Projects / South Africa · Canceled
PBMR demonstration power plant at Koeberg (terminated)
Eskom planned a demonstration pebble-bed modular reactor at Koeberg and committed to operate it.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
On 30 January 2007 World Nuclear News reported that the environment minister rejected appeals against the separate Pelindaba pilot fuel plant, and that Earthlife Africa had challenged the Koeberg record of decision in the Cape High Court. South Africa's CNS report says the PBMR licensing application was withdrawn and the project was terminated in 2010. Output and a module count are not stored. Distinct from the 2026 Necsa demonstration at Pelindaba.
Key facts
- Design
- PBMR (Pebble Bed Modular Reactor) (SMR)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Operator(s)
- Eskom
- Vendor for linked design
- PBMR (Pty) Ltd
- Location
- Koeberg nuclear station site (PBMR) · South Africa · precision: site area (named plant, laboratory, base, port, campus or parcel)
Coordinates of the Koeberg station from the NuclearChain reactors export (CC BY 4.0), whose unit points derive from GEM's Global Nuclear Power Tracker; site-area point for a project never built. - Coordinates
- -33.6746, 18.4321 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded. The opened accounts describe one planned demonstration at Koeberg and do not state a module count.
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 19 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
PBMR demonstration power plant at Koeberg (terminated) is recorded at Koeberg nuclear station site (PBMR), Western Cape, South Africa. Operator: Eskom. Recorded vendor: PBMR (Pty) Ltd. Stage: Canceled. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'koeberg-nuclear-power-plant-1' (-33.6746, 18.4321)
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 400 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorEskom
- Reactor supplier
- Vendor for the linked designPBMR (Pty) Ltd
- Customer or offtaker
Source-backed project statement Nuclear Engineering International's 18 November 2025 history says Eskom committed to purchase the PBMR demonstration reactor and to operate it, with the test reactor to be built at Koeberg. Eskom, the planned operator, was therefore the committed buyer of the plant. No separate electricity or process-heat buyer is named, and the project was terminated in 2010. NEI: South Africa revives PBMR project
- Fuel
- Project fuel information is described in the source-backed statement below.
Source-backed project statement World Nuclear News reported on 30 January 2007 that fuel for Eskom's planned PBMR at Koeberg would be manufactured by Necsa at a pilot plant in its BEVA complex at Pelindaba, with raw material from Durban and finished fuel taken to Koeberg. This was a planned fuel arrangement for a project terminated in 2010. No quantity or delivery is reported, and the minister treated the fuel plant and the reactor as separate approvals. WNN: Appeals rejected against PBMR fuel plant
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
- Contractor
World Nuclear News' 30 January 2007 report describes Eskom's application to build the PBMR at Koeberg, and Nuclear Engineering International's 18 November 2025 history says many domestic and foreign subcontractors became involved in the program without naming a Koeberg construction firm. Eskom was the operator and PBMR (Pty) Ltd the vendor. No construction contractor for the demonstration is named, and the project was terminated in 2010. WNN: Appeals rejected against PBMR fuel plant; NEI: South Africa revives PBMR project; South Africa national report, 7th CNS review meeting
- Funding and government decisions
Nuclear Engineering International's 18 November 2025 history says the South African government ceased funding PBMR in 2010 and that ZAR 10 billion had been spent on developing the technology, with a further ZAR 30 billion estimated to commercialise it. Those figures concern the PBMR program as a whole. No source read states a funder, instrument or amount for the Koeberg demonstration itself. NEI: South Africa revives PBMR project
- Comparable schedule revision
Comparable schedule revision not established. World Nuclear News' 30 January 2007 report dates a fuel-plant decision and gives no Koeberg construction date, and South Africa's August 2016 nuclear safety report says the PBMR project was terminated in 2010 after its license application was withdrawn. No earlier and later targets for the same Koeberg milestone appear in the sources read. The 2025 Pelindaba demonstration is a separate record. WNN: Appeals rejected against PBMR fuel plant; South Africa national report, 7th CNS review meeting; NEI: South Africa revives PBMR project
Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. The 30 January 2007 article reports Earthlife Africa's Cape High Court challenge to the Koeberg record of decision, that the CNS report says the PBMR licensing application was withdrawn in 2010, and that Eskom remains the intended operator because it committed to operate the demonstration. Output and module count stay unstored. A 2025 article describes lifting the technology from care and maintenance and a possible demonstration at Pelindaba. That is not a restart of this Koeberg record. Last checked 20 Oct 2026. WNN: Appeals rejected against PBMR fuel plant; South Africa national report, 7th CNS review meeting; NEI: South Africa revives PBMR project
What would change this
A court judgment or NNR notice that states the outcome of the Koeberg record-of-decision challenge. Next scheduled check: 20 Jan 2027.
- Plant capacity (scope qualified): Not disclosed in the reviewed evidence. The opened Koeberg accounts name the demonstration and the separate fuel plant. They do not state an electrical or thermal output for the Koeberg plant, so none is stored. Last checked 19 Oct 2026. WNN: Appeals rejected against PBMR fuel plant
What would change this
A project document that states the Koeberg demonstration's output and its gross or net basis. Next scheduled check: 19 Jan 2027.
- Module/unit count: Not disclosed in the reviewed evidence. The opened accounts describe one planned demonstration at Koeberg and do not state a module count. No count is stored. Last checked 19 Oct 2026. WNN: Appeals rejected against PBMR fuel plant
What would change this
A project document that states how many modules the Koeberg demonstration comprised. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not applicable. The project was terminated in 2010 after its licensing application was withdrawn, so no decision is pending. The government's 2025 decision to lift the PBMR technology from care and maintenance concerns Necsa's revival of the technology, not this Koeberg plant, and is recorded separately. Last checked 23 Oct 2026. South Africa national report, 7th CNS review meeting; NEI: South Africa revives PBMR project
What would change this
A source tying a revived PBMR plan specifically to the Koeberg site. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Koeberg demonstration plant received an environmental record of decision, which World Nuclear News reported in January 2007 had been successfully challenged in the Cape High Court by Earthlife Africa. South Africa's national safety report says the PBMR licensing application was later withdrawn and the project terminated in 2010. No nuclear license was issued. Last checked 23 Oct 2026. WNN: Appeals rejected against PBMR fuel plant; South Africa national report, 7th CNS review meeting
What would change this
None expected for this terminated project; a new application would be a separate record. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Nuclear Engineering International's November 2025 history says the PBMR demonstration reactor was to be built at the Koeberg nuclear plant site north of Cape Town. World Nuclear News reported in January 2007 that Earthlife Africa had successfully challenged in the Cape High Court the environmental record of decision for the Koeberg PBMR, and South Africa's report to the nuclear safety convention says the licensing application was withdrawn and the project terminated in 2010. No site authorization survived. Last checked 23 Oct 2026. NEI: South Africa revives PBMR project; WNN: Appeals rejected against PBMR fuel plant; South Africa national report, 7th CNS review meeting
What would change this
None expected for Koeberg; the 2025 PBMR revival is planned at Pelindaba under a separate record. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. No PBMR reactor was built or operated at Koeberg, so no reactor spent fuel arose; South Africa's convention report says the licensing application was withdrawn and the project terminated in 2010. Nuclear Engineering International reports that PBMR then went into care and maintenance, was reincorporated into Eskom in 2012, and that custodianship of the technology and its remaining facilities, including the fuel development laboratory and helium test facility, has passed to Necsa. These sources do not set out decommissioning costs for those facilities. Last checked 23 Oct 2026. NEI: South Africa revives PBMR project; South Africa national report, 7th CNS review meeting
What would change this
A Necsa or Eskom statement on decommissioning or reuse liabilities of the remaining PBMR facilities. Next scheduled check: 23 Apr 2027.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- South Africa national report, 7th CNS review meeting (government, accessed 2 Oct 2026)
- NEI: South Africa revives PBMR project (news report, accessed 2 Oct 2026)
- WNN: Appeals rejected against PBMR fuel plant (news report, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: PBMR demonstration power plant at Koeberg (terminated) — https://smrmap.com/projects/pbmr-koeberg/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “PBMR demonstration power plant at Koeberg (terminated)”. Record reviewed 19 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/pbmr-koeberg/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.