Projects / Norway · Siting

Taftøy Aure / Heim SMR proposal

Government approved the impact assessment program in February 2026.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 1 of 5 listed sources has a publication or document date recorded here: 10 Apr 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
Announced 11 Feb 2026 · Announcement: Taftøy Aure / Heim SMR proposal documented. Government approved the impact assessment program in February 2026. Source: Norwegian government Taftøy assessment programme. Updates entry
More on this development

This is not a construction permit or final policy decision. Technology and unit configuration remain unselected.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.
  • State or province is not recorded.
  • Expected for this stage but not recorded as a structured fact: Design identified (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

This is not a construction permit or final policy decision. Technology and unit configuration remain unselected. Norsk Kjernekraft reports that the government has set the assessment program for this project, the first for a concrete nuclear project in Norway. The DSA/DSB/NVE recommendation describes Trondheimsleia Kjernekraft AS as the proponent, established in partnership with the prospective host municipalities, NEAS and Norsk Kjernekraft. The cited passages state no financing commitment or amount.

Key facts

Design
Design profile not linked (SMR)
Technology
Not recorded on a linked design profile — see the description
Operator(s)
Not recorded
Vendor for linked design
No selected-design vendor recorded
Location
Taftøy Næringspark, Aure and Heim · Norway · precision: site area (named plant, laboratory, base, port, campus or parcel)
The government names Taftøy Næringspark (Aure and Heim); the park has no published point and an island centroid is not used as a pin.
Coordinates
Named site, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Taftøy Aure / Heim SMR proposal is recorded at Taftøy Næringspark, Aure and Heim, state or province not recorded, Norway. Operator: No operator is recorded. Recorded vendor: No selected-design vendor is recorded. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); named site, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Funding and government decisions

Source-backed project statement The DSA/DSB/NVE recommendation describes Trondheimsleia Kjernekraft AS as established in partnership with the prospective host municipalities, NEAS and Norsk Kjernekraft. The cited passages state no financing commitment or amount. Partnership alone does not establish share ownership or a paid equity contribution. DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure; Norsk Kjernekraft: locations (ten project companies)

Programs and agreements naming the project
Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
Customer or offtaker

The reviewed sources do not establish a named project-specific power or heat purchaser, contractual quantity or completed offtake. Intended uses, host municipalities and general company customer plans are not buyer commitments. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Norsk Kjernekraft: Taftøy assessment programme set by the government; Norsk Kjernekraft: locations (ten project companies); DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure

Contractor

The reviewed sources do not establish an additional project-specific engineering, preparatory-work or construction assignment. A supplier’s general capabilities or an industry-wide agreement do not establish a contract for this site. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Norsk Kjernekraft: locations (ten project companies); DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure; Norsk Kjernekraft: Taftøy assessment programme set by the government

Fuel
No design profile is linked, so no stated fuel is shown.No project-specific fuel supply arrangement is recorded as a structured fact.

The reviewed sources do not establish a project-specific fuel supplier commitment or delivery. General supply-market plans and reactor-design fuel requirements are kept separate. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure; Norsk Kjernekraft: Taftøy assessment programme set by the government

Comparable schedule revision

Comparable schedule revision not established. The reviewed sources do not establish two dated statements revising the same project milestone. A single target, a fleet-level ambition or a different project’s timetable is not a schedule revision. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. Norsk Kjernekraft: Taftøy assessment programme set by the government; DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure

Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Reactor supplier; Site host or owner
Operator or intended licensed owner
Reactor supplier
Site host or owner

Timeline

Recorded developments

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(7 notes)
  • Evidence review. Trondheimsleia Kjernekraft AS is the proponent (tiltakshaver) of a nuclear power plant at Taftøy næringspark in Heim and Aure municipalities, Norway, according to the assessment program recommended by the directorates DSA, DSB and NVE (in Norwegian), which says the proponent was originally Norsk Kjernekraft AS. Norsk Kjernekraft's homepage says the government has, for the first time, set an assessment program for a concrete nuclear project, starting the impact assessment for the Aure and Heim project; the government's own announcement (the stored February 2026 decision) and its program PDF both returned an access refusal (HTTP 403), so the decision date was not re-read. Neither readable source names a reactor design, vendor, unit count or output: the recommendation requires the proponent to state the basis for its choice of reactor technology, including the number and type of reactors, and to cover the alternatives being considered, while Norsk Kjernekraft refers only to SMRs and proven technology from international suppliers. An assessment program sets what the impact assessment must cover; it is not a license application or permission. No readable source calls Trondheimsleia the intended reactor operator, so the stored operator_ids is better carried as a project_proposer role; stage stays siting, design stays unselected and capacity stays unstored. The next documentary decision is the proponent's impact assessment, followed by a license application under the Atomic Energy Act. Last checked 19 Oct 2026. Norsk Kjernekraft: Taftøy assessment programme set by the government; DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure; Norwegian government Taftøy assessment programme
    What would change this

    The completed impact assessment or a license (konsesjon) application by Trondheimsleia Kjernekraft naming a reactor technology, or a readable copy of the government's set program, would change this record. Next scheduled check: 19 Jan 2027.

  • Design identified: Not disclosed in the reviewed evidence. No readable source names a design. The directorates' recommendation requires the proponent to justify its choice of reactor technology and to make the assessment representative of the installations being considered, which shows the choice was open when it was written; Norsk Kjernekraft speaks only of SMRs from international suppliers. Neither source calls the project technology-neutral, so not_applicable is not used. Last checked 19 Oct 2026. Norsk Kjernekraft: Taftøy assessment programme set by the government; DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure
    What would change this

    The proponent's impact assessment or license application, which must state the chosen reactor technology and number of reactors, would settle the design. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed. The directorates' recommendation names the site as Taftøy næringspark in Heim and Aure municipalities, with Trondheimsleia Kjernekraft AS as proponent. No coordinates are given, so the park is recorded as a named site without a map pin. Last checked 19 Oct 2026. DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure
    What would change this

    Impact assessment maps or a license application giving the plant footprint would allow an approximate or exact location. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The ministries have set the assessment program for Trondheimsleia Kjernekraft's Taftøy project, so the next step is the developer's impact assessment under it; an April 2026 company release says the program allows about two years for that work. The license application and the authorities' decision would follow. No date for an application is given. Last checked 23 Oct 2026. Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026); DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure
    What would change this

    The completed impact assessment or a license application for Taftøy. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. On the ministries' commission, the radiation, civil-protection and energy directorates drafted a recommended joint impact-assessment program for the plant at Taftøy industrial park in Heim and Aure. It requires the developer to plan public participation with the host municipalities, involve authorities, organizations and landowners, and prepare an English version for a cross-border Espoo hearing. An assessment program is not a license or construction permit. Last checked 23 Oct 2026. DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure
    What would change this

    The completed impact assessment or a license application to the authorities. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). The directorates' recommended program for the Taftøy industrial park site requires the developer to map the exact placement of all plant components and describe water sources and a secure cooling-water supply, including under extreme conditions, as well as the grid connection. These are assessment requirements; no land, grid or water arrangement is described. Last checked 23 Oct 2026. DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure
    What would change this

    The completed impact assessment or a grid-connection decision for Taftøy. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. The recommended assessment program requires the developer to describe how radioactive waste and spent fuel would be handled, including any storage at the plant, and to describe the planned disposal solution. This sets what must be assessed; no storage, disposal or funding arrangement for Taftøy is established. Last checked 23 Oct 2026. DSA, DSB and NVE: recommended assessment programme for a nuclear power plant at Taftøy næringspark, Heim and Aure
    What would change this

    The completed impact assessment describing waste and spent-fuel handling and disposal. Next scheduled check: 21 Jan 2027.

Evidence dates

(1 of 5 sources with a publication or document date)
Latest dated listed source publication: Norsk Kjernekraft: Fensfjorden Kjernekraft starts impact assessment (10 Apr 2026): 10 Apr 2026.Latest dated recorded event: Taftøy Aure / Heim SMR proposal documented: 11 Feb 2026.4 of 5 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(5)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Taftøy Aure / Heim SMR proposal — https://smrmap.com/projects/taftoy-smr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Taftøy Aure / Heim SMR proposal”. Record reviewed 2 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/taftoy-smr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.