Projects / Norway · Siting
Fensfjorden Kjernekraft SMR proposal near Mongstad (Austrheim and Alver)
Fensfjorden Kjernekraft, owned by Norsk Kjernekraft and Austrheim municipality, proposes a nuclear plant of up to 1,200 MW near the Mongstad refinery in Norway.
Current status
- How current
- General record check . Bounded evidence review . 2 of 5 listed sources have a publication or document date recorded here; the newest is 10 Apr 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
It sent a notification with a proposed impact-assessment program to the Energy Ministry on 1 September 2025. In April 2026 it began assessment work for the Mongstad region (Austrheim and Alver). Norsk Kjernekraft's projects are based on commercially available SMR technology; no technology is selected and the capacity figure is not stored. Separate from the Øygarden project. The project's notification describes feasibility work involving Norsk Kjernekraft and DL Energy before Fensfjorden Kjernekraft was established. This is preparatory collaboration; the cited passage does not establish a construction or EPC award.
Key facts
- Design
- Design profile not linked (SMR)
- Technology
- Not recorded on a linked design profile — see the description
- Operator(s)
- Norsk Kjernekraft
- Vendor for linked design
- No selected-design vendor recorded
- Location
- Proposed Fensfjorden site, Austrheim · Norway · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate location stated in the September 2025 notification, Table 1-1, for proposed properties 130/160 and 130/159. This is a proposed site, not a site approval; final plant extent remains subject to assessment. - Coordinates
- 60.792, 5.012 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 3 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Fensfjorden Kjernekraft SMR proposal near Mongstad (Austrheim and Alver) is recorded at Proposed Fensfjorden site, Austrheim, Vestland, Norway. Operator: Norsk Kjernekraft. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025, September 2025 notification, Table 1-1, approximate location of properties 130/160 and 130/159
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorNorsk Kjernekraft
- Contractor
Source-backed project statement The notification describes feasibility work involving Norsk Kjernekraft and DL Energy before Fensfjorden Kjernekraft was established. This is preparatory collaboration; the cited passage does not establish a construction or EPC award. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: locations (ten project companies); Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026)
- Programs and agreements naming the project
- Feasibility or siting study; completedNorwegian Nuclear Commission report (NOU 2026:4): prepare for possible future nuclear power but start no process now…
Not found in the sources we checked (4): Customer or offtaker; Funding and government decisions; Fuel; Comparable schedule revision
- Customer or offtaker
The reviewed sources do not establish a named project-specific power or heat purchaser, contractual quantity or completed offtake. Intended uses, host municipalities and general company customer plans are not buyer commitments. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Norsk Kjernekraft: Austrheim and Norsk Kjernekraft send nuclear assessment notification (1 Sep 2025); Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Taftøy assessment programme set by the government
- Funding and government decisions
The reviewed sources do not establish a project-specific financing commitment or amount. General company backing, ownership and policy support do not by themselves establish allocated or paid project funding. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Taftøy assessment programme set by the government
- Fuel
- No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.
The reviewed sources do not establish a project-specific fuel supplier commitment or delivery. General supply-market plans and reactor-design fuel requirements are kept separate. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026)
- Comparable schedule revision
Comparable schedule revision not established. The reviewed sources do not establish two dated statements revising the same project milestone. A single target, a fleet-level ambition or a different project’s timetable is not a schedule revision. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Damaged table text does not securely associate every year with its milestone; no target is inferred from it. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026); Norsk Kjernekraft: Taftøy assessment programme set by the government
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Reactor supplier; Site host or owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Reactor supplier
- Site host or owner
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. Proposed capacity is up to 1,200 MW, not a selected count or scalar module rating. Austrheim/Mongstad is the candidate area; municipal landownership is named, but no final site selection is established. These notification and assessment accounts do not select a reactor vendor or model. Fensfjorden Kjernekraft is the joint project company and filer; municipal participation is not an operator appointment. The company reports its notification with proposed assessment program on 1 September 2025, not a license. The April 2026 account says this project’s own assessment program remains to be established; work using the separate Trondheimsleia framework is not its approval. Last checked 20 Oct 2026. Norsk Kjernekraft: Austrheim and Norsk Kjernekraft send nuclear assessment notification (1 Sep 2025); Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026)
What would change this
A project-specific adopted assessment program, final site/design selection or permission instrument; preserve the distinction between proposal and approval. Next scheduled check: 20 Jan 2027.
- Design identified: Not disclosed in the reviewed evidence. The notice describes a nuclear plant near Mongstad. It names no reactor model. Last checked 19 Oct 2026. Norsk Kjernekraft: Austrheim and Norsk Kjernekraft send nuclear assessment notification (1 Sep 2025)
What would change this
Fensfjorden Kjernekraft names a reactor model. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed. Fensfjorden Kjernekraft's September 2025 notification identifies proposed properties 130/160 and 130/159 in Austrheim, beside Fensfjorden and FV57, with approximate coordinates 60.792°N, 5.012°E. The proposal covers about 300 dekar; final plant extent remains subject to assessment. Last checked 26 Oct 2026. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025
What would change this
A planning or assessment decision confirming or changing the proposed properties or final plant extent. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next formal step is for the authorities to put the September 2025 notification to public hearing and set the project's impact-assessment program; the April 2026 release says that program had not yet been set. The company started early assessment work on the framework already set for the separate Aure and Heim project. Last checked 23 Oct 2026. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026)
What would change this
The ministry's decision setting this project's assessment program. Next scheduled check: 21 Jan 2027.
- Permissions and public process. Fensfjorden Kjernekraft sent its notification with a proposed impact-assessment program to the Energy Ministry on 1 September 2025; the notification calls this the first of several regulatory steps, followed by a public hearing and the authorities setting the program. The company says open public meetings were held in Austrheim. In April 2026 the project's own program had not yet been set; work began under the framework set for a separate project. No license exists. Last checked 23 Oct 2026. Norsk Kjernekraft: Austrheim and Norsk Kjernekraft send nuclear assessment notification (1 Sep 2025); Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026)
What would change this
The ministry's hearing or decision setting this project's impact-assessment program. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The September 2025 notification places the candidate area beside the Lindås transformer station, with grid options still to be assessed, and treats Fensfjorden as a suitable recipient for cooling-water discharge, with the cooling method still to be studied. The company says Austrheim municipality owns the plot. These are proposals for assessment, not secured grid, water or land agreements. Last checked 23 Oct 2026. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Austrheim and Norsk Kjernekraft send nuclear assessment notification (1 Sep 2025)
What would change this
An adopted assessment program, impact assessment or grid-connection agreement for the Mongstad area site. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The September 2025 notification says the plant would include equipment for treating and interim storage of radioactive waste, with spent fuel cooled in pools before cask storage, and that a separate notification covering a waste facility is filed by Halden Kjernekraft, with cooperation between the two companies. In April 2026 the company said it would study radiation protection and waste first. No waste arrangement or disposal route is established. Last checked 23 Oct 2026. Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025; Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026)
What would change this
An impact assessment or license application describing spent-fuel storage and disposal responsibility. Next scheduled check: 21 Jan 2027.
Evidence dates
(2 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- Norsk Kjernekraft: Austrheim and Norsk Kjernekraft send nuclear assessment notification (1 Sep 2025) (company, accessed 3 Oct 2026)
- Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026) (company, published 10 Apr 2026, accessed 3 Oct 2026)
- Fensfjorden Kjernekraft: notification with proposed assessment programme, September 2025 (company, published Sep 2025, accessed 21 Oct 2026)
- Norsk Kjernekraft: locations (ten project companies) (company, accessed 3 Oct 2026)
- Norsk Kjernekraft: Taftøy assessment programme set by the government (company, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Fensfjorden Kjernekraft SMR proposal near Mongstad (Austrheim and Alver) — https://smrmap.com/projects/fensfjorden-smr/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Fensfjorden Kjernekraft SMR proposal near Mongstad (Austrheim and Alver)”. Record reviewed 3 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/fensfjorden-smr/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.