of Ministers resolution adopting the updated multi-year Polish Nuclear Power Programme (Program PEJ), made under the development policy act and art. As a Council of Ministers resolution it is a government program act that directs the administration; it is not a statute and creates no rights or obligations for investors. 108d of Prawo atomowe (§ 1). It sets the implementation period at 2026 to 2038 with a perspective to 2046 (§ 2), entrusts coordination to the minister responsible for energy raw materials (§ 3), repeals the 2020 program resolution no. 141 (§ 4) and took effect the day after its publication on 6 October 2026 (§ 5). The program's goal is to build and commission nuclear power plants of about 6 to 9 GWe in total based on proven large-scale Generation III(+) water reactors. It describes the support model for the first plant (EJ1), including debt with 100% State Treasury guarantees and a two-way contract for difference. For nuclear projects outside the program, including SMR projects, it says the government will support them as far as public finances allow, that decisions on optional support instruments follow a case-by-case assessment, that the government follows technology neutrality without preferential conditions for chosen investors or technologies, and that a roadmap for SMRs in Poland will be prepared. Annex 3 lists state budget spending by administration bodies for 2026 to 2038. The resolution funds, licenses or sites no SMR project.

Not approved or still pending

The SMR roadmap the program announces was not found or read. The program's account of the European Commission's state-aid decision for the first large plant was not checked against that decision. No project is recorded here as eligible for or receiving support. (Record checked .)