Projects / China · Siting

SPIC Jiamusi nuclear heating demonstration (Hongxing site)

SPIC's Jiamusi nuclear heating demonstration at the Hongxing site in Huachuan county, China, is a heat-only district-heating project at the siting stage.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 1 of 2 listed sources has a publication or document date recorded here: 9 Dec 2019. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

SPIC's Heilongjiang branch is the owner of the Jiamusi nuclear heating demonstration project at the Hongxing site in Huachuan county. Its environmental impact report, published by the Ministry of Ecology and Environment in August 2020, plans the site for four 200 MWt integrated heating reactors and builds two in phase one, with first concrete then planned for May 2021 subject to state approval. The report applies China's review principles for small pressurized-water reactors and places the project under the state catalog item for multipurpose modular small reactors. No construction approval or later milestone has been found. The design name is not stored.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
SPIC
Vendor for linked design
No selected-design vendor recorded
Location
Hongxing site, Simajia town, Huachuan county (Jiamusi) · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
Site coordinate stated in the 2020 environmental impact report (E 130°32'7.30", N 46°44'22.20"); a published site point, not a surveyed reactor-building location.
Coordinates
46.7395, 130.535361 · site-area point (approximate)
Electrical capacity
thermal only (no MWe) · scope: module
Thermal capacity
200 MWth (nameplate; basis unspecified)
Modules planned
2
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
3 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

SPIC Jiamusi nuclear heating demonstration (Hongxing site) is recorded at Hongxing site, Simajia town, Huachuan county (Jiamusi), Heilongjiang, China. Operator: SPIC. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020), 2020 environmental impact report, site coordinate E 130°32'7.30", N 46°44'22.20"

This project is recorded as thermal only (no MWe). Modules planned: 2. Recorded thermal output is 200 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Customer or offtaker

Source-backed project statement The Jiamusi environmental report published in August 2020 says the plant's heating station would feed the Jiamusi city primary heat network in the heating season and supply steam to a planned biomass power plant on the site's west side outside it, and lists the city heating and gas office's 2019 approval for connecting the project to the city heat network. The recipient is the city heat network. No heat-sale contract or buyer company is named. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)

Contractor

Source-backed project statement China Energy News reported on 9 December 2019 that State Nuclear Power Technology and the Shanghai Nuclear Engineering Research and Design Institute signed, with SPIC's Heilongjiang branch and SPIC's Jilin company, general-contracting framework agreements for the Jiamusi nuclear heating demonstration and the Baishan project. The August 2020 environmental report also shows Suzhou Nuclear Power Research Institute arranging its environmental monitoring. A framework agreement is preparatory, not an EPC contract or construction approval. 中国能源报: 东北两核能供热项目加快推进; MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)

Not found in the sources we checked (3): Funding and government decisions; Fuel; Comparable schedule revision
Funding and government decisions

The Jiamusi environmental report published in August 2020 gives a total investment of 3.886 billion yuan (388,605 ten-thousand yuan), excluding network connection, of which 398.74 million yuan is environmental protection. That is a cost estimate. The report names no funder, financing instrument or approval of the investment. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

The Jiamusi environmental report published in August 2020 says the project uses SAF-6 fuel assemblies and that the owner must engage a qualified carrier and seek approval to use the new-fuel transport container in China. That names the fuel assembly type, not a fabricator, quantity or delivery. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)

Comparable schedule revision

Comparable schedule revision not established. The Jiamusi environmental report published in August 2020 planned simultaneous first concrete for units 1 and 2 on 30 May 2021 and operation on 30 May 2024, subject to the start date approved by the state. That target is stated once in the sources read, and no later date is given, so there is no recorded revision. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Reactor supplier; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(7 notes)
  • Evidence review. The environmental impact report for the SPIC Jiamusi nuclear heating demonstration project, posted by the Ministry of Ecology and Environment in August 2020 (the saved text has no title page; its cited input studies are dated May 2020), places the project at the Hongxing site in Simajia town, Huachuan county, Jiamusi, Heilongjiang, and gives the site coordinates as E 130°32'7.30", N 46°44'22.20". The site is planned for four 200 MWt integrated nuclear heating reactors, and phase one builds two of them (units 1 and 2) for district heating; SPIC's Heilongjiang branch is named as owner responsible for construction and operations management. The report describes the reactor only as integrated heating-reactor technology (a partially integrated, fully natural-circulation design with an external pressuriser) and names no design or vendor. It planned simultaneous first concrete for units 1 and 2 on 30 May 2021 and operation on 30 May 2024, subject to the start date approved by the state. No later instrument (state approval, construction permit or progress) appears in the opened source, so the next documentary decision remains state project approval and a construction permit. The stored siting stage, two 200 MWt reactors with module scope, heat-only basis and SPIC as operator stay; the report's coordinates can be stored as the site point, and the design stays unnamed. Because the planned 2021 start passed with no evidenced follow-up, the project's current status is unverified. Last checked 19 Oct 2026. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)
    What would change this

    A state project approval or National Nuclear Safety Administration construction permit for Jiamusi units 1 and 2, or an SPIC notice that the Hongxing project was deferred or relocated, which would change the stage or status. Next scheduled check: 19 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. The report calls the reactor an integrated nuclear heating reactor of 200 MWt, partially integrated with full natural circulation and an external pressuriser, but gives no design name or vendor. Two bounded searches found no primary source naming the Jiamusi design; a secondary snippet about SPIC's pool-type HAPPY200 does not match the vessel-type description in this report and is not evidence. Last checked 19 Oct 2026. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)
    What would change this

    A National Nuclear Safety Administration construction-permit notice or SPIC project document naming the heating-reactor design for the Hongxing site, which would let design_id be set. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed. The report names the Hongxing site in Simajia town, Huachuan county, Jiamusi, and gives its site coordinates as E 130°32'7.30", N 46°44'22.20" (about 46.73950 N, 130.53536 E). That is the published site point, not a reactor-building survey; the two reactor-island centers are given only in CGCS2000 plane coordinates, which are not converted here. Last checked 19 Oct 2026. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)
    What would change this

    None needed for the site point; a construction-permit document would confirm the site if the project proceeds. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The August 2020 environmental report planned first concrete for units 1 and 2 on 30 May 2021 and start-up on 30 May 2024, with the start date subject to state approval. Both target dates have passed and no state construction approval or later milestone was found, so the next consequential step remains a state decision to approve construction, with no current date in the sources reviewed. Last checked 23 Oct 2026. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)
    What would change this

    A state approval or NNSA construction license, or an SPIC statement deferring or canceling the Jiamusi project. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. The environmental impact report for the SPIC Jiamusi nuclear heating demonstration, published by the Ministry of Ecology and Environment in August 2020, is a filing under review, not a permission; its public participation section says the owner would supply the public participation statement separately. The report lists local preparatory letters but no state construction approval, and no NNSA license or approved report was found in the sources reviewed. Last checked 23 Oct 2026. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)
    What would change this

    An MEE approval of the environmental report, an NNSA construction license or a state approval for the Jiamusi heating reactors. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). The August 2020 environmental report lists a 2019 Jiamusi natural resources bureau letter giving its opinion on site selection and construction land, and a 2019 Jiamusi heating office approval for the plant to connect to the city heat network. It plans land acquisition for all four reactors at once and draws water from the Songhua River, with no cooling-water discharge because all heat goes to district heating. These are local opinions and plans from 2019-2020, not proof that land has been acquired or the connection built. Last checked 23 Oct 2026. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)
    What would change this

    A later land-use permit, heat-supply agreement or construction-stage environmental report for the Jiamusi project. Next scheduled check: 23 Oct 2027.

  • Spent fuel, waste and closure. The August 2020 environmental report plans an on-site spent fuel pool sized for at least ten years of discharged fuel plus a full core, with spent fuel later shipped off site in transport casks once its activity has fallen. It does not name the off-site destination, owner of long-term responsibility or a disposal arrangement in the passages reviewed; these are planned design arrangements, not executed contracts. Last checked 23 Oct 2026. MEE: environmental impact report, SPIC Jiamusi nuclear heating demonstration project (August 2020)
    What would change this

    A construction-stage environmental report or license condition fixing the spent fuel route for the Jiamusi reactors. Next scheduled check: 23 Oct 2027.

Evidence dates

(1 of 2 sources with a publication or document date)
Latest dated listed source publication: 中国能源报: 东北两核能供热项目加快推进: 9 Dec 2019.Latest dated recorded event: no date recorded.1 of 2 listed sources has no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(2)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: SPIC Jiamusi nuclear heating demonstration (Hongxing site) — https://smrmap.com/projects/jiamusi-nuclear-heating/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “SPIC Jiamusi nuclear heating demonstration (Hongxing site)”. Record reviewed 3 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/jiamusi-nuclear-heating/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.