Projects / Argentina · Suspended

CAREM-25

CAREM-25 is CNEA's Argentine prototype iPWR of 25 MWe net and 100 MWth at Lima, Zárate, shown as suspended after press reported that works ceased early in 2025.

Current status

Stage
Suspended
How current
General record check . Bounded evidence review . 5 of 13 listed sources have a publication or document date recorded here; the newest is 2023 or 30 Oct 2023. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Integral pressurized water reactor. How it works, with a 3D view.
Schematic of CAREM-25. A single pressure vessel holds the core below helical steam generators, with a steam dome at the top.
Schematic of CAREM-25.

Description

IAEA RDS-2/46 lists CAREM25 at 100 MWth, 29 MWe gross and 25 MWe net, with CNEA as operator and supplier. The stored 25 MWe is that net figure. The 2024 IAEA catalog's about 30 MWe is not stored as a second rating. Construction was widely reported incomplete. In April 2026 press reported that works had ceased early in 2025 and that CNEA would downgrade the project's management. No cancellation document was found. RDS-2/46 and PRIS still list it under construction from 25 August 2015. That Member-State listing conflicts with the reported stoppage and is not evidence that work resumed, so the stage stays suspended.

Key facts

Design
CAREM-25 (SMR)
Technology
Integral pressurized water reactor (iPWR) · light water
Operator(s)
CNEA (Argentina)
Vendor for linked design
CNEA (Argentina)
Location
CAREM site (Lima, Zárate) · Argentina · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the CAREM unit beside the Atucha complex at Lima (CC BY 4.0, derived from GEM's tracker); not a surveyed plot. Replaces an earlier hand-rounded point.
Coordinates
-33.9678, -59.21301 · site-area point (approximate)
Electrical capacity
25 MWe (net) · scope: module
IAEA-RDS-2/46 lists CAREM25 at 100 MWth, 29 MWe gross and 25 MWe net.
Thermal capacity
100 MWth (nameplate; basis unspecified)
Modules planned
1
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
9 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

CAREM-25 is recorded at CAREM site (Lima, Zárate), Buenos Aires, Argentina. Operator: CNEA (Argentina). Recorded vendor: CNEA (Argentina). Stage: Suspended. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'carem-nuclear-power-plant' (-33.9678, -59.21301)

Recorded electrical output is 25 MWe (net), scope module. IAEA-RDS-2/46 lists CAREM25 at 100 MWth, 29 MWe gross and 25 MWe net. Modules planned: 1. Recorded thermal output is 100 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Contractor

Source-backed project statement CNEA's undated presentation reports a contract signed with Na-Sa in the first half of 2020 to complete the CAREM25 nuclear building's civil works. This is a historical civil-works contract, not a full EPC award or confirmation of the contractor's status after the later suspension. The presentation's publication date is not established. CNEA presentation by Adriana C. Serquis: CAREM-25 future milestones

Funding and government decisions

Source-backed project statement EconoJournal reported in April 2026, attributing the estimate to the Secretaría de Asuntos Nucleares, that at least roughly US$750 million of capital had been invested in the prototype. This is an attributed press-reported estimate, not a verified current budget, new award or itemized disbursement. EconoJournal: CAREM paused; CNEA to downgrade the project (April 2026)

Fuel
  • Fuel form stated for CAREM-25UO2 pellet
  • Enrichment stated for CAREM-253.1% for the CAREM25 prototype, as given by CNEA in the 2024 IAEA catalog.
Project fuel information is described in the source-backed statement below.
Source-backed project statement

CNEA's annual report for 2013 records a contract signed with CONUAR on 9 October 2013 to manufacture nuclear fuel elements and control-rod assemblies for CAREM. Its CONUAR section describes a five-year contract term. This establishes a historical project-specific fabrication commitment, not current contract validity, completed fuel fabrication or delivery to the suspended project. Those later outcomes are not established by the reviewed report. Small Modular Reactor Technology Catalogue, 2024 edition: CAREM; CNEA: Memoria y Balance Anual 2013, CAREM and CONUAR sections

Comparable schedule revision

Source-backed project statement CAREM-25 has a partial history of changed criticality expectations. POWER's 1 January 2015 article attributed a 2017 criticality target to CNEA, without dating CNEA's statement. An undated CNEA presentation by Adriana C. Serquis separately listed first criticality in the first half of 2025. Its content establishes only that it was prepared no earlier than mid-2021; the conference label and upload path do not establish its statement date or place it precisely in the forecast sequence. World Nuclear News reported on 30 October 2023 that CNEA had expected initial criticality by the end of 2027 in an October 2022 statement. The dated attribution and full sequence remain incomplete, so these accounts are not treated as a single ten-year delay. The reviewed evidence establishes no current criticality target; the recorded 2025 construction suspension is not a revised target date. IAEA PRIS statistics: reactors by country code (Argentina), captured 9 October 2026; EconoJournal: CAREM paused; CNEA to downgrade the project (April 2026); Small Modular Reactors Speaking in Foreign Tongues; CNEA and Nucleoeléctrica sign CAREM SMR agreement - World Nuclear News; CNEA presentation by Adriana C. Serquis: CAREM-25 future milestones

Not found in the sources we checked (1): Customer or offtaker
Customer or offtaker

The 2024 IAEA SMR catalog describes CAREM as an electricity source for regions with small demand that can also support desalination. That is a design application. Neither the catalog, the IAEA PRIS record nor EconoJournal's 2 April 2026 report names a buyer or supply agreement for the CAREM25 prototype's output. Small Modular Reactor Technology Catalogue, 2024 edition: CAREM; EconoJournal: CAREM paused; CNEA to downgrade the project (April 2026)

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. EconoJournal reported on 2 April 2026 that CAREM construction work at the Atucha complex in Lima stopped at the beginning of 2025, that CNEA will downgrade the project management, and that the reported scope is now finishing and starting the prototype. The article calls the prototype 32 MWe, originally 25 MW, and mentions commercial modules of 120 MW as an ambition that was set aside. PRIS, in the 9 October 2026 statistics file, still lists CAREM25 as Under Construction, with 100 MW thermal, 29 MW gross and 25 MW net, and CNEA as operator. An energy-map note says the project was halted at roughly 85 percent in September 2024, while the article says physical progress was 63 percent at the end of 2024. Those percentages and the 32 MWe figure are not stored. No cancellation instrument is quoted. Last checked 20 Oct 2026. EconoJournal: CAREM paused; CNEA to downgrade the project (April 2026); IAEA PRIS statistics: reactors by country code (Argentina), captured 9 October 2026; EnergyNote 2026 SMR licensing map
    What would change this

    A CNEA or government decision that either restarts construction or cancels the prototype. Next scheduled check: 20 Jan 2027.

  • Plant capacity (scope qualified). IAEA-RDS-2/46 lists CAREM25 at 100 MWth, 29 MWe gross and 25 MWe net. The stored 25 MWe is that net figure. The 2024 catalog lists thermal/electrical capacity as 100 / ~30 for CAREM25. That tilde figure is not stored as a second rating. Last checked 19 Oct 2026. IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026); Small Modular Reactor Technology Catalogue, 2024 edition: CAREM
    What would change this

    A CNEA or IAEA document that states one electrical output for the CAREM25 prototype and identifies it as gross or net. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites: Not disclosed in the reviewed evidence. An April 2026 trade-press report says construction at the Atucha site stopped early in 2025 at about 63% physical progress, and that CNEA would downgrade the project's management unit. It reports no decision, date or funding to resume or to terminate the prototype. The last evidenced state is a pause, not a cancellation. Last checked 23 Oct 2026. EconoJournal: CAREM paused; CNEA to downgrade the project (April 2026)
    What would change this

    A CNEA or government decision to resume, re-scope or terminate CAREM-25 construction. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). EconoJournal reported in April 2026 that the CAREM prototype stands inside the Atucha nuclear complex at Lima, with physical progress of about 63% at the end of 2024, mostly civil works, and that CNEA suspended construction work in early 2025. The report describes no grid-connection or cooling-water arrangement. Last checked 23 Oct 2026. EconoJournal: CAREM paused; CNEA to downgrade the project (April 2026)
    What would change this

    A CNEA or regulator document describing CAREM25 site infrastructure or a decision to resume construction. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. Argentina's nuclear regulator (ARN) says in its 2022 annual report that it continued licensing work on the CAREM 25 prototype under the authorization for site use and construction then in force, reviewed a new revision of the project's quality manual and ran its inspection program for construction of the civil structures. That authorization is not an operating license, and the report does not give its date. No later licensing step is recorded in the sources reviewed. Last checked 23 Oct 2026. Informe Anual 2022, Capítulo 4: Seguridad radiológica y nuclear
    What would change this

    A later ARN annual report or resolution on CAREM 25, such as a commissioning authorization or a change after the reported 2025 stoppage. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. CNEA staff's 2022 presentation describes a CAREM-25 pool sized for fuel from ten years of full-power operation, followed by interim dry storage at the reactor site. It also describes long interim storage of radioactive waste on site. Use of the ASECQII facility would require further shielding and cooling assessment; infrastructure needs had not yet been analyzed. These dated design plans do not establish implemented arrangements or a final disposal route, and the project is now recorded as suspended. Last checked 23 Oct 2026. BEFC Considerations for the CAREM (IAEA Technical Meeting presentation)
    What would change this

    An ARN licensing document or CNEA environmental study confirming CAREM-25 spent-fuel storage and its final route, or a restart decision that changes the design. Next scheduled check: 21 Jan 2027.

Evidence dates

(5 of 13 sources with a publication or document date)
Latest dated listed source publication: Informe Anual 2022, Capítulo 4: Seguridad radiológica y nuclear: 2023; CNEA and Nucleoeléctrica sign CAREM SMR agreement - World Nuclear News: 30 Oct 2023; overlapping date precision — latest not uniquely established.Latest dated listed source document: CNEA: Memoria y Balance Anual 2013, CAREM and CONUAR sections: 2013.Latest dated recorded event: no date recorded.8 of 13 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(13)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: CAREM-25 — https://smrmap.com/projects/carem-25/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “CAREM-25”. Record reviewed 9 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/carem-25/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.