Natura MSR-1
Natura identifies its MSR-1 demonstration at Abilene Christian University; NRC calls the same ACU facility the molten-salt research reactor. NRC lists its proposed power level as up to 1 MWth and says this research reactor will not produce electricity. This is the research configuration, not the separate commercial MSR-100 concept.
- Reactor type
- Molten salt reactor. How it works, with a 3D view.
- Projects
- Construction: Natura MSR-1 demonstration at Abilene Christian University.
- Evidence
- 4 sources; first primary source: Natura MSR-1 demonstration at ACU. Record reviewed 8 Oct 2026.
Key facts · Tracked projects · Agreements · Sources · Evidence · Regulatory actions · Its projects in the table · Compare with other designs
Key facts
- Class
- SMR
- Technology
- Molten salt reactor (MSR)
- Coolant
- Molten salt
- Spectrum
- Thermal
- Developer / vendor(s)
- Natura Resources
- Module electrical
- thermal only (no MWe)
- Module thermal
- up to 1 MWth (nameplate; basis unspecified)
- Fuel form
- HALEU dissolved in Flibe salt
- Enrichment
- HALEU
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 8 Oct 2026 (record review date, not proof of current availability or a deployment)
Tracked deployment projects
- Natura MSR-1 demonstration at Abilene Christian University — Construction · United States
Agreements naming this design (2)
Agreements, plans, studies and government programs whose sources name this design. They are not deployment projects.
- DOE Reactor Pilot Program (DOE-authorized advanced test reactors) — Government program · Active · announced 18 Jun 2025
Concerns United States - Texas Tech, Abilene Christian University, Natura Resources and Texas Produced Water Consortium molten-salt-reactor… — Research program · Active · announced Jan 2025
Concerns United States
Design sources
(4)
- Natura MSR-1 demonstration at ACU (company, accessed 16 Oct 2026)
- NRC: ACU molten-salt research reactor application (regulator, accessed 8 Oct 2026)
- U.S. NRC: Natura MSR-1 (academic, published 15 Jan 2025, accessed 14 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
Evidence and open questions
(1 note)
- Evidence review. Natura identifies MSR-1 as its demonstration reactor before the commercial MSR-100. DOE's July 2026 pilot-program slides independently describe MSR-1 at Abilene as 1 MWt, supporting that attributed nominal thermal description. NRC separately gives an up-to-1-MWth ceiling and says the research reactor will not produce electricity, with HALEU dissolved in Flibe salt. The NRC construction permit was issued to ACU on 16 September 2024; it is not an operating license. The nominal design description does not establish achieved output, and it is not obtained by converting the NRC ceiling to a point. ACU's permit-holder role and Natura's developer identity remain distinct from current operating authority. Last checked 19 Oct 2026. Natura MSR-1 demonstration at ACU; NRC: ACU molten-salt research reactor application; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
What would change this
An NRC operating license or Natura update that changes the MSR-1 power level or shows electricity production. Next scheduled check: 19 Jan 2027.
Regulatory actions
Compare reviews and approvals across designs
Construction applications and decisions
- ACU Molten Salt Research Reactor construction permit — Natura MSR-1 demonstration at Abilene Christian University
Construction permission · Issued / approved · NRC · decided 16 Sep 2024 · submitted 12 Aug 2022 · permit CPRR-124 · docket 50-610 · ADAMS ML24243A040 · 89 FR 77197
The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center on its Abilene campus. ACU's application is dated 12 August 2022; the NRC notified ACU by letter dated 18 November 2022 that it was acceptable for docketing. Operation needs a separate operating license.
Sources: Federal Register 89 FR 77197 (20 Sep 2024): ACU Molten Salt Research Reactor construction permit; Federal Register 89 FR 18678 (14 Mar 2024): ACU Molten Salt Research Reactor environmental assessment; Federal Register 87 FR 73051 (28 Nov 2022): ACU construction permit application accepted for docketing