Projects / China · Announced

Maoming Green Energy HTGR proposal (Phase 1 planning)

CNNC/Chinergy Maoming Zero-Carbon / Green Energy park proposal includes an HTGR component.

Current status

Stage
Announced
How current
General record check . Bounded evidence review . None of the 5 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Developer or proposer. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

A 2023 BJX-reported Guangdong energy plan list names Maoming Green Energy Phase 1 as 3 x 200 MW (preliminary preparation); treat that as a dated planning configuration, not three verified reactor modules. CNNC exhibit language pairs Hualong One and HTGR for the park; Hualong capacity is excluded here. design_id remains null; do not inherit HTR-PM module specs. No pin.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Not recorded
Vendor for linked design
No selected-design vendor recorded
Location
Maoming Green Energy / Zero-Carbon Industrial Park (HTGR component) · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
Named Maoming park/project; no verified reactor parcel. Do not use GEM approximate coords as pin without project-named-location evidence package.
Coordinates
Named site, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Maoming Green Energy HTGR proposal (Phase 1 planning) is recorded at Maoming Green Energy / Zero-Carbon Industrial Park (HTGR component), Guangdong, China. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); named site, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Contractor

Source-backed project statement The Foshan Geological Bureau reported on 21 March 2023 that its regional geological survey center carried out the feasibility-study-stage geological survey for the Maoming Green Energy project from early December 2022, and that the results were accepted on 15 March 2023 at a meeting chaired by the owner, CNNC's Chinergy (中核能源科技有限公司). This is a completed preparatory siting survey, not a design or construction contract. Guangdong Foshan Geological Bureau: Maoming Green Energy site geological survey acceptance

Not found in the sources we checked (4): Customer or offtaker; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

CNNC's 25 November 2025 expo report says the Maoming Zero-Carbon Industrial Park plan uses Hualong One and HTGR technology and couples nuclear energy with petrochemical industry, which names a sector, not a buyer. Neither it nor the Foshan Geological Bureau's 21 March 2023 page names a recipient of heat or power from the HTGR component. CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit; Guangdong Foshan Geological Bureau: Maoming Green Energy site geological survey acceptance

Funding and government decisions

CNNC's 25 November 2025 expo report and the Foshan Geological Bureau's 21 March 2023 page state no amount, funder or allocation for the Maoming HTGR component. The saved copy of a June 2023 BJX planning article is a web challenge page and could not be read. CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit; BJX: Guangdong energy project list naming Maoming Green Energy Phase 1 3x200 MW

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

CNNC's 25 November 2025 expo report lists nuclear fuel among expo topics, not as a Maoming supply, and CNNC's 7 December 2023 page on fuel-element manufacturing concerns the HTR-PM demonstrator at Rongcheng in Shandong. Neither names a fuel supplier, allocation or delivery for the Maoming HTGR component. CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit; CNNC EN: Chinergy commercialising modular HTR technology

Comparable schedule revision

Comparable schedule revision not established. The Foshan Geological Bureau's 21 March 2023 page dates only a geological survey, done from December 2022 and accepted on 15 March 2023, and CNNC's 25 November 2025 report dates an expo. Neither gives a construction or operation date for the Maoming HTGR, so no milestone is revised. The HTR-PM dates on CNNC's 2023 page are for Rongcheng. Guangdong Foshan Geological Bureau: Maoming Green Energy site geological survey acceptance; CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit; CNNC EN: Chinergy commercialising modular HTR technology

Not recorded in SMRMap's reviewed evidence (5): Project proposer or applicant; Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes, 2 not yet reviewed)
  • Evidence review. Maoming's green-energy park includes an HTGR component. Guangdong's geological bureau reports acceptance of siting-survey work on 15 March 2023 and names Chinergy as the project client. CNNC's 2025 park exhibit pairs Hualong One and HTGR technologies; it does not select an HTGR model, module count or reactor rating for this proposal. The captured BJX page is a web-application challenge, so its historical 3 × 200 MW configuration was not reconfirmed here. Acceptance of geological work is not a construction permission. Last checked 19 Oct 2026. Guangdong Foshan Geological Bureau: Maoming Green Energy site geological survey acceptance; CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit
    What would change this

    An opened Maoming-specific planning or licensing document naming the HTGR configuration, plot, project companies and next decision. Next scheduled check: 19 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. The Maoming documents name HTGR technology, not a selected model; Shandong HTR-PM specifications do not identify this project. Last checked 19 Oct 2026. CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit
    What would change this

    An opened Maoming-specific planning or licensing document naming the HTGR configuration, plot, project companies and next decision. Next scheduled check: 19 Jan 2027.

  • Developer or proposer. The geological bureau names 中核能源科技有限公司 (Chinergy) as the survey project's client. A separate linked organization identity and reactor operating appointment are not established here. Last checked 19 Oct 2026. Guangdong Foshan Geological Bureau: Maoming Green Energy site geological survey acceptance
    What would change this

    An opened Maoming-specific planning or licensing document naming the HTGR configuration, plot, project companies and next decision. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. Maoming and a park are named. The opened material does not disclose the reactor parcel or boundary. Last checked 19 Oct 2026. Guangdong Foshan Geological Bureau: Maoming Green Energy site geological survey acceptance; CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit
    What would change this

    An opened Maoming-specific planning or licensing document naming the HTGR configuration, plot, project companies and next decision. Next scheduled check: 19 Jan 2027.

  • Permissions and public process. A Tsinghua University Asset Management page says the Guangdong Maoming high-temperature reactor project, among others, has obtained provincial approval to begin preliminary work (a provincial 'road permit'). That allows project preparation; it is not a state project approval or nuclear safety license, and no NNSA siting opinion or environmental approval for the Maoming HTGR is shown in the sources reviewed. Last checked 23 Oct 2026. Tsinghua University Asset Management: regional economic and social development projects
    What would change this

    An NNSA siting opinion, MEE environmental report notice or State Council approval for the Maoming HTGR. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). A March 2023 Guangdong geological bureau item says the geological survey of the near region and site vicinity for the feasibility-study stage of the Maoming Green Energy project, owned by Chinergy, passed expert acceptance. CNNC's November 2025 exhibit describes the Maoming Zero-Carbon Industrial Park as using Hualong One and HTGR technology to supply the petrochemical park. These are a site study and a plan; the parcel, steam offtake and grid arrangements are not described. Last checked 23 Oct 2026. Guangdong Foshan Geological Bureau: Maoming Green Energy site geological survey acceptance; CNNC EN: Maoming Zero-Carbon Industrial Park Hualong One and HTGR exhibit
    What would change this

    A siting-stage environmental report or announcement describing the Maoming HTGR site and its steam and grid connections. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure; Next decision and prerequisites. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 5 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: no date recorded.5 of 5 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(5)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Maoming Green Energy HTGR proposal (Phase 1 planning) — https://smrmap.com/projects/maoming-green-energy-htgr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Maoming Green Energy HTGR proposal (Phase 1 planning)”. Record reviewed 2 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/maoming-green-energy-htgr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.