Projects / United States · Construction
Natura MSR-1 demonstration at Abilene Christian University
Natura Resources' MSR-1 is a molten salt research reactor at Abilene Christian University in the United States, recorded as under construction.
Current status
- How current
- General record check . Bounded evidence review . 10 of 16 listed sources have a publication or document date recorded here; the newest is 22 Sep 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: ACU Molten Salt Research Reactor construction permit (16 Sep 2024). No operating license or other operating authority is recorded as issued. All permissions and applications
- Latest development
- 18 Sep 2026 · Recorded development: FLiBe coolant salt arrives at Natura's MSR-1 facility at Abilene Christian University. DOE says more than 4,700 pounds of FLiBe salt, once the coolant of Oak Ridge's Molten Salt Reactor Experiment, arrived at Natura's facility for MSR-1, shipped with Oak Ridge and Idaho national laboratories. Source: naturaresources.com: Natura receives FLiBe coolant salt for MSR-1 (published 18 Sep 2026); DOE Office of Nuclear Energy: Department of Energy Provides Rare Salt Material to Natura Resources (published 22 Sep 2026). Updates entry
More on this development
A salt delivery is not fuel loading, criticality or operation.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Construction start evidence (reviewed: sources conflict; see Evidence and open questions); Operation or first-criticality target (non-power reactor) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Molten salt reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
DOE described it as under construction on 26 August 2025, and Natura described it as being built on 21 July 2026; no source read dates the start of reactor installation. The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center. That limit is not stored as a point thermal rating, and no electrical output is recorded. Natura Resources is the recorded vendor and reports the reactor being built; no operator is recorded separately. The completed building and non-nuclear salt loops are not a fueled reactor. DOE says more than 4,700 pounds of FLiBe salt, once the coolant of Oak Ridge's Molten Salt Reactor Experiment, arrived at Natura's facility at the university on 18 September 2026 for MSR-1; that delivery is not fuel loading, and no fuel loading is recorded. Natura said in July 2026 that the reactor is advancing under DOE authorization in the Reactor Pilot Program, after DOE approved its nuclear safety design agreement; the NRC construction permit remains on record. Natura said in December 2025 that, under its current plan, MSR-1 will reach initial operation and criticality under DOE authorization, after which Natura and the university intend to continue NRC licensing as a university research reactor; the NRC's page, updated 15 September 2026, lists no operating-license application. No dated operation target is stored. Natura said on 5 January 2026 that it remained on track to deploy MSR-1 in 2026. Fortune reported on 4 July 2026 that Natura was focused on bringing the reactor fully online by 2028, calling 2026 an early goal, and quoted its chief operating officer distinguishing a criticality test from a full reactor system. No later Natura, university, DOE or NRC statement read repeats the 2026 aim or gives another date. DOE's July 2026 update lists MSR-1 at 1 MWt, and the NRC permit describes a research reactor of up to 1 MWth producing no electricity; that limit is kept in text and not stored as a rating. DOE made a conditional HALEU commitment to Abilene Christian University and Natura on 26 August 2025 for the research reactor. ANS reported in December 2025 that Natura had signed an Other Transaction Agreement with DOE, and quoted the university's NEXT Lab director describing the project as switching to DOE authorization. Natura's 2026 HALEU agreement with Quadrant Nuclear Industries covers its commercial reactors, not MSR-1. On 5 January 2026 Natura reported selection for a DOE allocation of former MSRE coolant salt, completed detailed engineering and design, and procurement underway; allocation is distinct from the later salt delivery. In September 2023 it reported opening the non-reactor facility on 1 September and selecting Zachry the preceding month for detailed design engineering. These building and engineering steps were not reactor operation.
Key facts
- Design
- Natura MSR-1 (SMR)
- Technology
- Molten salt reactor (MSR) · molten salt
- Operator(s)
- Not recorded
- Vendor for linked design
- Natura Resources
- Location
- Science and Engineering Research Center, Abilene Christian University · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
OSM campus point for Abilene Christian University; the named SERC building is not separately mapped in OSM, so this is a campus pin, not the building footprint. Geocode: Query 'Abilene Christian University' -> amenity=university 'Abilene Christian University, 1600, East North 20th Street, Abilene Heights, Abilene, Taylor County, Texas, 79699, United States'. Query naming SERC returned 0 results. - Coordinates
- 32.469973, -99.707359 · site-area point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: plant
- Thermal capacity
- Not recorded
- Purpose
- Research or test reactor
- Construction start
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 20 Oct 2026. How current names both.
Could not be confirmed on . Attempted official source: NRC: ACU molten-salt research reactor application. This is an access or status observation only; the record review date is unchanged.
Site and capacity notes
Natura MSR-1 demonstration at Abilene Christian University is recorded at Science and Engineering Research Center, Abilene Christian University, Texas, United States. Operator: No operator is recorded. Recorded vendor: Natura Resources. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Abilene Christian University' (amenity=university), Abilene, Texas
This project is recorded as thermal only (no MWe). Modules planned: 1. Thermal output is not recorded on this project. The linked design record states up to 1 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Application filing entityAbilene Christian University · source
- Reactor supplier
- Vendor for the linked designNatura Resources
- Funding and government decisions
- Funder or lender named for this projectNatura Resources · sourceCommitted to invest $30.5 million in the reactor project ($21.5 million to ACU, the rest to three partner universities), per ACU; amount disbursed not stated.
Source-backed project statement
The university says Natura committed to investing $30.5 million in the molten salt research reactor project, with $21.5 million of that for Abilene Christian University and the rest for the other universities in the alliance. That is a stated commitment, and the page does not show the amount paid. Natura's 21 July 2026 description of more than $120 million in private funding and $120 million from the State of Texas is not identified as money for this reactor. Abilene Christian University: NEXT Lab research with Natura; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1
- Fuel
- Fuel supplier named for this projectU.S. Department of Energy · sourceConditional commitment (26 Aug 2025) to provide HALEU for this molten salt research reactor; no contract or delivery recorded.
- Fuel form stated for Natura MSR-1HALEU dissolved in Flibe salt
- Enrichment stated for Natura MSR-1HALEU
Source-backed project statement
On 26 August 2025 the Department of Energy made a conditional commitment to provide high-assay low-enriched uranium to Abilene Christian University and Natura for a molten salt research reactor under construction in Texas, with contracting still to be initiated. On 22 September 2026 the Department said more than 4,700 pounds of FLiBe salt, formerly coolant from the Molten Salt Reactor Experiment, arrived on 18 September 2026 for MSR-1. The salt arrival is not uranium delivery or fuel loading. The NRC table's description of fuel dissolved in salt is a design description, not a supply record. DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry; DOE Office of Nuclear Energy: Department of Energy Provides Rare Salt Material to Natura Resources; NRC: ACU molten-salt research reactor application
- Site host or owner
- Site hostAbilene Christian University · source
- Programs and agreements naming the project
- Research program; activeTexas Tech, Abilene Christian University, Natura Resources and Texas Produced Water Consortium molten-salt-reactor…
- Government program; activeDOE Reactor Pilot Program (DOE-authorized advanced test reactors)
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
The NRC page says the Molten Salt Research Reactor is a low-power reactor to support academic research and that it will not produce electricity. The university describes a research alliance with Georgia Tech, Texas A&M, and the University of Texas to design, license, and build it. Neither those pages nor Natura's 21 July 2026 release names a research-service customer or an electricity buyer for MSR-1. The commercial MSR-100 market language on that release is a different product. NRC: ACU molten-salt research reactor application; Abilene Christian University: NEXT Lab research with Natura; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1
- Contractor
The NRC permit page, the university partnership page, Natura's 21 July 2026 release, and the 22 September 2026 salt notice name no engineering or construction firm for MSR-1. Natura is the developer and Abilene Christian University holds the construction permit. Those roles are not a construction award. NRC: ACU molten-salt research reactor application; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1; DOE Office of Nuclear Energy: Department of Energy Provides Rare Salt Material to Natura Resources
- Comparable schedule revision
Comparable schedule revision not established. The NRC page records completed review dates and the 16 September 2024 construction permit, and it states no operation date. Natura's 21 July 2026 release describes progress toward eventual operation without a date, and the university timeline says the reactor will go critical without a date. These pages do not give two dated forecasts for the same operation milestone. NRC: ACU molten-salt research reactor application; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1; Abilene Christian University: NEXT Lab research with Natura
Not recorded in SMRMap's reviewed evidence (1): Operator or intended licensed owner
- Operator or intended licensed owner
- Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
Timeline
Recorded developments
- · Recorded development
FLiBe coolant salt arrives at Natura's MSR-1 facility at Abilene Christian University - Announced · Announcement
Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1 - Reported · Contract
Natura signs an Other Transaction Agreement with DOE for MSR-1 - Announced · Recorded development
DOE commits HALEU to Abilene Christian University and Natura for MSR-1 - · Recorded development
Natura (MSR-1) selected for DOE's Reactor Pilot Program
Earlier developments (5)
- · Construction permission recorded
Construction permission recorded: ACU Molten Salt Research Reactor construction permit - · Recorded development
NRC issues environmental assessment and FONSI for the ACU construction permit - · Regulatory step
Federal Register notice: NRC accepts and dockets the ACU construction permit application - · Regulatory step
ACU submits construction permit application for the Molten Salt Research Reactor - Application dated · Application submitted
ACU applies for its molten salt research reactor construction permit
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- ACU Molten Salt Research Reactor construction permit
Construction permission · Issued / approved · NRC · decided 16 Sep 2024 · submitted 12 Aug 2022 · permit CPRR-124 · docket 50-610 · ADAMS ML24243A040 · 89 FR 77197
The NRC issued construction permit CPRR-124 to Abilene Christian University on 16 September 2024 for a non-power molten salt research reactor of up to 1 MWth in the Dillard Science and Engineering Research Center on its Abilene campus. ACU's application is dated 12 August 2022; the NRC notified ACU by letter dated 18 November 2022 that it was acceptable for docketing. Operation needs a separate operating license.
Sources: Federal Register 89 FR 77197 (20 Sep 2024): ACU Molten Salt Research Reactor construction permit; Federal Register 89 FR 18678 (14 Mar 2024): ACU Molten Salt Research Reactor environmental assessment; Federal Register 87 FR 73051 (28 Nov 2022): ACU construction permit application accepted for docketing
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(10 notes)
- Evidence review. The NRC's project page says Abilene Christian University (ACU) applied on 12 August 2022 for a construction permit for a molten salt research reactor in Abilene, Texas, and that the NRC issued that construction permit to ACU on 16 September 2024; a construction permit is not an operating license, and no operating-license application appears in the opened sources. The NRC page gives a power level of up to 1 MWth and says the reactor will not produce electricity; DOE's Reactor Pilot Program slides (file created 17 July 2026) list MSR-1 in Abilene at 1 MWt, and ANS (19 December 2025) calls it the 1-MWt liquid-fueled molten fluoride reactor planned for ACU's NEXT Lab. ANS reported on 19 December 2025 that Natura had executed an Other Transaction Agreement with DOE, under which pilot-program reactors progress through DOE authorization rather than NRC licensing; Natura's release of 5 January 2026 says it is pursuing DOE authorization to construct and operate, and its release of 21 July 2026 says DOE approved the Nuclear Safety Design Agreement for the demonstration reactor being built at ACU. The release combines authorization language with prospective construction and operating steps; no opened decision establishes the exact authorized scope; Natura says DOE's pathway includes preliminary and final safety analyses for construction and operation, and no opened source reports either approval. On site versus nuclear work: the host building opened on 1 September 2023 (Natura release of 14 September 2023), and on 5 January 2026 Natura said the facility was constructed, detailed engineering complete and procurement begun for the reactor deployment; DOE described the reactor as under construction on 26 August 2025, but no opened source dates reactor installation or any other nuclear construction. DOE says the FLiBe coolant-salt shipment arrived at Natura's facility at ACU on 18 September 2026; a salt delivery is not fuel loading, and no fuel loading, criticality or operation is reported. Targets are imprecise: ANS reported an August 2025 forecast of construction within a year and operation within five years, and Natura said on 5 January 2026 it remained on track to deploy MSR-1 in 2026; no opened source reports that aim met. Historical ACU intent does not settle the current DOE-route operating entity; the interaction between the NRC permit and DOE pathway remains unresolved. Stored fields stay as they are, including the unfilled scalar thermal field; DOE’s 1 MWt description and NRC’s up-to limit remain explicitly distinguished in text; the stored construction stage rests on DOE and Natura describing the reactor as under construction or being built, with no dated start of nuclear construction. Last checked 20 Oct 2026. NRC: ACU molten-salt research reactor application; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); ANS Nuclear Newswire: Natura executes an OTA with the DOE; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1; Natura Resources issuer release, 2026-01-05; DOE Office of Nuclear Energy: Department of Energy Provides Rare Salt Material to Natura Resources; DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry; Natura Resources issuer release, 2023-09-14
What would change this
DOE approval of the MSR-1 preliminary safety analysis or of authorization to construct or operate, or a dated DOE, Natura or ACU report of reactor installation, fuel loading or first criticality. Next scheduled check: 20 Jan 2027.
- Operator or intended licensed owner: Not disclosed in the reviewed evidence. ACU stated historical intent to build and operate under the NRC route and holds that construction permit. Natura later pursued DOE authorization. The current DOE-route operating entity remains unestablished in the opened sources; no new operator is assigned. Last checked 20 Oct 2026. ANS Nuclear Newswire: Natura executes an OTA with the DOE; Natura Resources issuer release, 2026-01-05; NRC: ACU molten-salt research reactor application
What would change this
DOE authorization to operate MSR-1, or a Natura, ACU or DOE statement naming the operating organization. Next scheduled check: 20 Jan 2027.
- Plant capacity (scope qualified): Not disclosed in the reviewed evidence. DOE describes MSR-1 as 1 MWt, separately from NRC’s up-to-1-MWth permit ceiling. Preserve both qualified descriptions without assigning a new scalar in this review. The non-power reactor produces no electricity. Last checked 20 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); ANS Nuclear Newswire: Natura executes an OTA with the DOE; NRC: ACU molten-salt research reactor application
What would change this
A DOE authorization document for MSR-1 states a different power level. Next scheduled check: 20 Jan 2027.
- Module/unit count. One research reactor under construction permit CPRR-124. Last checked 18 Oct 2026. Federal Register 89 FR 77197 (20 Sep 2024): ACU Molten Salt Research Reactor construction permit
What would change this
A second reactor is proposed at the university. Next scheduled check: 18 Jan 2027.
- Construction start evidence: Sources conflict. DOE described the research reactor as under construction on 26 August 2025, and Natura described it as being built on 21 July 2026; ANS reported that ACU's NEXT Lab director predicted in August 2025 that it would be under construction within a year, and Natura said on 5 January 2026 that the facility was complete and procurement for the reactor deployment had begun. The host building opened on 1 September 2023. No dated start of reactor installation or other nuclear construction is published. Last checked 20 Oct 2026. DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry; ANS Nuclear Newswire: Natura executes an OTA with the DOE; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1; Natura Resources issuer release, 2026-01-05; Natura Resources issuer release, 2023-09-14
What would change this
Natura, ACU or DOE dates the start of reactor installation in the research building. Next scheduled check: 20 Jan 2027.
- Operation or grid target (type stated): Not disclosed in the reviewed evidence. Natura's release of 5 January 2026 says it remained on track to deploy MSR-1 in 2026, and its 21 July 2026 release describes progress toward operational readiness and eventual operation with no date. ANS reported an August 2025 forecast of operation within five years, and Fortune reported on 4 July 2026 that Natura was focused on bringing MSR-1 fully online by 2028, quoting its chief operating officer distinguishing a criticality test from a full reactor system. Natura's December 2025 release says first operation and criticality would come under DOE authorization; the NRC's page, updated 15 September 2026, lists no operating-license application. No company or regulator source gives a dated first-criticality or operation target, so no date is stored. Last checked 28 Oct 2026. Natura Resources issuer release, 2026-01-05; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1; ANS Nuclear Newswire: Natura executes an OTA with the DOE; Fortune: How a third-generation Texas oilman transformed an organic farming company into a nuclear startup; Natura Resources: Natura advances MSR-1 toward criticality through DOE pilot program; NRC: ACU molten-salt research reactor application
What would change this
Natura, ACU or DOE publishes a dated fuel-loading or first-criticality target for MSR-1. Next scheduled check: 28 Jan 2027.
- Next decision and prerequisites. The university timeline says an operating license will be submitted to the NRC and does not say that application has been filed. Natura said on 21 July 2026 that, after the safety design agreement, it will support the Department of Energy's review toward construction, operational readiness, and eventual operation. The same release also describes the demonstration reactor as authorized by the Department and being built, and the pages do not explain how that pathway interacts with the NRC construction permit. Last checked 23 Oct 2026. Abilene Christian University: NEXT Lab research with Natura; naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1; NRC: ACU molten-salt research reactor application
What would change this
A filed operating-license application, or a source that states which authorization governs the next MSR-1 operating decision. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The NRC page says it issued a construction permit for the Molten Salt Research Reactor to Abilene Christian University on 16 September 2024, after an application it dates to 12 August 2022, and that the reactor will not produce electricity. The same page records an initial environmental assessment on 30 November 2023 and an environmental assessment on 14 March 2024. The university timeline also dates the permit 16 September 2024 and says an operating license will be submitted, which is not recorded as filed. The university's application date of 15 August 2022 is not the NRC page's 12 August 2022 date. Last checked 23 Oct 2026. NRC: ACU molten-salt research reactor application; Abilene Christian University: NEXT Lab research with Natura
What would change this
An operating-license application filed for MSR-1, or an NRC decision on that application. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The university timeline says the Dillard Science Engineering and Research Center opened in September 2023 and includes a research bay intended to support construction of the research reactor. The NRC page places the reactor in Abilene and says it will not produce electricity, so no export connection is part of that description. No cooling-water arrangement or separate land instrument is stated. Last checked 23 Oct 2026. Abilene Christian University: NEXT Lab research with Natura; NRC: ACU molten-salt research reactor application
What would change this
A stated cooling-water arrangement, or terms of the university site beyond the research-center description. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. INL's September 2024 ACU reactor fuel report says the existing university-reactor fuel take-back service would need new systems and capabilities for ACU's fuel salt. A proposed Hades Report would assess storage locations, processing options and implementation. This identifies an unresolved take-back pathway, not an executed ACU-DOE return agreement. The report does not establish the eventual storage period or disposal destination. Last checked 23 Oct 2026. Natura Resources Molten Salt Research Reactor Fuel Workshop summary report (INL/RPT-24-81994)
What would change this
DOE's planned molten salt fuel take-back report, an executed ACU-DOE fuel take-back agreement, or the NRC environmental review for the operating license. Next scheduled check: 21 Jan 2027.
Evidence dates
(10 of 16 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(16)
- Natura MSR-1 demonstration at ACU (company, accessed 16 Oct 2026)
- Federal Register 89 FR 77197 (20 Sep 2024): ACU Molten Salt Research Reactor construction permit (regulator, accessed 3 Oct 2026)
- Federal Register 89 FR 18678 (14 Mar 2024): ACU Molten Salt Research Reactor environmental assessment (regulator, accessed 3 Oct 2026)
- DOE Office of Nuclear Energy: Department of Energy Provides Rare Salt Material to Natura Resources (government, published 22 Sep 2026, accessed 16 Oct 2026)
- ANS Nuclear Newswire: Natura executes an OTA with the DOE (news report, published 19 Dec 2025, accessed 18 Oct 2026)
- DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry (government, published 26 Aug 2025, accessed 30 Oct 2026)
- Natura: Natura Resources Announces Agreement with Quadrant Nuclear Industries for HALEU Fuel Supply (company, published 11 Jun 2026, accessed 18 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
- NRC: ACU molten-salt research reactor application (regulator, accessed 8 Oct 2026)
- naturaresources.com: Natura announces DOE approval of the Nuclear Safety Design Agreement for MSR-1 (company, published 21 Jul 2026, accessed 14 Oct 2026)
- Natura Resources issuer release, 2026-01-05 (company, published 5 Jan 2026, accessed 19 Oct 2026)
- Natura Resources issuer release, 2023-09-14 (company, published 14 Sep 2023, accessed 19 Oct 2026)
- Abilene Christian University: NEXT Lab research with Natura (academic, accessed 21 Oct 2026)
- Natura Resources Molten Salt Research Reactor Fuel Workshop summary report (INL/RPT-24-81994) (government, published Sep 2024, accessed 23 Oct 2026)
- Natura Resources: Natura advances MSR-1 toward criticality through DOE pilot program (company, published 15 Dec 2025, accessed 28 Oct 2026)
- Fortune: How a third-generation Texas oilman transformed an organic farming company into a nuclear startup (news report, published 4 Jul 2026, accessed 28 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Natura MSR-1 demonstration at Abilene Christian University — https://smrmap.com/projects/natura-msr-1-acu/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Natura MSR-1 demonstration at Abilene Christian University”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/natura-msr-1-acu/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.