SMR design reviews and approvals by regulator

Unlike Policy and licensing, which lists measures and every permit by date, this page groups regulators' decisions by reactor design: design approvals and reviews, and permits for projects that use each design.

The 41 reactor designs that a recorded regulatory action names, with each step by country: design approvals and reviews, and the site, construction and operating permissions issued or sought for projects using the design.

19 of these designs have a design-level review or approval recorded, finished or not. By furthest step:

DesignFurthest stepUnited StatesCanadaUnited KingdomOther countries
HTR-10INET, Tsinghua UniversityOperating authority issuedFirst: NNSA, 2000None recordedNone recordedNone recorded
HTR-PMOperating authority issuedFirst: NNSA, 20 Aug 2021None recordedNone recordedNone recorded
TMSR-LF1 experimental molten-salt reactorShanghai Institute of Applied PhysicsOperating authority issuedFirst: NNSA, 7 Jun 2023None recordedNone recordedNone recorded
ACP100 (Linglong One)China National Nuclear CorporationConstruction permission issuedFirst: NNSA, 1 Jul 2021None recordedNone recordedNone recorded
BWRX-300GE Vernova Hitachi Nuclear EnergyConstruction permission issuedFirst: CNSC, 4 Apr 2025
  • Generic design assessment: step completed Dec 2025, not an approvalStep 2 statement issued December 2025. No Step 3 or design acceptance recorded. · ONR and Environment Agency
None recorded
Hermes / KP-FHRKairos PowerConstruction permission issuedFirst: NRC, 14 Dec 2023None recordedNone recordedNone recorded
NatriumTerraPowerConstruction permission issuedFirst: NRC, 9 Mar 2026None recorded
  • Generic design assessment: under reviewStep 1 began 5 June 2026. · ONR and Environment Agency
None recorded
Natura MSR-1Natura ResourcesConstruction permission issuedFirst: NRC, 16 Sep 2024None recordedNone recordedNone recorded
RITM-200NRosatomConstruction permission issuedFirst: Industrial, Radiation and Nuclear Safety Committee, 4 Jun 2026None recordedNone recordedNone recorded
  • License to construct: issued 4 Jun 2026RITM-200N Jizzakh · Uzbekistan · Industrial, Radiation and Nuclear Safety Committee
  • Site permission: issued 23 Mar 2026Permit to use the site for nuclear installations (Farish district NPP site) — RITM-200N Jizzakh · Uzbekistan · Industrial, Radiation and Nuclear Safety Committee
Xe-100X-energyConstruction permission issuedFirst: NRC, 9 Nov 2026
  • Vendor design review: phase completed, executive summary dated Dec 2023, not an approvalCombined Phases 1 and 2. · CNSC
  • Generic design assessment: requested, not startedONR said on 15 September 2026 that regulators were asked to begin. Not started at its 28 September update. · ONR and Environment Agency
None recorded
NuScale US600NuScale PowerDesign approval or certification issuedFirst: NRC, 11 Sep 2020
  • Design certification: issued 19 Jan 2023Certification rule published 19 January 2023, effective 21 February 2023. · NRC
  • Standard design approval: issued 11 Sep 2020Approved 11 September 2020, before the 2023 certification. · NRC
None recordedNone recordedNone recorded
NuScale VOYGR (US460 / NPM)NuScale PowerDesign approval or certification issuedFirst: NRC, 29 May 2025
  • Standard design approval: issued 29 May 2025NRC standard design approval for the NuScale US460 · NRC
None recordedNone recorded
SMARTKorea Atomic Energy Research InstituteDesign approval or certification issuedFirst: NSSC, 4 Jul 2012None recordedNone recordedNone recorded
  • Standard design approval: issued 4 Jul 2012Original SMART design. SMART100 has its own 2024 approval. · South Korea · NSSC
SMART100Korea Atomic Energy Research InstituteDesign approval or certification issuedFirst: NSSC, 26 Sep 2024None recordedNone recordedNone recorded
  • Standard design approval: issued 26 Sep 2024Korean standard design approval for SMART100 · South Korea · NSSC
Huakun One floating reactor platformChina General Nuclear Power GroupSite permission issuedFirst: NNSA, 2 Nov 2026None recordedNone recordedNone recorded
Thorcon 500 (TMSR500)PT Thorcon Power IndonesiaSite permission issuedFirst: BAPETEN, 30 Jul 2025None recordedNone recordedNone recorded
ARC-100ARC Clean TechnologyDesign review completed, not an approvalFirst: CNSC, Jul 2025None recorded
  • Vendor design review: phase completed, executive summary dated Jul 2025, not an approvalPhase 2. Phase 1 summary dated October 2019. · CNSC
  • License to prepare site: under review (applied 30 Jun 2023)NB Power ARC-100 at Point Lepreau · CNSC
None recordedNone recorded
Global First Power Micro Modular ReactorGlobal First PowerDesign review completed, not an approvalFirst: CNSC, Feb 2019None recorded
  • Vendor design review: phase completed, executive summary dated Feb 2019, not an approvalPhase 1. No later phase listed. · CNSC
None recordedNone recorded
Holtec SMR-160Holtec InternationalDesign review completed, not an approvalFirst: CNSC, Aug 2020None recorded
  • Vendor design review: phase completed, executive summary dated Aug 2020, not an approvalPhase 1. No later phase listed. · CNSC
None recordedNone recorded
Holtec SMR-300Holtec InternationalDesign review completed, not an approvalFirst: ONR and Environment Agency, 31 Mar 2026None recorded
  • Generic design assessment: step completed 31 Mar 2026, not an approvalStep 2 completed 31 March 2026. No Step 3 or design acceptance recorded. · ONR and Environment Agency
None recorded
IMSR (Integral Molten Salt Reactor)Terrestrial EnergyDesign review completed, not an approvalFirst: CNSC, Apr 2023None recorded
  • Vendor design review: phase completed, executive summary dated Apr 2023, not an approvalPhase 2. Phase 1 summary dated November 2017. · CNSC
None recordedNone recorded
Rolls-Royce SMRRolls-Royce SMRDesign review completed, not an approvalFirst: ONR and Environment Agency, 30 Jul 2024None recordedNone recorded
  • Generic design assessment: step completed 30 Jul 2024, not an approvalStep 2 completed 30 July 2024. Step 3 is listed separately as under way. · ONR and Environment Agency
  • Generic design assessment: under reviewStep 3 under way since July 2024. · ONR and Environment Agency
None recorded
SSR-WMoltex EnergyDesign review completed, not an approvalFirst: CNSC, May 2021None recorded
  • Vendor design review: phase completed, executive summary dated May 2021, not an approvalPhase 1. No later phase listed. · CNSC
None recordedNone recorded
Aalo-XAalo AtomicsEnvironmental or other decision onlyFirst: DOE Idaho Operations Office, 14 Apr 2026None recordedNone recordedNone recorded
Antares Mark-0Antares NuclearEnvironmental or other decision onlyFirst: DOE Idaho Operations Office, 26 Jan 2026None recordedNone recordedNone recorded
AuroraOklo Inc.Environmental or other decision onlyFirst: DOE Idaho Operations Office, 20 Jul 2026
  • Environmental decision: issued 20 Jul 2026Oklo Aurora-INL · DOE Idaho Operations Office
None recordedNone recordedNone recorded
HTTRJapan Atomic Energy AgencyEnvironmental or other decision onlyFirst: NRA, 3 Jun 2020None recordedNone recordedNone recorded
Last Energy PWR-5Last EnergyEnvironmental or other decision onlyFirst: DOE Office of Nuclear Energy, 30 Sep 2026None recordedNone recordedNone recorded
MARVELIdaho National LaboratoryEnvironmental or other decision onlyFirst: DOE Idaho Operations Office, 12 Nov 2021None recordedNone recordedNone recorded
Project Pele microreactor (BWXT HTGR)BWX TechnologiesEnvironmental or other decision onlyFirst: DoD Strategic Capabilities Office, 5 Apr 2022None recordedNone recordedNone recorded
UnityDeployable EnergyEnvironmental or other decision onlyFirst: DOE Idaho Operations Office, 15 Apr 2026None recordedNone recordedNone recorded
Ward 250Valar AtomicsEnvironmental or other decision onlyFirst: DOE Office of Nuclear Energy, 22 Apr 2026None recordedNone recordedNone recorded
Alvin experimental molten-salt reactorStellariaApplications or reviews onlyNone recordedNone recordedNone recorded
CAL-30CalogenaApplications or reviews onlyNone recordedNone recordedNone recorded
  • Design assessment: under review (applied 31 Oct 2024)Calogena CAL30 safety-options requests · France · ASNR
eVinciWestinghouse Electric CompanyApplications or reviews onlyNone recorded
  • Vendor design review: on holdPhase 2 started June 2023 and is on hold. · CNSC
None recordedNone recorded
HEXANAHEXANAApplications or reviews onlyNone recordedNone recordedNone recorded
  • Design assessment: application received (applied 30 Sep 2026)HEXANA first safety-options request · France · ASNR
Jimmy Fermi heat microreactorJimmyApplications or reviews onlyNone recordedNone recordedNone recorded
KRONOS MMRNANO Nuclear EnergyApplications or reviews onlyNone recordedNone recordedNone recorded
LFR-AS-30newcleoApplications or reviews onlyNone recordedNone recordedNone recorded
  • Design assessment: application received (applied 19 Dec 2025)newcleo LFR-AS-30 safety-options request · France · ASNR
OTRERA ONEOtrera New EnergyApplications or reviews onlyNone recordedNone recordedNone recorded
  • Design assessment: application received (applied 30 Jul 2026)OTRERA ONE safety-options request · France · ASNR
PWR-20Last EnergyApplications or reviews onlyNone recordedNone recordedNone recorded

Decisions recorded without a design link

Each of these records belongs to a project and names no design, so it is not in the table above.

All designs · Permissions and design reviews · Policy and licensing · Downloads

Cite or share this page

SMRMap. “SMR design reviews and approvals by regulator”. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/design-approvals.html (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.